This document is a solicitation for a construction project to build a slab foundation for a family restroom at a national park campground. The National Park Service Pacific West Region is seeking a contractor to construct the slab foundation at Olympic National Park in Forks, Washington for a total small business set-aside amount of $25,000 to $100,000. Quotes are due by September 8, 2023 and the contract is to be awarded by September 25, 2023. The work must be completed within 190 calendar days of award. The solicitation includes specifications for the project, required forms, clauses, and evaluation criteria.

View the file

Other files

File Type Posted
Attachment_1_READ_ME_FIRST.pdf PDF
Attachment_3_Wage_Rates.pdf PDF
Attachment_4_Specificaitons.pdf PDF
Attachment_2_FORMS_TO_RETURN_WITH_QUOTE.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

CALL:

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0040624814

NPS, PWR - OLYM MABO

600 E. Park Avenue

Port Angeles WA 98362-6757

PPY

Email to Phaedra_Fuller@nps.gov

Phaedra Fuller (360) 565-3009

108/23/2023

140P8323Q0043

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

This is a Request for Quotations (RFQ) for the National Park Service, Olympic

National Park. The work of this contract is to construct a slab foundation for a family restroom at the Kalaloch Campground Comfort Station Loop D.

This project is being solicited and awarded as a total (100%) Small Business set-aside. The NAICS code for this solicitation is 238110, Poured Concrete

Foundation and Structure Contractors, with an associated small business size standard of $19 million. In accordance with Federal Acquisition Regulation (FAR)

Subpart 36.204, the estimated magnitude of this construction project is $25,000 to

$100,000. This is not the Government estimate. Government has anticipated this requirement to be between $45,000 to $65,000.

To complete this SF-1442, write your business name, address, and point of contact in

Block 14 and complete Blocks 15 through 19 (acknowledge any amendments issued in box

19), and complete blocks 20a through 20c.

Refer to Solicitation Terms, Provisions, and Clauses included below, specifically

Section L.3 for instructions on what to include in quote, as well as all other

Continued ...

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 190 calendar days and complete it within ________________ ________________ calendar days after receiving

Terms, Section F.2

09/08/2023

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 8/2014)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document and return (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.

No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

NPS, PWR - OLYM MABO

600 E. Park Avenue

Port Angeles WA 98362-6757

PPY

Phaedra Fuller

28. NEGOTIATED AGREEMENT 29. AWARD

Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.)

10 U.S.C. 2304(c) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 8/2014) BACK

Continued...

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 17

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140P8323Q0043 associated attachments no. 1 through 4.

This purchase is for the federal government and is thus exempt from state sales tax (#140001849).

Delivery: 190 Days After Award

Delivery Location Code: 0009819256

NPS, Olympic NP

600 E Park Avenue

Port Angeles WA 98362 US

Period of Performance: 09/25/2023 to 03/31/2024

00010 DO NOT USE THIS LINE ITEM TO SHOW YOUR OFFERED

PRICE. Instead, fill in all prices using the

Price Schedule in Attachment no. 2, Forms to

Submit with Quote. If you do not provide a price for each line item stated in the Price Schedule, your quote may be ineligible.

Product/Service Code: Y1QA

Product/Service Description: CONSTRUCTION OF

RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE)

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Solicitation (RFQ) no. 140P8323Q0043 – Terms, Provisions, Clauses (8/23/23)

Construct Slab Foundation for Family Restroom at Kalaloch Campground, OLYM

For this solicitation, please substitute the words “quote” and “Quoter” for “offer” and “Offeror.”

SECTION B: Price Schedule

Prices shall be filled in using the price schedule template provided in Attachment no. 2, Forms to Submit with

Quote. The price schedule contains a single line item for the requirement that is fully funded. There are no optional line items.

SECTION C – DESCRIPTIONS/SPECIFICATIONS/STATEMENT OF WORK

This document is attached and incorporated into this solicitation/contract, as shown in Section J: Attachment 4, Specifications.

Project Location: Olympic National Park, Kalaloch Campground, U.S. Highway 101, Forks, WA 98331.

Specifications include site map information.

SECTION D: Packaging and Marking (not used)

SECTION E: Inspection and Acceptance

52.246-12 Inspection of Construction. (AUG 1996)

52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (Aug 1996)

SECTION F: Deliveries or Performance

F.1 52.242-14 Suspension of Work. (APR 1984)

F.2 FAR 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the

Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than *190 days after the date the Contractor receives the notice of award. The time stated for completion shall include pre-construction meeting, issuance of the notice to proceed, substantial and final completion notifications, and final cleanup of the premises.

* Period of performance is from September 25, 2023 to March 31, 2024. This is the total time that contractor must start and finish all work. After the pre-construction meeting, and as scheduled with the Contracting Officer’s

Representative (COR), once onsite work begins, the Government anticipates contractor can complete all work within a 90 day period.

F.3 Seasonal Break in Contract Performance

Although NPS does not intend to suspend work during contract performance, seasonal weather conditions may restrict or prohibit normal contract activities. The Contractor’s construction schedule should take into account historic weather patterns when planning the work sequence.

52.252-2 Federal Acquisition Regulation (FAR) and Department of the Interior (DIAR) Clauses

Incorporated By Reference (Feb 1998)

This solicitation and resulting contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses

(clauses are from the FAR unless noted):

FAR https://www.acquisition.gov/?q=browsefar

DIAR http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl

Full text versions of all Deviations are found at https://www.acquisition.gov/content/caac-letters.

http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl

SECTION G: Contract Administration Data

1452.201-70, Authorities and Delegations (September 2011)

(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.

(c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without prior authority. The Contractor shall notify the Contracting

Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting

Officer's response issued under paragraph (e) of this clause.

(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause.

A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the

Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.

1452.204-70 Release of Claims—Department of the Interior (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

G.1 Appointment of Contractor Representative / Superintendent

Prior to commencement of work on this contract, the contractor shall provide to the Contracting Officer and COR the name and telephone number of at least one responsible individual who will serve to respond to operational problems and/or emergencies on a daily basis. The contractor agrees that notice to the designated representative shall constitute notice to the contractor and agrees to be bound by any commitments or representations made by the representative.

G.2 ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS - Invoice Processing Platform (IPP) (April 2013)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing

Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Contractor’s business invoice (upload your business invoice as an attachment to the IPP invoice),

2. Contractor’s signed certification required by FAR clause 52.232-5 (Certification for Construction Progress

Payment), and

3. Schedule of Values (can also be built into the business invoice)

Contractor’s failure to attach the required documentation as specified above may result in the IPP invoice being rejected.

The Contractor must use the IPP website to register, access, and use IPP for submitting requests for payment. The

Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

G.3 NPS Team – Contact Information

Contracting Officer (CO): Phaedra Fuller, Olympic National Park (OLYM), Port Angeles, WA

Office: 360-565-3009 Email: Phaedra_Fuller@nps.gov

Contracting Officer’s Representative (COR):

David Weaver, Facility Management Team (Maintenance), Olympic National Par

(OLYM)

Office: 360-565-3173 Email: Kerri_Cook@nps.gov

COR’s Project Inspector (onsite day-to-day point of contact):

To be determined

Contract Specialist (will be assisting CO with some post-award contract administration):

Sue Mayo, OLYM

Office: 360-565-3038 Email: Sue_Mayo@nps.gov

Invoice/Payment (will be responsible for receipt of invoices submitted in IPP, routing for approval of payment, processing receiving documentation in NPS finance system):

Kasey Weaver, Administrative Support Assistant, OLYM

Office: 360-565-3160 Email: Kasey_Weaver@nps.gov

G.4 CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM

1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the

Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.

2. In accordance with NPS Acquisition Policy and Procedures Memorandum 1443.42-01, the Contracting Officer may enter a formal evaluation of the contractor’s performance in the Contractor Performance Assessment Reporting System

(CPARS). The Contractor will have the opportunity to review and comment on the Government’s performance ratings before they are finalized and used in future government source selections.

https://www.ipp.gov/ mailto:ippgroup@bos.frb.org mailto:Kerri_Cook@nps.gov mailto:Sue_Mayo@nps.gov https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html

SECTION H: Special Contract Requirements

H.1 Wage Determination

Attachment 3, U.S. Department of Labor General Wage Decision #WA20230029 dated 2/3/23 (Jefferson County, Washington), is incorporated into this solicitation/contract, as shown in Section J.

H.2 Payment Bond (post-award requirement)

After award, contractor shall submit a Payment Bond in 100% of the amount of the awarded contract price, submitted on

Standard Forms 25a, or in the form of a certified or cashier’s check, bank draft, post office money order, or currency, or

United States Government bonds or notes (at par value) deposited in accordance with Treasury Regulations. Money orders or checks shall be drawn payable to: USDI-National Park Service. The NPS prefers contractor submit the payment bond via Standard Form 25A.

Upon receipt of the bid guarantee and performance and payment bonds, Contracting Officer is required to verify the surety (bonding company) is listed on the Dept. of Treasury’s approved list of sureties for the payment bond to be acceptable. DOT’s approved list of sureties is available at https://www.fiscal.treasury.gov/surety-bonds/list-certified-companies.html

H.3 Preconstruction Conference

The Contracting Officer will conduct a preconstruction conference. The Contracting Officer’s notification will include specific details regarding the date, time, and whether conference call line or via Microsoft Teams, any need for attendance by subcontractors, and information regarding the items to be discussed. Preconstruction Conference is also addressed in

Attachment no. 4, Specifications.

H.4 DIAR 1452.228-70 Liability Insurance—Department of the Interior (JUL 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer.

The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$200,000 each person

$500,000 each occurrence

$ 20,000 property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.

(c) The Contractor shall also maintain compensation insurance for employees engaged in the work, complying with the worker's compensation laws of the State in which the work is to be performed, and furnish evidence of such coverage to the Contracting Officer at the same time as the liability insurance certificate.

H.5 Archeological Findings

Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the

Government. Should Contractor's operations uncover or his employees find any archeological remains, Contractor shall follow the protocols in Attachment 3, Inadvertent Discovery Plan; suspend operations at the site of discovery; notify

Contracting Officer immediately of the findings; and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, s/he will be compensated by an equitable adjustment under the General Provisions of the Contract.

H.6 Conduct of Operations

At all times the Contractor shall conduct their organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. The park compendium is available at https://www.nps.gov/olym/learn/management/superintendent-s-compendium.htm; this document will be updated in early 2022; the contractor must comply with the compendium in effect at the time.

The playing of radios, cassette recorders, etc., is prohibited on site or in buildings. Rowdy and disruptive behavior or sexual harassment by contractor’s employees will not be tolerated; individuals failing to comply will be removed from the site. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with prior approval of the Contracting Officer. Work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer.

H.7 Interpretations of Contract: Notice of Ambiguities

This written contract and any and all identified writings or documents incorporated by reference herein or physically attached hereto constitute the parties' complete agreement and no other prior or contemporaneous agreements either written or oral shall be considered to change, modify, or contradict it. Any ambiguity in the contract will not be strictly construed against the drafter of the contract language but shall be resolved by applying the most reasonable interpretation under the circumstances, giving full consideration to the intentions of the parties at the time of contracting.

It is the Contractor’s obligation to exercise due diligence to discover and to bring to the attention of the Contracting

Officer at the earliest possible time any ambiguities, discrepancies, inconsistencies, or conflicts in or between the specifications and the applicable drawings or other documents incorporated. Failure to comply with such obligation shall be deemed a waiver and release of any and all claims for extra costs or delay arising out of such ambiguities, discrepancies, inconsistencies, and conflicts.

SECTION I: Contract Clauses

52.203-19 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or

Statements (JAN 2017)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUN 2020)

52.204-13 System for Award Management Maintenance. (OCT 2018)

52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020)

52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021)

52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

(NOV 2021)

52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) [only applies if award is $3,000 or more]

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

52.219-6 Notice of Total Small Business Set-Aside (NOV 2020)

52.219-28 Post-Award Small Business Program Re-representation. (SEP 2021)

52.222-3 Convict Labor. (JUN 2003)

52.222-6 Construction Wage Rate Requirements (AUG 2018)

52.222-7 Withholding of Funds. (MAY 2014)

52.222-8 Payrolls and Basic Records. (JUL 2021)

52.222-9 Apprentices and Trainees. (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)

52.222-11 Subcontracts (Labor Standards). (MAY 2014)

52.222-12 Contract Termination - Debarment. (MAY 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

52.222-15 Certification of Eligibility. (MAY 2014)

52.222-21 Prohibition of Segregated Facilities. (APR 2015)

52.222-26 Equal Opportunity. (SEP 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)

52.222-36 Equal Opportunity for Workers with Disabilities (JUN 2020) [only applies if award is $15,000 or more]

52.222-50 Combating Trafficking in Persons. (NOV 2021)

52.222-55 Minimum Wages Under Executive Order 13658 (JAN 2022)

52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017)

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. (SEP 2013)

52.223-3, Alt. 1 Hazardous Material Identification and Material Safety Data (FEB 2021), Alternate 1 (JUL 1995)

52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)

52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items. (MAY 2008)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts. (MAY 2008)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (JUN 2020)

52.225-9 Buy American–Construction Materials. Buy American–Construction Materials (NOV 2021)

52.225-13 Restrictions on Certain Foreign Purchases. (FEB 2021)

52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007)

52.228-5 Insurance-Work on a Government Installation (JAN 1997)

52.228-2 Addition Bond Security (OCT 1997) [refer to Section H.2, Payment Bond, required after award in 100% amount of awarded contract price. Performance bond not required for contracts awarded less than $150,000.]

52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022)

52.228-13 Alternative Payment Protections (JUL 2000) [refer to H.2, Payment Bond. NPS prefers contractor submit the

Payment Bond on SF-25A.]

52.228-14 Irrevocable Letter of Credit (NOV 2014)

52.232-5 Payments under Fixed-Price Construction Contracts. (JUN 2020)

52.232-23 Assignment of Claims. (MAY 2014)

52.232-27 Prompt Payment for Construction Contracts. (JAN 2017)

52.232-33 Payment by Electronic Funds Transfer-System for Award Management (OCT 2018)

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (NOV 2021)

52.233-1 Disputes (MAY 2014) Alternate 1 (DEC 1991)

52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

52.236-2 Differing Site Conditions. (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)

52.236-5 Material and Workmanship. (APR 1984)

52.236-6 Superintendence by the Contractor. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984)

52.236-11 Use and Possession Prior to Completion. (APR 1984)

52.236-12 Cleaning Up. (APR 1984)

52.236-13 Accident Prevention (NOV 1991)

52.236-14 Availability and Use of Utility Services. (APR 1984)

52.236-17 Layout of Work. (APR 1984)

52.236-21 Specifications and Drawings for Construction. (FEB 1997)

52.236-26 Preconstruction Conference (FEB 1995)

52.243-5 Changes and Changed Conditions. (APR 1984)

52.244-6 Subcontracts for Commercial Items. (JAN 2022)

52.246-21 Warranty of Construction. (MAR 1994) - Alternate I (APR 1984)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (short form). (APR 1984)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

52.252-6 Authorized Deviations in Clauses (APR 1984) (b) Department of the Interior (48 CFR 14)

52.253-1 Computer Generated Forms. (JAN 1991)

1452.215-70 Examination of Records by the Department of the Interior (APR 1984)

1452.203-70 Restriction on Endorsements (JUL 1996)

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205-1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

1452.204-70 Release of Claims (JUL 1996)

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

1452.236-70 Prohibition Against Use of Lead-based Paint—Department of the Interior (JUL 1996)

Paint containing more than .06 percent by weight of lead in paint, or the equivalent measure of lead in the dried film of paint already applied, shall not be used in the construction or rehabilitation of residential structures under this contract or any resulting subcontracts.

SECTION J: List of Documents, Exhibits and Other Attachments

Reminder: Solicitation Terms, Provisions, and Clauses are included in the SF-1442 Solicitation form.

Attachment

Number Title/Description

Total

Pages

1 READ ME FIRST document 2

2 Forms to Submit with Quote 9

Department of Labor Wage Decision

no. WA20230029 (2/3/23)

4 Specifications (8/22/23) 31

Information and requirements stated in Sections A through J above, apply to this solicitation and the subsequent contract.

Sections K through M below, apply to the solicitation only.

SECTION K -- Representations, Certifications and Other Statements of Offerors

K.1 52.204-16 Commercial and Government Entity Code Reporting (AUG 2020)

K.2 52.204-08, Annual Representations and Certifications (MAR 2020) This provision is provided in full text in

Attachment 2, Forms to Submit with Quote. Quoter is required to fill in paragraph (b) items (i) and (ii).

K.3 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or

Equipment (NOV 2021) This provision is provided in full text in Attachment no. 2, Forms to Submit with

Quote. Quoter shall refer to the full text provision, specifically paragraph (d), items (1) and (2).

52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference in Sections K and L with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available.

The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at these addresses:

• Federal Acquisition Regulation (FAR) https://www.acquisition.gov/far https://www.acquisition.gov/far

SECTION L: Instructions, Conditions, and Notices to Offerors (Quoters)

L.1 INQUIRIES

a) To ensure questions are adequately addressed and appropriate action taken prior to submission of quote, questions must be received no later than 2:00 pm (PDT) on September 6, 2023. Questions and/or comments received after this time may or may not be addressed prior to the solicitation closing date. Note:

Amendment(s) to the solicitation answering any questions relative to these documents will be timely posted at SAM.gov. Send written inquiries to phaedra_fuller@nps.gov. Please reference solicitation number

140P8323Q0043 in the subject line of emailed questions.

b) “Or Equal” product requests: The Government's evaluation of requests to substitute specified products will be made after contract award as part of the submittal review process (reference FAR clause 52.236-5).

L.2 SITE VISIT

a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions

Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, quoters are urged and expected to inspect the site where the work will be performed and the logistics associated with the site.

b) An organized pre-quote site visit will not be scheduled. We believe sufficient project description, site location, sample foundation photos are in the Specifications for interested parties to make their own individual site visits if they choose. Contractors wishing to visit the site on their own should give project point of contact David Weaver a heads-up you’ll be in the area looking around. Contact David “Dave”

Weaver at mobile number 360-461-2695 or send email beforehand to David_W_Weaver@nps.gov, cc:

Phaedra_Fuller@nps.gov. Project site is located at Olympic National Park, Kalaloch Campground, U.S.

Highway 101, Forks, WA 98331. Specifications include site map information.

L.3 QUOTE CONTENTS – What to Include in Quote

(a) The quote should include documents listed below.

1. Standard Form 1442, Solicitation, Offer, and Award, (Construction, Alteration, or Repair): Complete

Blocks 14 through 20C only. An official having the authority to contractually bind the Quoter's company must sign the SF1442 in accordance with the procedures prescribed in FAR 4.102 (FAR 4.102 Contractor Signature

Acquisition.GOV).

2. Acknowledgement all Amendments. Offerors may acknowledge any amendments issued by fill in Block 19 on the SF-1442. Offeror may also submit the SF-30 Amendment form(s) so long as Offeror fills in blocks 8 (business name/address/SAM.gov EUI Number), 15A, 15B, and 15C.

3. Fill in all sections of attachment no. 2, Forms to Submit with Quote:

a) Price schedule – fill in pricing on all line items

b) FAR Representation 52.204-08 – see paragraph (a), items (2) (i) and (ii)

c) FAR Representation 52.204-24 – see paragraph (d), items (1) and (2)

d) Respond to evaluation factors in Section M.2, below.

mailto:phaedra_fuller@nps.gov mailto:David_W_Weaver@nps.gov https://www.acquisition.gov/far/part-4#FAR_4_102 https://www.acquisition.gov/far/part-4#FAR_4_102

4. Small Business Program Rerepresentation. In accordance with the clause 52.219-28 incorporated by reference in Section I.1 above, in Attachment 2, Forms to Submit with Proposal, fill in the small business rerepresentation only if quoter does not have a representation in their SAM Reps/Certs for the NAICS code applicable to this solicitation (fill in if quoter does not have NAICS 238110 as part of their online Reps/Certs in SAM.gov at time of submitting quote).

(b) Prior to the solicitation closing date and time the prime contractor’s (quoter’s) SAM registration status must be

“Active” at www.SAM.gov which means Quoter’s SAM.gov registration status must be current, not shown as

“expired” or “pending.”

(c) By submission of a quote, the Contractor (Quoter) certifies that neither it, nor any person or firm who has an interest in the Contractor's firm, is a person or firm ineligible to be awarded Government contracts by virtue of being suspended or debarred in accordance with FAR Subpart 9.4 (Part 9 - Contractor Qualifications | Acquisition.GOV)

L.4 SUBMITTING YOUR QUOTE

Submit one PDF file in which the items listed above are combined. If necessary, you may submit separate files in

Microsoft Word, Excel, or PDF format only and indicate in the subject line of each email sent the solicitation number.

Email quote to Phaedra_Fuller@nps.gov. Each email sent must not include attachments larger than 20MB in size due to system limitations.

L.5 52.216 Type of Contract (APR 1984)

The Government contemplates award of one firm fixed-price contract resulting from this solicitation.

L.6 FAR Provisions Incorporated by Reference

52.204-16 Commercial and Government Entity Code Reporting (AUG 2020)

52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020)

52.215-1 Instructions to Offerors—Competitive Acquisition (NOV 2021)

52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (MAY 2014)

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction

(FEB 1999) [The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are: (1) Goals for Minority Participation for Each Trade is 6.1% and (2) Goals for Female Participation for Each Trade: 6.9%)]

52.225-10 Notice of Buy American Act Requirement - Construction Materials. (MAY 2014) http://www.sam.gov/ https://www.acquisition.gov/far/part-9#FAR_Subpart_9_4 mailto:Phaedra_Fuller@nps.gov

SECTION M: Evaluation Factors for Award

(a) Evaluation is an assessment of the quote and of the quoter's ability to perform the prospective contract successfully.

Evaluation and award will be conducted using the simplified acquisition procedures described in FAR Part 13 and will be based solely on the quote and its associated documents. Review instructions above to ensure quote is complete.

(b) The Government will award a single firm-fixed-price contract resulting from this solicitation to the responsible quoter whose quote conforming to the solicitation represents the best value to the Government, price and other factors considered.

(c) The following factors will be used to evaluate each quote. When combined, the non-price factors are approximately equal to price.

1. Price. NPS will perform a price evaluation to determine the reasonableness of the quoted price.

Reasonableness will be determined considering other competitive prices received and comparison to the independent Government estimate (IGE) or to any other information the Contracting Officer deems useful in their discretion. The Government will look at whether a quoted price is too high, possibly indicative of capabilities that exceed those needed for successful performance of the work; and may also consider whether a quoted price is too low, since this may indicate a lack of technical understanding on the quoter's part or a performance risk associated with the quote that the agency may not be willing to accept.

2. Technical capability

a. Experience. This factor includes an assessment of the Quoter’s relevant experience, because it is an opportunity to learn about performance methods, problems, and solutions by having done the same or similar work in the recent past. The quoter’s relevant experience can be their direct participation as a prime contractor or subcontractor. Quoter shall have at least three years or more of experience constructing slab foundations for buildings. Use the Relevant Experience template provided in

Attachment 2, Forms to Submit with Quote to document relevant experience (use one form per project).

b. Approach/Work Plan. Quoter shall demonstrate that the work can be accomplished in accordance to the project specifications by providing a written work plan that explains their approach to the project, sequence of the work, and provide a project schedule that shows all tasks/phases of the project scheduled out. Having a written approach/work plan and project schedule will assist the Government in evaluating your quote to determine your understanding of the project as specified.

3. Past Performance of the quoter on projects similar in scope and complexity. This measures the degree to which a [sub]contractor has satisfied its customers in the past and is a measure of quality (e.g. Did the firm complete previous jobs timely? With a high level of quality and in accordance with the specifications? Did they manage the administrative functions well?). Based on the findings, we will assess the government’s confidence for each quoter to successfully perform the contract requirements. Each project on which past performance information is collected will be rated for recency and relevance. Past performance information for projects that are more recent and/or more relevant will receive more weight in the confidence assessment. The Government may contact sources listed by the quoter and/or other sources of information including, but not limited to, Federal, State and Local governments, better business bureaus, published media, and electronic databases to verify the information provided in the quote. References provided in your Relevant Experience forms may be contacted.