SO-21-001 SOW Wartsila Cylinder Ovhl.docx

DOCX document 38 KB Posted

Attached to
Wartsila overhaul of steering and reverse steering cylinders
Solicitation number
N3220521Q2187
Issued by

View the file

Other files

File Type Posted
QUALITY ASSURANCE SURVEILLANCE PLAN (003).docx DOCX document
COMBINED SYNOPSIS N3220521Q2187.docx DOCX document
52.204-24 required doc.pdf PDF
TAX LIABILITY FORM.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS NEWPORT

(EPF 12)

MACHINERY, PROPULSIONSERVICE ORDER 21-001
27 November 2020
ITEM NO. SO-21-001CATEGORY “A”MSC/Midkiff/SM

WARTSILA CYLINDER OVERHAUL

1.0 ABSTRACT

1.1 This item describes OEM services for the Wartsila waterjet System to overhaul the EPF class waterjet steering and reversing cylinders.

2.0 REFERENCES: None

3.0 ITEM LOCATION/DESCRIPTION:

3.1 Locations: Contractors Facility

3.2 Quantity:

3.2.1 32 (thirty two) each waterjet steering cylinders, P/N PAAI034123

3.2.2 16 (sixteen) each waterjet reversing cylinders, P/N PAAI034122

4.0 GOVERNMENT FURNISHED MATERIAL/EQUIPMENT/SERVICE: NONE

5.0 NOTES:

5.1 Performance Period: 1 June, 2021 – 20 September 2021

5.2 Port Engineer:

Stephen Midkiff Cell: 757-376-7943 Email: stephen.midkiff@navy.mil

6.0 QUALITY ASSURANCE REQUIREMENTS:

6.1 Perform system pressure test and operational test with in the presence on ABS and MSCREP.

7.0 STATEMENT OF WORK REQUIRED:

7.1 Provide the service of Wartsila waterjet OEM facility to take receipt of items described in para 3.0 and perform the following:

7.1.1 Disassemble cylinders, replace all seals, sensors, and wear items with OEM material.

7.1.2 Reassemble cylinders and calibrate feedback sensors.

7.1.3 Pressure test cylinders to OEM specifications and proved feedback readings in the presence of ABS. Provide test report to MSCREP upon completion of testing.

7.1.4 Prep, prime and paint cylinders to match existing.

7.1.5 Package each cylinder individually for international shipment and notify MSCREP for shipment.

7.2 Contractor shall furnish an as found condition and completion report stating work performed and cylinder condition at completion.

7.3 Manufacturer’s OEM Representative:

7.3.1 Erin Lake

Project Manager
Wartsila Defense Inc
Chesapeake, VA23323 USA

Office (757) 434-7432 erin.lake@wartsiladefense.com www.wartsila.com

8.0 GENERAL REQUIREMENTS: NONE