Sol_140P1325Q0035.pdf

PDF 496 KB Posted

Attached to
WACO Rehabilitate Amphitheater Expansion & Repoint
Solicitation number
140P1325Q0035
Issued by

About this file

This is a Request for Quote (RFQ) for a construction project to rehabilitate the amphitheater at Waco Mammoth National Monument in Waco, Texas. The National Park Service seeks a contractor to perform amphitheater expansion and repointing work, including adding approximately 10-15 linear feet of limestone seating, repointing existing mortar joints, extending concrete walking surfaces, and installing a limestone curb. The project requires a stone mason with a minimum of 5 years' experience and will be awarded as a firm fixed-price contract.

Key requirements include repointing approximately 50% of limestone walls and 75% of amphitheater seating joints using Type N mortar, extending exposed aggregate concrete surfaces by 161 square feet, and ensuring Americans with Disabilities Act (ABAAS) compliance. The total project magnitude is between $25,000 and $100,000, with a performance period from July 17, 2025 to October 15, 2025. Quotes are due by June 23, 2025, with a site visit scheduled for May 28, 2025. Award will be based on best value considering price, technical capability, and past performance, with a 90-calendar day quote validity period.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0044007257

NPS, IMR - Santa Fe MABO

1100 Old Santa Fe Trail Building

P.O. Box 728 Santa Fe NM 87505

PIS

Brian Dankmeyer 2025735697

105/22/2025

140P1325Q0035

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

B08 Attachment 1 Bid Schedule-Repoint-Modify Amphitheater

B08 Attachment 2 308925 WACO - AMPHITHEATER PLAN AND DETAILS FINAL updated

B08 Attachment 3 DOL WD TX20250260 5.16.2025

B08 Attachment 4 CM16-Submittal Form

B08 Attachment 5 FACTS Sheet WACO Rehab Amphitheater

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 90 calendar days and complete it within ________________ ________________ calendar days after receiving

52.211-10

06/23/2025

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

NPS, IMR - Santa Fe MABO 1100 Old Santa Fe Trail Building

P.O. Box 728 Santa Fe NM 87505

PIS

Brian Dankmeyer

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 43

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140P1325Q0035

The government anticipates awarding a firm fixed-price purchase order as a result of this solicitation.

Delivery: 90 Days After Notice to Proceed

Delivery Location Code: 0011286314

NPS, Waco Mammoth National Monument

6220 Steinbeck Bend Road

Waco TX 76708 US

Period of Performance: 07/17/2025 to 10/15/2025

00010 Amphitheater Rehab

Product/Service Code: Z2QA

Product/Service Description: REPAIR OR ALTERATION

OF RESTORATION OF REAL PROPERTY (PUBLIC OR

PRIVATE)

POC

CO: Brian Dankmeyer, brian_dankmeyer@nps.gov

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED

140P1325Q0035

PAGE OF

4 | 43

Part I – The Schedule

SECTION B – Price/Bid Schedule

The contractor shall complete and submit Attachment 1 Bid Schedule as their quote, which shall be valid for a minimum of 90-calendar days.

In accordance with FAR 36.204 Disclosure of the magnitude of construction projects, the magnitude for this project is between: $25,000 and $100,000.

SECTION C – Description/Specifications/Statement of Work

WACO Amphitheater Expansion and Repointing PMIS: 308925

Waco Mammoth National Monument

1.0 GENERAL

This project is located at Waco Mammoth National Monument (WACO), in Waco, TX. The entrance to the park is south off Steinbeck Bend Road where the entry road leads to the Visitor Center and parking lot. To access the Amphitheater for construction, continue past the visitor center along the entry road to the Amphitheater rehabilitation project site (See Site Map). One parking space will be allowed on the north side of the park entry road across from the Dig Shelter and a portion of the visitor parking lot can be used as staging. Potable water, cell service and restrooms will not be provided during the duration of the construction project. This project requires a stone mason with a minimum of 5-years of experience. The prime contractor may employee the stone mason or subcontract with a stone mason that meets the minimum requirement.

2.0 PROJECT DESCRIPTION / SUMMARY: PMIS: 308925 – WACO

The project site is located southeast of the WACO Mammoth National Monument Dig shelter. Access to the shelter shall be limited during the entire construction period of this project and the contractor shall be responsible

AMPHITHEATER

R

AMPHITHEATER

AMPHITHEATER

(PMIS 308925)

Staging Area ~40’x40’

Site Visit Meeting Location https://www.nps.gov/waco/index.htm

140P1325Q0035

PAGE OF

5 | 43 for coordinating and rerouting the flow of pedestrian traffic with input from the COR. The contractor shall provide all signs and barriers that will clearly inform visitors how to navigate the construction site safely.

This project will add approximately 10 to 15 linear feet of seating to the existing 3-feet high limestone seat wall.

This work includes repointing the entire seat wall as over half of the mortared joints are failing. The mortar shall be Type N and a color additive shall be used to match and blend with existing limestone steps. The contractor shall submit a mock-up to be inspected and approved by the COR before ordering and repointing begins. This project will also extend the existing concrete amphitheater walking surface area to the north and south with approximately 161 S.F. of exposed aggregate concrete. The new concrete shall match the exposed aggregate of the existing adjacent concrete paving surface for both the amphitheater and the sidewalk. The finish of the concrete shall be exposed aggregate and shall match in color and texture the existing amphitheater and sidewalk concrete finish. Contractor shall submit a 2-feet by 2-feet mock-up panel poured and finished to be approved by the COR prior to ordering materials. The edge of the new amphitheater surface will be lined with a limestone curb (W6” x H8”-10”), which will serve as visible amphitheater edge and help retain the additional plaza fill material.

The amphitheater plaza must be reconstructed to provide access that meets the Architectural Barriers Act Accessibility Standards (ABAAS) for the major routes and facilities. This project will also include placing approximately 5 yards of crushed limestone a maximum of 3 inch in diameter with a minimum diameter of 1.5 inches around the perimeter of the amphitheater to create a visible footprint and minimize erosion. Existing vegetation shall be left undisturbed beyond the limit-of-disturbance. All vegetation adjacent to the amphitheater shall be protected at all times. Any damage to existing vegetation shall be reported to the CO immediately and all damaged vegetation shall be replaced by the contractor to the satisfaction of the COR, at no cost to the Government.

General tasks include extending exposed aggregate concrete to match existing adjacent sidewalk paving and shall be ABAAS compliant in running and cross slopes as noted on plans. The COR will verify that slopes conform with ABAAS.

All work shall be performed in a professional manner and shall carry a minimum of a 1-year workmanship warranty. This is a primary visitor use area; therefore, visitor safety and meeting ABAAS requirements is key for project success. The contractor shall be responsible for developing a construction schedule and coordinating all work with the COR so as to limit visitor impact as the Dig Shelter will remain open during construction.

2.1OBJECTIVES:

This project is intended to rehabilitate the amphitheater area by modifying the amphitheater paving surface area to minimize social trails. The amphitheater plaza shall be extended to provide access that meets the ABAAS for the major routes and facilities. The rehabilitation includes the addition of an ABAAS companion seating area.

2.2BACKGROUND:

The amphitheater was constructed in 2008. Construction was contracted by the City of WACO. In 2015 Waco Mammoth National Monument was established in partnership with the National Park Service, City of WACO, Baylor University and the Waco Mammoth Foundation, Inc. A steel post and fabric shade sail style awning were constructed in 2016. The amphitheater rests on both Federal and Waco City property and consists of a pie shaped concrete pad with two-stone step seating on the outer edge. Visitation has increased and tour groups have worn down grassy areas around the amphitheater causing erosion issues.

Work shall be conducted between the hours of 8:00 AM and 4:00 PM, Monday through Friday, and actual work dates and schedule shall be coordinated with the COR and CO at least ten (10) working days in advance.

Upon receiving Notice to Proceed, contractor shall begin work within 10 days.

140P1325Q0035

PAGE OF

6 | 43

2.3SPECIFIC WORK / TASKS:

Note: The following task list does not dictate the sequence of construction. Contractor shall determine appropriate means and methods to accomplish project objectives. The contractor is expected to visit the site to quantify and verify existing scope, measurements, and to confirm appropriate remedial action before commencement of work. Any conditions on the work site that can be detected during a site visit shall not be grounds for any modification. All work shall be completed in accordance with the SOW and Drawings.

A. Field inspections:

A site visit is strongly recommended for the purpose of determining all related scope factors and dimensional configurations that may affect work prior to quoting. Refer to the site visit clause 52.236-27 for information with regard to the site visit. Inspection and acceptance shall be validated by coordinating a walkthrough of the work with the COR.

B. Equipment and materials:

The Contractor will provide all necessary materials, personnel, equipment, and safety equipment necessary and incidental to carry out the construction contract and shall ensure that installation work is in accordance with all applicable Federal (ABAAS), State, and Local building Codes. Location of Equipment and stockpiled materials will be coordinated after award.

C. Submittals

30 Days prior to commencement of on-site work, contractor shall provide to NPS Contracting Officer’s Representative (COR) and CO the following:

Document Description Due 1 Payment Bonds 10 days after award 2 Certificate of Insurance (COI) 10 days after award 3 SF-1413 for each prime subcontractor 14 Days After Award 4 Safety/Accident Prevention Plan 14 Days After Award 5 Site Use Plan w/government input 20- Day After Award

6 Construction Schedule 1-Day after Preconstruction Meeting

7 Product, Material Data, and Mock-ups Ongoing with long lead time items first

1. Site Use Plan - with input from park staff. Staging of materials shall be limited to paved areas (to be clarified by COR during the Contractor’s site visit), and NPS resources staff will approve and mark a route that leads from the parking lot to the amphitheater to protect areas with identified artifacts (if any) prior to mobilization. Contactors will only be allowed to use this flagged route, and no materials are approved to be placed on the ground outside of the staging area and the actual worksite.

2. Safety Plan to include Weather Contingencies for any major weather event such tornados, flooding, and electrical storms typical of the area.

3. The following submittals shall be received prior to ordering with sufficient lead time to ensure no delays in construction if submittal is rejected.

a. Product data for all project components including:

i. Product Data: for each type of project listed in attached Specification 040140.62

– Stone Repointing. (See attached).

1. Mortar materials

140P1325Q0035

PAGE OF

7 | 43

2. Mortar mixes

3. Colored mortar

b. Samples: For each exposed product and for each color and texture specified. Dry samples of at least 3 colors, to be approved by the CO prior to repointing.

c. Contractor shall use CM-16 Form for all submittals.

D. Verify location of utilities.

The contractor is responsible for verifying the location and depth of any and all utilities within the work zone prior to construction commencement.

E. Site Features

Site features such as lights, shade structure support posts to remain and shall be protected in place.

F. Site Concrete

1. All trails within the project area and amphitheater paving shall be power washed so that new concrete installment is fabricated to match adjacent concrete in color and texture.

Water to perform power washing is on site and can be used by the contractor.

2. Remove existing concrete as identified on plans, haul off and dispose of legally.

3. Prepare base for new concrete with 4” compacted ¾” aggregate base per plans.

4. Contractor shall provide concrete mix psi for aggregate walking trail pavers for approval.

Contractor shall coordinate all pours with the COR so that they may be present at the time of the pour. If the concrete is defective or does not align with the color and texture of nearby surfaces, the contractor shall be responsible for replacing all defective concrete at no additional cost to the government.

5. Finish concrete surface and joints per plans. Contractor shall provide joint sealants that match the color of the finished concrete. Provide samples for COR approval prior to purchase. Install compatible backer rods as required. Acceptable sealants are the following:

a. Single-Component, Nonsag, Silicone Joint Sealant: ASTM D5893/D5893M, Type NS

b. Single-Component, Self-Leveling, Silicone Joint Sealant: ASTM D5893/D5893M, Type SL

6. Provide concrete mix design and mock-up for approval.

7. Concrete placement shall not be performed when weather is expected to be at or below

40° F or above 95° F for proper curing of the concrete. The contractor shall be responsible for monitoring and understanding local weather patterns associated with temperatures when planning and scheduling all concrete work.

G. Repointing (Type N mortaring) limestone amphitheater seating

1. Rake out and repoint joints to the following extent:

a. Limestone walls – approximately 50% of joints require repointing.

b. Amphitheater seating – approximately 75% of joints require repointing with approximately (122 LF) includes upper and lower seating.

c. Joints indicated as sealant-filled joints. Seal joints according to Section 079200 "Joint

Sealants."

d. Joints at locations of the following defects:

i. Holes and missing mortar.

ii. Cracks that can be penetrated 1/4 inch or more by a knife blade 0.027 inch thick.

140P1325Q0035

PAGE OF

8 | 43

iii. Cracks 1/8 inch or more in width and of any depth.

iv. Hollow-sounding joints when tapped by metal object.

v. Eroded surfaces 1/4 inch or more deep.

vi. Deterioration to point that mortar can be easily removed by hand, without tools.

vii. Joints filled with substances other than mortar.

2. Do not rake out and repoint joints where not required.

3. Rake out joints as follows, according to procedures demonstrated in approved mockup:

a. Remove mortar from joints to depth of 2-1/2 times joint width and not less than that required to expose sound, nonweathered mortar. Do not remove unsound mortar more than 2 inches deep; consult COR for direction.

b. Remove mortar from stone surfaces within raked-out joints to provide reveals with square backs and to expose stone for contact with pointing mortar. Brush, vacuum, or flush joints to remove dirt and loose debris.

c. Do not spall edges of stone units or widen joints. Replace or patch damaged stone units as directed by COR.

4. Notify, via email, the Contracting Officer and their Representative of unforeseen detrimental conditions including voids in mortar joints, cracks, loose stone, rotted wood, rusted metal, and other deteriorated items when discovered.

5. Pointing with Mortar:

a. Rinse joint surfaces with water to remove dust and mortar particles. Time rinsing application so, at time of pointing, joint surfaces are damp but free of standing water. If rinse water dries, dampen joint surfaces before pointing.

b. Apply pointing mortar first to areas where existing mortar was removed to depths greater than surrounding areas. Apply in layers not greater than 3/8 inch until a uniform depth is formed. Fully compact each layer and allow it to become thumbprint hard before applying next layer.

c. After deep areas have been filled to same depth as remaining joints, point joints by placing mortar in layers not greater than 3/8 inch. Fully compact each layer and allow to become thumbprint hard before applying next layer. Where existing stone has worn or rounded edges, slightly recess finished mortar surface below face of stone to avoid widened joint faces. Take care not to spread mortar beyond joint edges onto exposed stone surfaces or to featheredge the mortar.

d. When mortar is thumbprint hard, tool joints to match original appearance of joints as demonstrated in approved mockup. Remove excess mortar from edge of joint by brushing.

e. Cure mortar by maintaining in thoroughly damp condition for at least 72 consecutive hours, including weekends and holidays.

f. Hairline cracking within mortar or mortar separation at edge of a joint is unacceptable and shall be completely removed by the contractor and repointed at no additional cost to the government.

6. Where repointing work precedes cleaning of existing stone, allow mortar to harden at least 30 days before beginning of cleaning work.

7. Apply spray waterproofing membrane, to be reviewed and approved by the COR, to seal masonry work once completed.

8. Final Cleaning

a. After mortar has fully hardened, thoroughly clean exposed stone surfaces of excess mortar and foreign matter; use wood scrapers, stiff-nylon or -fiber brushes, and clean water, applied by low-pressure spray.

i. Do not use metal scrapers or brushes.

ii. Do not use acidic or alkaline cleaners.

140P1325Q0035

PAGE OF

9 | 43

H. Amphitheater Limestone Seating Modification:

1. The amphitheater shall extend to the north as shown on drawings.

2. Maintain fill slopes, and ditches within the limits of the new construction until final acceptance.

Repair damaged areas at no additional expense to the Government.

3. Do not commence earth moving operations until temporary erosion- and sedimentation-control measures are in place.

4. Do not commence earth moving operations until plant-protection measures are in place.

5. The following practices are prohibited within protection zones unless authorized by CO or COR:

a. Storage of construction materials, debris, or excavated material.

b. Parking vehicles or equipment.

c. Foot traffic.

d. Erection of sheds or structures.

e. Impoundment of water.

f. Excavation or other digging unless otherwise indicated.

6. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.

Complete clearing and grubbing. Where new material is to be placed on compacted subgrade, use roto tiller or similar to ground surface to provide bond between old and new material. Due to the culturally sensitive area, the Contractor shall notify the CO if this action will require mitigation.

Paleontological monitoring is required during excavation and installation activities associated with grading and drainage. Coordinate with COR for monitoring by paleontology and cultural resources staff during work.

3.0 GOVERNMENT FURNISHED EQUIPMENT / MATERIALS / OTHER

A. Equipment: None.

B. Materials: None.

C. Other: Drawings for reference:

1. Site Construction Drawings

SPECIAL CONDITIONS / REQUIREMENTS:

A. The Visitor Center and Dig Shelter will be open to the public during construction. Ensure safe access through existing egress doors at all times for the protection of visitors and contractor personnel.

Coordinate with COR to phase work to ensure safe egress is available at all times.

B. Contractor shall provide their own restroom facilities for staff.

C. Vehicles are to operate safely with visitors present. NPS will provide staging area for equipment storage and use on a daily basis. Staging area will not be secured by NPS at end of business day and NPS will not be responsible for any damage or loss.

D. Location of material and equipment staging shall not impede visitor use of the area. Contractor to review location with NPS for approval.

6.0 PLACE OF PERFORMANCE

A. 6220 Steinbeck Bend Dr. Waco, TX 76708 - This project is located at Waco Mammoth National Monument located 75 miles north of Austin, TX and 90 miles south of Dallas. To access the project site from Austin or Dallas, take IH 35 north from Austin or IH 35 South from Dallas to Waco, TX. The Visitor Center/Dig Shelter/Park Headquarters can be found in Waco, TX located at 6220 Steinbeck Bend Dr, Waco, TX 76708.

140P1325Q0035

PAGE OF

10 | 43

7.0 PERFORMANCE PERIOD / SCHEDULE REQUIREMENTS:

A. The construction delivery date for this project is 90-caledar days after issuance of Notice to Proceed. Mobilization and commencement of work on site shall begin 10-calendar days after Notice to Proceed.

B. Work hours: The Visitor Center is open seven days a week, 8:30am to 4:00pm. Work required beyond these hours, or on Federal holidays MUST be coordinated with park COR in writing at least 48 hours in advance.

8.0 APPENDIX A

SECTION 040140.62 - STONE REPOINTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes repointing joints with mortar.

1.2 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings.

C. Samples: For each exposed product and for each color and texture specified.

1.4 INFORMATIONAL SUBMITTALS

A. Quality-control program.

B. Mockups: Prepare mockups of stone repointing to demonstrate aesthetic effects and to set quality standards for materials and execution.

1. Repointing: Rake out joints in two separate areas each approximately 36 inches high by 48 inches wide unless otherwise indicated for each type of repointing required and repoint one of the areas.

PART 2 - PRODUCTS

2.1 MORTAR MATERIALS

A. Portland Cement: ASTM C150/C150M, Type I or Type II, except Type III may be used for cold-weather construction; white or gray, or both where required for color matching of mortar.

1. Provide cement containing not more than 0.60 percent total alkali when tested according to ASTM C114.

B. Hydrated Lime: ASTM C207, Type S.

C. Masonry Cement: ASTM C91/C91M.

D. Mortar Cement: ASTM C1329/C1329M.

E. Mortar Sand: ASTM C144.

1. Match size, texture, and gradation of existing mortar sand as closely as possible.

Blend several sands if necessary to achieve suitable match.

2. Color: Natural sand or ground marble, granite, or other sound stone of color necessary to produce required mortar color.

F. Mortar Pigments: ASTM C979/C979M, compounded for use in mortar mixes, and having a record of satisfactory performance in stone mortars.

G. Water: Potable.

2.2 MORTAR MIXES

A. Measurement and Mixing: Measure cementitious materials and sand in a dry condition by volume or equivalent weight. Do not measure by shovel; use known measure. Mix materials in a clean, mechanical batch mixer.

1. Mixing Pointing Mortar: Thoroughly mix cementitious materials and sand together before adding any water. Then mix again, adding only enough water to produce a

140P1325Q0035

PAGE OF

11 | 43 damp, unworkable mix that retains its form when pressed into a ball. Maintain mortar in this dampened condition for 15 to 30 minutes. Add remaining water in small portions until mortar reaches desired consistency. Use mortar within one hour of final mixing; do not retemper or use partially hardened material.

B. Colored Mortar: Produce mortar of color required by using specified ingredients. Do not alter specified proportions without Contracting Officer or their Representative's approval.

Park shall review and approve color before construction.

1. Mortar Pigments: Where mortar pigments are indicated, do not add pigment exceeding 10 percent by weight of the cementitious or binder materials, except for carbon black which is limited to 2 percent.

C. Do not use admixtures in mortar unless otherwise indicated.

D. Mixes: Mix mortar materials in the following proportions:

1. Pointing Mortar by Volume: ASTM C270, Proportion Specification, 1 part Portland cement, 1 part lime, and 6 parts sand. Add mortar pigments to produce mortar colors required.

PART 3 - EXECUTION

3.1 REPOINTING

A. Rake out and repoint joints to the following extent:

1. All joints in areas indicated.

2. Joints indicated as sealant-filled joints. Seal joints according to Section 079200

"Joint Sealants."

3. Joints at locations of the following defects:

a. Holes and missing mortar.

b. Cracks that can be penetrated 1/4 inch or more by a knife blade 0.027 inch thick.

c. Cracks 1/8 inch or more in width and of any depth.

d. Hollow-sounding joints when tapped by metal object.

e. Eroded surfaces 1/4 inch or more deep.

f. Deterioration to point that mortar can be easily removed by hand, without tools.

g. Joints filled with substances other than mortar.

B. Do not rake out and repoint joints where not required.

C. Rake out joints as follows, according to procedures demonstrated in approved mockup:

1. Remove mortar from joints to depth of 2-1/2 times joint width and not less than that required to expose sound, nonweathered mortar. Do not remove unsound mortar more than 2 inches deep; consult Contracting Officer or their Representative for direction.

2. Remove mortar from stone surfaces within raked-out joints to provide reveals with square backs and to expose stone for contact with pointing mortar. Brush, vacuum, or flush joints to remove dirt and loose debris.

3. Do not spall edges of stone units or widen joints. Replace or patch damaged stone units as directed by Contracting Officer or their Representative.

D. Notify Contracting Officer or their Representative of unforeseen detrimental conditions including voids in mortar joints, cracks, loose stone, rotted wood, rusted metal, and other deteriorated items.

E. Pointing with Mortar:

1. Rinse joint surfaces with water to remove dust and mortar particles. Time rinsing application so, at time of pointing, joint surfaces are damp but free of standing water. If rinse water dries, dampen joint surfaces before pointing.

2. Apply pointing mortar first to areas where existing mortar was removed to depths greater than surrounding areas. Apply in layers not greater than 3/8 inch until a uniform

140P1325Q0035

PAGE OF

12 | 43 depth is formed. Fully compact each layer and allow it to become thumbprint hard before applying next layer.

3. After deep areas have been filled to same depth as remaining joints, point joints by placing mortar in layers not greater than 3/8 inch. Fully compact each layer and allow to become thumbprint hard before applying next layer. Where existing stone has worn or rounded edges, slightly recess finished mortar surface below face of stone to avoid widened joint faces. Take care not to spread mortar beyond joint edges onto exposed stone surfaces or to featheredge the mortar.

4. When mortar is thumbprint hard, tool joints to match original appearance of joints as demonstrated in approved mockup. Remove excess mortar from edge of joint by brushing.

5. Cure mortar by maintaining in thoroughly damp condition for at least 72 consecutive hours, including weekends and holidays.

6. Hairline cracking within mortar or mortar separation at edge of a joint is unacceptable and shall be completely removed by the contractor and repointed at no additional cost to the government.

F. Where repointing work precedes cleaning of existing stone, allow mortar to harden at least 30 days before beginning cleaning work.

3.2 FINAL CLEANING

A. After mortar has fully hardened, thoroughly clean exposed stone surfaces of excess mortar and foreign matter; use wood scrapers, stiff-nylon or -fiber brushes, and clean water, applied by low-pressure spray.

1. Do not use metal scrapers or brushes.

2. Do not use acidic or alkaline cleaners.

SECTION D - Packaging and Marking

{No clauses included}

SECTION E - Inspection and Acceptance

Clauses Incorporated by Reference:

52.246-12 Inspection of Construction (AUG 1996)

SECTION F - Deliveries or Performance

Work shall be completed by a stone mason with 5-years’ experience and skilled personnel per industry standards and manufacturer specifications.

Clauses Incorporated by Reference:

52.242-14 Suspension of Work (APR 1984)

Full Text Clauses:

52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90-calendar days after receipt of Notice to Proceed. The time stated for completion shall include final cleanup of the premises.

140P1325Q0035

PAGE OF

13 | 43

(End of clause)

SECTION G - Contract Administration Data

(a) Contact Information:

The Contracting Officer administrating the Contract:

Brian Dankmeyer Contracting Officer Brian_dankmeyer@nps.gov 202-573-5697

(b) The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the event the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.

(c) Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.

(d) Any request for contract changes/modifications shall be submitted to the CO.

(e) The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items. All field changes must be approved by the CO prior to execution.

(f) All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.

FINAL PAYMENT

Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, warranty of construction, release of claims and any other documents requested by the contracting office as applicable. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.

AVAILABILITY OF UTILITIES SERVICES

Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.

UTILITIES CONSERVATION

The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.

mailto:Brian_dankmeyer@nps.gov

140P1325Q0035

PAGE OF

14 | 43

OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS

The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.

INTERIM AND FINAL INSPECTIONS

1. Prior to covering, enclosing, or hiding any of type work, the Contractor must contact the Government representative to perform an interim inspection. Failure to contact the Government representative perform an interim inspection prior to concealment may result in the Contractor being required to uncover performed work sufficiently to allow for proper inspection.

2. When ready for final inspection, the Contractor shall notify the CO and COR, requesting a final inspection in writing to the CO. The final inspection shall normally be requested a minimum of three (3) calendar days before the desired date or as otherwise negotiated with the Contracting Officer.

3. The final inspection will be onsite with the Contractor, the Contracting Officer’s Representative, and Contract Specialist/Contracting Officer (when possible).

Full Text Clauses:

1452.201-70 Authorities and Delegations (Sep 2011)

a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.

b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment. The COR for this contract will be: TBD

c) The COR is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the Disputes Clause;

(4) Terminate, for any reason, the Contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government.

d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR’s appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the

140P1325Q0035

PAGE OF

15 | 43 categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph

(e) of this clause.

e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.

f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.

g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor’s risk.

(End of Local Clause)

Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Feb 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Copy of vendor invoice document in PDF format.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

Construction Contract Administration

Federal Acquisition Regulation (FAR) 36.211(b) requires agencies provide description of policies and procedures that apply to definitization of equitable adjustments for change orders under construction contracts and data on the time required to definitize equitable adjustments for change orders under construction contracts. This information can be found at: https://www.doi.gov/pam/acquisition/policy/constructioncontract.

COMPLIANCE WITH RECENT EXECUTIVE ORDERS 14148/14208

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations, including 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals—Representation, and paragraph (t) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Agencies will not consider or use https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov https://www.doi.gov/pam/acquisition/policy/constructioncontract

140P1325Q0035

PAGE OF

16 | 43 these representations. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

SECTION H - Special Contract Requirements

PROHIBITION OF ALL TERRAIN VEHICLES (ATVS) - NPS REGIONS 6, 7, AND 8

The contractor is prohibited from utilizing All-Terrain Vehicles (ATV)s on National Park Service lands. ATV is defined as: A motorized off-highway vehicle (OHV) traveling on four or more low-pressure tires, having a seat to be straddled by the operator and a handlebar for steering control.

Use of Utility Terrain Vehicles (UTVs) are permitted. UTV (also called a side-by-side) is defined as: A motorized OHV having four or more low pressure tires, designed with side-by-side seats, seatbelts, steering wheel, and optional cab, brush cage, or ROPS.

(End of Clause)

Part II – Contract Clauses

SECTION I - Contract Clauses

52.252-2 – Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://www.acquisition.gov

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-18 Commercial and Government Entity Code Maintenance (Aug 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Nov 2021) 52.204-27 Prohibition on a ByteDance Covered Application (Jun 2023) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan 2025) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.215-8 Order of Precedence -- Uniform Contract Format (Oct 1997) 52.219-6 Notice of Total Small Business Set-Aside (Nov 2020) 52.219-28 Post-Award Small Business Program Representation (Jan 2025) 52.222-1 Notice to the Government of Labor Disputes (Feb 1997) 52.222-3 Convict Labor (June 2003) 52.222-6 Construction Wage Rate Requirements (Aug 2018) 52.222-7 Withholding of Funds (May 2014) 52.222-8 Payrolls and Basic Records (Jul 2021) 52.222-9 Apprentices and Trainees (Jul 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination-Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) http://www.acquisition.gov/

140P1325Q0035

PAGE OF

17 | 43

52.222-15 Certification of Eligibility (May 2014) 52.222-26 Equal Opportunity (Sep 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-50 Combating Trafficking in Persons (Nov 2021) 52.222-55 Minimum Wages Under Executive Order 13658 (Jan 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2022) 52.223-2 Reporting of Biobased Products Under Service and Construction Contracts (May 2024) (DEVIATION Feb 2025) 52.223-5 Pollution Prevention and Right-to-Know Information (May 2024) 52.223-10 Waste Reduction Program (May 2024) (DEVIATION Feb 2025) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (May 2024) 52.223-20 Aerosols (May 2024) 52.223-21 Foams (May 2024) 52.223-23 Sustainable Products and Services (May 2024) (DEVIATION Feb 2025) 52.225-9- Buy American–Construction Materials (Oct 2022) 52.225-13 Restriction on Certain Foreign Purchases (Feb 2021) 52.226-7 Drug-Free Workplace (May 2024) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (May 2024) 52.227-1 Authorization and Consent (Jun 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (Jun 2020) 52.227-4 Patent Indemnity- Construction Contracts (Dec 2007) 52.228-2 Additional Bond Security (Oct 1997) 52.228-11 Individual Surety - Pledges of Assets (Feb 2021)(DEVIATION May 2023) 52.228-14 Irrevocable Letter of Credit (Nov 2014) 52.229-11 Tax on Certain Foreign Procurements – Notice and Representation (Jun 2020) 52.229-12 Tax on Certain Foreign Procurements (Feb 2021) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-16 Progress Payments (Nov 2021) 52.232-23 Assignment of Claims (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer - System for Award Management (Oct 2018) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-3 Site Investigation and Conditions Affecting the Work (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-6 Superintendence by the Contractor (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-8 Other Contracts (Apr 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-10 Operations and Storage Areas (Apr 1984) 52.236-11 Use and Possession Prior to Completion (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.236-14 Availability and Use of Utility Services (Apr 1984) 52.236-17 Layout of Work (Apr 1984) 52.236-21 Specifications and Drawings for Construction (Feb 1997) 52.236-26 Preconstruction Conference (Feb 1995) 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024)

140P1325Q0035

PAGE OF

18 | 43

52.243-5 Changes and Changed Conditions (Apr 1984) 52.244-6 Subcontracts for Commercial Products and Commercial Services (Jan 2025) 52.246-21 Warranty of Construction (Mar 1994) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.253-1 Computer Generated Forms (Jan 1991)

CLAUSES INCORPORATED BY FULL TEXT

1452.203-70 -- Restrictions on Endorsements (Jul 1996)

Restriction on Endorsements—Department of the Interior

The Contractor shall not refer to contracts awarded by the Department of the Interior in commercial advertising, as defined in FAR 31.205–1, in a manner which states or implies that the product or service provided is approved or endorsed by the Government, or is considered by the Government to be superior to other products or services. This restriction is intended to avoid the appearance of preference by the Government toward any product or service. The Contractor may request the Contracting Officer to make a determination as to the propriety of promotional material.

(End of clause)

1452.204-70 -- Release of Claims – Department of Interior (Jul 1996)

Release of Claims—Department of the Interior

After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.

(End of clause)

1452.228-70 -- Liability Insurance—Department of the Interior (Jul 1996)

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$200,000.00 each person

$500,000.00 each occurrence

$500,000.00 property damage

(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect…

This is the start of the file's text. The full file is on GovTribe.