SOI Document.pdf

PDF 104 KB Posted

Attached to
A&E Services, BHSU Campus, Water Main Replacement
Solicitation number
24SOI10684
Issued by
Kingsbury County, South Dakota

About this file

This document is a Request for Statement of Interest (SOI) from the State of South Dakota's Office of the State Engineer (OSE) for professional services related to the design, bid, and construction of a water main replacement project at the Black Hills State University (BHSU) campus in Spearfish, South Dakota. The project, identified as OSE# R0824--06X/ARPA, is funded through the American Rescue Plan Act (ARPA) and must be executed by December 31, 2024. Firms interested in providing these services are requested to submit statements of interest addressing qualifications and experience by 3:00 pm MT on Thursday, April 25, 2024. Evaluation criteria include specialized expertise, available resources, past performance, project locale familiarity, and proposed project management techniques. Firms seeking additional site/project information should contact the OSE Project Engineer, Camilla Widvey, or the BHSU Director of Facilities Services, Randy Culver, to schedule a site visit.

The construction budget for the project is $1,650,000, but this amount is subject to change. Construction is anticipated to begin in August 2024 and be completed by December 2024. The SOI submission requirements and evaluation criteria are detailed in the document. No information is provided regarding pricing terms, set asides, incumbents, funding sources, or other salient details.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

March 26, 2024

RE: REQUEST FOR STATEMENT OF INTEREST

CAMPUS, WATER MAIN REPLACEMENT

BLACK HILLS STATE UNIVERSITY

SPEARFISH, SOUTH DAKOTA

OSE# R0824--06X/ARPA

The State is looking for firms interested in providing professional services for the project referenced above.

The project scope will involve the design, bid and construction for Campus, Water Main Replacement at the Black Hills State University in Spearfish, South Dakota, OSE # R0824--06X/ARPA.

The Black Hills State University (BHSU) campus is located within the city of Spearfish, South Dakota. The existing main water line is original from the 1940s and needs replaced due to significant breaks that are occurring. This project is American Rescue Plan Act (ARPA) funded. This funding has a requirement to have all contracts, including design and construction, executed by December 31, 2024. Due to this timeline, great emphasis during scoring will be on availability to complete the design in an expedited manner.

The construction budget for the project is $1,650,000, but be advised that this number is subject to change.

Construction is anticipated to start in August 2024 and be completed in December 2024.

Firms desiring to be considered for providing professional services for this project should send a statement of interest that outlines qualifications and experience for this project. Statements of Interest should at a minimum include the following:

1. Specialized expertise, capabilities, and technical competence as demonstrated by the team's capabilities, proposed approach and methodology to meet the project requirements. (20%)

2. Resources available to perform the work, including any specialized services, within the specified time limits for the project. Include resumes of all personnel, including sub-consultants who will be assigned to this project for the entire duration. (40%)

3. Record of past performance, including price and cost data from previous projects, quality of work, ability to meet schedules, cost control, and contract administration. (10%)

4. Availability to project locale. (5%)

5. Familiarity with project locale. (5%)

6. Proposed project management techniques. (10%)

7. Ability and project history in handling special project constraints. (10%)

A technical review committee will select the firm based on the criteria shown. The committee respectfully requests that statements of interest be limited to 25 pages or less. This is not a requirement; merely a request.

Copies of the statement of interest must be submitted by 3:00 pm MT on Thursday, April 25, 2024. Please send electronic copies (as an e-mail attachment) as quantified to each of the following:

Camilla Widvey, P.E., Project Engineer Randy Culver Office of the State Engineer Director Facilities Services Joe Foss Building Black Hills State University

523 E. Capitol Avenue 1200 University Street Pierre, SD 57501-3182 Spearfish, SD 57799 Phone: 605-910-4799 Phone: 605-642-6157 E-mail: cami.widvey@state.sd.us E-mail: randy.culver@bhsu.edu

Firms wanting additional site/project information should contact the OSE Project Engineer, Camilla Widvey.

To schedule a site visit contact Randy Culver. Thank you for your interest in this project; we look forward to working with you.

Respectfully, Stacy Watters, PE State Engineer

CC: Camilla Widvey, PE, OSE Randy Culver, BHSU mailto:cami.widvey@state.sd.us mailto:randy.culver@bhsu.edu

File details come from the government source that posted it. Updated .