Sol_140FC224Q0032.pdf
PDF 1 MB Posted
- Attached to
- MN AGASSIS NWR RODAHL TRAIL REPAIR
- Solicitation number
- 140FC224Q0032
About this file
This document is a solicitation for a construction contract to repair and resurface the Rodahl Trail on the Agassiz National Wildlife Refuge in Minnesota. The key details are:
The project includes rehabbing the side slopes of the road and resurfacing the road top with 2 inches of crushed concrete. The magnitude of the project is between $25,000 and $100,000. Bids are due on June 28, 2024 at 3:00 pm EST. The work must be completed by August 30, 2024. The contract will be awarded based on price only. This is a small business set-aside solicitation issued by the U.S. Fish & Wildlife Service.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140FC224Q0032_Amd_0003.pdf | ||
| Amendment_3_Questions_and_Answers_0003.pdf | ||
| Sol_140FC224Q0032_Amd_0002.pdf | ||
| Sol_140FC224Q0032_Amd_0001.pdf | ||
| Amendment_1__0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040662218
FWS Constr A/E 2
FWS, Construction A/E Team 2
5275 Leesburg Pike Falls Church VA 22041
FC2
William Koski
106/07/2024
140FC224Q0032
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Repair and resurface road on Agassiz National Wildlife Refuge. This includes rehabbing the side slopes of the road and re-surfacing the road top with crushed concrete.
The Magnitude of project is between $25,000 and $100,000.
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 180 calendar days and complete it within ________________ ________________ calendar days after receiving
06/28/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Rachel Williams
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 69
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140FC224Q0032
This project is to resurface the aggregate surface of Rodahl Trail and remove some trees.
Delivery: 08/30/2024
Delivery Location Code: 0008349530
FWS AGASSIZ NWR
22996 290TH STREET NORTHEAST
MIDDLE RIVER MN 56737-9754 US
Period of Performance: 07/01/2024 to 08/30/2024
00010 Rodahl Trail Work
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
United States Department of the Interior
U.S. Fish and Wildlife Service
Agassiz National Wildlife Refuge
22996 290th Street NE
Middle River, MN 56737
218/461-8970
STATEMENT OF WORK
Agassiz NWR Rodahl Trail
Overview:
Seeking quotes from contractors to repair and resurface road on Agassiz National Wildlife Refuge. This project includes rehabbing the side slopes of the road and re-surfacing the road top with crushed concrete.
Specifications on work for each will be outlined below. Read carefully as specifications per site and materials provided vary.
Location:
Agassiz National Wildlife Refuge Headquarters, 22996 290th Street NE, Middle River, Minnesota 56737
Contractor Responsibilities:
Bids are due June 28, 2024 at 3:00 pm EST.
Basis for Award: Price Only
Questions are due June 14, 2024 at 3:00 pm EST to the POC listed in Contacts.
Site Visit: Contact POC for Site Visit is Cody Okeson, Deputy Refuge Manager, 320-333-4933, cody_okeson@fws.gov .
It is highly recommended that contactors attend the site visit prior to submitting a bid or quote.
Work must be completed by: Aug 30, 2024
Equipment left on-site must be secured and is the sole responsibility of the contractor.
Equipment must be cleaned pre and post entry of the site for noxious and invasive species.
Work will be conducted in a manner that will minimize rutting, disturbance, or compaction of soil or sod and the spread of noxious and invasive species.
Payment will be processed following receipt of proper invoices and inspection of work for contract compliance through the Federal Government’s Invoice Processing Platform, www.ipp.gov .
mailto:cody_okeson@fws.gov http://www.ipp.gov/
United States Department of the Interior
U.S. Fish and Wildlife Service
Agassiz National Wildlife Refuge
22996 290th Street NE
Middle River, MN 56737
218/461-8970
Description of Work to be Completed:
Rodahl Trail – 0.60 Miles – 12 feet wide – Location: 48.276364°, -96.067278°
Contractor will first rehab the road side slopes from the road shoulder to the ditch bottom on both sides.
This includes first removing any remaining trees and cut tree stumps 6 inches in diameter or larger along both side slopes the entire length. Then filling in holes and leveling the side slopes to match the surrounding grade. Contractor shall then spread 2 inches of crushed concrete along the entire road surface including the overlook and viewing area on the east end of the road, leveling and packing according to the specifications below. The aggregate and incidentals are to be provided by the contractor.
General Process:
Remove remaining trees and tree stumps from side slopes that are 6 inches in diameter and larger.
Trees and tree stumps can be piled on the north side of the road in location designated by the
Agassiz NWR Project Manager.
Roadbed should be smooth as possible free of rocks and other debris before placing crushed concrete.
Place 2 inches of crushed concrete 12 feet wide along entire road length and viewing area.
Finished road grade must have a crown of approximately one-half inch drop per foot on each side of the road to facilitate proper drainage.
The aggregate should be compacted utilizing a roller packer or pneumatic (rubber tired) roller.
Contact:
William Koski, Contract Specialist, US Fish & Wildlife Service
William_koski@fws.gov
(413)336-4079 mailto:William_koski@fws.gov
"General Decision Number: MN20240057 01/05/2024
Superseded General Decision Number: MN20230057
State: Minnesota
Construction Type: Highway
Counties: Beltrami, Clearwater, Hubbard, Kittson, Lake of the Woods, Marshall, Norman, Pennington, Polk, Red Lake and Roseau Counties in Minnesota.
HIGHWAY CONSTRUCTION PROJECTS
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(1).
|If the contract is entered |� Executive Order 14026 | |into on or after January 30, | generally applies to the | |2022, or the contract is | contract. | |renewed or extended (e.g., an |� The contractor must pay | |option is exercised) on or | all covered workers at | |after January 30, 2022: | least $17.20 per hour (or | | | the applicable wage rate | | | listed on this wage | | | determination, if it is | | | higher) for all hours | | | spent performing on the | | | contract in 2024. | |If the contract was awarded on|� Executive Order 13658 | |or between January 1, 2015 and| generally applies to the | |January 29, 2022, and the | contract. | |contract is not renewed or |� The contractor must pay all| |extended on or after January | covered workers at least | |30, 2022: | $12.90 per hour (or the | | | applicable wage rate listed| | | on this wage determination,| | | if it is higher) for all | | | hours performing on that | | | contract in 2024. |
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number Publication Date
5/22/24, 9:25 AM SAM.gov https://sam.gov/wage-determination/MN20240057/0 1/7
0 01/05/2024
SUMN2022-002 02/26/2020
Rates Fringes
BOILERMAKER......................$ 39.69 29.16
BRICKLAYER.......................$ 29.89 14.40
CARPENTER........................$ 32.32 23.20
CEMENT MASON.....................$ 36.88 19.25
ELECTRICIAN
Electrician.................$ 31.19 24.27 Ground Person...............$ 10.33 ** 0.00 Lineman.....................$ 20.00 0.00
IRONWORKER.......................$ 35.09 31.80
LABORER
Blaster.....................$ 17.98 5.92 Common or General...........$ 27.50 20.74 Flag Person.................$ 27.50 20.74 Landscaping (Gardener, Sod Layer and Nursery Operator).$ 19.00 2.00 Pipelayer (Water, Sewer and Gas)....................$ 29.75 19.94 Skilled (Assisting Skilled Craft Journeyman)...........$ 26.25 19.94 Underground & Open Ditch (8 ft below starting grade level)......................$ 24.74 18.05
MILLWRIGHT.......................$ 40.99 21.72
PAINTER
Including Hand Brushed, Hand Sprayed, and the Taping of Pavement Markings.$ 27.48 20.17
PILEDRIVERMAN (Including Vibratory Driver or Extractor for Piling and Sheeting Operations)......................$ 42.15 26.04
PLUMBER..........................$ 30.00 0
POWER EQUIPMENT OPERATOR:
GROUP 2.....................$ 32.40 23.45
GROUP 3.....................$ 29.72 21.40
GROUP 4.....................$ 31.16 23.45
GROUP 5.....................$ 29.45 23.45
GROUP 6.....................$ 28.85 23.45
Special Equipment Articulated Hauler.........$ 31.16 23.45 Landscaping Equipment- Includes Hydro Seeder or Mulcher, Sod Roller, Farm Tractor with Attachment Speciafically Seeding, Sodding, or Plant, and Two-Framed Forklift (Excluding Front, Posit-https://sam.gov/wage-determination/MN20240057/0 2/7
Track, and Skid Steer Loaders), No Earthwork or Grading for Elevations.....$ 24.00 2.00 Off-Road Truck.............$ 31.16 23.45 Pavement Marking or Marking Removal Equipment Operator (one or two person operators), Self- Propelled Truck or Trailer Mounted Units......$ 35.00 2.86
OPERATING ENGINEER CLASSIFICATIONS
GROUP 2: Helicopter Pilot; Concrete Pump; Cranes over 135 ft boom excluding jib; Dragline, Crawler, Hydraulic Backhoe (Track or wheel mounted) and other similar equipment with shovel-type controls 3 cu yd & over manufacturer's rated capacity including all attachments; Grader or Motor Patrol;
Pile Driving; Tugboat 100 H.P. and over when license required GROUP 3: Asphalt Bituminous Stabilizer Plant; Cableway;
Concrete Mixer, Stationary Plant; Derrick (guy or stiff leg)(power)(skids or stationary); Dragline, Crawler, Hydraulic Backhoe (track or wheel mounted) and other similar equpment with shovel-type controls including attachments up to 3 cu yd manufacturer's rated capacity including all attachments;
Dredge or Engineers, Dredge (Power) and engineer; Front end loader 5 cu yd and over including attachments ; Locomotive Crane Operator; Mixer (paving) concrete paving, Road Mole including Mucking operations, Conway or similar type;
Mechanic, Welder on power equipment; Tractor, Boom type.
Tandem Scraper; Truck Crane, Crawler Crane;Tugboat 100 H.P and over. GROUP 4: Air Track Rock Drill; Automatic Road Machine CMI or similar; Backfiller operator; Concrete Batch Plant operator; Bituminous Roller, Rubber Tire or Steel Drum 8 tons & over; Bituminous Spreader & Finishing Machine (power), including pavers, Macro Surfacing & Micro Surfacing or similar types (Operator & Screed person);
Brokk or RTC remote control or similar type with attachments;
Cat Challenger Tractor or similar types pulling Rock Wagons;
Bulldozer & Scraper; Chip Harvester & Tree Cutter; Concrete Distributor & Spreader Finishing Machine, Longitudinal Float, Joint Machine, Spray Machine; Concrete Mixer on jobsite;
Concrete Mobil; Crusing Plant (gravel, stone) or Gravel Washing, Crushing & Screening Plant; Curb Machine; Directional Boring Machine; Dope Machine; Drill Rigs, Heavy Rotary or Churn or Cable Drill; Dual Tractor; Elevating Grader; Fork Lift or Staraddle Carrier; Fork lift or Lumber Stacker; Front End, Skid Steer 1 to 5 cu yd; GPS Remote Operating of equipment; Hoist Engineer (power); Hydraulic Tree Planter;
Launcher Person; Locomotive; Milling, Grinding, Planing, Fine Grade, or Trimmer Machine; Multiple Machines such as Air Comressors, Welding Machines, Generators, Pumps; Pavement Breaker or Tamping Machine, Mighty Mite or similar type;
Pickup Sweeper 1 cu yd & over hopper capacity; Pipeline Wrapping, Cleaning or Bending Machine; Power Actuated Horizontal Boring Machine, over 6 inches; Pugmill; Pumpcrete;
Rubber Tired Farm Tractor with Backhoe attachment; Scraper;
Self-Propelled Soil Stabilizer; Slip Form (power driven) paving;Tie Tamper and Ballast Machine; Tractor, Bulldozer;
Wheel type Tractor over 50 H.P with PTO unrealted to Landscaping; Trenching Machine (sewer, water, gas) excludes walk behind Trencher; Tub Grinder, Morbark or similar type;
Well Point installation or Dismantling.
GROUP 5: Air Compressor 600 cfm or over; Bituminous Roller under 8 tons; Concrete Saw multiple blade; Form Tench Digger (power); Front End Skid Steer up to 1 cu yd; Gunite Gunall;
Hydraulic Log Splitter; Loader, Barber Greene or similar; Post https://sam.gov/wage-determination/MN20240057/0 3/7
Hole Driving Machine/Post Hole Auger; Power Actuated Auger & Boring Machine; Power Actuated Jack; Pump; Self-Propelled Chip Spreader (Flaherty or similar); Sheep Foot Compactor with blade 200 hp & over; Shouldering Machine (Power) APSCO or similar type including self-propelled Sand and Chip Spreader;
Stump Chipper and Tree Chipper; Tree Farmer (Machine).
GROUP 6: Cat, Challenger or siliar tractor when pulling Disk or Roller; Conveyor; Dredge Deck Hand; Fire Person or Tank Car Heater; Gravel Screening Plant (portable, not crushing or washing); Greaser (tractor); Lever Person; Oiler (Power Shovel, Crane,Truck Crane, Dragline, Crusher and Milling Machines, or other similar heavy equipment; Power Sweeper;
Sheep Foot Roller & Rollers on Gravel Compaction including vibrating rollers; Wheel type Tractor over 50 hp.
SHEET METAL WORKER...............$ 33.55 25.96
STEAMFITTER/PIPEFITTER...........$ 38.59 17.67
Survey Field Technician (Operate total station, GPS receiver, Level, Rod or Range Poles, Steel Tape Measurement; Mark and Drive Stakes; Hand or Power Digging for and Identification of Markers or Monuments; Perform and Check Calculations;
Review and Understand Construction Plans and Land Survey Materials.)...............$ 20.33 3.17
TRAFFIC CONTROL (Temporary Signage).........................$ 21.39 14.90
TRUCK DRIVER
GROUP 1.....................$ 28.92 21.35
GROUP 2.....................$ 21.12 13.26
GROUP 3.....................$ 28.26 21.35
GROUP 4.....................$ 28.26 21.35
TRUCK DRIVER CLASSIFICATIONS:
GROUP 1: Mechanic, Welder; Tractor Trailer Driver; Truck Driver hauling machinery including operation of hand and power operated winches.
GROUP 2: Four or more axle unit, straight body truck.
GROUP 3: Bituminouos Distributor driver; Bituminous Distributor (one person operation); Three Axle units.
GROUP 4: Bituminous Distributor Spray operator (rear and oiler); Dump Person; Greaser; Pilot Car; Rubber Tire self-propelled Packer under 8 tons; Two Axle unit; Slurry Operator;
Tank Truck Tender (gas, oil, road oil,and water); Tractor Operator under 50 hp.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
** Workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.20) or 13658 ($12.90). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to https://sam.gov/wage-determination/MN20240057/0 4/7 which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average https://sam.gov/wage-determination/MN20240057/0 5/7 rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour National Office because National Office has responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.) and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an https://sam.gov/wage-determination/MN20240057/0 6/7 interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
https://sam.gov/wage-determination/MN20240057/0 7/7
Agassiz NWR Rodahl Trail 140FC224Q0032
Section Title
Part I—The Schedule
A Solicitation/Contract Form
B Prices
C Description/Specifications/Statement of Work
D Packaging and Marking
E Inspection and Acceptance
F Project Delivery
G Contract Administration Data
H Special Contract Requirements
Part II—Contract Clauses
I Contract Clauses
Part III—List of Documents, Exhibits, and Other Attachments
J List of Attachments
Part IV—Representations and Instructions
K Representations, Certifications, and other Statements of Offerors
L Instructions, Conditions, and Notices to Offerors
M Evaluation Factors for Award
SECTION B – PRICES (QUOTE SCHEDULE)
N/A
SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
See Attached SOW
(End of Section C)
SECTION D – PACKAGING AND MARKING
D.1.0 PAYMENT OF POSTAGE FEES
All postage and fees related to submitting information forms, reports, etc., to the CO or the COR shall be paid by the contractor.
D.2.0 MARKING
All information submitted to the Contracting Officer or the Contracting Officer's Representative shall clearly indicate the Contract Number of the contract for which the information is being submitted.
(End of Section D)
SECTION E – INSPECTION AND ACCEPTANCE
The following clauses are incorporated by reference:
52.246-12 INSPECTION OF CONSTRUCTION AUG 1996
(End of Section E)
SECTION F – PROJECT DELIVERY
F.1.0 PERIOD OF PERFORMANCE
See clause 52.211-10 in this section.
52.242-14 SUSPENSION OF WORK APR 1984
The following clauses are provided in full text:
52.211-10 – COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by July 1, 2024. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
(End of Clause)
(End of Section F)
SECTION G – CONTRACT ADMINISTRATION DATA
Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP)
(February 2021)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform
System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice:
1. Invoice billed according to contract line items and rates.
2. Certified payrolls and Statement of Compliance in accordance with clause 52.222-8.
3. If the partial payment is billed and the invoice states a lump sum, the invoice shall include an itemized breakdown and narrative progress summary of the work performed during this https://www.ipp.gov/ invoice period.
4. If final payment is billed, the last invoice shall state “FINAL”.
5. Contractor’s Release of Claims shall be submitted with the final invoice.
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor
Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve
Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-
3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause)
(End of Section G)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
H.1.0 WORK HOURS
Unless otherwise specified in Section C, work hours under this contract shall be limited to the time between one-half hour before sunrise to one-half hour after sunset each day. No work will be performed on Saturday, Sunday, or Federal holidays unless authorized by the COR.
H.2.0 ENVIRONMENTAL INTERRUPTION OF WORK
H.2.1 Environmental - The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration. An allowance has been included in the contract time for environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger. The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions.
H.2.2 Endangered Species - The Government may direct the Contractor to discontinue all operations in the event that listed or proposed threatened or endangered plants or animals protected under the Endangered Species Act of 1973, as amended, are discovered to be present in or adjacent to the project area.
H.3.0 DRAWINGS
H.3.1 Reduced Size Drawings. Drawings appearing in this package may be photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. The Contractor may request full-size drawings from the COR.
H.4.0 PRESERVATION OF HISTORICAL AND ARCHEOLOGICAL DATA
H.4.1 Public Law 93-291, May 24, 1974, provides for the preservation of scientific, prehistorical, and archeological data
(including relics and specimens) which might otherwise be lost due to alteration of the terrain as a result of any Federal construction project.
H.4.2 The Contractor agrees that should any contractor employee, in the performance of this contract, discover evidence of possible scientific, prehistorical, historical, or archeological data the contractor will notify the Contracting Officer immediately in writing giving the location and nature of the findings.
mailto:IPPCustomerSupport@fiscal.treasury.gov
H.4.3 Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the applicable clauses in Section I of this contract.
H.4.4 The Contractor agrees to insert this requirement in all subcontracts which involve the performance of work on the terrain of the site.
H.5.0 SUBSTITUTION – PROCESSION OF WORK
Any proposed key personnel, minimum qualifications for incoming or replacement key personnel, subcontractors, processes, procedures or materials included in the quotation are hereby incorporated into the contract. Performance shall be limited to the personnel, qualifications, firms, procedures, and materials that were specifically identified in the
RFQ response. The Contractor shall obtain the Contracting Officer’s written consent before making any substitutions or changes. All substitutions or replacements shall comply with the terms and conditions of the contract.
H.6.0 ENVIRONMENTAL IMPACT
All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with
Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ); the
Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ); the Endangered Species Act, as amended (16 U.S.C. Sec
1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic
Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C.
6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ).
Should the United States Government be held liable for any neglect or improper actions by the contractor or any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.
H.7.0 HAZARDOUS MATERIALS
Any material suspected of being hazardous that is unexpectedly encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.
Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.
H.8.0 GREEN PROCUREMENT REQUIREMENTS
In the performance of this construction contract, the Contractor shall make maximum use of products identified on the mandatory environmental purchasing list at the following links, as applicable:
U.S. EPA Comprehensive Procurement Guidelines published at www.epa.gov/cpg/products.htm.
USDA Biobased product listings published at www.biopreferred.gov.
Energy Star® product listings published at www.energystar.gov/products.
FEMP Low Standby Power product listings published at http://energy.gov/eere/femp/covered-product-categories http://www.epa.gov/cpg/products.htm http://www.bioprefferd.gov/ http://www.energystar.gov/products http://energy.gov/eere/femp/covered-product-categories
Contractor shall comply with all reporting requirements of the following clauses when applicable (See Clause and
Provision sections):
52.223-1 Biobased Product Certification
52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts
52.223-4 Recovered Material Certification
52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items
52.223-15 Energy Efficiency in Energy Consuming Products
52.223-17 Affirmative Procurement of EPA Designated Items in Service and Construction Contracts
H.9.0 UNAUTHORIZED PERSONNEL
The contractor shall inform all personnel working under their jurisdiction (including subcontractor and visiting supplier personnel) that access to restricted areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.
H.10.0 DAVIS-BACON WAGE RATES APPLICABLE TO TRUCK DRIVERS
29 CFR 5.2(j) limits coverage of construction contractor or subcontractor employees performing as truck drivers under the Davis-Bacon Act (FAR 52.222-6) to only their time spent directly upon the "site of the work" or when hauling between the site of the work and a facility which is dedicated to and located in the proximity of the actual construction location. Other transportation of materials or supplies to or from the site of work by employees of the construction contractor or subcontractor is not “construction” at the site of work and accordingly is not subject to the Davis-Bacon
Act.
H.11.0 FIRE DANGER SEASON
If the COR allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.
(End of Section H)
SECTION I – CONTRACT CLAUSES
Clause Title Date
52.201-1 DEFINITIONS JUN 2020
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND
REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS
JUN 2020
52.203-18 PROHINITION ON CONTRACTING ENTITIES THAT REQUIRE CERTAIN
INTERNAL CONFIDENTIALTY AGREEMENTS OR STATEMENTS-
REPRESNTATION
JUN 2017
52.204-7 SYSTEM FOR AWARD MANAGEMENT OCT 2018
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL JAN 2011
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE OCT 2018
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND
CERTIFICATIONS
DEC 2014
52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017
52.204-23 PROHINITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND
SERVICES DEVELOPED BY KASPERSKY LAB AND OTHER COVERED
ENTITIES
NOV 2021
52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND
VIDEO SURVEILLANCE SERVICES OR EQUIPMENT
NOV 2021
52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS NOV 2021
AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT
52.204-26 COVERED TELECOMMUNICATIONS EQUIPMENT OR SERVICES-
REPRESENTATION
NOV 2021
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC
CORPORATIONS
NOV 2015
52.209-11 REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX
LIABILITY OR A FELONY CONVICTION UNDER ANY FEDERAL LAW.
FEB 2016
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK APR 1984
52.213-4 TERMS AND CONDITIONS-SIMPLIFIED ACQUISITIONS (OTHER THAN
COMMERCIAL ITEMS)
JUN 2023
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS. NOV 1999
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY APR 1991
52.219-1 SMALL BUSINESS PROGRAM REPRESENTATIONS. MAR 2023
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE NOV 2020
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION FEB 2024
52.222-3 CONVICT LABOR JUN 2003
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS AUG 2018
52.222-7 WITHHOLDING OF FUNDS MAY 2014
52.222-8 PAYROLLS AND BASIC RECORDS JUL 2021
52.222-9 APPRENTICES AND TRAINEES JULY 2005
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS FEB 1988
52.222-11 SUBCONTRACTS (LABOR STANDARDS) MAY 2014
52.222-12 CONTRACT TERMINATION – DEBARMENT MAY 2014
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND
RELATED REGULATIONS
MAY 2014
52.222-14 DISPUTES CONCERNING LABOR STANDARDS FEB 1988
52.222-15 CERTIFICATION OF ELIGIBILITY MAY 2014
52.222-21 PROHIBITION OF SEGREGATED FACILITIES APR 2015
52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS FEB 1999
52.222-25 AFFIRMATIVE ACTION COMPLIANCE APR 1984
52.222-26 EQUAL OPPORTUNITY SEP 2016
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR
CONSTRUCTION
APR 2015
52.222-30 CONSTRUCTION WAGE RATE REQUIREMENTS – PRICE ADJUSTMENT
(NONE OR SEPARATELY SPECIFIED PRICING METHOD
AUG 2018
52.222-31 CONSTRUCTION WAGE RATE REQUIREMENTS – PRICE ADJUSTMENT
(PERCENTAGE METHOD)
AUG 2018
52.222-50 COMBATING TRAFFICKING IN PERSONS OCT 2020
52.223-3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY FEB 2021
52.222-99 COMBATING RACE AND SEX STEREOTYPING. [(DEVIATION 20-09)]
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION. MAY 2011
52.223-6 DRUG-FREE WORKPLACE MAY 2001
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE
AND CONSTRUCTION CONTRACTS
AUG 2018
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING
WHILE DRIVING
JUN 2020
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES FEB 2021
52.225-25 PROHIBITION ON CONTRACTING WITH ENTITIES ENGAGING IN
CERTAIN ACTIVITIES OR TRANSACTIONS RELATING TO IRANIAN
REPRESENTATION AND CERTIFICATIONS
JUN 2020
52.227-4 PATENT INDEMNITY-CONSTRUCTION CONTRACTS DEC 2007
52.227-17 RIGHTS IN DATA—SPECIAL WORKS DEC 2007
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS MAY 2014
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS JAN 2017
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS JUN 2013
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS MAR 2023
SUBCONTRACTORS
52.233-3 PROTEST AFTER AWARD. AUG 1996
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM. OCT 2004
52.236-2 DIFFERING SITE CONDITIONS APR 1984
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984
52.236-5 MATERIAL AND WORKMANSHIP APR 1984
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984
52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT,
UTILITIES, AND IMPROVEMENTS
APR 1984
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984
52.236-12 CLEANING UP APR 1984
52.236-13 ACCIDENT PREVENTION NOV 1991
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES APR 1984
52.236-16 QUANTITY SURVEYS APR 1984
52.236-17 LAYOUT OF WORK APR 1984
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION FEB 1997
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION – ALTERNATE I APR 1984
52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995
52.236-27 SITE VISIT (CONSTRUCTION). FEB 1995
52.236-28 PREPARATION OF PROPOSALS-CONSTRUCTION. OCT 1997
52.242-14 SUSPENSION OF WORK. APR 1984
52.243-5 CHANGES AND CHANGED CONDITIONS APR 1984
52.245-1 GOVERNMENT PROPERTY. SEP 1991
52.245-9 USE AND CHARGES APR 2012
52.246-21 WARRANTY OF CONSTRUCTION MAR 1994
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) . APR 1984
52.252-2 CLAUSES INCORPORATED BY REFERENCE. FEB 1998
52.253-1 COMPUTER GENERATED FORMS. JAN 1991
1452.204-70 RELEASE OF CLAIMS - DEPARTMENT OF THE INTERIOR JUL 1996
The following clauses are provided in full text:
52.213-4 – TERMS AND CONDITIONS – SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL PRODUCTS
AND COMMERCIAL SERVICES (FEB 2024)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses that are incorporated by reference:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN
2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L. 113-
235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(ii) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by
Kaspersky Lab Covered Entities (DEC 2023) (Section 1634 of Pub. L. 115-91).
(iii) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or
Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).
(iv) 52.204-27, Prohibition on a ByteDance Covered Application (JUN 2023) (Section 102 of Division R of Pub. L.
117-328), unless the agency grants an exception - see paragraph (b) of 52.204-27.
https://www.acquisition.gov/far/52.203-19#FAR_52_203_19 https://www.acquisition.gov/far/52.204-23#FAR_52_204_23 https://www.acquisition.gov/far/52.204-25#FAR_52_204_25 https://www.acquisition.gov/far/52.204-27#FAR_52_204_27
(v) 52.204–30, Federal Acquisition Supply Chain Security Act Orders—Prohibition. (DEC 2023) (Pub. L. 115–
390, title II).
(vi) 52.222-3, Convict Labor (JUN 2003) (E.O.11755).
(vii) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
(viii) 52.222-26, Equal Opportunity (Sep 2016) (E.O.11246).
(ix) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
(x) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) ( 31 U.S.C.
3903 and 10 U.S.C. 3801).
(xi) 52.233-3, Protest After Award (AUG 1996) ( 31 U.S.C.3553).
(xii) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) ( Pub. L. 108-77 and 108-78 ( 19 U.S.C.
3805 note)).
(2) Listed below are additional clauses that apply:
(i) 52.232-1, Payments (APR 1984).
(ii) 52.232-8, Discounts for Prompt Payment (FEB 2002).
(iii) 52.232-11, Extras (APR 1984).
(iv) 52.232-25, Prompt Payment (JAN 2017).
(v) 52.232-39, Unenforceability of Unauthorized Obligations (JUN 2013).
(vi) 52.233-1, Disputes (MAY 2014).
(vii) 52.244-6, Subcontracts for Commercial Products and Commercial Services (DEC 2023).
(viii) 52.253-1, Computer Generated Forms (JAN 1991).
(b) The Contractor shall comply with the following FAR clauses, incorporated by reference, unless the circumstances do not apply:
(1) The clauses listed below implement provisions of law or Executive order:
(i) 52.203-17, Contractor Employee Whistleblower Rights (NOV 2023) ( 41 U.S.C. 4712); this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).
(ii) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020)(Pub. L. 109-
282) ( 31 U.S.C. 6101 note) (Applies to contracts valued at or above the threshold specified in FAR 4.1403(a) on the date of award of this contract).
(iii) 52.222-19, Child Labor-Cooperation with Authorities and Remedies (FEB 2024) (E.O. 13126) (Applies to contracts for supplies exceeding the micro-purchase threshold, as defined in 2.101 on the date of award of this contract).
https://www.acquisition.gov/far/52.204-30#FAR_52_204_30 https://www.acquisition.gov/far/52.222-3#FAR_52_222_3 https://www.acquisition.gov/far/52.222-21#FAR_52_222_21 https://www.acquisition.gov/far/52.222-26#FAR_52_222_26 https://www.acquisition.gov/far/52.225-13#FAR_52_225_13 https://www.acquisition.gov/far/52.232-40#FAR_52_232_40 https://www.govinfo.gov/link/uscode/31/3903 https://www.govinfo.gov/link/uscode/31/3903 https://www.govinfo.gov/link/uscode/10/3801 https://www.acquisition.gov/far/52.233-3#FAR_52_233_3 http://uscode.house.gov/browse.xhtml;jsessionid=114A3287C7B3359E597506A31FC855B3 https://www.acquisition.gov/far/52.233-4#FAR_52_233_4 https://www.govinfo.gov/link/plaw/108/public/77 https://www.govinfo.gov/link/uscode/19/3805 https://www.govinfo.gov/link/uscode/19/3805 https://www.acquisition.gov/far/52.232-1#FAR_52_232_1 https://www.acquisition.gov/far/52.232-8#FAR_52_232_8 https://www.acquisition.gov/far/52.232-11#FAR_52_232_11 https://www.acquisition.gov/far/52.232-25#FAR_52_232_25 https://www.acquisition.gov/far/52.232-39#FAR_52_232_39 https://www.acquisition.gov/far/52.233-1#FAR_52_233_1 https://www.acquisition.gov/far/52.244-6#FAR_52_244_6 https://www.acquisition.gov/far/52.253-1#FAR_52_253_1 https://www.acquisition.gov/far/52.203-17#FAR_52_203_17 https://www.govinfo.gov/link/uscode/41/4712 https://www.acquisition.gov/far/3.900#FAR_3_900 https://www.acquisition.gov/far/52.204-10#FAR_52_204_10 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/4.1403#FAR_4_1403 https://www.acquisition.gov/far/52.222-19#FAR_52_222_19 https://www.acquisition.gov/far/2.101#FAR_2_101
(iv) 52.222-20, Contracts for Materials, Supplies, Articles, and Equipment., Contracts for Materials, Supplies, Articles, and Equipment (JUN 2020) ( 41 U.S.C.chapter 65) (Applies to supply contracts over the threshold specified in FAR
22.602 on the date of award of this contract, in the United States,…
This is the start of the file's text. The full file is on GovTribe.