This is a combined synopsis/solicitation issued by the Bureau of Reclamation seeking quotes for crane inspection and maintenance services. The solicitation is set aside for small businesses and offers a firm fixed-price, indefinite delivery/indefinite quantity contract for an initial period of performance from March 2024 through March 2029 with four optional one-year extensions. Quotes are due by March 1, 2024 and must include pricing for inspection and maintenance of eleven cranes and hoists located across various facilities. The work includes annual inspections, load testing, maintenance, and repairs performed in compliance with all applicable safety and inspection standards.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140R2024Q0032_Amd_0001.pdf | ||
| El_Dorado_WD_2015-5631_Rev_20.pdf | ||
| Calaveras_WD_2015-5665_Rev_23.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUMIS CHECKED
CODE 18a. PAYMENT WILL BE MADE BY
CODE
FACILITYCODE
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
OFFEROR
R20
See Schedule
CODE 16. ADMINISTERED BYCODE
X
X
X
811310
SIZE STANDARD:
% FOR:SET ASIDE:UNRESTRICTED ORR20
REQUEST FOR
PROPOSAL
(RFP)
INVITATION
FOR BID (IFB)
10. THIS ACQUISITION ISCODE
REQUEST FOR
QUOTE (RFQ)
14. METHOD OF SOLICITATION
13b. RATING
NORTH AMERICAN INDUSTRY
CLASSIFICATION STANDARD
(NAICS):
SMALL BUSINESS
03/01/2024 1000 PS
02/20/2024
916-978-4459George Ramos (No collect calls)
INFORMATION CALL:
FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME
4. ORDER NUMBER3. AWARD/ 6. SOLICITATION
140R2024Q0032
5. SOLICITATION NUMBER
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF
1 36 OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
TELEPHONE NO.
17a. CONTRACTOR/
Folsom CA 95630-1799 7794 Folsom Dam Road Central California Area Office Bureau of Reclamation
15. DELIVER TO
Sacramento CA 95825-1898 2800 Cottage Way, Room E-1815 Division of Acquisition Services Regional Office Mid-Pacific Region
9. ISSUED BY
7.
2. CONTRACT NO.
EFFECTIVE DATE
$12.5
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
ISSUE DATE
DELIVERY FOR FREE ON BOARD
(FOB) DESTINATION UNLESS
BLOCK IS MARKED
11.
SEE SCHEDULE
12. DISCOUNT TERMS THIS CONTRACT IS A RATED
ORDER UNDER THE DEFENSE
PRIORITIES AND ALLOCATIONS
SYSTEM - DPAS (15 CFR 700)
13a.
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
(SDVOSB)
HUBZONE SMALL
BUSINESS
8(A)
Bureau of Reclamation
WOMEN-OWNED SMALL
BUSINESS (WOSB)
ECONOMICALLY DISADVANTAGED
WOMEN-OWNED SMALL
BUSINESS (EDWOSB)
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
ADMINISTERED BY:
Bureau of Reclamation Mid-Pacific Region Regional Office Division of Acquisition Services 2800 Cottage Way, Room E-1815 Sacramento CA 95825-1898 US Period of Performance: 03/19/2024 to 03/18/2029
(Use Reverse and/or Attach Additional Sheets as Necessary)
HEREIN, IS ACCEPTED AS TO ITEMS:
XX
DATED
Margaret Jones
. YOUR OFFER ON SOLICITATION (BLOCK 5),
INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER
ARE
ARE
31c. DATE SIGNED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA
31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)
ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL
SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
27a. SOLICITATION INCORPORATES BY REFERENCE (FEDERAL ACQUISITION REGULATION) FAR 52.212-1, 52.212-4. FAR 52.212-3
AND 52.212-5 ARE ATTACHED. ADDENDA
26. TOTAL AWARD AMOUNT (For Government Use Only)
OFFER
STANDARD FORM 1449 (REV. 11/2021)
Prescribed by GSA - FAR (48 CFR) 53.212
ARE NOT ATTACHED.
ARE NOT ATTACHED.
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
30b. NAME AND TITLE OF SIGNER (Type or print)
30a. SIGNATURE OF OFFEROR/CONTRACTOR
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
25. ACCOUNTING AND APPROPRIATION DATA
29. AWARD OF CONTRACT: REFERENCE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER
37. CHECK NUMBER
FINALPARTIAL
36. PAYMENT
FINALPARTIAL
35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER33. SHIP NUMBER
COMPLETE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)
42b. RECEIVED AT (Location)
42a. RECEIVED BY (Print)
41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
STANDARD FORM 1449 (REV. 11/2021) BACK
24.
AMOUNT
23.
UNIT PRICE
22.
UNIT
21.
QUANTITY
20.
SCHEDULE OF SUPPLIES/SERVICES
19.
ITEM NO.
32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE
36 2 of
Combined Synopsis/Solicitation 140R2024Q0032
CCAO Crane Hoist Inspection
Contracting Office:
Bureau of Reclamation
Interior Region 10 · California-Great Basin Acquisitions and Services Division
Supply and Services Branch Sacramento CA 95825
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in Subpart 12.6, as supplemented with FAR parts 13 and additional information included in this notice. The Bureau of Reclamation intends to award a Firm-Fixed Price purchase order strategic plan training as represented in the Performance Work Statement (PWS). This announcement constitutes the only solicitation; quotes are being requested and a written solicitation will not be issued. The solicitation document and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2024-02, as of December 23, 2023.
This requirement is being solicited as 100% total woman owned small business set-aside. The Government will award a Purchase Order resulting from the comparative evaluation of quotes received in response to this solicitation in evaluating price and past performance.
GENERAL INFORMATION
RFQ: 140R2024Q0032
Request for Quotation (RFQ) Request for Proposal (RFP) Invitation for Bid (IFB)
North American Industry Classification Code (NAICS): 811310 Size Standard: $12.5M
QUOTE DUE DATE, DELIVERY AND CONTACT INFORMATION
Competition: 100% Women Owned Small Business
Quotes Due Date: March 1, 2024 at 10:00 AM, Pacific Time
Submit Quotes via email to: George L. Ramos, gramos@usbr.gov
Vendor’s Business Information:
Business Name: ___________________________________________________________
Point of Contact: ____________________________________________________
POC Email & Phone Number: __________________________________________
SAM Unique Entity ID/Cage Code: ___________________________________________
Business Size (select one): Large Small
Please see further instructions for quote submission and required documents under Provision 52.212-1 Addendum and 52.212-2 Addendum.
mailto:gramos@usbr.gov
QUOTE/PRICING SCHEDULE
Option Year 1
Line Item Description Firm-Fixed Priced Base Year Total
00010 Folsom Auxiliary Dam Jib Crane (N&S) $
00020 Folsom Dam 140 Ton Crane 25&10 Ton Hoist $
00030 FOP 275 Ton Crane, 30&10 Ton Hoist $
00040 FOP Draft Tube 10 Ton Monorail Crane $
00050 FUP 7.5 Ton Bridge Crane $
00060 NM Powerplant 375 Ton Bridge Crane, 25T $
00070 Nimbus Powerplant 50 Gantry Crane 10 Ton $
00080 Nimbus Dam 2 Ton Jib Crane $
00090 Warehouse 30 Ton Bridge Crane $
00100 Mobile 40 Ton Grove Mobile Crane $
00110 Mobile Truck Mounted 18 Ton ALTEC Crane $
Base Year Grand Total $
Line Item Description Firm-Fixed Priced Option Year 1 Total
00120 Folsom Auxiliary Dam Jib Crane (N&S) $
00130 Folsom Dam 140 Ton Crane 25&10 Ton Hoist $
00140 FOP 275 Ton Crane, 30&10 Ton Hoist $
00150 FOP Draft Tube 10 Ton Monorail Crane $
00160 FUP 7.5 Ton Bridge Crane $
00170 NM Powerplant 375 Ton Bridge Crane, 25T $
00180 Nimbus Powerplant 50 Gantry Crane 10 Ton $
00190 Nimbus Dam 2 Ton Jib Crane $
00200 Warehouse 30 Ton Bridge Crane $
00210 Mobile 40 Ton Grove Mobile Crane $
00220 Mobile Truck Mounted 18 Ton ALTEC Crane $
Option Year 1 Grand Total $
Option Year 2
Option Year 3
Line Item Description Firm-Fixed Priced Option Year 2 Total
00230 Folsom Auxiliary Dam Jib Crane (N&S) $
00240 Folsom Dam 140 Ton Crane 25&10 Ton Hoist $
00250 FOP 275 Ton Crane, 30&10 Ton Hoist $
00260 FOP Draft Tube 10 Ton Monorail Crane $
00270 FUP 7.5 Ton Bridge Crane $
00280 NM Powerplant 375 Ton Bridge Crane, 25T $
00290 Nimbus Powerplant 50 Gantry Crane 10 Ton $
00300 Nimbus Dam 2 Ton Jib Crane $
00310 Warehouse 30 Ton Bridge Crane $
00320 Mobile 40 Ton Grove Mobile Crane $
00330 Mobile Truck Mounted 18 Ton ALTEC Crane $
Option Year 2 Total $
Line Item Description Firm-Fixed Priced Option Year 3 Total
00340 Folsom Auxiliary Dam Jib Crane (N&S) $
00350 Folsom Dam 140 Ton Crane 25&10 Ton Hoist $
00360 FOP 275 Ton Crane, 30&10 Ton Hoist $
00370 FOP Draft Tube 10 Ton Monorail Crane $
00380 FUP 7.5 Ton Bridge Crane $
00390 NM Powerplant 375 Ton Bridge Crane, 25T $
00400 Nimbus Powerplant 50 Gantry Crane 10 Ton $
00410 Nimbus Dam 2 Ton Jib Crane $
00420 Warehouse 30 Ton Bridge Crane $
00430 Mobile 40 Ton Grove Mobile Crane $
00440 Mobile Truck Mounted 18 Ton ALTEC Crane $
Option Year 3 Grand Total $
Option Year 4
Base Year + 4 Option Years Grand Total
QUOTE VALID DATE
Quotes/offers shall be valid for 60 days from the quote due date.
Quotes shall be submitted on or before March 1, 2024 at 10:00 AM, Pacific Time.
Please see further instructions for quote submission under Addendum to Provision 52.212-1
Documents necessary for quote submission are as follows:
1. Completed vendor information and price schedule.
2. Past Performance documentation (If Applicable) for previous contracts with a similar scope of work.
Include contract number, dollar amount, description of the project, and a point of contact from the agency or commercial organization.
3. Submit quote through email to gramos@usbr.gov
Line Item Description Firm-Fixed Priced Option Year 4 Total
00450 Folsom Auxiliary Dam Jib Crane (N&S) $
00460 Folsom Dam 140 Ton Crane 25&10 Ton Hoist $
00470 FOP 275 Ton Crane, 30&10 Ton Hoist $
00480 FOP Draft Tube 10 Ton Monorail Crane $
00490 FUP 7.5 Ton Bridge Crane $
00500 NM Powerplant 375 Ton Bridge Crane, 25T $
00510 Nimbus Powerplant 50 Gantry Crane 10 Ton $
00520 Nimbus Dam 2 Ton Jib Crane $
00530 Warehouse 30 Ton Bridge Crane $
00540 Mobile 40 Ton Grove Mobile Crane $
00550 Mobile Truck Mounted 18 Ton ALTEC Crane $
Option Year 4 Grand Total $
Statement of Work (SOW) Crane Inspection and Load Testing
1.01 BACKGROUND
The Central California Area Office of the Bureau of Reclamation necessitates an annual inspection of cranes and hoisting equipment. The inspection and quadrennial load testing requirements apply to nine land-based cranes and two mobile cranes. The types of cranes include gantry cranes, bridge cranes, monorail hoists, mobile cranes, and truck-mounted boom cranes. Occasionally, assistance may be required to perform repairs and restore crane service.
1.02 SCOPE
Each crane is to undergo a thorough inspection, functional testing of all systems, and maintenance as specified in this Statement of Work (SOW). A qualified and authorized crane inspector will issue an Inspection Certificate upon completion.
The Contractor will coordinate crane access with the Contracting Officer Representative (COR) or On-site Government Representative (OGR). The Contractor is also responsible for providing test weights for all load tests.
The Contractor is expected to develop and submit a Crane Management Work Plan and Schedule. This plan should detail the work on each crane and a schedule for current and future inspections, certifications, load testing, corrective work orders, and emergency repairs of the CCAO Crane Inventory.
1.03 OBJECTIVE
1. Conduct a comprehensive inspection of CCAO cranes and hoists in compliance with ASME and OSHA standards.
2. Successfully load/proof test CCAO cranes and provide test reports as evidence of successful load testing.
3. Check and calibrate the load cell of each hoist on the Folsom Dam 140T crane, concurrent with the load testing.
4. Complete all on-site work and submit test and certification reports within five business days following successful load tests.
5. Perform necessary repairs for CCAO cranes, including wire rope replacement, motor repairs, control adjustments, brake maintenance, and load cell recalibration.
1.04 TYPE OF CONTRACT
The government intends to award a firm-fixed-price service contract, with the possibility of yearly extensions.
Period of Performance: The contract’s performance period is one year, starting from the award date (March 19, 2024 – March 18, 2025). The contract includes options for four additional years, ending on March 18, 2029.
1.05 ADMINISTRATIVE REQUIREMENTS
The Contracting Officer’s Representative (COR), appointed at the time of award, will administer this contract. The Contractor should coordinate work and communication through the Contracting Officer’s Representative. The Contractor is responsible for performing the crane inspection and maintenance as outlined under Part 2 Technical Requirements. The Contractor must provide a point of contact, including name, title, and telephone number, for the government to schedule crane inspections and discuss work under this contract during normal working hours.
Contractor Qualifications:
The Contractor must provide documentation demonstrating their qualifications to inspect cranes as per 29 CFR 1910, 1926 Subpart CC, and the applicable ANSI/ASME standards. This includes the ability to inspect, test, and issue certification documents for land-based cranes and hoists.
The Lead Field Technician must have a minimum of 2,000 hours of crane inspection experience, along with classroom training for Crane Inspection provided by a recognized crane training agency within the previous 24 months.
The Contractor must provide only qualified and experienced crane operators, riggers, and crane service technicians to perform the work. Recent training certificates for rigging and crane operation are required.
1.06 SCHEDULE AND WORKING HOURS
The Contractor will receive a minimum of 15 working days’ notice prior to the required date of a crane inspection.
The Contractor is expected to provide a field crew to perform the crane inspection as scheduled by the government.
The Contractor’s work hours are from 7:30 AM to 4:00 PM, Monday through Friday.
Work will not be performed on recognized federal holidays or during declared national, state, or local emergencies.
Recognized Holidays:
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day Juneteenth
1.07 LOCATION OF WORK
The cranes requiring inspection are located at power plants and dams within Sacramento County, CA, with the exception of the New Melones Power Plant in Calaveras County, CA.
The Contractor should incorporate travel and lodging expenses into the cost of performing the crane inspections.
This should also include the logistics and cost of delivering a man lift and/or scissor lift to each location as required.
The Contractor should consider the cost of test weights and the time required to fill and empty water weights, assemble and disassemble concrete weights, and transport steel weights.
The Contractor Field Crew should initially report to the Central California Area Office located at 7794 Folsom Dam Road, Folsom, CA 95630, unless directed otherwise by the Contracting Officer’s Representative.
The Contractor Field Crew should report to the Nimbus Powerplant located near 1901 Hazel Ave, Gold River, CA 95670 and the New Melones Powerplant located near 16805 Peoria Flat Road, Jamestown CA 95327 as directed by the Contracting Officer’s Representative.
1.08 CRANES TO BE INSPECTED AND MAINTAINED
The following cranes require inspection:
Location Manufacturer Description Hoist Capacity
Folsom Auxiliary Dam Abell Howe Jib Crane North 3 Ton
Jib Crane South 3 Ton
Folsom Dam Judson Pacific (Murphy) Gantry Crane 140 Ton
Auxiliary Hoist 25 Ton
Auxiliary Hoist 10 Ton
Folsom Powerplant Judson Pacific (Murphy) Bridge Crane 275 Ton
Auxiliary Hoist 30 Ton
Underhung Hoist 10 Ton
Folsom Powerplant Draft Tube Kone Monorail crane 10 Ton
Folsom Pumping Plant The Euclid Crane and Hoist Company Bridge Crane 7.5 Ton
New Melones Powerplant Ederer Corporation Gantry Crane 375 Ton
Auxiliary Hoist 1 25 Ton
Auxiliary Hoist 2 25 Ton
Nimbus Powerplant Judson Pacific (Murphy) Gantry Crane 50 Ton
Auxiliary Hoist 10 Ton
Location Manufacturer Description Hoist Capacity
Nimbus Dam Downs Crane & Hoist Co Jib Crane 2 Ton
Warehouse Cyclops Bridge Crane 30 Ton
Mobile Grove TMS500-2 Mobile Crane 40 Ton
Mobile ALTEC AC18-70 Truck Mount Crane 18 Ton
1.09 SAFETY
1. The Contractor is required to perform the work in compliance with the applicable Federal OSHA standards.
2. Before commencing field work, Contractor field personnel must attend a 30-minute Hazardous Energy
Control training session provided by the government. This training is valid for twelve months.
3. A Special Work Permit issued by the government is required for work involving Lockout/Tagout (LOTO).
The Contractor’s Lead Field Technician must sign this permit.
1.10 SECURITY
1. The work will be performed at a secure government facility.
2. Contractor employees working in the field must provide current photo identification at each scheduled field visit for security purposes. They will be issued a contractor badge that must be displayed throughout the duration of the work performed on site.
3. Contractor employees are only permitted to work in the areas confined by the operation of the crane being inspected.
1.11 SUPPLIED BY THE GOVERNMENT
Utilities:
1. Power at 120 Volts off a single 20 Amp circuit is available at some, but not all, crane locations.
2. Compressed air at 90 psi and 10 CFM is available at some, but not all, crane locations.
3. No potable water is available.
4. Toilet and washroom facilities are not available at all crane locations.
Test Weights: The New Melones Powerplant has a 375 Ton concrete test weight apparatus located near the facility that may be used for load testing at the site. Drawings and assembly information are available upon request.
PART 2 TECHNICAL REQUIREMENTS
2.01 DOCUMENTATION
Inspection Qualifications and Standards
1. As a federal facility, crane inspections must comply with US Department of Labor OSHA and applicable ANSI/ASME standards, not CAL-OSHA standards.
2. The government prefers that the Contractor inspects each crane following the latest edition of the Standards and Guidelines for Professional Services Performed on Overhead and Traveling Cranes and Associated Hoisting Equipment Publication No. 78 by the Crane Manufacturers Association of America, Incorporated.
Alternatively, the Contractor can provide documentation demonstrating the use of an equivalent inspection standard.
3. The Contractor must provide the Crane Inspection Certificate Template intended for documenting each crane’s inspection certificate. The government will review this Certificate Template and provide appropriate comments.
4. The Crane Inspection Certificate Template must clearly state what the inspector is certifying, what has been inspected, and what standards have been applied.
2.02 WORK TO BE PERFORMED
The Contractor is required to provide all labor, tools, special tools, man lifts, safety equipment, and consumable materials, including cleaning products, spray lubricants, and grease, necessary to complete the work.
A crane load test may coincide with the annual crane inspection. In such instances, the Contractor must use test weights and rigging to perform an operational test of the crane under full load.
With government approval, the Contractor is expected to perform crane maintenance and repair within the scope specified in this Statement of Work. If maintenance cannot be completed during a site visit coinciding with inspection, the work must be authorized by the Contracting Officer and then coordinated, planned, and scheduled with the COR. Completion should occur within the next 365 days, depending on the impact of continued operation.
2.03 CRANE INSPECTION
Inspection Qualifications and Standards: The government recognizes the Standards and Guidelines for Professional Services Performed on Overhead and Traveling Cranes and Associated Hoisting Equipment Publication No. 78 by the Crane Manufacturers Association of America, Incorporated as the industry standard for crane inspection. The Contractor should inspect the crane following the latest edition of CMMA Publication No. 78, or an equivalent inspection standard developed and provided by the Contractor. The Contractor must provide sufficient documentation to demonstrate adherence to a similar crane inspection standard.
The crane inspection requirement under this contract involves inspecting and functionally operating all the electrical and mechanical systems and safety devices. The Contractor must report whether these systems and devices are working as intended by the original equipment manufacturer (OEM).
The Contractor must functionally test all mechanical and electrical systems through their full range of operation. The hoists should be functionally tested without load to verify the proper operation of controls and verify settings of limit switches.
The crane inspection should include, but not be limited to, the items listed below:
MINIMUM ITEMS TO BE INSPECTED FOR FIXED CRANES AND HOISTS
1. Safety Devices
2. Warning Labels and Devices
3. Guards and Enclosures
4. Travel Limits a. Main Hoist over hoist limit switch b. Auxiliary Hoist over hoist limit switch c. Trolley
Travel limit switches
5. Emergency Stop
6. Hook latches
7. Electrical Systems a. Main Disconnect b. Conductors and Collectors c. Wiring and Conduit d. Speed
Controls e. Contactors f. Resistors g. Motors
8. Crane Controls a. Crane and Trolley Travel Controls b. Hoist and Lowering Controls
9. Mechanical Systems a. Gearboxes and lubrication b. Shafts and couplings c. Bearings and seals d. Sheaves and assemblies e. Wire Rope Drums f. Hoist Blocks g. Hooks and bearings h. Wheel assemblies and wheel wear patterns
10. Braking Systems a. Trolley Brakes b. Hoist Brakes c. Crane drive brake
11. Structural Components a. Crane beams and supporting structures b. Trolley frame and supporting structures
c. Trolley tracking and dimensionally square d. Crane rails e. Trolley rails f. Bumper stops
Inspection Reports: The Contractor must provide a preliminary crane inspection report within five business days after the completion of the crane inspection.
Deficiency Reports:
1. The Contractor must provide a preliminary crane deficiency report within five business days after the completion of the crane inspection.
2. The deficiency report should contain two separate lists. The first list should describe deficiencies that require correction for the inspector/examiner to certify that the crane is operating within the crane manufacturer’s original configuration or within the applicable industry standards. The second list should describe recommendations that are maintenance items and do not render the crane unsafe to operate under applicable laws and regulations.
3. Deficiencies deemed significant enough by the inspector/examiner to render the crane inoperable should be justified, citing relevant and applicable standards.
Final Report and Crane Inspection Certificate
1. A final report and crane inspection certificate should be prepared and submitted within ten business days after the completion of work for each crane.
2. The final report should include inspection reports, deficiency reports, details of repairs and adjustments, load test details and results (if performed), and a Certificate of Inspection signed by a qualified inspector.
2.04 CRANE MAINTENANCE
1. Component Cleaning and Lubrication: Clean all mechanical and electro-mechanical components as necessary to facilitate a comprehensive inspection. Apply lubrication where needed to ensure optimal operation.
2. Inspection-Driven Adjustments: Following the crane inspection, make necessary adjustments to both electrical and mechanical components to align with OEM specifications or crane industry standards. For cranes with dual trolleys, speed controller adjustments for each hoist may be necessary and are considered part of crane maintenance. This section’s intended adjustments include tightening loose fasteners, realigning components, calibrating limit switches, adjusting brakes, and other similar activities.
3. Trolley Rails:
a. Conduct a visual inspection of trolley rails for signs of excessive wear, deflection, movement, or misalignment.
b. Ensure trolley rails are straight, level, and parallel within a tolerance of 0.125 inches every 20 feet. The
Contractor is expected to measure and report rail alignment diligently.
c. Examine all trolley rail clamps and fasteners. Tighten any loose fasteners and replace any necessary hardware.
4. Crane Rails:
a. Visually inspect crane rails for signs of excessive wear, deflection, movement, or misalignment.
b. Ensure crane rails are straight, level, and parallel within a tolerance of 0.25 inches every 100 feet. The
Contractor is expected to measure and report rail alignment diligently.
c. Check all rail clamps and fasteners. Tighten any loose fasteners and replace any necessary hardware.
5. Monorail Crane Beam Inspection:
a. Visually inspect monorail beam flanges for signs of excessive wear and deflection.
b. Ensure monorail beam flanges are straight and level within a tolerance of 0.25 inches every 100 feet.
The Contractor is expected to measure and report wear and deflection of the monorail beam.
6. Ropes
a. Visually inspect ropes for signs of excessive wear, broken strands, and proper reeving.
b. The Contractor is expected to ensure ropes are properly lubricated.
2.05 REPAIRS
1. The Contractor is required to provide a detailed proposal outlining the necessary repairs for any identified deficiencies. Upon approval by the Contracting Officer (CO), the Contractor shall proceed with the repairs and any subsequent retesting in accordance with ASME B30 standards.
2. In the event of a rope replacement, the Contractor shall:
a. Remove the existing ropes. Prior to the installation of new ropes, clean drums, blocks, hooks, etc., to remove grease, dirt, and debris. Conduct an inspection of all sheaves and bearings for damage and proper operation.
b. Inspect crane hooks in compliance with ASME B30.10. Examine block sheaves and bearings.
Measure the hook throat opening and other key parameters to establish baseline data for future inspections. If available, compare these measurements with manufacturer data. Submit findings for this item (6.3.B), and provide baseline measurements on a manufacturer drawing or sketch indicating the key baseline dimensions for future reference.
c. Re-lubricate hook(s) and block(s) as necessary, and reuse them to maintain existing configurations.
d. Reeve and terminate rope(s) in a manner identical to existing installations.
e. Hang a light weight (10% of rated load) on the rope to allow proper set-in of the rope and associated equipment. This ensures the rope and associated equipment are properly aligned.
2.06 LOAD TESTING
Quadrennial Inspection: Conduct a quadrennial inspection while the crane is load tested to 100 – 125% of its rated capacity. Perform all operational movements in accordance with ASME B30.2, Section 2-2.3.2.
Test and Certification Report: Upon completion of all work, provide a comprehensive test and certification report.
Load Testing Weights: The Contractor is responsible for supplying all weights necessary for load testing.
Water Weights: If the Contractor chooses to use water weights, they must supply all water bags for load testing and pumps for filling the bags.
Power Plant Approval: If water weights are used around power plants, approval and a mitigation plan will be required.
Mussel-Free Certification: The Contractor must ensure and provide documentation that the water weight bags are free of mussels.
Load Test Schedule
Crane Next Load Test Due
Nimbus Dam November 8, 2024
Nimbus Dam Jib TBD
Folsom Dam November 9, 2024
Folsom Powerplant Draft Tube November 10, 2024
Folsom Pumping Plant November 10, 2024
Folsom Powerplant November 11, 2024
Folsom Auxiliary Dam (FOX) October 16, 2026
Warehouse October 16, 2026
New Melones Powerplant March 27, 2027
Mobile Crane TBD
Truck mounted crane TBD
SECTION C CLAUSES
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
Federal Acquisition Regulation: https://www.acquisition.gov/far Department of the Interior Acquisition Regulation: https://www.acquisition.gov/diar
(End of clause)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE
MAINTENANCE
AUG 2020
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS
SUBCONTRACTORS
MAR 2023
52.228-5 INSURANCE – WORK ON A GOVERNMENT INSTALLATION JAN 1997
52.242-15 STOP – WORK ORDER AUG 1989
52.212-4 CONTRACT TERMS AND CONDITIONS –COMMERCIAL
PRODUCTS AND COMMERCIAL SERVICES
NOV 2023
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO
INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (DEVIATION 2017-02) (NOV 2023)
(a) This contract and employees working on this contract will be subject to the whistleblower rights and remedies established at 41 U.S.C. 4712 and Federal Acquisition Regulation (FAR) 3.900 through 3.905.
(b) The Contractor shall inform its employees in writing, in the predominant language of the workforce, of employee whistleblower rights and protections under 41 U.S.C. 4712, as described in FAR 3.900 through 3.905.
(c) The Contractor shall insert the substance of this clause, including this paragraph (c), in all subcontracts.
(End of clause)
52.217-8 OPTION TO EXTEND SERVICES (NOV 1999)
The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days prior to contract expiration date.
(End of clause) http://www.acquisition.gov/far http://www.acquisition.gov/diar
52.217-9 OPTION TO EXTEND THE TERM OF THE CONTRACT (MAR 2000)
(a) The Government may extend the term of this contract by written notice to the Contractor within 30 days; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least 60 days before the contract expires. The preliminary notice does not commit the Government to an extension.
(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.
(c) The total duration of this contract, including the exercise of any options under this clause, shall not
(d) exceed 5 years.
(End of clause)
52.219-30 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, WOMEN-OWNED SMALL
BUSINESS CONCERNS ELIGIBLE UNDER THE WOMEN-OWNED SMALL BUSINESS PROGRAM
(OCT 2022)
Women-owned small business (WOSB) concern eligible under the WOSB Program (in accordance with 13 CFR part 127), as used in this clause, means a small business concern that is at least 51 percent directly and unconditionally owned by, and the management and daily business operations of which are controlled by, one or more women who are citizens of the United States, and the concern is certified by SBA or an approved third-party certifier in accordance with 13 CFR 127.300 as a WOSB. A certified EDWOSB is automatically eligible as a certified WOSB.
WOSB Program Repository means a secure, Web-based application that collects, stores, and disseminates documents to the contracting community and SBA, which verify the eligibility of a business concern for a contract to be awarded under the WOSB Program.
(b) Applicability. This clause applies only to-
(1) Contracts that have been set aside for, or awarded on a sole-source basis to, WOSB concerns eligible under the WOSB Program;
(2) Part or parts of a multiple-award contract that have been set aside for WOSB concerns eligible under the WOSB Program;
(3) Orders set aside for WOSB concerns eligible under the WOSB Program, under multiple-award contracts as described in 8.405-5 and 16.505(b)(2)(i)(F); and
(4) Orders issued directly to WOSB concerns eligible under the WOSB Program under multiple-award contracts as described in 19.504(c)(1)(ii).
(c) General. (1) For WOSB set-aside procurements, offers are solicited only from certified WOSB concerns eligible under the WOSB Program or WOSB concerns with a pending application for certification status in the Dynamic Small Business Search (DSBS).
(2) For WOSB sole-source awards, offers are solicited only from certified WOSB concerns.
(3) Offers received from other concerns shall not be considered.
(4) Any award resulting from this solicitation will be made to a certified WOSB concern eligible under the WOSB Program.
(d) Joint venture. A joint venture may be considered a WOSB concern eligible under the WOSB Program if—
(1) At least one party to the joint venture complies with the criteria defined in paragraph (a) and (c)(3) of this clause, and 13 CFR 127.506(c); and
(2) Each party to the joint venture qualifies as small under the size standard for the solicitation, or the protégé is small under the size standard for the solicitation in a joint venture comprised of a mentor and protégé with an approved mentor-protégé agreement under the SBA mentor-protégé program.
(e) In a joint venture that complies with paragraph (d) of this clause, the WOSB party or parties to the joint venture shall perform at least 40 percent of the work performed by the joint venture. Work performed by the WOSB party or parties to the joint venture must be more than administrative functions.
(End of clause)
52.237-2 PROTECTION OF GOVERNMENT BUILDINGS, EQUIPMENT, AND VEGETATION (APR 1984)
The Contractor shall use reasonable care to avoid damaging existing buildings, equipment, and vegetation on the Government installation. If the Contractor’s failure to use reasonable care causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government as the Contracting Officer directs. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.
(End of clause)
DOI-AAAP-0028 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS-INVOICE
PROCESSING PLATFORM (IPP) (FEB 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
'Payment request' means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is:
https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
Contractor must provide documentation to support that the services have been performed.
When submitting invoices to IPP, the Contractor is advised to upload supporting documentation that will allow Reclamation to verify that the products or services comply with the terms of the contract. The information in the uploaded documents should not conflict with the data fields in the IPP submissions (service dates, invoice number, etc.). Prior to submitting an invoice to IPP, the contractor may coordinate with the designated Contracting Officer's Representative (COR), for review and verification of quantities for payment and for compliance with the applicable progress payment requirements of this contract. Prior coordination with the COR will allow for streamlined processing of the invoice.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause) http://www.ipp.gov/
DOI-AAAP-0050 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (DEC 2015)
1) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3) We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4) When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5) Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a) Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b) Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c) All information provided should be reviewed for accuracy prior to submission.
d) If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e) Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f) If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6) The following guidelines apply concerning your use of the past performance evaluation:
a) Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c) Prohibit the use of or reference to evaluation data for advertising, promotional material, pre- award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
DIAR 1452.201-70 AUTHORITIES AND DELEGATIONS (SEP 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of Clause)
WBR 1452.201-80 CONTRACTING OFFICER’S REPRESENTATIVE’S AUTHORITIES AND
LIMITATIONS -- BUREAU OF RECLAMATION (MAY 2018)
a) Performance of the work under this contract shall be subject to the technical direction of the Reclamation Contracting Officer's Representative (COR). The term "technical direction" is defined to include, without limitation:
(1) Inspecting and accepting or rejecting work performed under the contract.
(2) Representing the Government in technical phases of the work. The COR is responsible for the technical administration of the contract and will provide instructions and interpretations to the Contractor on all technical matters relating to the contract. The COR will supervise or oversee all Government technical and administrative personnel assigned to assist the COR.
(3) Reviewing and, where required by the contract, approving submittals of technical data, shop drawings, samples, literature, plans, or other data required to be delivered by the Contractor to the Government.
(b) The Contractor will receive a copy of the written COR designation from the Contracting Officer. It will specify the extent of the COR's authority to act on behalf of the Contracting Officer.
(c) Technical direction must be within the scope of work stated in the contract. Only the Contracting Officer is authorized to determine if a change is within the scope of the contract; therefore, the COR does not have the authority to, and may not, issue any technical direction that -
(1) Constitutes a direction of additional work outside the Contract requirements;
(2) Constitutes a change as defined in the contract clause entitled "Changes;"
(3) In any manner causes an increase or decrease in the total contract cost, or the time required for contract performance;
(4) Changes any of the expressed terms, conditions or specifications of the contract; or
(5) Interferes with the Contractor's right to perform the terms and conditions of the contract.
(d) All technical direction shall be issued in writing by the COR.
(e) The Contractor must proceed promptly with the performance of technical direction duly issued by the COR in the manner prescribed by this clause and within its authority under the provisions of this clause. If, in the opinion of the Contractor, any instruction or direction by the COR falls within one of the categories defined in (c)(1) through (c)(5) of this clause, the Contractor must not proceed and must notify the Contracting Officer in writing within five (5) working days after receipt of any such instruction or direction and must request the Contracting Officer to modify the contract accordingly. Upon receiving the notification from the Contractor, the Contracting Officer must -
(1) Advise the Contractor in writing after receipt of the Contractor's letter that the technical direction is within the scope of the contract effort and does not constitute a change under the Changes clause of the contract; or
(2) Advise the Contractor that the Government will issue a written change order.
(f) A failure of the Contractor and Contracting Officer either to agree that the technical direction is within the scope of the contract or to agree upon the contract action to be taken with respect to the technical direction will be subject to the provisions of the clause entitled "Disputes."
(End of clause)
WBR 1452.223-81 SAFETY AND HEALTH – BUREAU OF RECLAMATION (AUG 2021)
(a) The Contractor shall not require any person employed in the performance of this contract (including subcontracts) to work under conditions which are unsanitary, hazardous, or dangerous to the employee's health or safety.
(b) Contractor shall comply with the most current version of the Bureau of Reclamation Reclamation Safety and Health Standards (RSHS) and, if applicable, the requirements of the Accident Prevention Clause (FAR 52.236- 13 ).
The RSHS manual shall be obtained at http://www.usbr.gov/ssle/safety/RSHS/rshs.html
(c) Comply with the standards issued by the Secretary of Labor at 29 CFR Part 1926 and 29 CFR Part 1910 from the Occupational Safety and Health Administration, U.S. Department of Labor, www.osha.gov.
(d) In the event there is a conflict between the requirements contained in paragraphs (b) and (c) referenced herein, the more stringent requirement shall prevail.
(e) The Contractor shall submit a written proposed safety program as prescribed in the RSHS and the written specifications.
(f) The Contractor shall maintain an accurate record of, and shall report to the Contracting Officer (or authorized representative) in the manner prescribed by the Contracting Officer, all cases of death, occupational diseases, or traumatic injury to employees or the public involved, and property damage in accordance with the RSHS and OSHA guidelines.
(g) The rights and remedies of the Government provided in this clause are in addition to any other rights and remedies provided by law or under this contract.
(h) If the RSHS is updated or amended by Reclamation during the course of this contract, the contractor will be notified in writing. The contractor shall comply with the current RSHS immediately upon written notification.
Should the contractor feel that the updated version of RSHS constitutes a substantive change to the contract, affecting price or time (or both), the contractor may request an equitable adjustment in the contract price. Any such requests shall include a price proposal submitted in compliance with Contract Clause WBR 1452.243-80, Modification Proposals - Bureau of Reclamation, and in sufficient detail to allow meaningful analysis of labor, equipment and material.
(End of clause)
WBR 1452.223-82, ENSURING ADEQUATE COVID-19 SAFETY PROTOCOLS IN FEDERAL
BUILDINGS AND FEDERALLY CONTROLLED FACILITIES -- BUREAU OF RECLAMATION (NOV
2022)
When accessing Federal buildings and federally controlled facilities under this contract, contractor employees shall comply with the Safer Federal Workforce Task Force’s current guidance for COVID-19 workplace safety protocols for Federal agencies at https://www.saferfederalworkforce.gov/.
(End of clause)
WBR 1452.237-80 SECURITY REQUIREMENTS -- BUREAU OF RECLAMATION (MAR 2022)
(a) General Security Requirements:
(1) This clause addresses security requirements, including general procedural requirements, information security requirements, contractor employee suitability requirements, identification card requirements, site security requirements, vessel exclusion barriers, and information technology security requirements. Within this clause, COR means Contracting Officer's Representative. If there is no COR appointed and identified to the Contractor, the term https://www.acquisition.gov/far/part-52#FAR_52_236_13 http://www.usbr.gov/ssle/safety/RSHS/rshs.html http://www.osha.gov/ https://www.saferfederalworkforce.gov/ instead will mean the Program Manager or any other authorized individual responsible for technical oversight under the contract. “Work site” means the Government facility, office, construction site, and any other area within the Government office or facility that the Contractor must access to accomplish work under this contract.
(2) The work performed under this contract shall only be accomplished by individuals (in the employment of the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .