This is a Solicitation (Standard Form 1442) for a small business set-aside construction contract for milling and paving services at the USGS Eastern Ecological Science Center in Laurel, Maryland. The U.S. Geological Survey's Reston Acquisition Branch is seeking a contractor to complete parking lot and structure milling, paving, and traffic paint application within 90 days of notice to proceed. The total contract value is estimated between $25,000 to $100,000, with NAICS code 238990 and a size standard of $19.0 million.

Key dates include the solicitation release on 07/08/2025, a mandatory site visit scheduled for 07/21/2025 at 10:00 AM Eastern Time, and written quotes due by 08/07/2025. The anticipated contract award date is 08/14/2025. Contractors must be registered in the System for Award Management (SAM) and submit quotes and questions via email to Daniel Galvin at dgalvin@usgs.gov. The evaluation will consider technical approach and past performance as equally important factors, with these non-price factors being approximately equal in importance to the proposed price.

View the file

Other files

File Type Posted
Sol_140G0125Q0145_Amd_0001.pdf PDF
QandA_140G0125Q0145_0001.pdf PDF
A2_-_Wage_Determination_20150121_3-14-25.pdf PDF
A1_-_SOW_6-13-25.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION, OFFER,

AND AWARD

2. TYPE OF SOLICITATION

6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.

PAGE OF PAGES

7. ISSUED BY CODE 8. ADDRESS OFFER TO

SOLICITATION

(Construction, Alteration, or Repair)

1. SOLICITATION NO. 3. DATE ISSUED

IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.

9.

INFORMATION CALL

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."

FOR

SEALED BID (IFB)

NEGOTIATED (RFP)

0044020091

USGS OAG RESTON ACQUISITION BRANCH

205 NATIONAL CENTER

12201 SUNRISE VALLEY DRIVE

RESTON VA 20192

GRB

Daniel Galvin 703-648-7397

107/08/2025

140G0125Q0145

INVITATION FOR BID

REQUEST FOR PROPOSAL

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)

Statement of Work (06/13/2025)

11. The Contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and is not required.is, b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

d. Offers providing less than

12b. CALENDAR DAYSYES NO

(If "YES", indicate within how many calendar days after award in Item 12b.)

10 90 calendar days and complete it within ________________ ________________ calendar days after receiving

Clause 52.211-10

08/07/2025

NSN 7540-01-155-3212

x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________

STANDARD FORM 1442 (Rev. 12/2022)

Prescribed by GSA

FAR(48 CFR) 53.236-1(d)

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than item 14.)

CODE FACILITY CODE

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGEMENT OF AMENDMENTS

OFFER (Must be fully completed by offeror)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE

BY

2PAGE OF

USGS OAG RESTON ACQUISITION BRANCH

205 NATIONAL CENTER

12201 SUNRISE VALLEY DRIVE

RESTON VA 20192

GRB

Daniel Galvin

28. NEGOTIATED AGREEMENT 29. AWARD

and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

10 U.S.C. 3204(a) 41 U.S.C. 3304(a)

STANDARD FORM 1442 (REV. 12/2022) BACK

Continued...

and return

(Contractor is not required to sign this document.) Your offer on this

ITEM NO.

(A)

SUPPLIES/SERVICES

(B)

QUANTITY

(C)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

NAME OF OFFEROR OR CONTRACTOR

3 50

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

140G0125Q0145

Delivery: 90 Days After Notice to Proceed

Delivery Location Code: 0011277197

USGS Eastern Ecological Science Ctr

12100 Beech Forest Road

Laurel MD 20708 US

00010 Milling and Paving in accordance with Attachment

1 - Statement of Work

Product/Service Code: Z2LZ

Product/Service Description: REPAIR OR ALTERATION

OF PARKING FACILITIES

For questions regarding this request for quotations (RFQ) contact Daniel (Dan) Galvin at dgalvin@usgs.gov / 703-648-7397.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

SECTION B - Supplies or Services SECTION C - Description/Specifications/Statement of Work

C.1 Statement of Work SECTION D - Packaging and Marking SECTION E - Inspection and Acceptance

E.1 52.246-12 Inspection of Construction. (AUG 1996) SECTION F - Deliveries or Performance

F.1 Deliverables F.2 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) F.3 52.236-2 Differing Site Conditions. (APR 1984) F.4 52.242-14 Suspension of Work. (APR 1984) F.5 GS0919 Legal Holidays (JUN 2021)

SECTION G - Contract Administration Data G.1 GS0231 Technical Liaison-Technical Direction (NOV 2014) G.2 GS1131 Unilateral Deobligation of Unexpended Funds (MAY 2013)

SECTION H - Special Contract Requirements H.1 GS1326 Indemnity (JUL 2001) H.2 GS1338 Notice to Government of Delays (JUL 2001) H.3 GS1346 Compliance with OSHA-Govt owned Facilities/Equipment (APR 2003) H.4 GS1348 Accident Reporting (APR 2003) H.5 GS1440 Wage Determination Applicable (JUL 2001) H.6 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (February 2021)

SECTION I - Contract Clauses I.1 52.204-13 System for Award Management Maintenance. (OCT 2018) I.2 52.204-18 Commercial and Government Entity Code Maintenance. (AUG 2020) I.3 52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014) I.4 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(NOV 2021)

I.5 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025) I.6 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015) I.7 52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Products and Commercial Services). (JAN 2025) I.8 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997) I.9 52.219-28 Postaward Small Business Program Rerepresentation. (JAN 2025) I.10 52.222-6 Construction Wage Rate Requirements. (AUG 2018) I.11 52.222-7 Withholding of Funds. (MAY 2014) I.12 52.222-8 Payrolls and Basic Records. (JUL 2021) I.13 52.222-10 Compliance With Copeland Act Requirements. (FEB 1988) I.14 52.222-11 Subcontracts (Labor Standards). (MAY 2014) I.15 52.222-12 Contract Termination - Debarment. (MAY 2014) I.16 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014) I.17 52.222-14 Disputes Concerning Labor Standards. (FEB 1988) I.18 52.222-15 Certification of Eligibility. (MAY 2014) I.19 52.223-3 Hazardous Material Identification and Material Safety Data. (FEB 2021) - Alternate I (JUL 1995) I.20 52.225-9 Buy American - Construction Materials. (OCT 2022) I.21 52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007) I.22 52.228-2 Additional Bond Security. (OCT 1997) I.23 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) I.24 52.228-11 Individual Surety-Pledge of Assets. (FEB 2021) I.25 52.228-12 Prospective Subcontractor Requests for Bonds. (DEC 2022) I.26 52.228-13 Alternative Payment Protections. (JUL 2000) I.27 52.228-14 Irrevocable Letter of Credit. (NOV 2014) I.28 52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014) I.29 52.232-23 Assignment of Claims. (MAY 2014)

I.30 52.232-27 Prompt Payment for Construction Contracts. (JAN 2017) I.31 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) I.32 52.236-5 Material and Workmanship. (APR 1984) I.33 52.236-7 Permits and Responsibilities. (NOV 1991) I.34 52.236-14 Availability and Use of Utility Services. (APR 1984) I.35 52.236-17 Layout of Work. (APR 1984) I.36 52.243-5 Changes and Changed Conditions. (APR 1984) I.37 52.252-2 Clauses Incorporated by Reference. (FEB 1998) I.38 52.252-6 Authorized Deviations in Clauses. (NOV 2020) I.39 52.253-1 Computer Generated Forms. (JAN 1991) I.40 1452.225-70 Use of Foreign Construction Materials (JUL 1996) I.41 1452.228-70 Liability Insurance (JUL 1996) I.42 52.219-6 Notice of Total Small Business Set-Aside (DEVIATION 2019-01)

SECTION J - List of Documents, Exhibits, and Other Attachments SECTION K - Representations, Certifications, and Other Statements of Bidders

K.1 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.

(NOV 2021)

K.2 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran- Representation and Certifications. (JUN 2020) K.3 52.204-8 Annual Representations and Certifications (Jan 2025) (DEVIATION FEB 2025)

SECTION L - Instructions, Conditions, and Notices to Bidders L.1 Instructions for Submitting Quotations L.2 52.204-7 System for Award Management. (NOV 2024) L.3 52.204-16 Commercial and Government Entity Code Reporting. (AUG 2020) L.4 52.204-22 Alternative Line Item Proposal. (JAN 2017) L.5 52.216-1 Type of Contract. (APR 1984) L.6 52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (MAY 2014) L.7 52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014) L.8 52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998) L.9 1452.215-71 Use and Disclosure of Proposal Information-Department of the Interior. (APR 1984) L.10 1452.233-2 Service of Protest L.11 52.236-27 Site Visit (Construction). (FEB 1995) - Alternate I (FEB 1995)

SECTION M - Evaluation Factors for Award M.1 GS2320 Evaluation Factors for Award

SECTION B - Supplies or Services

[Section intentionally left blank]

SECTION C - Description/Specifications/Statement of Work

C.1 Statement of Work

See Attachment 1 for Statement of Work

SECTION D - Packaging and Marking

[Section intentionally left blank]

SECTION E - Inspection and Acceptance

E.1 52.246-12 Inspection of Construction. (AUG 1996)

SECTION F - Deliveries or Performance

F.1 Deliverables

Deliverable Reference Due Deliver To All labor, materials and equipment necessary to construct all items described in performance work statement and attachments

Statement of Work, Clause 52.211-10 NTP + 90 Days

USGS

Payment Bond or Irrevocable Letter of Credit

Section I: 52.228-13 & 52.228-14 Within 14 days after receipt of contract award

Contracting Officer

Proof of Liability Insurance Section I: 1452.228-70 Within 14 days after receipt of contract award

Contracting

Contractor Generated Invoices Section H: DOI Electronic Invoicing No more often than monthly

IPP

DI-137 Release of Claims Section H: DOI Electronic Invoicing Section I: 1452.204-70

Prior to submitting final invoice.

IPP

Certification of Progress Payment, if requesting progress payments

Section H: DOI Electronic Invoicing Section I: 52.232-5

As work proceeds ¿ no more often than monthly

IPP

Weekly Payrolls for contractor and each subcontractor

Section I: 52.222-8

The contractor is required to submit copies of all payrolls. The prime contractor is responsible for the submission of copies of payrolls by all subcontractors. This information may be submitted in any form. The optional form WH- 347 from the Department of Labor may be used and is available at:

http://www.dol.gov/whd/forms/wh347.pdf

Within 7 days after regular payment date of the payroll week covered

Contracting Officer Ref: FAR 22.406-6(c) for examination of payrolls and statements.

Further compliance checking may be done

IAW FAR

22.406-7.

SF-1413 Statement and Acknowledgment for each subcontractor.

Section I: 52.222-11

The contractor is required to submit statement and acknowledgement to the Contracting Officer on the Standard Form (SF) 1413 or a statement that no subcontractors will be employed.

Within 14 days after award of this contract, and within 14 days after the award of each subcontract thereafter

Contracting http://www.dol.gov/whd/forms/wh347.pdf

F.2 52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within ten (10) calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days from the date the notice to proceed is received. The time stated for completion shall include final cleanup of the premises.

(End of clause)

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

F.3 52.236-2 Differing Site Conditions. (APR 1984)

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of (1) subsurface or latent physical conditions at the site which differ materially from those indicated in this contract or (2) unknown physical conditions at the site, of an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

(b) The Contracting Officer shall investigate the site conditions promptly after receiving the notice. If the conditions do materially so differ and cause an increase or decrease in the Contractor's cost of, or the time required for, performing any part of the work under this contract, whether or not changed as a result of the conditions, an equitable adjustment shall be made under this clause and the contract modified in writing accordingly.

(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in paragraph (a) above for giving written notice may be extended by the Contracting Officer.

(d) No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.

(End of clause)

F.4 52.242-14 Suspension of Work. (APR 1984)

F.5 GS0919 Legal Holidays (JUN 2021)

SECTION G - Contract Administration Data

G.1 GS0231 Technical Liaison-Technical Direction (NOV 2014)

(a) The performance required herein shall be subject to the technical direction of the Technical Liaison (TL) as identified below. As used herein, "technical direction" is defined as direction to the contractor that fills in details, suggests possible lines of approach, or otherwise supplements the scope of the work set forth herein and shall not constitute a new assignment, and does not supersede or modify any article or clause of this contract.

(b) The Technical Liaison is not authorized to perform, formally or informally, any of the following actions:

(1) Promise, award, agree to award, or execute any contract modification, or notice of intent that changes or may change this contract;

(2) Waive or agree to modification of the delivery schedule;

(3) Make any final decision on any contract matter subject to the

Disputes Clause;

(4) Terminate, for any reason, the contractor's right to proceed;

(5) Obligate in any way, the payment of money by the Government. Only a warranted Contracting Officer is authorized to obligate funds on this or any other contract action.

(c) The contractor shall immediately notify the Contracting Officer in writing if the Technical Liaison has taken an action (or fails to take action) or issues direction (written or oral) that the contractor considers to exceed the above limitations.

(d) The Technical Liaison assigned for this contract is:

Name: Will be provided with award

Telephone Number: []

Email: []

Address Line 1: USGS Eastern Ecological Science Center

Address Line 2: 12100 Beech Forest Road

Address Line 3: Laurel, MD 20708

(e) Only the Contracting Officer may designate a different Technical

Liaison.

G.2 GS1131 Unilateral Deobligation of Unexpended Funds (MAY 2013)

The contractor shall submit all invoices under the award no later than 90 calendar days after the period of performance has expired, unless a request for extension has been submitted to the Contracting Officer. After 120 days has passed since the expiration of the performance period, the government reserves the right to issue a unilateral modification deobligating any unexpended funds, and to initiate closeout procedures.

SECTION H - Special Contract Requirements

H.1 GS1326 Indemnity (JUL 2001)

The contractor herein is "an independent contractor" and shall obtain all necessary insurance to protect himself from liability arising out of this contract. The contractor hereby agrees to indemnify and hold the Government harmless in connection with, any loss or liability from damage to or destruction of property or from injuries to or death of persons (including the agents and employees of both parties) if such damage, destruction, injury or death arises out of, or is caused by performance of work under this contract, unless such damage, destruction, injury or death is caused solely by the active negligence of the Government, its agents or employees. The contractor agrees to include this clause, appropriately modified, in all subcontracts to be performed under this contract.

H.2 GS1338 Notice to Government of Delays (JUL 2001)

In the event the contractor encounters difficulty in meeting performance requirements, or when it anticipates difficulty in complying with the contract delivery schedule or date, or whenever the contractor has knowledge that any actual or potential situation is delaying or threatens to delay the timely performance of this contract, the contractor shall immediately notify the contracting officer and the COR (if one has been designated), in writing, giving pertinent details.

This data shall be informational only in character. Notice under this provision shall not be construed as a waiver by the Government of any delivery schedule or date or of any rights or remedies provided by law or under this contract.

H.3 GS1346 Compliance with OSHA-Govt owned Facilities/Equipment (APR 2003)

Compliance with Occupational Safety and Health Act -- Government-Owned Performance of work hereunder shall comply with the provisions of the Occupational Health and Safety Act of 1970, as amended (OSHA). If, at any time during the performance of this contract, the Government-furnished facilities and/or equipment do not conform to OSHA standards, the contractor must so notify the Contracting Officer, in writing, including a recommendation of the corrective action needed.

H.4 GS1348 Accident Reporting (APR 2003)

If an accident occurs on Government-controlled facilities, a report must be provided to the Contracting Officer's Representative and the Contracting Officer within 48 hours. An accident is defined as an event which causes injury, illness, or loss or damage to Government-owned or private property. The contractor will cooperate with any ensuing Government accident investigation.

H.5 GS1440 Wage Determination Applicable (JUL 2001)

In the performance of this contract, the contractor shall comply with the requirements of U.S. Department of Labor Wage Determination Number MD20250121 dated 03/14/2025. The wage determination is incorporated into this contract as Attachment 2

H.6 DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (February 2021)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice [Contracting Officer to edit and include the documentation required under this contract]:

-Contractor generated invoice -Certification of Progress Payments - certification can be copied from clause 52.232-5(invoices for progress payments only) -Signed form DI-137 Release of Claims (final invoice only)

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

SECTION I - Contract Clauses

I.1 52.204-13 System for Award Management Maintenance. (OCT 2018)

I.2 52.204-18 Commercial and Government Entity Code Maintenance. (AUG 2020)

I.3 52.204-19 Incorporation by Reference of Representations and Certifications. (DEC 2014)

I.4 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021)

I.5 52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (JAN 2025)

I.6 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015)

I.7 52.213-4 Terms and Conditions - Simplified Acquisitions (Other Than Commercial Products and Commercial Services). (JAN 2025)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (DEC 2023) (Section 1634 of Pub. L. 115-91).

(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(iv) 52.204-27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section 102 of Division R of Pub. L.

117-328), unless the agency grants an exception-see paragraph (b) of 52.204-27.

(v) 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition. (DEC 2023) (Pub. L. 115-390, title

II).

(vi) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).

(vii) 52.222-21, Prohibition of Segregated Facilities (APR 2015).

(viii) 52.222-26, Equal Opportunity (SEP 2016) (E.O. 11246).

(ix) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).

(x) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) (31 U.S.C. 3903 and 10 U.S.C. 3801).

(xi) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).

(xii) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Pub. L. 108-77 and 108-78 (19 U.S.C. 3805 note)).

(2) Listed below are additional clauses that apply:

(i) 52.232-1, Payments (APR 1984).

(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).

(iii) 52.232-11, Extras (APR 1984).

(iv) 52.232-25, Prompt Payment (JAN 2017).

(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).

(vi) 52.233-1, Disputes (MAY 2014).

(vii) 52.244-6, Subcontracts for Commercial Products and Commercial Services (JAN 2025).

(viii) 52.253-1, Computer Generated Forms (JAN 1991).

(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:

(1) The clauses listed below implement provisions of law or Executive order:

(i) 52.203-17, Contractor Employee Whistleblower Rights (NOV 2023) (41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community-see FAR 3.900(a).

(ii) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L. 109-282) (31 U.S.C. 6101 note) (Applies to contracts valued at or above the threshold specified in FAR 4.1403(a) on the date of award of this contract).

(iii) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (JAN 2025) (E.O. 13126) (Applies to contracts for supplies exceeding the micro-purchase threshold, as defined in FAR 2.101 on the date of award of this contract).

(iv) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment (JUN 2020) (41 U.S.C. chapter 65) (Applies to supply contracts over the threshold specified in FAR 22.602 on the date of award of this contract, in the United States, Puerto Rico, or the U.S. Virgin Islands).

(v) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).

(vi) 52.222-36, Equal Employment for Workers with Disabilities (JUN 2020) (29 U.S.C. 793) (Applies to contracts over the threshold specified in FAR 22.1408(a) on the date of award of this contract, unless the work is to be performed outside the United States by employees recruited outside the United States). (For purposes of this clause, "United States" includes the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, and Wake Island.)

(vii) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212) (Applies to contracts valued at or above the threshold specified in FAR 22.1303(a) on the date of award of this contract).

(viii) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67) (Applies to service contracts over $2,500 that are subject to the Service Contract Labor Standards statute and will be performed in the United States, District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, or the outer Continental Shelf).

(ix)(A) 52.222-50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter 78 and E.O. 13627) (Applies to all solicitations and contracts).

(B) Alternate I (MAR 2015) (Applies if the Contracting Officer has filled in the following information with regard to applicable directives or notices: Document title(s), source for obtaining document(s), and contract performance location outside the United States to which the document applies).

(x) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (JAN 2022) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States, the District of Columbia, Puerto Rico, the Northern Mariana Islands, American Samoa, Guam, the U.S. Virgin Islands, Johnston Island, Wake Island, and the outer Continental Shelf as defined in the Outer Continental Shelf Lands Act (43 U.S.C. 1331, et seq.))).

(xi) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2022) (E.O. 13706) (Applies when 52.222-6 or 52.222-41 are in the contract and performance in whole or in part is in the United States (the 50 States and the District of Columbia.))

(xii) 52.223-5, Pollution Prevention and Right-to-Know Information (MAY 2024) (42 U.S.C. 11001-11050 and 13101- 13109) (Applies to services performed on Federal facilities).

(xiii) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to contracts for products as prescribed at FAR 23.109(d)(1)).

(xiv) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to maintenance, service, repair, or disposal of refrigeration equipment and air conditioners).

(xv) 52.223-20, Aerosols (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons as a propellant or as a solvent; or contracts for maintenance or repair of electronic or mechanical devices).

(xvi) 52.223-21, Foams (MAY 2024) (42 U.S.C. 7671, et seq.) (Applies to contracts for products that may contain high global warming potential hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons as a foam blowing agent; or contracts for construction of buildings or facilities.

(xvii) 52.223-23, Sustainable Products and Services (MAY 2024) (E.O. 14057, 7 U.S.C. 8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. 7671l) (Applies to contracts when the agency identifies in the statement of work, or elsewhere in the contract, the sustainable products and services that apply to the acquisition).

(xviii)(A) 52.225-1, Buy American- Supplies (OCT 2022) (41 U.S.C. chapter 67) (Applies to contracts for supplies, and to contracts for services involving the furnishing of supplies, for use in the United States or its outlying areas, if the value of the supply contract or supply portion of a service contract exceeds the micro-purchase threshold, as defined in

2.101 on the date of award of this contract, and the acquisition-

(1) Is set aside for small business concerns; or

(2) Cannot be set aside for small business concerns (see 19.502-2), and does not exceed $50,000).

(B) Alternate I (OCT 2022) (Applies if the Contracting Officer has filled in the domestic content threshold below, which will apply to the entire contract period of performance. Substitute the following sentence for the first sentence of paragraph (1)(ii)(A) of the definition of domestic end product in paragraph (a) of 52.225-1:

(A) The cost of its components mined, produced, or manufactured in the United States exceeds [ ] percent of the cost of all its components. [Contracting officer to insert the percentage per instructions at 13.302-5(d)(4).])

(xix) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (JUN 2020) (42 U.S.C. 1792) (Applies to contracts greater than the threshold specified in FAR 26.404 on the date of award of this contract, that provide for the provision, the service, or the sale of food in the United States).

(xx) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management (OCT 2018) (Applies when the payment will be made by electronic funds transfer (EFT) and the payment office uses the System for Award Management (SAM) as its source of EFT information).

(xxi) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management (JUL 2013) (Applies when the payment will be made by EFT and the payment office does not use the SAM database as its source of EFT information.)

(xxii) 52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act-Covered Foreign Entities (Nov 2024). (Sections 1821-1826, Pub. L. 118-31, 41 U.S.C. 3901 note prec.).

(xxiii) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV 2021) (46 U.S.C. 55305) (Applies to supplies transported by ocean vessels (except for the types of subcontracts listed at 47.504(d).)

(xxiv) 52.247-69, Reporting Requirement for U.S.-Flag Air Carriers Regarding Training to Prevent Human Trafficking (JAN 2025) (49 U.S.C. 40118(g)). (Applies to contracts with a U.S.-flag carrier for the transportation by air of passengers; does not apply to contracts awarded by the Department of Defense or contracts for commercial products).

(2) Listed below are additional clauses that may apply:

(i) 52.204-21, Basic Safeguarding of Covered Contractor Information Systems (NOV 2021) (Applies to contracts when the contractor or a subcontractor at any tier may have Federal contract information residing in or transiting through its information system.)

(ii) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (JAN 2025) (Applies to contracts over the threshold specified in FAR 9.405-2(b) on the date of award of this contract).

(iii) 52.211-17, Delivery of Excess Quantities (SEP 1989) (Applies to fixed-price supplies).

(iv) 52.247-29, F.o.b. Origin (FEB 2006) (Applies to supplies if delivery is f.o.b. origin).

(v) 52.247-34, F.o.b. Destination (JAN 1991) (Applies to supplies if delivery is f.o.b. destination).

(c) FAR 52.252-2, Clauses Incorporated by Reference (FEB 1998). This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

[Insert one or more Internet addresses]

(d) Inspection/Acceptance. The Contractor shall tender for acceptance only those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. The Government must exercise its postacceptance rights-

(1) Within a reasonable period of time after the defect was discovered or should have been discovered; and

(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.

(e) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence, such as acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.

(f) Termination for the Government's convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges that the Contractor can demonstrate to the satisfaction of the Government, using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor's records. The Contractor shall not be paid for any work performed or costs incurred that reasonably could have been avoided.

(g) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.

(h) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.

(End of clause)

I.8 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997)

I.9 52.219-28 Postaward Small Business Program Rerepresentation. (JAN 2025)

I.10 52.222-6 Construction Wage Rate Requirements. (AUG 2018)

I.11 52.222-7 Withholding of Funds. (MAY 2014)

I.12 52.222-8 Payrolls and Basic Records. (JUL 2021)

I.13 52.222-10 Compliance With Copeland Act Requirements. (FEB 1988)

I.14 52.222-11 Subcontracts (Labor Standards). (MAY 2014)

I.15 52.222-12 Contract Termination - Debarment. (MAY 2014)

I.16 52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

I.17 52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

I.18 52.222-15 Certification of Eligibility. (MAY 2014)

I.19 52.223-3 Hazardous Material Identification and Material Safety Data. (FEB 2021) - Alternate I (JUL 1995)

(a) Hazardous material, as used in this clause, includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract).

(b) The offeror must list any hazardous material, as defined in paragraph (a) of this clause, to be delivered under this contract. The hazardous material shall be properly identified and include any applicable identification number, such as National Stock Number or Special Item Number. This information shall also be included on the Material Safety Data Sheet submitted under this contract.

Material (if none, insert None) Identification No.

(c) This list must be updated during performance of the contract whenever the Contractor determines that any other material to be delivered under this contract is hazardous.

(d) The apparently successful offeror agrees to submit, for each item as required prior to award, a Material Safety Data Sheet, meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous material identified in paragraph (b) of this clause. Data shall be submitted in accordance with Federal Standard No. 313, whether or not the apparently successful offeror is the actual manufacturer of these items. Failure to submit the Material Safety Data Sheet prior to award may result in the apparently successful offeror being considered nonresponsible and ineligible for award.

(e) If, after award, there is a change in the composition of the item(s) or a revision to Federal Standard No. 313, which renders incomplete or inaccurate the data submitted under paragraph (d) of this clause, the Contractor shall promptly notify the Contracting Officer and resubmit the data.

(f) Neither the requirements of this clause nor any act or failure to act by the Government shall relieve the Contractor of any responsibility or liability for the safety of Government, Contractor, or subcontractor personnel or property.

(g) Nothing contained in this clause shall relieve the Contractor from complying with applicable Federal, State, and local laws, codes, ordinances, and regulations (including the obtaining of licenses and permits) in connection with hazardous material.

(h) The Government's rights in data furnished under this contract with respect to hazardous material are as follows:

(1) To use, duplicate and disclose any data to which this clause is applicable. The purposes of this right are to-

(i) Apprise personnel of the hazards to which they may be exposed in using, handling, packaging, transporting, or disposing of hazardous materials;

(ii) Obtain medical treatment for those affected by the material; and

(iii) Have others use, duplicate, and disclose the data for the Government for these purposes.

(2) To use, duplicate, and disclose data furnished under this clause, in accordance with subparagraph (h)(1) of this clause, in precedence over any other clause of this contract providing for rights in data.

(3) The Government is not precluded from using similar or identical data acquired from other sources.

(i) Except as provided in paragraph (i)(2) the Contractor shall prepare and submit a sufficient number of Material Safety Data Sheets (MSDS's), meeting the requirements of 29 CFR 1910.1200(g) and the latest version of Federal Standard No. 313, for all hazardous materials identified in paragraph (b) of this clause.

(1) For items shipped to consignees, the Contractor shall include a copy of the MSDS with the packing list or other suitable shipping document which accompanies each shipment. Alternatively, the Contractor is permitted to transmit MSDS's to consignees in advance of receipt of shipments by consignees, if authorized in writing by the Contracting Officer.

(2) For items shipped to consignees identified by mailing address as agency depots, distribution centers or customer supply centers, the Contractor shall provide one copy of the MSDS's in or on each shipping container. If affixed to the outside of each container, the MSDS must be placed in a weather resistant envelope.

(End of clause)

I.20 52.225-9 Buy American - Construction Materials. (OCT 2022)

(a) Definitions. As used in this clause-

Commercially available off-the-shelf (COTS) item- (1) Means any item of supply (including construction material) that is-

(i) A commercial product (as defined in paragraph (1) of the definition of "commercial product" at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means-

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S. supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means-

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if-

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The construction material is a COTS item; or

(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".

Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.

Foreign construction material means a construction material other than a domestic construction material.

Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.

Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.

Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.

United States means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference. (1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:

None

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that-

(i) The cost of domestic construction material would be unreasonable.