This is a Request for Quotation (RFQ) for construction services issued by the Bureau of Land Management (BLM) Barstow Field Office for roofing work at the Apple Valley Fire Center in San Bernardino County, California.
The RFQ seeks quotes for the Apple Valley Fire Center Engine Bay Roofing System project, a firm fixed-price construction contract with a price range between $25,000 and $100,000. This is a small business set-aside under NAICS code 238160 with a size standard of $19.0 million. The solicitation number is 140L1226Q0028, and quotes are due by August 14, 2026 at 5:00 PM Pacific Time. A mandatory site visit is scheduled for August 4, 2026 at 10:00 AM at 18809 Central Road, Apple Valley, CA 92307, with questions due by August 7, 2026. The contract requires a 60-day delivery period following Notice to Proceed, with all work to be performed during regular business hours (7:00 AM to 5:00 PM, Monday through Friday) unless otherwise approved. The delivery term is FOB Destination.
Respondents must submit a completed Standard Form 18 with lump-sum pricing, a short cover letter with company information and responses to suspension/debarment questions, proof of California roofing licenses and certifications, experience documentation for similar projects within the last three years, a construction schedule demonstrating understanding of project execution, and a bid guarantee of 20% of the proposal price. Award will be made to the lowest-priced, technically acceptable quoter meeting all requirements. The contractor must comply with Davis-Bacon wage requirements, maintain specified liability insurance, submit invoices through the Invoice Processing Platform (IPP), and provide performance/payment bonds or alternative payment protections if the award exceeds $35,000. The contracting officer is Laurie Ehlinger (Laurie_ehlinger@ios.doi.gov), and all quotes must be submitted electronically.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L1226Q0029_Amd_0001.pdf | ||
| B03_Wage_Determination_CA20260026_05182026.pdf | ||
| B08_Attachment_1_Statement_of_Work_.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR QUOTATION
(THIS IS NOT AN ORDER)
THIS RFQ IS IS NOT A SMALL BUSINESS SET-ASIDE
15. DATE OF QUOTATION
16. SIGNER
a. NAME (Type or print)
c. TITLE (Type or print)
b. TELEPHONE
AREA CODE
NUMBER
STANDARD FORM 18 (REV. 6/1995)
Prescribed by GSA-FAR (48 CFR) 53.215-1(a)
AUTHORIZED FOR LOCAL REPRODUCTION
Previous edition not usable
8. TO:
b. COMPANYa. NAME
c. STREET ADDRESS
d. CITY e. STATE f. ZIP CODE
9. DESTINATION
a. NAME OF CONSIGNEE
b. STREET ADDRESS
d. STATE e. ZIP CODE
7. DELIVERY
FOB DESTINATION
OTHER
(See Schedule)
10. PLEASE FURNISH QUOTATIONS TO THE
ISSUING OFFICE IN BLOCK 5a ON OR BEFORE CLOSE OF BUSINESS (Date)
IMPORTANT: This is a request for information and quotations furnished are not offers. If you are unable to quote, please so indicate on this form and return it to the address in Block 5a. This request does not commit the Government to pay any costs incurred in the preparation of the submission of this quotation or to contract for supplies or service. Supplies are of domestic origin unless otherwise indicated by quoter. Any representations and/or certifications attached to this Request for Quotation must be completed by the quoter.
11. SCHEDULE (Include applicable Federal, State and local taxes)
ITEM NUMBER
(a)
SUPPLIES/SERVICES
(b)
QUANTITY
(c)
UNIT
(d)
UNIT PRICE
(e)
AMOUNT
(f)
12. DISCOUNT FOR PROMPT PAYMENT
a. 10 CALENDAR DAYS (%) b. 20 CALENDAR DAYS (%) c. 30 CALENDAR DAYS (%) d. CALENDAR DAYS
NUMBER PERCENTAGE
NOTE: Additional provisions and representations are are not attached.
13. NAME AND ADDRESS OF QUOTER
a. NAME OF QUOTER
b. STREET ADDRESS
c. COUNTY
d. CITY e. STATE f. ZIP CODE
14. SIGNATURE OF PERSON AUTHORIZED TO
SIGN QUOTATION
PAGE OF PAGES
1. REQUEST NUMBER 2. DATE ISSUED 3. REQUISITION/PURCHASE REQUEST NUMBER 4. CERT. FOR NAT. DEF.
UNDER BDSA REG. 2
AND/OR DMS REG. 1
RATING
5a. ISSUED BY 6. DELIVER BY (Date)
NAME TELEPHONE NUMBER
AREA CODE NUMBER
c. CITY
5b. FOR INFORMATION CALL (NO COLLECT CALLS)
2601 BARSTOW ROAD
BLM CA-STATE OFC BUS SVC BR (CA944)
2800 COTTAGE WAY, SUITE W-1834
SACRAMENTO CA 95825
0044042599140L1226Q0029
Laurie Ehlinger
377-3532
BLM-CA BARSTOW FIELD OFFICE
92311
07/23/2026
08/14/2026 1700 PD
60 Days After Notice to Proceed
BARSTOW
CA
SUMMARY: Apple Valley Fire Center Engine
Bay Roofing System
SUBMIT QUOTES TO:
laurie_ehlinger@ios.doi.gov
All responses to this notice must be In
Accordance With (IAW) the attached
Solicitation, Contract Clauses, Specifications, Requirements, Provisions, Terms, and Conditions.
This will be firm fixed purchase order
Include all Shipping and/or Travel costs in the current line items
Continued...
1 15
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140L1226Q0029
F.O.B. DESTINATION
00010 Apple Valley Fire Center Engine Bay Roof in accordance with the Statement of Work (SOW).
The vendor will provide a breakdown of the quote along with information from the
"quotation submittal" that is found in the solicitation.
Product/Service Code: Y1AA
Product/Service Description: CONSTRUCTION OF
OFFICE BUILDINGS
Delivery: 60 Days After Notice to Proceed
SOLICITATION NO: 140L1226Q0028
Apple Valley Fire Center Engine Bay Roofing System
Request For Quotation
This solicitation is a Request for Quotation (RFQ) using Simplified Acquisition Procedures (SAP) under FAR Part 12
Type of Contract: Construction, Firm Fixed Priced (FFP), Single Award Contract Place of Performance: San Bernardino County, CA Type of Construction: Roofing Contractors
Price Magnitude:
Between $25,000.00 and $100,000.00
NAICS:
238160
SIZE STD:
$19.0 Million
SET-ASIDE:
Small Business
Bureau of Land Management Contacts Contracting Officer (CO)
Name: Laurie Ehlinger
Email: Laurie_ehlinger@ios.doi.gov
Quote Submittal Information:
Site Visit: 08/04/2026 at 10:00 AM Pacific Time (POC: Ike Miller, imiller@blm.gov; 760-718-0640)
Questions Due Date: 08/07/20265:00 PM Pacific Time
Quote Due Date: 08/14/2026 5:00 PM Pacific Time
Award Selection Process: Lowest Price Technically Acceptable / FAR Part 12 mailto:imiller@blm.gov
GENERAL
(a) The Bureau of Land Management (BLM) is seeking quotations for construction services as attached in the accompanying project documentation (see attachments). The BLM intends to conduct this acquisition by using simplified acquisition procedures in accordance with FAR Part 12. A single contract award will be made to the responsible contractor whose quotation represents the best value in accordance with the evaluation methodology outlined in the “basis for contract award.”
(b) Solicitation documents and incorporated provisions and clauses are those in effect through Federal Acquisition Circular 2026-01 effective 03/13/2026. It is the responsibility of the contractor to be familiar with the applicable clauses and provisions. Clauses and provisions may be accessed in full text at the following websites: https:/www.acquisition.gov/far/ and https://www.acquisition.gov/diar
(c) A contract award will not be made if the resulting contract would not represent the "best value" to the government.
(d) To ensure timely and equitable evaluation of quotations, respondents are cautioned to strictly comply with all instructions within this solicitation to ensure submission of a complete quote. Respondents are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and any stated technical requirements. Failure to adhere to solicitation requirements, at the time of submission, may result in a respondent’s quote being deemed unacceptable to the government and the respondent may be eliminated from award consideration. It is the responsibility of respondents to ensure their quote is received by the government at the designated due date and time.
(e) Quoters are cautioned to submit adequate information to enable the government to fully ascertain each respondent’s capability to perform the requirements in accordance with the requirements of the request for quotation (RFQ).
(f) If a respondent believes that requirements in these instructions contain an error, omission, or are otherwise flawed, the respondent shall immediately notify the contracting officer via email with supporting rationale prior to the question deadline specified on the cover page of this document.
(g) This RFQ does not commit the government to any costs incurred during the preparation and submission of quotes or for any other costs incurred by any firm submitting a quote in response to this solicitation. Note specifically that the respondent will not be participating in a sealed bid procurement process. Issuance of this RFQ does not constitute an award commitment on behalf of the government.
(h) Quotations must be valid for a minimum of 60 days.
(i) Respondents must complete and maintain an active registration in the System for Award Management (SAM) at https://www.sam.gov/portal/public/SAM/. The government will obtain representations and certifications through this system.
(j) Award is subject to availability of funds. This project is currently funded based upon an independent cost estimate.
(k) All questions should be emailed directly to the contracting office primary POC by the deadline listed on the first page of this document. Only written RFI’s will be considered and responded to by the government. Responses to RFIs will be posted as an amendment to the solicitation. Respondents shall not contact any government personnel related to this requirement other than contracting office personnel.
(l) Depending on the value of the subsequent contract award, the awardee may be required to submit either Alternative Payment Protections or Performance/Payment Bonds. Refer to the “Post-Award Bonds and Alternative Payment Protections” requirements as outlined in the “Special Contract Requirements” section of this solicitation.
(m) This RFQ encompasses both Revolutionary FAR Overhaul (RFO, FAR Overhaul - FAR Part Deviation Guidance | Acquisition.GOV) and Federal Acquisition Regulations (FAR, FAR | Acquisition.GOV). The RFO regulations are in accordance with when the Department of Interior adopted them. Any regulations that are not referred to as RFO are still in accordance with the FAR. The purpose of the RFO is to amend the FAR to ensure that it contains only provisions that are required by statute or that are otherwise necessary to support simplicity and usability, strengthen the efficacy of the procurement system, or protect economic or national security interests (E.O. 14275).
(n) See instructions on pages 14-15 for required Quote Package Contents.
(o) This procurement is set aside for Small Business Concerns only.
Checklist for Quote Submittal:
☐ Completed Standard Form 18 ☐ Signed Amendment(s) (if issued) ☐ Technical Quote Package https://www.acquisition.gov/far/ https://www.acquisition.gov/diar https://www.sam.gov/portal/public/SAM/
CONTRACT CLAUSES
CLAUSES INCORPORATED BY REFERENCE
Clause Title Date
FAR 52.204-9 Personal Identity Verification of Contractor Personnel January 2011
RFO 52.204-13 System for Award Management Maintenance March 2026
FAR 52.204-19 Incorporation by Reference of Representations and Certifications
December 2014
RFO 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations
May 2026
RFO 52.213-4 Terms and Conditions – Simplified Acquisitions (Other Than Commercial Items)
March 2026
RFO 52.219-6 Notice of Total Small Business Set Aside Jan 2026
RFO 52.219-28 Post-Award Small Business Program Representation Jan 2026 RFO 52.222-6 Construction Wage Requirements May 2026 RFO 52.222-7 Withholding of Funds May 2026 RFO 52.222-8 Payrolls and Basic Records May 2026 RFO 52.222-9 Apprentices and Trainees May 2026 RFO 52.222-10 Compliance with Copeland Act Requirements May 2026 RFO 52.222-11 Subcontracts (Labor Standards) May 2026 FAR 52.222-12 Contract Termination-Debarment May 2014 FAR 52.222-13 Compliance with Construction Wage Rate Requirements and
Related Act Regulations May 2014
RFO 52.222-14 Disputes Concerning Labor Standards May 2026 RFO 52.222-54 Employment Eligibility Verification May 2026 RFO 52.223-2 Reporting of Biobased Products Under Service and
Construction Contracts May 2026
RFO 52.223-3 Hazardous Material Identification and Material Safety Data, Alt I
May 2026 FAR 52.223-5 Pollution Prevention and Right-to-Know Information May 2024 RFO 52.223-23 Sustainable Products May 2026
FAR 52.225-9 Buy American-Construction Materials October 2022 FAR 52.226-7 Drug-Free Workplace May 2024 FAR 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While
Driving May 2024
FAR 52.228-11 Individual Surety – Pledges of Assets February 2021
FAR 52.228-14 Irrevocable Letter of Credit November 2014 FAR 52.232-5 Payments under Fixed-Price Construction Contracts May 2014
FAR 52.232-23 Assignment of Claims May 2014
FAR 52.232-27 Prompt Payment for Construction Contracts January 2017
FAR 52.233-1, Alt 1 Disputes May 2014 December 1991
RFO 52.236-2 Differing Site Conditions Jan 2026 RFO 52.236-3 Site Investigation and Conditions Affecting the Work Jan 2026
RFO 52.236-5 Material and Workmanship Jan 2026 RFO 52.236-6 Superintendence by the Contractor Jan 2026 RFO 52.236-7 Permits and Responsibilities Jan 2026 RFO 52.236-8 Other Contracts Jan 2026 RFO 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.
Jan 2026
RFO 52.236-10 Operations and Storage Areas Jan 2026
RFO 52.236-11 Use and Possession Prior to Completion Jan 2026
RFO 52.236-12 Cleaning up Jan 2026
RFO 52.236-13 Accident Prevention Jan 2026
RFO 52.236-17 Layout of Work Jan 2026 RFO 52.236-21, Alt I Specifications and Drawings for Construction Jan 2026
FAR 52.242-14 Suspension of Work April 1984
RFO 52.243-5 Changes and Changed Conditions April 1984
RFO 52.244-6 Subcontracts for Commercial Products and Commercial Services
May 2026
FAR 52.245-1 Government Property September 2021
FAR 52.245-9 Use and Charges April 2012
FAR 52.246-21 Warranty of Construction March 1994
FAR 52.248-3 Value Engineering – Construction October 2020 FAR 52.249-1 Termination for the Convenience of the Government (Fixed
Price)(Short Form) April 1984
CLAUSES INCORPORATED BY FULL TEXT
RFO 52.222-90 Addressing DEI Discrimination by Federal Contractors (MAY 2026) (DEVIATION MAY 2026)
(a) Definitions. As used in this clause Program participation means membership or participation in, or access or admission to: training, mentoring, or leadership development programs; educational opportunities; clubs; associations; or similar opportunities that are sponsored or established by the contractor or subcontractor.
Racially discriminatory diversity, equity, and inclusion (DEI) activities means disparate treatment based on race or ethnicity in the recruitment, employment (e.g., hiring, promotions), contracting (e.g., vendor agreements), program participation, or allocation or deployment of an entity's resources.
(b) In connection with the performance of work under this contract, the Contractor agrees as follows:
(1) The Contractor will not engage in any racially discriminatory DEI activities;
(2) The Contractor will furnish all information and reports, including providing access to books, records, and accounts, as required by the Contracting Officer, for purposes of ascertaining compliance with this clause;
(3) In the event of the Contractor's or a subcontractor's noncompliance with this clause, this contract may be canceled, terminated, or suspended in whole or in part, and the Contractor or subcontractor may be declared ineligible for further Government contracts;
(4) The Contractor will report any subcontractor's known or reasonably knowable conduct that may violate this clause to the Contracting Officer and take any appropriate remedial actions directed by the Contracting Officer; and
(5) The Contractor will inform the Contracting Officer if a subcontractor sues the Contractor and the suit puts at issue, in any way, the validity of this clause.
(6) The Contractor recognizes that compliance with the requirements of this clause are material to the Government's payment decisions for purposes of 31 U.S.C. 3729(b)(4).
(c) The Contractor must include the substance of this clause, including this paragraph (c), in subcontracts at any tier, including those for commercial products and commercial services, except those where the place of delivery or performance is outside the United States.
(End of clause)
FAR 52.228-13 ALTERNATIVE PAYMENT PROTECTIONS (July 2000)
(a) The Contractor shall submit one of the following payment protections:
1) A payment bond (or)
2) An irrevocable letter of credit (ILC)
(b) The amount of the payment protection shall be 100 percent of the contract price.
(c) The submission of the payment protection is required within 10 days of contract award.
(d) The payment protection shall provide protection for the full contract performance period plus a one-year period.
(e) Except for escrow agreements and payment bonds , which provide their own protection procedures, the Contracting Officer is authorized to access funds under the payment protection when it has been alleged in writing by a supplier of labor or material that a nonpayment has occurred, and to withhold such funds pending resolution by administrative or judicial proceedings or mutual agreement of the parties.
(f) When a tripartite escrow agreement is used, the Contractor shall utilize only suppliers of labor and material that signed the escrow agreement.
(End of Clause)
FAR 52.228-15 PERFORMANCE AND PAYMENT BONDS – CONSTRUCTION (June 2020)
(a) Definitions. As used in this clause- Original contract price means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.
(b) Amount of required bonds . Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:
(1) Performance bonds ( Standard Form 25). The penal amount of performance bonds at the time of contract award shall be 100 percent of the original contract price.
(2) Payment Bonds ( Standard Form 25A). The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.
(3) Additional bond protection.
(i) The Government may require additional performance and payment bond protection if the contract price is increased. The increase in protection generally will equal 100 percent of the increase in contract price.
(ii) The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond or to obtain an additional bond.
(c) Furnishing executed bonds . The Contractor shall furnish all executed bonds , including any necessary reinsurance agreements, to the Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.
(d) Surety or other security for bonds . The bonds shall be in the form of firm commitment, supported by corporate sureties whose names appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States . Treasury Circular 570 is published in the Federal Register or may be obtained from the:
U.S. Department of the Treasury, Financial Management, Service Surety Bond Branch, 3700 East West Highway, Room 6 F01, Hyattsville, MD 20782.
Or via the internet at http://www.fms.treas.gov/c570/.
(e) Notice of subcontractor waiver of protection ( 40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.
(End of Clause)
FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (February 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address (es): http://acquisition.gov/far/index.html.
(End of Clause)
FAR 52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (November 2020)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
https://www.acquisition.gov/far/part-28#FAR_28_102_1 https://www.gsa.gov/forms-library/performance-bond https://www.gsa.gov/forms-library/payment-bond http://www.fms.treas.gov/c570/ http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 http://acquisition.gov/far/index.html
(b) The use in this solicitation or contract of any Department of Interior Acquisition Regulation (48 CFR Chapter 14) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of Clause)
DIAR 1452.201-70 AUTHORITIES AND DELEGATIONS (September 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of Clause)
DIARS 1452.228-70 LIABILITY INSURANCE - DEPARTMENT OF THE INTERIOR (July 1996)
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
Workers’ Compensation and Employer’s Liability - $100,000 General Liability - $500,000 Automobile Liability:
$200,000 per person $500,000 per occurrence for bodily injury $20,000 per occurrence property damage
(b) Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
(End of Clause)
SPECIAL CONTRACT REQUIREMENTS
WORK HOURS
The performance period established for this contract is based upon all work being conducted during regular working hours between 7:00am and 5:00pm, Monday through Friday, excluding government holidays. If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the Contracting Officer in sufficient time to allow satisfactory arrangements to be made by the Government for access to the work site and inspection. In addition to holidays declared by Executive Order, the following federal legal holidays are observed:
New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Juneteenth Day Independence Day Labor Day Columbus Day Veterans’ Day Thanksgiving Day Christmas Day
FIRE DANGER SEASON
If the Government allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the Government.
DRAWINGS
(a) Reference scope of work.
(b) Typical Drawings. Any drawings titled typical are general only and dimensions of each structure will be fixed by the contracting officer to adapt the design to existing conditions at the structure location.
(c) Reduced Size Drawings. Any drawings identified as "REDUCED SIZE DRAWINGS" appearing in the solicitation are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective offerors desiring to review a copy of the full-size drawings may contact the primary contracting office point-of-contact contracting identified in the solicitation.
PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
(a) The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
(b) If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
(c) Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.
(d) The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System
(IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice date and Government Contract Number
2. Billing period specified with beginning and ending dates. The beginning date must not be later than the completion date or within any previous billing dates.
3. The accounting must follow the approved schedule of values as described in the specification attachment.
4. Total amount due for the billing period
5. Certification of Progress Payment
6. Payrolls (Mail weekly)
7. Substantiation of Subcontractor Payment
8. 52.223-9 Certification with final payment request.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Clause)
LOCAL INTERNET PAYMENT PLATFORM (IPP) HOTLINE
To check payment status, contact the Payment Hotline at 877-480-9724 or 303-236-2850. You will need to leave a message with the following information:
1. Company Name
2. Contract Number
3. Invoice Number
4. Invoice Amount
5. A brief description of why you are calling
6. Your contact information
If you do not receive a callback from the Payment Hotline within 72 hours, please contact the Contracting Officer with the day and time you contacted the Payment Hotline.
(End of Clause)
POST-AWARD BONDS AND ALTERNATIVE PAYMENT PROTECTIONS
Quoters receiving awards valued at $35,000 or less will not be required to provide bonds or alternative payment protections. Quoters receiving awards greater than $35,000, but not greater than $150,000, will be required to submit one of the two alternative payment protections as specified in FAR 52.228-13 of this solicitation. Any quoter receiving an award in excess of $150,000 shall provide both performance and payment bonds. Bonds or alternative payment protections are the sole responsibility of the awardee and any associated costs shall be included in the quoter’s price. Equitable adjustments will not be granted for awardees failing to include bonds or alternative payment protection costs within their price. Any required bonds or alternative payment protections shall be submitted within 10 days of the contract award.
(End of Clause)
LIST OF ATTACHMENTS
Number Description Number of Pages
1 B08 Attachment 1 Statement of Work 13 2 B03 Attachment No. 2 Davis-Bacon Act WD # CA20260009 18
Construction wage rate requirements are applicable to this project. Current prevailing wage determination(s) at time of issuance of solicitation are included in this Section. Applicable wage rates can be found at sam.gov.
SOLICITATION PROVISIONS
PROVISIONS INCORPORATED BY REFERENCE
Clause Title Date
RFO 52.204-7 System for Award Management May 2026
FAR 52.214-34 Submission of Offers in the English Language April 1991
FAR 52.214-35 Submission of Offers in U.S. Currency April 1991
RFO 52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work May 2026 FAR 52.225-10 Notice of Buy American Requirement-Construction Materials May 2014 FAR 52.228-1 Bid Guarantee September 1996 FAR 52.228-17 Individual Surety – Pledge of Assets (Bid Guarantee) February 2021 DIAR 1452.215-71 Use and Disclosure of Proposal Information – Department of Interior April 1984
PROVISIONS INCORPORATED BY FULL TEXT
52.237-1 Site Visit (Apr 1984)
Offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable.
In no event shall failure to inspect the site constitute grounds for a claim after contract award.
Date: Tuesday, August 4, 2026
Time: 10:00 am Local time Meeting place: The meeting site will be Apple Valley Fire Center at: 18809
Central Rd., Apple Valley, CA 92307 BLM staff will begin the site visit at 10:00am giving access to site area needed for assessment.
Special Instructions: Project site is NOT open to public use and CANNOT be accessed at any other time. BLM Barstow Field Office staff will be present at the project site on 4 August 2026 at 10:00am for an on-site review of the project area and specifications.
Interested contractors are encouraged to attend this site visit
Point of Contact for Site Visit: Ike Miller Role/Title: BLM Barstow Field Office Civil Engineering Technician Phone: (760) 718-0640 Email: imiller@blm.gov
(End of provision)
FAR 52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this address: http://acquisition.gov/far/index.html.
(End of Provision)
FAR 52.252-5 Authorized Deviations in Provisions (Nov 2020) mailto:imiller@blm.gov http://acquisition.gov/far/index.html
(a) The use in this solicitation of any Federal Acquisition Regulation (48 CFR Chapter 1) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the provision.
(b) The use in this solicitation of any Department of the Interior Acquisition Regulation (48 CFR Chapter 14) provision with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
(End of Provision)
INSTRUCTIONS TO QUOTERS
QUOTATION SUBMITTAL
Quotes must be in accordance with and in the order detailed in this section. Quotes must be submitted via email to the contract specialist and contracting officer by the due date and time specified on the cover page of this document.
REQUIRED DOCUMENTATION
Respondents shall submit the following information in response to this RFQ:
1) Short Cover Letter:
a. Company name, address, SAM Unique Entity Identifier (UEI) number, Entity Identification number (EIN) or tax ID number, and phone number
b. Point of contact for individuals within the company (phone number and email address)
c. A statement that the quote is valid for 60 days.
d. A response to the following questions:
i. Judgments, Claims, and Lawsuits: Are there any judgments, claims, and/or lawsuits pending or outstanding against or involving entity or partners comprising your entity?
• No ___, Yes ___. If “Yes,” submit details of all judgments or claims against either parent office or division/branch that will be responsible for the accomplishment of this project on a separate sheet.
ii. Is your entity or partners comprising your entity under suspension or debarment by any Federal, state or local agency, or have been terminated on any past projects (Federal or others)?
• No ___, Yes ___. If “Yes,” submit details on a separate sheet.
2) Sign Standard Form (SF) 18, Request for Quotation. Please insert lump-sum pricing for all items listed in block 11 and complete blocks 13, 14, and 15. An official having the authority to contractually bind the quoter’s company must sign SF 18 in accordance with the procedures prescribed in the Federal Acquisition Regulation Subpart 4.102.
3) Acknowledgement of Amendments: Acknowledge all solicitation amendments (if issued by the government) by signing and returning all individual SF30s with your quote.
4) Bid Guarantee in accordance with FAR 52.228-1, “Bid Guarantee (September 1996).” Offerors shall include a digital copy within their proposal submission. Bid guarantees shall be executed on a GSA form SF24-16d, including all appropriate signatures, seals, and be in the amount of 20% of the offeror’s proposal price.
BASIS FOR CONTRACT AWARD
1) This acquisition is a Small Business set-aside under the North American Industry Classification System (NAICS) Code 238160 with a small business size standard of $19.0 Million. An offeror determined to be other than a small business will be deemed ineligible for the award.
2) The government intends to make ONE award based upon evaluation of quotes received. Award will be given to the responsible quoter whose quote conforms with all solicitation requirements to include terms and conditions, representations & certifications, technical requirements, and also provides the lowest total price.
3) The Government will evaluate evaluation for reasonableness of pricing schedule (both pay rates and methods of calculating payment and work progress). The quoter will provide a lump sum price in the solicitation line items SF18 but will also provide a breakout of their quote. A breakdown of the offer will be provided with details of pay rates, travel/lodging, materials and tasks.
4) The Government will evaluate technical acceptability in accordance with the following non-price factors:
# FACTOR ACCEPTABLE UNACCEPTABLE
1 Certification Quoter provides proof of licenses and certifications for the state of California to perform roofing project.
No information provided or information provided does not demonstrate the quoter’s licenses or certification.
2 Experience and Capability to Complete Project
Quoter provides experience working with similar types of roofing projects within the last three years. The description shall include name of agency, performance dates, point of contacts, value of project and physical location of the project.
Quotation demonstrates contractors’ ability to provide the labor and materials listed in the Scope of Work (SOW).
No information provided or information provided does not demonstrate the quoter’s capability to complete the project, e.g. project provided has no similarity to this project
3 Schedule Quoter provides the construction plan shall exhibit a clear understanding of the proposed construction project and consideration of material and labor availability. This is demonstrated by detailing the sequence and execution of work from start to completion.
No information provided or information provided does not demonstrate the quoter’s understanding of what is required to complete the project within the required timeframe.
| Request for quotations |
| Request number |
| Date issued |
| Requisition/purchase request number |
| CERT. FOR NAT. DEF. UNDER BDSA REG. 2 AND/OR DMS REG. 1 |
| Issued by |
| For information call |
| Name |
| Telephone number |
| Area code |
| number |
| Deliver by (date) |
| Delivery |
| To: |
| Name |
| Company |
| Street address |
| City |
| State |
| Zip code |
| Destination |
| Name of consignee |
| Street address |
| City |
| State |
| Zip code |
| Please furnish quotations to the issuing office in block 5a on or before close of business |
| Schedule |
| Discount for prompt payment |
| 10 calendar days (%) |
| 20 calendar days (%) |
| 30 calendar days (%) |
| Calendar days |
| Number |
| Percentage |
| Name and address of quoter |
| Name of quoter |
| Street address |
| County |
| City |
| State |
| Zip code |
| Signature of person authorized to sign quotation |
| Date of quotation |
| Signer |
| Name |
| Telephone |
| Area code |
| Number |
Title
| AUTHORIZED FOR LOCAL REPRODUCTION Previous edition not usable |
| Standard form 18 (Rev. 6/1995) |