This document is a combined synopsis/solicitation for a firm fixed price commercial services contract for the Bureau of Land Management (BLM) Oregon State Office (OSO) office renovation in Portland, Oregon. The contractor will be required to reconstruct room 1305 of the Edith Green Wendell Wyatt Building, including creating workstations for visiting employees, an open-air conference room, a "situation room", and widening cubicle workspaces. The period of performance is September 13, 2024 through November 13, 2024. The procurement is unrestricted, with a NAICS code of 517810 and a small business size standard of $40.0 Million. The basis of award is the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. Responses are due by August 23, 2024 at 10:00am PDT via email.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L4324Q0178_Amd_0001.pdf | ||
| WD_2015-5563.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OSO OFFICE SPACE RENOVATION, PORTLAND, OREGON SOLICITATION NO. 140L4324Q0178
BLM STATE OFFICE Page 1 of 79
Streamlined Solicitation for Commercial Items (FAR 12.603)
Combined Synopsis/Solicitation
This is a combined synopsis/solicitation for commercial items prepared in accordance with the format in
FAR Subpart 12.6, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; proposals are being requested and a written solicitation will not be issued.
Solicitation no. 140L4324Q0178 has been issued as a Request for Quotation, for a firm fixed price commercial services contract for Oregon State Office (OSO) Office Renovation, Portland, OR, at one lump sum price. See the below schedule for item description and quantities. For services, the scope of work includes the description of all work contained below. The period of performance will be September
13, 2024-November 13, 2024.
The solicitation document and incorporated provisions and clauses are those in effect through Federal
Acquisition Circular 2024-05 effective May 22nd, 2024. The provision at 52.212-1, Instructions to
Offerors - Commercial, applies to this acquisition. The provision at 52.212-2, Evaluation - Commercial
Items, applies to this acquisition. The following factors shall be used to evaluate offers: Price. Offerors are advised to submit a completed copy of the provision at 52.212-3, Offeror Representations and
Certifications - Commercial Items, with its offer. The clause at 52.212-4, Contract Terms and Conditions
- Commercial Items, applies to this acquisition, see additional applicable clauses below. The clause at 52.212-5 Contract Terms and Conditions Required to Implement Statutes Or Executive Orders -
Commercial Items applies to this acquisition. Additional clauses and provisions are listed below. Please see Quotation Instructions in Section L of the solicitation.
This requirement is UNRESTRICTED. The NAICS code is 517810 and the small business size standard is $40.0 Million. The basis of award is the responsible offeror whose offer conforming to the solicitation will be most advantageous to the Government, price and other factors considered. Award will be made to the responsible respondent pursuant to FAR subpart 9.1. Responses shall be received via email at blm_or_so_952_mail@blm.gov and rmjones@blm.gov by the response due date and time of August 23, 2024 at 10:00am PDT.
BLM STATE OFFICE Page 2 of 79
SERVICES AND PRICES
This requirement is for one (1) Firm Fixed Price Commercial Services Contract for Oregon State Office (OSO)
Office Renovation Services, BLM State Office, Portland, OR.
BASE
Item no. Item Description Quantity Unit of
Measure
Unit Price Total
00010 AV Costs 1 Each $ $
00020 Office Remodel 1 Each $ $
GRAND TOTAL $
PERIOD OF PERFORMANCE: See Deliveries or Performance section.
(End of Supplies/Services and Prices/Costs)
BLM STATE OFFICE Page 3 of 79
STATEMENT OF WORK
1.0 GENERAL
1.1 Description of The Work
This work consists of reconstructing room 1305 of the Edith Green Wendell Wyatt Building, located in Portland, Oregon.
The reconstruction of room 1305 will consist of four main parts.
1. To create employee workstations for visiting employees.
2. To create an open-air conference room for large meetings.
3. To create a “situation room.”
4. To widen cubicle workspaces and remove old/unused furniture.
1.2 Period of Performance
Period of performance is September 13, 2024 through November 13, 2024.
1.3 Location
Work shall be performed at the Bureau of Land Management Oregon State Office, Fire and Aviation Office. Located in the Edith Green Wendell Wyatt Building at 1220 SW 3rd Avenue, Portland, OR 97204, on the 13 th floor.
2.0 SPECIFIC TASKS
Contractor shall use freight elevator when performing all tasking. Underground parking will be arranged for the contractor prior to the start of performance.
All furniture supplied as a part of this contract shall be consistent in design and look as the existing furniture within the workspace.
2.1 Create Employee Workstations:
• Supply and install large retaining wall to be situated behind the workstations by using existing cubicle walls, separating the cubicles and the workstations/conference room.
• The retaining wall is a large wall separating the four work cubicles and the newly remodeled area. It’s to keep sound down and to separate the new conference room from the old cubicles on the far side of the wall.
• New Furniture to be supplied and installed: Workstations will be four round chairs with personal U-shape laptop desks, one corner L-shape couch with coffee table, two ottomans, one round end table
• Contractor shall dismantle two cubicles that are in this area presently. The cubicle furniture, as well as two raising desks and five cabinets, will be taken away by the contractor and disposed of.
2.2 Open Air Conference Room:
• The contractor shall supply and resituate furniture in this space with the end result being, a large conference room table with electrical plugs, and ten chairs around table. The existing furniture will not be used.
• The conference room is open-air, that the contractor will not need to construct additional walls in this area. The table shall have electrical plugs and the cables will be running to existing outlets and then covered. Additional cabling into the floors and walls is not required.
• New Furniture to be supplied: Large conference table, aprox. 10 feet by 4 feet, and ten swivel chairs.
2.3 Create Situation Room:
BLM STATE OFFICE Page 4 of 79
• The contractor shall supply and install three 65” monitors, as well as all required wiring, cabling, peripherals, and hardware needed to install, for real-time fire monitoring and conference capabilities.
HDMI connections will be provided to each display. This will require drilling into the existing walls.
• Contractor shall move three electrical plugs behind the monitors, and mounting brackets on the walls will be added as part of the monitor installation. This will require moving existing wiring to the new plug locations.
2.4 Furniture Removal and Cubicle changes:
• Contractor shall widen the cubicles against the north wall. This will require moving the printer to the side near the interior conference room. The printer must be in working condition following the widening of the cubicles.
3.0 CONTRACTOR FURNISHED ITEMS
Contractor shall provide all equipment needed to complete the tasking above. See Section 2.0 for tasks that will utilize existing stock and will not require purchase. The Contractor shall provide all labor, and supervision necessary to perform the requirements of this contract.
Contractor must provide written acknowledgement from Steelcase Corporation that acknowledges your firm as being authorized to dissemble, transport, and reassemble furniture systems without voiding Steelcase’s warranty on furniture systems.
4.0 ACCESS
In the event of a site/facility closure, the Contractor shall not perform or make deliveries to the site/facility until it is reopened by the Government, unless otherwise instructed by the Contracting Officer or their designated representative.
5.0 SECURITY
5.1 Personal Identity Verification (PIV) Cards
The Contractor and its employees shall be issued individual temporary Government PIV cards authorizing access to the BLM Oregon State Office identified in this Contract. Coordinate with COR following contract award for PIV process. Upon the loss or removal of an employee, whether permanent or temporary, the Contractor shall retain that employee’s Government PIV card and submit it to the COR within seven (7) calendar days of the personnel action.
For temporary changes in force, Government PIV cards submitted to the COR will remain on file with the COR until the Contractor submits to the COR a written notice of employee reinstatement and the employee roster revision.
5.2 Employee Roster
Contractor shall submit to the COR a roster of all employees performing the work under this Contract. Within seven
(7) calendar days of any change to the Contractor’s work force (temporary or permanent), the contractor shall submit to the COR a legible revised version of the employee roster. The original and all submitted revisions shall remain on file with the COR.
Only employees named on the most current roster that the COR has on file and who are carrying valid Government
PIV cards are allowed inside the BLM Oregon State Office to perform services.
The Contractor and its employees shall solely occupy the grounds and facilities necessary to perform the requirements of this contract.
6.0 SAFETY
BLM STATE OFFICE Page 5 of 79
6.1 Equipment
Contractor’s equipment shall be rated for commercial application, listed with Underwriter Laboratories (UL) where applicable, and acceptable for use by industry standards for public and commercial settings. Electrical equipment shall operate without requiring or causing any changes or disruptions to existing building(s) electrical service. It shall be the responsibility of the Contractor to prevent such occurrences while performing work under this Contract.
7.0 GOVERNMENT FURNISHED PROPERTY AND SERVICES
7.1 Furniture
Minimal amounts of furniture are within the space and will be provided to the contractor to aid in performance of this contract:
• Existing cubicle retaining walls removed as part of Section 2.1 can be reutilized as needed.
• Cubicles identified within section 2.4 are presently in the space and will be reconfigured per the statement of work.
(End of Statement of Work)
BLM STATE OFFICE Page 6 of 79
INSPECTION AND ACCEPTANCE
The following clause is incorporated by reference:
Clause Title Date
52.246-1 CONTRACTOR INSPECTION REQUIREMENTS APR 1984
(End of Inspection and Acceptance)
BLM STATE OFFICE Page 7 of 79
DELIVERIES OR PERFORMANCE
F.1.0 PERIOD OF PERFORMANCE
The contract shall commence from September 13, 2024 through November 13, 2024.
F.2.0 PROGRESS PLAN
At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.
The following clause is incorporated by reference:
52.242-15 STOP WORK ORDER AUG 1989
The following clauses are provided in full text:
(End of Deliveries or Performance)
BLM STATE OFFICE Page 8 of 79
CONTRACT ADMINISTRATION DATA
The following local clauses are provided in full text:
CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (JULY 2010)
(a) FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The
Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System
(CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR42.15.
(b) The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available for Government use in evaluating past performance as part of a source selection action.
(c) We request that you furnish the Contracting Officer with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official. The report information must be protected as source selection sensitive information not releasable to the public.
(d) When your Contractor Representative(s) (Past Performance Points of Contact) are registered in CPARS, they will receive an automatically-generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/. The CPARS
User Manual, registration for On Line Training for Contractor Representatives, and a practice application may be found at this site.
(e) Within 60 days after the end of a performance period, the Contracting Officer will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/. Contractor
Representatives may then provide comments in response to the evaluation, or return the evaluation without comment. Comments are limited to the space provided in Block 22. Your comments should focus on objective facts in the Assessing Official's narrative and should provide your views on the causes and ramifications of the assessed performance. In addition to the ratings and supporting narratives, blocks 1 - 17 should be reviewed for accuracy, as these include key fields that will be used by the Government to identify your firm in future source selection actions. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating ''No comment" in Block 22, and then signing and dating Block 23 of the form. Without a statement in Block 22, you will be unable to sign and submit the evaluation back to the Government. If you do not sign and submit the CPAR within 30 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment." Your response is due within 30 calendar days after receipt of the CPAR.
(f) The following guidelines apply concerning your use of the past performance evaluation:
(1) Protect the evaluation as "source selection information." After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the Contracting Officer for instructions.
https://www.cpars.gov/
BLM STATE OFFICE Page 9 of 79
(2) Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
(3) Prohibit the use of or reference to evaluation data for advertising, promotional material, preaward surveys, responsibility determinations, production readiness reviews, or other similar purposes.
(g) If you wish to discuss a past performance evaluation, you should request a meeting in writing to the
Contracting Officer no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 30- day review period.
(h) A copy of the completed past performance evaluation will be available in CPARS for your viewing and for
Government use supporting source selection actions after it has been finalized.
(End of clause)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)
(APR 2013)
Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice
Processing Platform System (IPP).
“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable
Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions –
Commercial Products and Commercial Services included in commercial products and commercial services contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice billed according to contract line items and rates.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The
Contractor Government Business Point of Contract (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) prior to the contract award date, but no more than 3 – 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP
Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the
Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
(End of Contract Administration Data) https://www.ipp.gov/ mailto:ippgroup@bos.frb.org
BLM STATE OFFICE Page 10 of 79
SPECIAL CONTRACT REQUIREMENTS
1.0 ACCESS
In the event of a site/facility closure, the Contractor shall not perform or make deliveries to the site/facility until it is reopened by the Government, unless otherwise instructed by the Contracting Officer or their designated representative.
2.0 WORK HOURS
Unless otherwise specified in Section C, Specifications, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be done on Saturday, Sunday, or Federal holidays unless authorized by the COR.
3.0 ENVIRONMENTAL INTERRUPTION OF WORK
3.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. An allowance has been included in the contract time for all environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger. The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration.
3.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species
Act of 1973, as amended, or Federal candidate (Category 1 and 2), sensitive or state listed species, identified under BLM Manual 6840, are discovered to be present in or adjacent to the project area.
4.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
4.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data (including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.
4.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the
Contracting Officer immediately in writing giving the location and nature of the findings.
4.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in the Contract
Clauses Section of this contract.
4.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.
5.0 ENVIRONMENTAL IMPACT
All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13
October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control
Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ);
the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control
Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16
BLM STATE OFFICE Page 11 of 79
U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the
Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the
United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the
Government for all such liability.
6.0 HAZARDOUS MATERIALS
Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.
Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR
1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.
7.0 GREEN PROCUREMENT REQUIREMENTS
In the performance of this service or construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, if applicable:
• U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.
• USDA Biobased product listings published at www.biopreferred.gov.
• Energy Star® product listings published at www.energystar.gov/products.
• FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories
Contractor shall comply with all reporting requirements stated in the applicable clause(s):
• 52.223-1 Biobased Product Certification
• 52.223-2 Reporting of Biobased Products under Service and Construction Contracts
• 52.223-4 Recovered Material Certification
• 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items
8.0 RESTORATION OF RESOURCES
8.1 Cleanup - The Contractor is responsible for cleaning up all camp and worksites before leaving the area.
Final payment or other alternative deemed feasible may be withheld until the Contractor has complied with this requirement.
8.2 Site and Access Roads – Site and public or private access roads damaged by the Contractor shall be restored to the same condition they were in at the commencement of work, at the expense of the Contractor.
http://www.epa.gov/cpg/products.htm http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories http://energy.gov/eere/femp/covered-product-categories
BLM STATE OFFICE Page 12 of 79
9.0 UNAUTHORIZED PERSONNEL
The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
10.0 OREGON FARM/FOREST LABOR CONTRACTOR'S LICENSE
If the State of Oregon requires an Oregon Farm/Forest Labor Contractor's License, then the contractor awarded this contract and all first-tier subcontractors shall be required to obtain and maintain, during the term of this contract, such a license. Contractors not having a current license will be required to furnish evidence of having obtained such license within ten (10) days after receipt of written notification of contract award. Failure to obtain, keep and maintain a current license during the term of this contract or the extension thereof shall be a basis for termination for default.
Information on obtaining this license may be obtained from:
Bureau of Labor and Industries Contact: Licensing Unit
Wage and Hour Division Telephone: (503) 373-1463
3865 Wolverine St. NE; E-1 Fax: (503) 373-7636
Salem, OR 97305-1268
11.0 FIRE DANGER SEASON
If the COR allows the Contractor to continue work during periods of declared fire danger or season, the
Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR and outlined in the attachment at the end of this section.
The following clause is provided in full text:
SECURITY REQUIREMENTS: FACILITY ACCESS and INFORMATION TECHNOLOGY (August 2016)
(a) All Contractor employees must have an "Enter on Duty" (EOD) approval issued by the Bureau
Personnel Security Office (PSO) before they begin performing work on any Bureau contract. The Contractor must ensure that all employees requesting an EOD are citizens of the United States of America, or an alien who has been lawfully admitted for permanent residence or employment (indicated by immigration status) as evidenced by
Immigration and Naturalization Service documentation and the employee must have resided in the United States for a minimum of 3 years. The EOD may be issued in advance of a completed Background Investigation and may be rescinded by the PSO at any time. However, all contractors who require network access are required to complete the identity proofing process, and must be able to obtain a successfully adjudicated National Criminal History Check
(NCHC) and National Agency Check with Inquiries (NACI) or higher to stay on the contract.
(b) Starting Work - Contractor employees with an approved EOD may begin performing unsupervised work on Bureau contracts. To remain on the contract, the Contractor employees will need a completed favorable
Background Investigation.
(c) Rescission of EOD - The PSO may rescind the EOD at any time. This may occur as the result of additional information obtained or the final results of the background investigation.
(d) Background Investigation - Contractor employees who will have unsupervised access to Bureau facilities, access to the Department of the Interior (DOI) information technology (IT) systems or DOI data, or will
BLM STATE OFFICE Page 13 of 79 develop custom applications, must have a favorably adjudicated background investigation from the Office of
Personnel Management (OPM). Existing clearances at the same or higher level are acceptable upon the PSO’s review and approval. If the employee does not already have a complete investigation, they must apply for one. The employee may begin work with an EOD, but must receive a favorable background investigation to continue working on the contract. The background investigation includes obtaining fingerprints through a USAccess Credentialing
Center for an FBI criminal history and a credit report. Once the investigation has been scheduled by OPM, the
Bureau will receive advance reports. If those reports are favorable, the Bureau PSO will issue the EOD. The type of background investigation required is based on the risk/sensitivity level designation. Citizenship requirements and guidance for determining the appropriate type of background investigation required for the designated risk/sensitivity level are contained in DOI Departmental Manual (DM) Part 441. The DM is available on the Internet at http://elips.doi.gov/app_home/index.cfm?fuseaction=home.
(e) Electronic Questionnaire for Investigations Processing (e-QIP) – The Bureau uses the e-QIP for all background investigations or reinvestigations. To initiate an investigation, the Contractor, in collaboration with the
COR, will complete an e-QIP Request Form. This request form is available through the COR. The COR will submit the completed request form to the Bureau PSO. The PSO will enter the information into e-QIP to either establish a new applicant profile or determine if an existing investigation that meets Bureau requirements is on file. The PSO will then contact the applicant to provide additional information and instructions. Generally, the Contractor is required to complete the following forms:
▪ e-QIP application (on-line)
▪ Fair Credit Release
▪ OF-306
▪ Fingerprints via USAccess Credentialing Centers
The Contractor shall complete the required background investigation forms and submit them to the PSO. The PSO shall determine if individuals meet the required background investigation standards and citizenship requirements, and then make a suitability determination. Minimum standards used in suitability determinations are contained in the
DOI Departmental Manual Part 441. The Government will pay for any background investigations required for contractor employees. If the Contractor employee’s background investigation is returned as unfavorable, the
Government reserves the right to request reimbursement of the actual costs for the investigation from the Contractor.
(f) Reinvestigation - Contractor employees occupying high risk public trust positions must be reinvestigated every 5 years. A reinvestigation may be initiated prior to the normal periodic reinvestigation schedule when an individual’s continued ability to meet the minimum background investigation standards is in question. The electronic fingerprints on file in the USAccess system will be electronically submitted to OPM for the reinvestigation. The PSO shall review the records and documentation and make the suitability determination.
(g) Disputes - In the event of a disagreement between the Contractor and the Government concerning the suitability of a particular employee to perform work under this contract, the Government has the right of final determination. Determinations under this requirement are subject to the Disputes Clause, FAR 52.233-1. Failure of the Contractor to comply with the requirements of this clause could constitute grounds for termination for default.
(h) Physical Security Requirements - DOI Access Cards.
(1) Contractor employees must have a DOI Access Card before being given unsupervised access to a Government facility.
(2) To gain unsupervised access to Government facilities, Contractor employees must present their
DOI Access Card for examination by the security guard or electronically authenticate their DOI Access Card, as required. Contractor employees must keep their DOI Access Card in a shielded card holder, and visually display the
BLM STATE OFFICE Page 14 of 79 card at all times while in the facility. Refusal or repeated neglect to display the DOI Access Card may result in limiting Contractor employee’s access to Government facilities or revoking of authorized access.
(3) When a Contractor employee is no longer working under this award, the Contractor is responsible for returning all DOI Access Cards, keys, and other Government property issued to that employee. The
Contactor shall coordinate all returns with the COR. The COR is responsible for ensuring the Contractor complies with these requirements. However, failure by the Contractor to comply with these requirements may result in the
Contractor’s liability for all costs associated with correcting any resultant breech in building security.
(i) Issuance & Maintenance - DOI Access Cards
(1) Process: To obtain a DOI Access Card the COR will use the online DOIAccess System to initiate the access request. Contractor employees will receive email notificat ions to enroll at a USAccess Credentialing Center with two forms of identification, and after adjudication, a second email notification to pick up and activate their DOI Access Card. The Contractor employee shall schedule an enrollment appointment at a USAccess center at least two weeks prior to the targeted EOD.
(2) Contractor Responsibilities: Contractor employees must complete actions in a timely manner to prepare for on-boarding and access to DOI network resources. The Contractor shall allow their personnel sufficient time to schedule and attend an enrollment appointment at the USAccess center prior to the contract start date. If the Contractor employee’s DOI Access Card becomes lost or stolen, the contractor employee shall notify the
COR immediately to request a new DOI Access Card.
(3) COR Responsibilities: The COR (or designated individual) and Contractor shall maintain a listing of all Contractor employees who received a DOI Access Card, the date the card was issued, the date the electronic certificates expire (3 years from issue date), and the date the DOI Access Card expires (5 years from issue date). If the Contractor employee’s DOI Access Card or certificates will expire before the contract is completed, the
COR (or designated individual) and Contractor is responsible for ensuring that the Contractor employee visits a
USAccess center to update certificates on the existing card or obtain a new DOI Access Card. No later than one week prior to the DOI Access Card’s certificate or card expiration, the COR (or designated individual) shall notify the Contractor that DOI Access Card actions are required. The COR (or designated individual) and the Contractor shall update their listing to reflect the new issue date, certificate expiration date and card expiration date.
(j) Information Technology Security Requirements.
(1) Training – If contractor employees require access to any DOI/IT systems, the Contractor shall ensure its employees complete all Bureau/DOI required IT security training. The Contractor’s employees shall complete this training before being granted access to Bureau/DOI data or being issued network access. The current training requirements are: (i) annual end-user IT Security Awareness, (ii) annual IT Resources Rules of Behavior, and (iii) annual Role-Based Security training for IT professionals. The Contractor shall comply with all Bureau/DOI
IT security training requirements in effect during contract performance. The COR will notify the Contractor of all
Bureau mandatory IT training. The Contractor shall submit training completion certificates to the COR for all required training. Failure to meet this training requirement may result in removal of the contractor employee from the contract. The Bureau will determine if the contractor can later return to the contract.
(2) Access to Contractor’s Facilities for IT audit purposes - The Contractor shall afford Bureau and the Department of the Interior Office of Inspector General access to the Contractor’s and subcontractors’ facilities, installations, operations, documentation, databases, and personnel used in performance of the contract.
Access shall be provided to the extent required to carry out a program of IT inspection, investigation, and audit that will safeguard against threats and hazards to the integrity, availability, and confidentiality of Government data or to the function of computer systems operated on behalf of the Government and to preserve evidence of computer crime. If the Contractor questions the Government employee’s right to access its facilities, it should contact the CO for resolution.
BLM STATE OFFICE Page 15 of 79
(3) Contractor Location - Custom software development and outsourced operations shall be located in the United States to the maximum extent practical. If such services are proposed to be performed abroad, the Contractor shall provide an acceptable security plan that addresses the mitigation of problems related to communication, control, and protecting the confidentiality, integrity, and availability of IT systems and information.
(4) Applicable Standards - The Contractor shall follow all applicable Federal, DOI, and Bureau
Bulletins, Directives, Guidelines, Manuals, Processing Standards, Memoranda, Policies and Standards; applicable
OMB Memoranda; and all current National Institute of Standards & Technology (NIST) Special Publications. To comply with Federal Acquisition Regulation Subpart 39.101(d), contractors shall use the common security configurations available from the NIST website at http://checklists.nist.gov. NIST documents are available on the internet at http://csrc.nist.gov/publications/PubsSPs.html. OMB memoranda are available on the internet at http://www.whitehouse.gov/omb/memoranda/. The Contractor shall request copies of DOI and Bureau documents by contacting the COR.
(5) Incident Reporting - The Contractor shall immediately report computer security incidents affecting Bureau/DOI data and systems in accordance with the Bureau Computer Incident Response policy. The
Contractor shall request copies of the Bureau Computer Incident Response policy by contacting the COR.
(6) Assessment and Authorization (A&A) and Continuous Monitoring.– The Contractor shall comply with Bureau policy when developing, upgrading, modifying or supporting applications and/or systems that require A&A and Continuous Monitoring. The Contractor shall request copies of Bureau A&A policy by contacting the COR. The A&A requirement does not apply when the Contractor's employees merely access data or have "read only" access.
(k) Documentation - The Contractor shall document all work performed and ensure that the appropriate
Assessment and Authorization (A&A) documents are updated to reflect the work performed and the current state of
Bureau systems and networks. The Documentation requirement does not apply when the Contractor's employees merely access data or have "read only" access.
(l) Personnel Changes, Contractor Request - The Contractor shall immediately notify the COR and PSO when an employee is reassigned or leaves the Contractor’s employment and prior to any termination. The Contractor must adhere to the Bureau or Office’s mandatory exit clearance procedure. Once the COR has been notified that a
Contractor employee is leaving the contract, the COR will initiate the exit clearance process in the DOIAccess
System and forward to the Contractor the necessary instructions and form required to be completed prior to the contractor's employee’s departure. This form must be completed by the Contractor's employee and signed by both the Contractor's employee and the COR and then forwarded to the bureau/office specific program responsible for employee, volunteer, and contractor departures.
(m) Personnel Removal, Government Request - The Government retains the right to direct the Contractor to remove any prime or subcontractor personnel, regardless of prior clearance or background investigation adjudication status, whose actions, while assigned to this contract, clearly conflict with the security interests of the
Government. The justification for the Government’s direction to remove Contractor personnel will be documented and provided to the Contractor by the CO.
(n) Subcontract Inclusion - The requirements of this clause must be incorporated into any subcontract if the subcontractor’s employee must have access to Bureau facilities.
(End of Special Contract Requirements)
BLM STATE OFFICE Page 16 of 79
CONTRACT CLAUSES
The following provision is incorporated by reference:
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
The following clauses are incorporated by reference:
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR
PERSONNEL
JAN 2011
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE AUG 2020
52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC
CORPORATIONS - REPRESENTATION
NOV 2015
52.223-10 WASTE REDUCTION PROGRAM MAY 2024
52.223-19 COMPLIANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS MAY 2011
52.232-11 EXTRAS APR 1984
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS
SUBCONTRACTORS
MAR 2023
52.242-2 PRODUCTION PROGRESS REPORTS APR 1991
52.245-1 GOVERNMENT PROPERTY SEP 2021
52.245-1 GOVERNMENT PROPERTY – ALTERNATE I APR 2012
52.245-9 USE AND CHARGES APR 2012
52.253-1 COMPUTER GENERATED FORMS JAN 1991
The following clauses are provided in full text:
52.204-21 – BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (NOV
2021)
(a) Definitions. As used in this clause—
Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public websites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on
National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures.
http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3
BLM STATE OFFICE Page 17 of 79
(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by
Executive Order 13556.
BLM STATE OFFICE Page 18 of 79
(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial products or commercial services, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.
(End of clause)
52.212-4 – CONTRACT TERMS AND CONDITIONS – COMMERCIAL PRODUCTS AND COMMERCIAL
SERVICES (NOV 2023)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights-
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to 41 U.S.C. chapter 71, Contract Disputes. Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at Federal Acquisition Regulation
(FAR) 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
https://www.acquisition.gov/far/part-52#FAR_52_233_1 https://www.acquisition.gov/far/part-52#FAR_52_202_1
BLM STATE OFFICE Page 19 of 79
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include-
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking…