This is a Request for Quotation (RFQ) for construction services at McNary National Wildlife Refuge in Burbank, Washington. The solicitation (140FC326Q0023) seeks a firm fixed-price contract for sealcoating an asphalt paved hiking trail, with an estimated value under $25,000. The trail measures approximately 6,300 feet long and 5 feet wide and was originally constructed in 2019. This represents the second sealcoating application for the existing trail.

The contractor must provide all labor, equipment, and materials to perform sealcoating work, including surface preparation, repairs to structurally unsound asphalt (alligator cracking, birdbaths, rutting), and uniform application of asphalt sealcoat. Work must be completed between June 15, 2026, and October 15, 2026 (124-day performance period). Responses are due by June 15, 2026, at 5:00 PM PDT, with an RFI deadline of June 10, 2026. This is a small business set-aside acquisition. Evaluation will be based on two non-price factors—technical capability (two examples of similar projects completed within five years) and past performance (customer references)—plus price. The solicitation incorporates Davis-Bacon wage requirements, Buy American construction materials provisions, and standard federal clauses including those related to security prohibitions, environmental compliance, and contractor compliance certifications.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NO.

5. REQUISITION/PURCHASE REQUEST NO.

CODE

6. PROJECT NO.

8. ADDRESS OFFER TO

4. CONTRACT NO.

7. ISSUED BY

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

NEGOTIATED (RFP) REQUEST FOR PROPOSAL

3. DATE ISSUED PAGE OF

SEALED BID (IFB) INVITATION FOR BID

9. FOR

INFORMATION CALL

PAGES

140FC326Q0023

FWS Constr A/E 3 FWS, Construction A/E Team 3 5275 Leesburg Pike Falls Church VA 22041

0044045027

FC3

Cindy Salazar 5038722832

05/29/2026

06/15/2026

15 30 Statement of Work

This is for a firm fixed price contract.

See attached:

A04 Statement of Work

B03 Construction Wage Determination - General Decision Number: WA20260133 01/23/2026 Superseded General

Decision Number: WA20250133, State: Washington

A06 Quail Trail Reseal

Price Range: Less than $25,000

1 56

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT

27. PAYMENT WILL BE MADE BY

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

Continued...

AMENDMENT

NUMBER

DATE.

5275 Leesburg Pike Falls Church VA 22041

FC3

Cindy Salazar

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140FC326Q0023

Submit quote to Cindy Salazar via email:

cindy_salazar@ios.doi.gov

Responses Due by: 06/15/2026, 5:00 PM (PDT)

RFI Due by: 06/10/2026, 5:00 PM (PDT)

Site Visit - Contact Katherine at McNary to setup a site visit via email to

Kathrine_Maikis@fws.gov, Phone #: 509-380-4927

Period of Performance: 06/15/2026 to

10/15/2026

00010 Reseal Quail Trail

Requisition No: 0044045027

Delivery: 10/15/2026

McNary National Wildlife Refuge SOLICITATION NO. 140FC326Q0023 Sealcoat of Asphalt Paved Trail

Section Title

Part I—The Schedule

A Solicitation/Contract Form

B Prices

C Description/Specifications/Statement of Work

D Packaging and Marking

E Inspection and Acceptance

F Project Delivery

G Contract Administration Data

H Special Contract Requirements

Part II—Contract Clauses

I Contract Clauses

Part III—List of Documents, Exhibits, and Other Attachments

J List of Attachments

Part IV—Representations and Instructions

K Representations, Certifications, and other Statements of Offerors

L Instructions, Conditions, and Notices to Offerors

M Evaluation Factors for Award

NOTE: Be advised that the controlling law regarding certain terms and conditions of this agreement remains unsettled by the Federal judiciary at the time of award and will be enforced only to the extent permitted by law.

Notice will be provided regarding the legal outcomes that impact your agreement.

52.252-2 – CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

As prescribed in 52.107(b), insert the following clause:

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov/far-overhaul (FAR clauses begin with 52)

(End of Clause) https://www.acquisition.gov/far-overhaul

SECTION B – PRICES (QUOTE SCHEDULE)

Name of Firm: ________________________________________________________________________

Address: ____________________________________________________________________________

City: __________________________________ State: __________ Zip Code: __________________

Unique Entity ID (12 Digits assigned by SAM.gov) __________________ CAGE Code: _______________

Name and Title of Firm’s Point of Contact: _________________________________________________

Phone Number: ________________________ Email Address: _________________________

This requirement is for one (1) Firm Fixed Price Construction contract for Sealcoat of Asphalt Paved Trail in McNary National Wildlife Refuge, 497 Gallant Rd, Burbank, Washington.

Item no. Item Description Quantit y Unit of

Measure Unit Price Total

0001 Sealcoat of Asphalt Paved Qual Trail 1 LS $ $

GRAND TOTAL $

(End of Section B)

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

1.0 Project and Location:

Trail Resurfacing at McNary National Wildlife Refuge, 497 Gallant Rd, Burbank, WA, 99323

1.1 Background: The U.S. Fish and Wildlife Service (FWS) is the premier Government agency dedicated to the conservation, protection, and enhancement of fish, wildlife and plants, and their habitats. The McNary Maintenance shop has a requirement to sealcoat of an asphalt paved trail located at the McNary National Wildlife Refuge, 497 Gallant Rd, Burbank, Washington.

2.0 Scope of Work:

Contractor shall provide all labor, equipment and materials (with the exception of those listed as provided by the government) to perform all work required to sealcoat an asphalt surfaced hiking trail on McNary National Wildlife Refuge as specified herein. Appendix A shows the overall layout.

2.1 Existing Conditions:

The existing trail was constructed in 2019 and is in good condition. The contracted activity is the second sealcoating of the trail. The trail is estimated to be 6300 feet long and 5 feet wide.

2.2 The surface to receive asphalt sealcoat must be free of all foreign material and dry immediately prior to sealcoat application. Cleaning may be by air blowing, vacuum, mechanical sweeper, washing, or other techniques as approved by the manufacturer. If washing the existing surface is used, the surface shall not have any standing water prior to application of the sealcoat.

2.5 Areas of structurally unsound asphalt concrete such as alligator cracking, low spots (birdbaths) or rutting must be properly repaired prior to placement of the asphalt sealcoat.

2.6. Application

a. Application of the asphalt sealcoat shall be by mechanical means using rubber faced squeegees, brooms, distributor bar/wand, or combinations of these or other techniques approved by the Manufacturer.

b. The asphalt sealcoat being applied shall be uniform and free flowing, free of lumps and other inconsistencies.

c. Asphalt sealcoat shall be applied uniformly over the prescribed are in continuous parallel lines in a manner so that no ridges or uncoated areas shall exist. Application rates will vary depending on the texture of the existing asphalt surfaces requiring more sealcoat than smooth surfaces.

d. Traffic shall not be allowed on the asphalt sealcoat until the sealcoat is thoroughly cured which in warm weather conditions is approximately 24 hours. Minor scuffing or power steering marks may occur on a newly applied surface in warm weather.

e. Asphalt sealcoat shall not be applied when the ambient temperature is less than 55 degrees for the surface temperature is less than 60 degrees.

f. Sealcoat shall be applied within 24 hours prior to forecast rain, freezing temperatures, during rain, or when the surface contains standing water.

3.0 Period of Performance:

The period of performance is 124 days after the Notice to Proceed Approximate time frame: 06/15/2026 to 10/15/2026 The work must be completed on or before 10/15/2026.

See attached Statement of Work (SOW) or full details.

Attachments:

A04 Statement of Work 2026 A06 Qual Trail Reseal (google earth) 2026 B03 Construction Wage Determination 2026 B12 Bid Schedule 2026

(End of Section C)

SECTION D – PACKAGING AND MARKING

D.1.0 PAYMENT OF POSTAGE FEES

All postage and fees related to submitting information forms, reports, etc., to the CO or the COR shall be paid by the contractor.

D.2.0 MARKING

All information submitted to the Contracting Officer or the Contracting Officer's Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.

(End of Section D)

SECTION E – INSPECTION AND ACCEPTANCE

The following clauses are incorporated by reference:

52.246-12 Inspection of Construction AUG 1996

(End of Section E)

SECTION F – PROJECT DELIVERY

F.1.0 PERIOD OF PERFORMANCE

F.2.0 PROGRESS PLAN

At the prework conference, the Contractor shall provide to the COR a written "work progress plan" that details its proposed work force and schedule to provide for orderly completion of the work within the contract performance time. This work schedule must be acceptable to the Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of contract performance time.

52.242-14 Suspension of Work APR 1984

**The following clauses are provided in full text:

(End of Section F)

SECTION G – CONTRACT ADMINISTRATION DATA

ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INVOICE PROCESSING PLATFORM (IPP) (February 2021)

Payment requests must be submitted electronically through the U.S. Department of the Treasury’s Invoice Processing Platform System (IPP).

“Payment request” means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions – Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:

1. Invoice billed according to contract line items and rates.

2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.

3. If the partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this invoice period.

4. If final payment is billed, the last invoice shall state “FINAL”.

5. Contractor’s Release of Claims shall be submitted with the final invoice.

The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date.

Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Local Clause)

(End of Section G)

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H.1.0 WORK HOURS

Unless otherwise specified in Section C, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be performed on Saturday, Sunday, or Federal holidays unless authorized by the COR.

H.2.0 ENVIRONMENTAL INTERRUPTION OF WORK

H.2.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration. An allowance has been included in the contract time for environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger. The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions.

H.2.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov

Endangered Species Act of 1973, as amended, are discovered to be present in or adjacent to the project area.

H.3.0 DRAWINGS

H.3.1 Reduced Size Drawings. Drawings appearing in this package may be photographically reduced in size.

Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. The Contractor may request full-size drawings from the COR.

H.4.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA

H.4.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data (including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.

H.4.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.

H.4.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in Section I of this contract.

H.4.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.

H.5.0 SUBSTITUTION – PROCESSION OF WORK

Any proposed key personnel, minimum qualifications for incoming or replacement key personnel, subcontractors, processes, procedures or materials included in the quotation are hereby incorporated into the contract. Performance shall be limited to the personnel, qualifications, firms, procedures, and materials that were specifically identified in the RFQ response. The Contractor shall obtain the Contracting Officer’s written consent before making any substitutions or changes. All substitutions or replacements shall comply with the terms and conditions of the contract.

H.6.0 ENVIRONMENTAL IMPACT

All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ); the Endangered Species Act, as amended (16 U.S.C. Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.

H.7.0 HAZARDOUS MATERIALS

Any material suspected of being hazardous that is unexpectedly encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.

Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR

1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.

H.8.0 GREEN PROCUREMENT REQUIREMENTS

In the performance of this construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, as applicable:

• U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.

• USDA Biobased product listings published at www.biopreferred.gov.

• Energy Star® product listings published at www.energystar.gov/products.

• FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories

Contractor shall comply with all reporting requirements of the following clauses/provisions when applicable (See Clause and Provision sections):

• 52.223-1 Biobased Product Certification

• 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

• 52.223-4 Recovered Material Certification

• 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items

H.9.0 UNAUTHORIZED PERSONNEL

The contractor shall inform all personnel working under their jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

H.10.0 DAVIS-BACON WAGE RATES APPLICABLE TO TRUCK DRIVERS

http://www.epa.gov/cpg/products.htm http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories http://energy.gov/eere/femp/covered-product-categories

29 CFR 5.2(j) limits coverage of construction contractor or subcontractor employees performing as truck drivers under the Davis-Bacon Act (FAR 52.222-6) to only their time spent directly upon the "site of the work" or when hauling between the site of the work and a facility which is dedicated to and located in the proximity of the actual construction location. Other transportation of materials or supplies to or from the site of work by employees of the construction contractor or subcontractor is not “construction” at the site of work and accordingly is not subject to the Davis-Bacon Act.

H.11.0 FIRE DANGER SEASON

If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.

(End of Section H)

SECTION I – CONTRACT CLAUSES

Clause Title Date 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements

JAN 2017

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

JUN 2020

52.204-13 System for Award Management Maintenance OCT 2018 52.204-19 Incorporation By Reference of Representations and Certifications DEC 2014 52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab Covered Entities

DEC 2023

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment

NOV 2021

52.204-27 Prohibition on a ByteDance Covered JUN 2023 52.209-10 Prohibition on Contracting With Inverted Domestic Corporations NOV 2015 52.213-4 Terms and Conditions – Simplified Acquisitions (Other Than

Commercial Products and Commercial Services) (DEVIATION FEB 2025)

OCT 2025

52.219-6 Notice of Total Small Business Set-Aside NOV 2020 52.219-28 Post-Award Small Business Program Representation JAN 2025 52.222-3 Convict Labor JUN 2003 52.222-6 Construction Wage Rate Requirements AUG 2018 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records JUL 2021 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination – Debarment MAY 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014

52.222-32 Construction Wage Rate Requirements - - Price Adjustment (Actual

Method)

AUG 2018

52.222-50 Combating Trafficking in Persons OCT 2025 52.222-55 Minimum Wages for Contractor Workers Under Executive Order

14026

JAN 2022

52.222-62 Paid Sick Leave Under Executive Order 13706 JAN 2022 52.222-90 Addressing DEI Discrimination by Federal Contractors APR 2026 52.223-2 Reporting of Biobased Products Under Service and Construction MAY 2024 52.223-3 Hazardous Material Identification and Material Safety Data Alternate

I

JUL 1995

52.223-5 Pollution Prevention and Right-to-Know Information MAY 2024 52.223-23 Sustainable Products and Services (DEVIATION FEB 2025) MAY 2024 52.225-9 Buy American—Construction Materials OCT 2022 52.225-13 Restrictions on Certain Foreign Purchases FEB 2021 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving MAY 2024 52.227-1 Authorization and Consent JUN 2020 52.204-10 Reporting Executive Compensation and First-Tier Subcvontract

Awards (DEVIATION MAR 2026)

JUN 2020

52.204-13 System foir Award Management-Maintenance (DEVIATION MAR 2026)

OCT 2018

52.204-14 Service Contract Reporting Requirements (DEVIATION MAR 2026) Oct 2016 52.209-6 Protecting the Government’s Interest When Subcontracting with

Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (DEVIATION MAY 2026)

JAN 2025

52.209-10 Prohibition on Contracting with Inverted Domestic Corporation

(DEVIATION MAY 2026)

NOV 2015

52.213-4 Terms and Conditions-Simplied Acquisitions (Noncommecial)

(DEVIATION MAR 2026)

OCT 2025

52.219-6 Notice to Small Business Set-Aside (DEVIATION JAN 2026) NOV 2020 52.222-6 Construction Wage Rate Requirements (DEVIATION MAY 2026) AUG 2018 52.222-11 Subcontracts (Labor Standards) (DEVIATION MAY 2026) MAY 2014 52.222-36 Equal Opportunity for Workers with Disabilities (DEVVIATION MAY

2026)

JUN 2020

52.222-50 Combat Trafficking in Persons (DEVIATION MAY 2026) OCT 2025 52.222-90 Addressing DEI Discrimination by Federal Contractors (DEVIATION

MAY 2026)

MAY 2026

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement JUN 2020 52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.227-23 Rights to Proposal Data (Technical) JUN 1987 52.228-2 Additional Bond Security OCT 1997 52.228-11 Individual Surety – Pledges of Assets FEB 2021 52.228-12 Prospective Subcontractor Requests for Bonds DEC 2022 52.228-13 Alternative Payment JUL 2000 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds-Construction JUN 2020 52.232-5 Payments Under Fixed-Price Construction Contracts MAY 2014 52.232-27 Prompt Payment for Construction Contracts JAN 2017

52.232-33 Payment by Electronic Funds Transfer—System for Award

Management

OCT 2018

52.232-39 Clause for unenforceability of unauthorized obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors MAR 2023 52.233-1 Disputes MAY 2014 52.233-1 Dispuits-Alternate 1 DEC 1991 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work (DEVIATION

MAN 2026)

APR 1984

52.236-5 Material and Workmanship (DEVIATION JAN 2026) APR 1984 52.236-6 Superintendence By the Contractor (DEVIATION JAN 2026) APR 1984 52.236-7 Permits and Responsibilities (DEVIATION JAN 2026) NOV 1991 52.236-8 Other Contracts (DEVIATION JAN 2026) APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (DEVIATION JAN 2026)

APR 1984

52.236-10 Operations and Storage Areas (DEVIATION JAN 2026) APR 1984 52.236-11 Use and Possession Prior to Completion (DEVIATION JAN 2026) APR 1984 52.236-12 Cleaning Up (DEVIATION JAN 2026) APR 1984 52.236-13 Accident Prevention (DEVIATION JAN 2026) NOV 1991 52.236-14 Availability and Use of Utility Services (DEVIATION JAN 2026) APR 1984 52.236-16 Quantity Surveys APR 1984 52.236-17 Layout of Work (DEVIATION JAN 2026) APR 1984 52.236-21 Specifications and Drawings for Construction FEB 1997 52.236-26 Preconstruction Conference FEB 1995 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or

Assembled by American Security Drone Act-Covered Foreign Entities

NOV 2024

52.243-5 Changes and Changed Conditions (DEVIATION OCT 2025) APR 1984 52.244-6 Subcontracts for Commercial Products and Commercial Services

(DEVIATION FEB 2025)

Oct 2025

52.245-1 Government Property – Alternate I SEP 2021 52.245-9 Use and Charges APR 2012 52.246-21 Warranty of Construction MAR 1994 52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms (DEVIATION MAY 2026) JAN 1991

The following clauses are provided in full text:

52.204-14 Service Contract Reporting Requirements (OCT 2016) (DEVIATION MAR 2026)

As prescribed in 4.208(f)(2), insert the clause:

(a) Definition. As used in this clause—

First-tier subcontract means a subcontract awarded directly by the Contractor to acquire supplies or services

(including construction) for performing a prime contract. It does not include the Contractor's supplier agreements with vendors, such as long-term arrangements for materials or supplies that benefit multiple contracts and/or the costs of which are normally applied to a contractor's general and administrative expenses or indirect costs.

(b) Requirement. The Contractor shall report, according to paragraphs (c) and (d) of this clause, annually by

October 31, for services performed under this contract during the preceding Government fiscal year (October 1-

September 30).

(c) Report elements. The Contractor shall report the following information:

(1) Contract number and, as applicable, order number.

(2) The total dollar amount invoiced for services performed during the previous Government fiscal year under the contract.

(3) The number of Contractor direct labor hours expended on the services performed during the previous

Government fiscal year.

(4) Data reported by subcontractors under paragraph (f) of this clause.

(d) Remedies. The Contractor shall submit the information required in paragraph (c) of this clause in the System for Award Management (SAM) at https://www.sam.gov (see SAM User Guide). If the Contractor fails to submit the report in a timely manner, the Contracting Officer will exercise appropriate contractual remedies. In addition, the Contracting Officer will make the Contractor's failure to comply with the reporting requirements a part of the

Contractor's performance information under the Federal Acquisition Regulation part 42.

(e) Review. Agencies will review Contractor-reported information for reasonableness and consistency with available contract information. If the agency believes that revisions to the Contractor’s reported information are warranted, the agency will notify the Contractor no later than November 15. By November 30, the Contractor shall revise the report, or put its reason in writing for the agency.

(f) First-tier subcontracts.

(1) The Contractor shall require each first-tier subcontractor providing services under this contract, with subcontract(s) each valued at or above the thresholds set forth in 4.303(b), to provide the following detailed information to the Contractor in sufficient time to submit the report:

(i) Subcontract number (including subcontractor name and unique entity identifier); and

(ii) The number of first-tier subcontractor direct-labor hours expended on the services performed during the previous Government fiscal year.

https://www.sam.gov/

(2) The Contractor shall tell the subcontractor that the information will be made available to the public as required by section 743 of Division C of the Consolidated Appropriations Act, 2010.

(End of clause)

52.217-7 – OPTION FOR SEPARATELY PRICED LINE ITEM (MAR 1989) (altered clause)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 60 days.

(End of Clause)

52.219-28 Postaward Small Business Program Rerepresentation (JAN 2025) (DEVIATION JAN 2026)

As prescribed in 19.101(a)(2)(iii)(A), insert the clause:

(a) Definitions. As used in this clause—

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend

Services, or other appropriate authority.

Small business concern—

(1) Means a concern, including its affiliates, that is independently owned and operated, not dominant in its field of operation, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause.

(2) Affiliates, as used in this definition, means business concerns, one of whom directly or indirectly controls or has the power to control the others, or a third party or parties control or have the power to control the others. In determining whether affiliation exists, consideration is given to all appropriate factors including common ownership, common management, and contractual relationships. SBA determines affiliation based on the factors set forth at 13 CFR 121.103.

(b) If the Contractor represented that it was a small business concern, a small disadvantaged business concern, or a joint venture that was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts-

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at https://www.sba.gov/document/support--table-size-standards.

(d) The small business size standard for a Contractor providing an end item that it does not manufacture, process, or produce itself, for a contract other than a construction or service contract, is 500 employees, or 150 employees for information technology value-added resellers under NAICS code 541519, if the acquisition—

(1) Was set aside for small business and has a value above the simplified acquisition threshold;

(2) Used the HUBZone price evaluation preference regardless of dollar value, unless the Contractor waived the price evaluation preference; or

(3) Was an 8(a), HUBZone, service-disabled veteran-owned, economically disadvantaged women-owned, or women-owned small business set-aside or sole-source award regardless of dollar value.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the representation(s) required by paragraph (b) of this clause by validating or updating all its representations in the Representations and

Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause, that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in SAM, or does not have a representation in

SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

(1) The Contractor represents that it □ is, □ is not a small business concern under NAICS Code _____ assigned to contract number _____.

https://www.sba.gov/document/support--table-size-standards

(2) [Complete only if the Contractor represented itself as a small business concern in paragraph (g)(1) of this clause.] The Contractor represents that it □ is, □ is not, a small disadvantaged business concern as defined in 13

CFR 124.1001.

(3) Women-owned small business (WOSB) joint venture eligible under the WOSB Program. The Contractor represents that it □ is, □ is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through

(c). [ The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __.]

(4) Economically disadvantaged women-owned small business (EDWOSB) joint venture. The Contractor represents that it □ is, □ is not a joint venture that complies with the requirements of 13 CFR 127.506(a) through (c). [ The

Contractor shall enter the name and unique entity identifier of each party to the joint venture: __ .]

(5) Service-disabled veteran-owned small business (SDVOSB) joint venture eligible under the SDVOSB Program. The

Contractor represents that it □ is, □ is not an SDVOSB joint venture eligible under the SDVOSB Program that complies with the requirements of 13 CFR 128.402. [ The Contractor shall enter the name and unique entity identifier of each party to the joint venture: __.]

(6) HUBZone joint venture eligible under the HUBZone Program.[ Complete only if the offeror is a HUBZone small business concern. ] The offeror represents, as part of its offer, that It □ is, □ is not a HUBZone joint venture that complies with the requirements of 13 CFR 126.616(a) through (c). [ The Contractor shall enter the name and unique entity identifier of each party to the joint venture: _____. ] Each HUBZone small business concern participating in the HUBZone joint venture must be certified as a HUBZone concern. [ Contractor to sign and date and insert authorized signer's name and title.______________________ ]

(End of clause)

Alternate I (DEVIATION JAN 2026). As prescribed in 19.101(a)(2)(iii)(B), substitute the following paragraph (g)(1) for paragraph (g)(1) of the basic clause:

(g)(1) The Contractor represents its small business size status for each one of the NAICS codes assigned to this contract.

NAICS Code Small business concern (yes/no)

NAICS Code Small business concern (yes/no)

[Contracting Officer to insert NAICS codes.]

52.222-4 Contract Work Hours and Safety Standards -Overtime Compensation (MAY 2018) (DEVIATION MAY 2026)

As prescribed in 22.301-2, insert the clause:

(a) Overtime requirements. No Contractor or subcontractor employing laborers or mechanics (see Federal

Acquisition Regulation 22.301-1) must require or permit them to work over 40 hours in any workweek unless they are paid at least 1 and 1/2 times the basic rate of pay for each hour worked over 40 hours.

(b) Violation; liability for unpaid wages; liquidated damages. The responsible Contractor and subcontractor are liable for unpaid wages if they violate the terms in paragraph (a) of this clause. In addition, the Contractor and subcontractor are liable for liquidated damages payable to the Government. The Contracting Officer will assess liquidated damages at the rate specified at 29 CFR 5.5(b)(2) per affected employee for each calendar day on which the employer required or permitted the employee to work in excess of the standard workweek of 40 hours without paying overtime wages required by the Contract Work Hours and Safety Standards statute (found at 40

U.S.C. chapter 37). In accordance with the Federal Civil Penalties Inflation Adjustment Act of 1990 ( 28 U.S.C.

2461 Note), the Department of Labor adjusts this civil monetary penalty for inflation no later than January 15 each year.

(c) Withholding for unpaid wages and liquidated damages. The Contracting Officer will withhold from payments due under the contract sufficient funds required to satisfy any Contractor or subcontractor liabilities for unpaid wages and liquidated damages. If amounts withheld under the contract are insufficient to satisfy Contractor or subcontractor liabilities, the Contracting Officer will withhold payments from other Federal or federally assisted contracts held by the same Contractor that are subject to the Contract Work Hours and Safety Standards statute.

(d) Payrolls and basic records.

(1) The Contractor and its subcontractors must maintain payrolls and basic payroll records for all laborers and mechanics working on the contract during the contract and must make them available to the Government until 3 years after contract completion. The records must contain the name and address of each employee, social security number, labor classifications, hourly rates of wages paid, daily and weekly number of hours worked, deductions made, and actual wages paid. The records need not duplicate those required for construction work by http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title40-chapter37&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title40-chapter37&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title28-section2461&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title28-section2461&num=0&edition=prelim

Department of Labor regulations at 29 CFR 5.5(a)(3) implementing the Construction Wage Rate Requirements statute.

(2) The Contractor and its subcontractors must allow authorized representatives of the Contracting Officer or the

Department of Labor to inspect, copy, or transcribe records maintained under paragraph (d)(1) of this clause. The

Contractor or subcontractor also must allow authorized representatives of the Contracting Officer or Department of Labor to interview employees in the workplace during working hours.

(e) Subcontracts. The Contractor must insert the provisions set forth in paragraphs (a) through (d) of this clause in subcontracts that may require or involve the employment of laborers and mechanics and require subcontractors to include these provisions in any such lower tier subcontracts. The Contractor must be responsible for compliance by any subcontractor or lower-tier subcontractor with the provisions set forth in paragraphs (a) through (d) of this clause.

(End of clause)

52.222-90 Addressing DEI Discrimination by Federal Contractors (MAY 2026) (DEVIATION MAY 2026)

As prescribed in 22.2203, insert the clause:

(a) Definitions. As used in this clause—

Program participation means membership or participation in, or access or admission to: training, mentoring, or leadership development programs; educational opportunities; clubs; associations; or similar opportunities that are sponsored or established by the contractor or subcontractor.

Racially discriminatory diversity, equity, and inclusion (DEI) activities means disparate treatment based on race or ethnicity in the recruitment, employment (e.g., hiring, promotions), contracting (e.g., vendor agreements), program participation, or allocation or deployment of an entity's resources.

(b) In connection with the performance of work under this contract, the Contractor agrees as follows:

(1) The Contractor will not engage in any racially discriminatory DEI activities;

(2) The Contractor will furnish all information and reports, including providing access to books, records, and accounts, as required by the Contracting Officer, for purposes of ascertaining compliance with this clause;

(3) In the event of the Contractor's or a subcontractor's noncompliance with this clause, this contract may be canceled, terminated, or suspended in whole or in part, and the Contractor or subcontractor may be declared ineligible for further Government contracts;

(4) The Contractor will report any subcontractor's known or reasonably knowable conduct that may violate this clause to the Contracting Officer and take any appropriate remedial actions directed by the Contracting Officer;

and

(5) The Contractor will inform the Contracting Officer if a subcontractor sues the Contractor and the suit puts at issue, in any way, the validity of this clause.

(6) The Contractor recognizes that compliance with the requirements of this clause are material to the

Government's payment decisions for purposes of 31 U.S.C. 3729(b)(4).

(c) The Contractor must include the substance of this clause, including this paragraph (c), in subcontracts at any tier, including those for commercial products and commercial services, except those where the place of delivery or performance is outside the United States.

52.225-9 – BUY AMERICAN–CONSTRUCTION MATERIALS (OCT 2022)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at Federal Acquisition Regulation (FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

Cost of components means— https://www.acquisition.gov/far/2.101#FAR_2_101

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.

Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.

supply chain resiliency. The list of critical items is at FAR 25.105.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A)The cost of its components mined, produced, or manufactured in the United States exceeds 60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or

(B) The…