QandA_140G0125Q0145_0001.pdf
PDF 23 KB Posted
- Attached to
- Milling and Paving of Parking Lot & Structure
- Solicitation number
- 140G0125Q0145
About this file
This document is a Questions and Answers (Q&A) amendment for Request for Quotations 140G0125Q0145, providing clarification on two specific contractor inquiries. The first question addresses site access, with the response indicating that entry to the Eastern Ecological Science Center (EESC) is controlled, requiring contractors to contact the Technical Liaison daily when access is needed. The second question concerns worker eligibility, with the response confirming that all contractor and subcontractor employees must be legally authorized to work in the United States.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140G0125Q0145_Amd_0001.pdf | ||
| A2_-_Wage_Determination_20150121_3-14-25.pdf | ||
| Sol_140G0125Q0145.pdf | ||
| A1_-_SOW_6-13-25.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers
Request for Quotations 140G0125Q0145
AMENDMENT 1
1. Is there specific or special access to get on site?
a. Access to the Eastern Ecological Science Center (EESC) is controlled, so contractor personnel will be required to contact the Technical Liaison each day access is required.
2. I do not see a clause stating anything about US Citizens for the workers. Is this the case?
a. All contractor and subcontractor employees must be legally eligible to work in the United States.