Sol_140F0321Q0062.pdf

PDF 320 KB Posted

Attached to
CA-SAN DIEGO NWR COMPLX-SOLAR PANEL SYS
Solicitation number
140F0321Q0062
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEE ADDENDUMIS CHECKED

CODE 18a. PAYMENT WILL BE MADE BY

CODE

FACILITYCODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER

OFFEROR

F01

PORTLAND OR 97232-4181

911 NE 11TH AVENUE

EASTSIDE FEDERAL COMPLEX

FWS, DIVISION OF CONTRACTING AND GE

0008350448 CODE 16. ADMINISTERED BYCODE

X

X

X

238210

SIZE STANDARD:

% FOR:SET ASIDE:UNRESTRICTED ORF03

RFPIFB

10. THIS ACQUISITION ISCODE

RFQ

14. METHOD OF SOLICITATION

13b. RATING

NAICS:

SMALL BUSINESS

09/06/2021 1700 PD

08/06/2021

5038722832Cindy Salazar (No collect calls)

INFORMATION CALL:

FOR SOLICITATION 8. OFFER DUE DATE/LOCAL TIMEb. TELEPHONE NUMBER a. NAME

4. ORDER NUMBER3. AWARD/ 6. SOLICITATION

140F0321Q0062

5. SOLICITATION NUMBER

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS 1. REQUISITION NUMBER PAGE OF

1 32 0040543046OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

TELEPHONE NO.

17a. CONTRACTOR/

Chula Vista CA 91910 1080 Gundpowder Point Drive FWS SAN DIEGO NWR Complex

15. DELIVER TO

Bloomington MN 55437-1458 5600 American Blvd West Suite

9. ISSUED BY

7.

2. CONTRACT NO.

EFFECTIVE DATE

$16.50

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW

ISSUE DATE

DELIVERY FOR FOB DESTINA-

TION UNLESS BLOCK IS

MARKED

11.

SEE SCHEDULEX

12. DISCOUNT TERMS

THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13a.

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

HUBZONE SMALL

BUSINESS

8(A)

U.S. Fish & Wildlife Service, Rgn 3

WOMEN-OWNED SMALL BUSINESS

(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM

EDWOSB

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

Submit quote to Cindy Salazar via email cindy_salazar@fws.gov.

See attached:

Performance Based Statement of Work DOL Wage Determination Legacy Doc #: FWS Delivery: 06/30/2022

Continued ...

(Use Reverse and/or Attach Additional Sheets as Necessary)

HEREIN, IS ACCEPTED AS TO ITEMS:

X

XX

DATED

Cindy Salazar

. YOUR OFFER ON SOLICITATION (BLOCK 5),

INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE SET FORTH

COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER

ARE

ARE

31c. DATE SIGNED

27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA

31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (Type or print)

ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL

SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.

27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

OFFER

STANDARD FORM 1449 (REV. 2/2012)

Prescribed by GSA - FAR (48 CFR) 53.212

ARE NOT ATTACHED.

ARE NOT ATTACHED.

AUTHORIZED FOR LOCAL REPRODUCTION

PREVIOUS EDITION IS NOT USABLE

30b. NAME AND TITLE OF SIGNER (Type or print)

30a. SIGNATURE OF OFFEROR/CONTRACTOR

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN

25. ACCOUNTING AND APPROPRIATION DATA

29. AWARD OF CONTRACT:

REF.

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32c. DATE 32b. SIGNATURE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED:

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED

40. PAID BY39. S/R VOUCHER NUMBER38. S/R ACCOUNT NUMBER

37. CHECK NUMBER

FINALPARTIAL

36. PAYMENT

FINALPARTIAL

35. AMOUNT VERIFIED

CORRECT FOR

34. VOUCHER NUMBER33. SHIP NUMBER

COMPLETE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

42d. TOTAL CONTAINERS42c. DATE REC'D (YY/MM/DD)

42b. RECEIVED AT (Location)

42a. RECEIVED BY (Print)

41c. DATE41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT

STANDARD FORM 1449 (REV. 2/2012) BACK

24.

AMOUNT

23.

UNIT PRICE

22.

UNIT

21.

QUANTITY

20.

SCHEDULE OF SUPPLIES/SERVICES

19.

ITEM NO.

00010 Solar panel system San Diego NWR

Period of Performance: 09/10/2020 to 06/30/2022

Design and installation of a solar panel system on the maintenance facility at San Diego National

Wildlife Refuge Complex maintenance garage. The solar panel system should be an approximately

20kW DC system to power a future fleet of electric vehicles and the mai ntenance garage.

This is for a firm fixed price contract.

32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32 2 of

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

San Diego National Wildlife Refuge Design & Install Solar Panel System

Table of Content

Section Title Page

A Solicitation/Contract Form 1

B Schedule of Items 4

C Description 4

D Packaging (Not Used) 4

E Inspection 5

F Deliveries 7

G Contract Administration 8

H Special Contract Requirements 9

I Contract Clauses 12

J

K

List of Attachments

Representation/Certifications

L

M

Instructions

Evaluations

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

Section B

Bid Schedule

1. Bid Schedule for Design and Install Solar Panel System, San Diego National Wildlife Refuge, Chula Vista, California.

(See Attached Bid Schedule to fill out)

Description Price

Design & Installation of Solar Panel System on Maintenance Facility

(See Performance Statement of Work for full description) Total $

Section C

Descriptions/Specifications/Work Statement

The U.S. Fish & Wildlife Service has been asked to solicit for San Diego National Wildlife Refuge, Chula Vista, California. San Diego National Wildlife Refuge has a requirement to design & install solar panel system.

The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to design and install a solar panel system as described in the Performance Work Statement.

Please reference the attached Performance Statement of Work for complete description and additional information and Davis Bacon wage determination.

This section consists of the following:

1) Performance Statement of Work

2) Construction Wage Rates (Davis Bacon)

(See Section J. for List of Attachments.)

Section D

Packing and Marking

(NOT USED)

Section E

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

Inspection and Acceptance

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.246-12 Inspection Of Construction AUGUST 1996

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not—

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes re-inspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may—

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

(End of clause)

52.246-21 Warranty of Construction (Mar 1994)

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

(c) The Contractor shall remedy at the Contractor’s expense any failure to conform, or any defect. In addition, the Contractor shall remedy at the Contractor’s expense any damage to Government-owned or controlled real or personal property, when that damage is the result of --

(1) The Contractor’s failure to conform to contract requirements; or

(2) Any defect of equipment, material, workmanship, or design furnished.

(d) The Contractor shall restore any work damaged in fulfilling the terms and conditions of this clause. The Contractor’s warranty with respect to work repaired or replaced will run for 1 year from the date of repair or replacement.

(e) The Contracting Officer shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage.

(f) If the Contractor fails to remedy any failure, defect, or damage within a reasonable time after receipt of notice, the Government shall have the right to replace, repair, or otherwise remedy the failure, defect, or damage at the Contractor’s expense.

(g) With respect to all warranties, express or implied, from subcontractors, manufacturers, or suppliers for work performed and materials furnished under this contract, the Contractor shall --

(1) Obtain all warranties that would be given in normal commercial practice;

(2) Require all warranties to be executed, in writing, for the benefit of the Government, if directed by the Contracting Officer; and

(3) Enforce all warranties for the benefit of the Government, if directed by the Contracting Officer.

(h) In the event the Contractor’s warranty under paragraph (b) of this clause has expired, the Government may bring suit at its expense to enforce a subcontractor’s, manufacturers, or supplier’s warranty.

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(i) Unless a defect is caused by the negligence of the Contractor or subcontractor or supplier at any tier, the Contractor shall not be liable for the repair of any defects of material or design furnished by the Government or for the repair of any damage that results from any defect in Government-furnished material or design.

(j) This warranty shall not limit the Government’s rights under the Inspection and Acceptance clause of this contract with respect to latent defects, gross mistakes, or fraud.

(End of Clause)

Section F

Deliveries or Performance

52.211-18 Variation in Estimated Quantity (APR 1984)

52.242-15 Stop-Work Order (AUG 1989)

52.211-10 COMMENCEMENT, PROSECUTIONS, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than (to be determined at time of award). The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.242-14 Suspension of Work (APR 1984)

SUSPENSION OF WORK (APR 1984)

(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.

(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly.

However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.

(c) A claim under this clause shall not be allowed—

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

(End of clause)

Section G

CONTRACT ADMINISTRATION

CONTRACTING OFFICER'S REPRESENTATIVE DEFINITION

Contracting officer’s representative (COR)” means an individual, including a contracting officer’s technical representative (COTR), designated and authorized in writing by the contracting officer to perform specific technical or administrative functions.

PROJECT INSPECTOR DEFINITION

“Project Inspector” is the designated Government personnel that perform the on-the-job Government inspection of work accomplished by the Contractor.

RESPONSIBILITIES OF THE CONTRACTING OFFICER'S REPRESENTATIVE AND PROJECT

INSPECTOR

The COR’s authorities and responsibilities are defined in the COR’s Designation Letter. The COR is authorized to clarify technical requirements, and to review and approve work which is clearly within the scope of work. The COR is NOT authorized to issue changes or modify the scope of work in any way.

The Project Inspector is responsible for verifying the Contractor’s compliance with the technical specifications, drawings, work schedule, and labor provisions at the site of the work.

1.602-1 AUTHORITY

(a) Contracting officers have authority to enter into, administer, or terminate contracts and make related determinations and findings. Contracting officers may bind the Government only to the extent of the authority delegated to them. Contracting officers shall receive from the appointing authority (see 1.603-1) clear instructions in writing regarding the limits of their authority. Information on the limits of the contracting officers’ authority shall be readily available to the public and agency personnel.

(b) No contract shall be entered into unless the contracting officer ensures that all requirements of law, executive orders, regulations, and all other applicable procedures, including clearances and approvals, have been met.

DOI Electronic Invoicing and Payment Requirements – Invoice Processing Platform (IPP) (April 2013)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

https://www.acquisition.gov/far/html/Subpart%201_6.html#wp1050962

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts.

The IPP website address is: https://www.ipp.gov.

The following documents are required to be submitted as an attachment to the IPP System: Invoice

The Contractor must use the IPP website to register; access and use IPP for submitting requests for payment.

The Contractor Government Business Point of Contact (as listed in SAM will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date.

Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Clause)

Section H

Special Contract Requirements

Project Management

The Contractor shall have a competent Project Manager o r S u p e r v i s o r on-site for this contract, to supervise all phases of the contract, for the duration of on-site performance and until final inspection and acceptance of the work. The Project Manager shall have the authority to act for the Contractor and his/her name shall be submitted in writing to the Contracting Officer. The Contractor shall be responsible for the actions of the Project Manager who is acting in his behalf. Notification of deficiencies and problems, made to the Project Manager by the Government, shall effectively be notice to the Contractor of those deficiencies and problems.

2. Damages

(a) The Contractor shall assume all risks of injury to persons or property in connection with the performance of work under this contract and shall indemnify and save harmless the Government against all claims, causes of action, cost and expense, because of bodily injuries or death or damages to property arising from work activities of the Contractor.

(a) The Contractor shall not cut, remove, or knock down fences or leave any gate open without specific permission of the landowner or person in charge of the property.

(c) The Contractor shall not use any materials, w h i c h are poisonous or hazardous to animals.

https://www.ipp.gov/

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(d) The Contractor shall exercise extreme care so as to prevent the start or spread of fire and to prevent any damage to property. The Contractor shall leave the property as undisturbed as possible prior to departure.

3. Accident Prevention

(a) The Contractor shall, at all times, exercise reasonable precautions and provide for protecting the lives and health of employees and other persons in the performance of work under this contract.

Specifically, the Contractor shall comply with all applicable provisions of federal, state, local, safety, health, and sanitation laws, codes and regulations.

(b) The Contractor shall maintain an accurate record of and shall report to the Contracting Officer in the manner and on forms prescribed by the Contracting Officer, all causes of death, occupational diseases, traumatic injuries, lost-time accidents, or damage to property arising out of or in the course of employment incidental to performance of the work under this contract.

4. Clean-Up

(a) Except for monuments, witness posts and reference posts established by the Contractor, in accordance with the provisions of the contract, the Contractor shall remove all flags, markers, paneling, targets, stakes, rubbish, unused material, and any other materials belonging to the Contractor or used under the Contractor's direction during the performance of work under this contract.

(b) In the event the Contractor does not remove all materials and in terms discussed above, the Government may remove those items at the expense of the Contractor. Any monies due the Contractor may be offset by reasonable charges for this removal. If sureties are involved, they may also be liable for the costs for this removal effort.

5. Subcontracts (if applicable)

(a) The Contractor shall not, without prior written approval by the Contracting Officer, enter into any subcontract for any portions of the work directed by this contract.

(b) The Contracting Officer's approval of a subcontract will not in any way relieve the Contractor of full responsibility for satisfactory completion of all work directed under this contract.

(c) The Contractor shall be responsible for subcontractor compliance with all applicable requirements of this contract.

(d) No contractual relationship shall be created between the Government and the Contractor's subcontractors.

6. Meetings and Progress Reports

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(a) During the execution of field operations under this contract, the Contractor shall meet periodically with the Contracting Officer or the COR at the site at mutually agreed times. The purpose of the meetings is to obtain information on the progress of the fieldw ork .

7. Special Instructions

(a) Accuracy The Contractor's attention is directed to the fact that the precision, accuracy, and completeness of the work called for by this contract are essential. The detailed requirements of the contract will be rigidly interpreted and applied in determining the acceptability of the field work accomplished, monuments 'set' and referenced, and data delivered.

(b) Performance of Work by the Government Nothing in this contract shall be construed or interpreted to prohibit or restrict the Government's right to have Government employees perform work of the type covered by this contract.

8. Ordering

The Contracting Officer is the only person authorized to order work under this contract.

9. Work Hours

Work hours under this contract shall be limited to normal duty hours as stated in the Statement of Work. No work will be done on Saturday, Sunday, or legal National Holidays unless authorized by the COR.

10. Environmental Interruption of Work

The Contracting Officer, by issuance of a suspend work order, may direct the Contractor to shut down any work that may be subject to damage due to weather conditions, fire danger, or because it is impracticable to work during the winter season. The Contractor will be given a resume work order which will document the date the work suspension ends. An allowance has been included in the contract time for all environmental delays. The count of contract time will therefore continue during all periods of suspension due to normal weather conditions, including fire danger.

The Contractor will not be entitled to additional contract time for any suspensions except to the extent that they are due to unusually severe weather conditions. The Contractor will not be entitled to additional monetary compensation for such suspensions regardless of duration.

11. Hazardous Materials

All waste materials generated by any work under the contract performed on a Government installation shall at all times be handled, transported, stored, and disposed of by the contractor and by his subcontractors in accordance with all applicable Federal, state, and local laws, ordinances, regulations, court orders, and other types of rulings having the effect of the law, including, but not limited to Executive Order 12088, 13 October 1978, Federal Compliance with Pollution Control Standards; the Federal Water Pollution Control Act, as amended (33 U.S.C. 1251 ET SEQ);

the Clean Air Act as amended (42 U.S.C. Sec 7401 ET SEQ); the Endangered Species Act, as amended (16 U.S.C.

Sec 1531, ET SEQ); the Toxic Substances Control Act, as amended (15 U.S.C. Sec 2601, ET SEQ); the National Historic Preservation Act, as amended (16 U.S.C. Sec 470, ET SEQ); the Solid Waste Disposal Act, as amended (42 U.S.C. 6901 ET SEQ); and the Archaeological and Historic Preservation Act, as amended (16 U.S.C. Sec 469, ET SEQ). Should the United States Government be held liable for any neglect or improper actions by the contractor or

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System any subcontractor regarding removal or disposal of any hazardous waste, the contractor shall reimburse the Government for all such liability.

Any material suspected of being hazardous that is encountered during performance of a project shall immediately be brought to the attention of the Contracting Officer, at which time a determination will be made as to whether hazardous material testing shall be performed. If the Contracting Officer directs the contractor to perform tests, and/or the material is found to be of a hazardous nature requiring additional protective measures, a contract modification may be required, subject to equitable adjustment under the terms of the contract. The contractor is advised that friable and/or non-friable asbestos-containing material may be encountered in project areas. Friable asbestos-containing material is any material that contains more than one percent asbestos by weight, and that hand pressure can crumble, pulverize or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturation, impregnation or coating.

Non-friable asbestos-containing materials do not normally release airborne asbestos fiber during routine handling and end-use. However, excessive fiber concentrations may be produced during uncontrolled abrading, sanding, drilling, cutting, machining, removal, demolition, or other similar activities. 29 CFR 1910.1001 shall be referenced in the event asbestos-containing materials are encountered. Friable asbestos-containing materials are not authorized for use in new construction or maintenance projects.

12. Unauthorized Personnel

The contractor shall inform all personnel working under his jurisdiction (including subcontractor and visiting supplier personnel) that access to areas outside of the immediate work area; excluding direct haul and access routes, contracting and Civil Engineering offices and points of supply and storage; is prohibited. Circulation of said personnel will be limited to official business only. Persons in violation of the above will be apprehended and appropriately disciplined.

14. Wage rates

Applicable Construction Wage Rates (Davis Bacon) shall apply and will be included.

Section I

Contract Clauses

52.252-2 Clauses Incorporated by Reference. (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://www.acquisition.gov/far/

52.203-7 Anti-Kickback Procedures (JUN 2020)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017)

52.204-7 System for Award Management (OCT 2018)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUN 2020) http://www.acquisition.gov/far/

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

52.204-16 Commercial and Government Entity Code Reporting (AUG 2020)

52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020)

52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)

52.204-22 Alternative Line Item Proposal (JAN 2017)

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (JUL 2018)

52..204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (AUG 2020)

52.209-6 Protecting the Government’s Interest When Subcontracting with Contractors Debarred, Suspended or Proposed for Debarment (JUN 2020)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015)

52.209-13 Violation of Arms Control Treaties or Agreements – Certification (FEB 2021)

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

52.211-12 Liquidated Damages-Construction (SEPT 2000)

52.211-13 Time Extensions (SEPT 2000)

52.211-18 Variation in Estimated Quantity (APR 1984)

52.222-3 Convict Labor. (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards – Overtime Compensation (MAR 2018)

52.222-6 Construction Wage Rate Requirements. (AUG 2018)

52.222-7 Withholding of Funds. (MAY 2014)

52.222-8 Payrolls and Basic Records. (AUG 2018)

52.222-9 Apprentices and Trainees. (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)

52.222-11 Subcontracts (Labor Standards). (MAY 2014)

52.222-12 Contract Termination - Debarment. (MAY 2014)

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988)

52.222-15 Certification of Eligibility. (MAY 2014)

52.222-21 Prohibition of Segregated Facilities. (APR 2015)

52.222-26 Equal Opportunity. (SEP 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015)

52.222-35 Equal Opportunity for Veterans. (JUN 2020)

52.222-36 Affirmative Action for Workers with Disabilities. (JUN 2020)

52.222-37 Employment Reports on Veterans. (JUN 2020)

52.222-40 Notification of Employee Rights Under the National Labor Relations Act (DEC 2010)

52.222-50 Combating Trafficking in Persons. (OCT 2020)

52.222-55 Minimum Wages Under Executive Order 13658 (NOV 2020)

52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 17)

52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2011)

52.223-6 Drug-Free Workplace (MAY 2001)

52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016)

52.223-17 Affirmative Procurement of EPA-designated Items in Service and Construction Contracts (AUG 2018)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (JUN 2020)

52.223-20 Aerosols (JUN 2016)

52.223-21 Foams (JUN 2016)

52.225-9 Buy American-Construction Materials (FEB 2021)

52.225-10 Notice of Buy American Requirement-Construction Materials (MAY 2014)

52.225-13 Restrictions on Certain Foreign Purchases. (FEB 2021)

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

52.226-1 Utilization of Indian Organization and Indian-Owned Economic Enterprises (JUN 2000)

52.227-1 Authorization and Consent. (JUN 2020)

52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement. (JUN 2020)

52.227-4 Patent Indemnity – Construction Contracts (DEC 2007)

52.228-2 Additional Bond Security (OCT 1997)

52.228-5 Insurance - Work on a Government Installation. (JAN 1997)

52.228-11 Pledges of Assets (FEB 2018)

52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014)

52.228-14 Irrevocable Letter of Credit (NOV 2014)

52.228-15 Performance and Payment Bonds – Construction (JUN 2020)

52.229-3 Federal, State, and Local Taxes. (FEB 2013)

52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014)

52.232-17 Interest. (MAY 2014)

52.232-23 Assignment of Claims. (MAY 2014)

52.232-27 Prompt Payment For Construction Contracts. (JAN 2017)

52.232-33 Payment by Electronic Funds Transfer – System for Award Management. (OCT 2018)

52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (DEC 2013)

52.233-1 Disputes. (MAY 2014) {Alternate I (DEC1991)

52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

52.236-2 Differing Site Conditions. (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984)

52.236-5 Material and Workmanship. (APR 1984)

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

52.236-6 Superintendence by the Contractor. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-8 Other Contracts. (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984)

52.236-11 Use and Possession Prior to Completion. (APR 1984)

52.236-12 Cleaning Up. (APR 1984)

52.236-13 Accident Prevention. (NOV 1991)

52.236-14 Availability and Use of Utility Services. (APR 1984)

52.236-15 Schedules for Construction Contracts. (APR 1984)

52.236-17 Layout of Work (APR 1984)

52.236-21 Specifications and Drawings for Construction. (FEB 1997)

52.236-26 Preconstruction Conference. (FEB 1995)

52.242-13 Bankruptcy. (JUL 1995)

52.242-14 Suspension of Work. (APR 1984)

52.243-4 Changes. (JUN 2007)

52.244-2 Subcontracts (JUN 2020)

52.244-6 Subcontracts for Commercial Items. (NOV 2020)

52.246-12 Inspection of Construction. (APR 1996)

52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements. (AUG 1996)

52.246-21 Alt I Warranty of Construction. (MAR 1994) , Alt 1(APR 1984)

52.248-3 Value Engineering - Construction. (OCT 2020)

52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012), Alt 1 (SEP 1996)

52.249-3 Termination for Convenience of the Government (Dismantling, Demolition, or Removal of Improvements)

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(APR 2012)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

52.253-1 Computer Generated Forms. (JAN 1991)

1452.201-70 Authorities and Delegations (SEP 2011)

1452.203-70 Restrictions on Endorsements (JUL 1996)

1452.204-70 Release of Claims (JUL 1996)

1452.215-70 Examination of Records by the Department of the Interior (APR 1984)

1452.215-71 Use and Disclosure of Proposal Information (APR 1984)

1452.236-70 Prohibition Against Use of Lead-Based Paint (JUL 1996)

CLAUSES IN FULL TEXT

52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998) This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://www.acquisition.gov/far/

(End of provision)

52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment.

As prescribed in 4.2105(a), insert the following provision:

Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Oct 2020)

The Offeror shall not complete the representation at paragraph (d)(1) of this provision if the Offeror has represented that it "does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument" in paragraph (c)(1) in the provision at 52.204-26, Covered Telecommunications Equipment or Services— Representation, or in paragraph (v)(2)(i) of the provision at 52.212-3, Offeror Representations and Certifications- Commercial Items. The Offeror shall not complete the representation in paragraph (d)(2) of this provision if the Offeror has represented that it "does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services" in paragraph (c)(2) of the provision at 52.204-26, or in paragraph (v)(2)(ii) of the provision at 52.212-3.

http://www.acquisition.gov/far/ https://www.acquisition.gov/far/4.2105#FAR_4_2105 https://www.acquisition.gov/far/52.204-26#FAR_52_204_26 https://www.acquisition.gov/far/52.212-3#FAR_52_212_3 https://www.acquisition.gov/far/52.204-26#FAR_52_204_26 https://www.acquisition.gov/far/52.212-3#FAR_52_212_3

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(a) Definitions. As used in this provision—

Backhaul, covered telecommunications equipment or services, critical technology, interconnection arrangements, reasonable inquiry, roaming, and substantial or essential component have the meanings provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Prohibition.

(1) Section 889(a)(1)(A) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L.

115-232) prohibits the head of an executive agency on or after August 13, 2019, from procuring or obtaining, or extending or renewing a contract to procure or obtain, any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. Nothing in the prohibition shall be construed to—

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(2) Section 889(a)(1)(B) of the John S. McCain National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115-232) prohibits the head of an executive agency on or after August 13, 2020, from entering into a contract or extending or renewing a contract with an entity that uses any equipment, system, or service that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system. This prohibition applies to the use of covered telecommunications equipment or services, regardless of whether that use is in performance of work under a Federal contract. Nothing in the prohibition shall be construed to—

(i) Prohibit the head of an executive agency from procuring with an entity to provide a service that connects to the facilities of a third-party, such as backhaul, roaming, or interconnection arrangements; or

(ii) Cover telecommunications equipment that cannot route or redirect user data traffic or cannot permit visibility into any user data or packets that such equipment transmits or otherwise handles.

(c) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services".

(d) Representation. The Offeror represents that—

(1) It □ will, □ will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation. The Offeror shall provide the additional disclosure information required at paragraph (e)(1) of this section if the Offeror responds "will" in paragraph (d)(1) of this section; and

(2) After conducting a reasonable inquiry, for purposes of this representation, the Offeror represents that—

It □ does, □ does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services. The Offeror shall provide the additional https://www.acquisition.gov/far/52.204-25#FAR_52_204_25 https://www.sam.gov/

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System disclosure information required at paragraph (e)(2) of this section if the Offeror responds "does" in paragraph (d)(2) of this section.

(e) Disclosures.

(1) Disclosure for the representation in paragraph (d)(1) of this provision. If the Offeror has responded "will" in the representation in paragraph (d)(1) of this provision, the Offeror shall provide the following information as part of the offer:

(i) For covered equipment—

(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the original equipment manufacturer (OEM) or a distributor, if known);

(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and

(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.

(ii) For covered services—

(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or

(B) If not associated with maintenance, the Product Service Code (PSC) of the service being provided;

and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(1) of this provision.

(2) Disclosure for the representation in paragraph (d)(2) of this provision. If the Offeror has responded "does" in the representation in paragraph (d)(2) of this provision, the Offeror shall provide the following information as part of the offer:

(i) For covered equipment—

(A) The entity that produced the covered telecommunications equipment (include entity name, unique entity identifier, CAGE code, and whether the entity was the OEM or a distributor, if known);

(B) A description of all covered telecommunications equipment offered (include brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); and

(C) Explanation of the proposed use of covered telecommunications equipment and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.

(ii) For covered services—

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(A) If the service is related to item maintenance: A description of all covered telecommunications services offered (include on the item being maintained: Brand; model number, such as OEM number, manufacturer part number, or wholesaler number; and item description, as applicable); or

(B) If not associated with maintenance, the PSC of the service being provided; and explanation of the proposed use of covered telecommunications services and any factors relevant to determining if such use would be permissible under the prohibition in paragraph (b)(2) of this provision.

(End of provision)

52.204-26 Covered Telecommunications Equipment or Services-Representation.

As prescribed in 4.2105(c), insert the following provision:

Covered Telecommunications Equipment or Services-Representation (Oct 2020)

(a) Definitions. As used in this provision, "covered telecommunications equipment or services" and "reasonable inquiry" have the meaning provided in the clause 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

(b) Procedures. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) (https://www.sam.gov) for entities excluded from receiving federal awards for "covered telecommunications equipment or services".

(c) (1) Representation. The Offeror represents that it □ does, □ does not provide covered telecommunications equipment or services as a part of its offered products or services to the Government in the performance of any contract, subcontract, or other contractual instrument.

(2) After conducting a reasonable inquiry for purposes of this representation, the offeror represents that it □ does, □ does not use covered telecommunications equipment or services, or any equipment, system, or service that uses covered telecommunications equipment or services.

(End of provision)

52.225-9 Buy American-Construction Materials.

As prescribed in 25.1102(a), insert the following clause:

Buy American-Construction Materials (Feb 2021)

(a) Definitions. As used in this clause—

Commercially available off-the-shelf (COTS) item—

(1) Means any item of supply (including construction material) that is–

(i) A commercial item (as defined in paragraph (1) of the definition at Federal Acquisition Regulation

(FAR) 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and https://www.acquisition.gov/far/4.2105#FAR_4_2105 https://www.acquisition.gov/far/52.204-25#FAR_52_204_25 https://www.sam.gov/ https://www.acquisition.gov/far/25.1102#FAR_25_1102 https://www.acquisition.gov/far/2.101#FAR_2_101

Solicitation No. 140F0321Q0062 Solicitation No. 140F0121R0002

Design & Install Solar Panel System

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site.

Materials purchased directly by the Government are supplies, not construction material.

Cost of components means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

Domestic construction material means—

(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-

(i) An unmanufactured construction material mined or produced in the United States; or

(ii) A construction material manufactured in the United States, if–

(A) The cost of its components mined, produced, or manufactured in the United States exceeds 55 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic.