This statement of work outlines requirements for the installation of a Smartrack equipment tracking system at the 321st Special Tactics Squadron located at Royal Air Force Lakenheath in the United Kingdom. The contractor will provide all necessary hardware, software, scanners, cabling, RFID sensors and input STS equipment into the Smartrack system. The contractor will also train work center personnel on operating the system. The system will track over $20 million in COMSEC, CA/CRL and other equipment to provide accountability and maintain historical records. The contractor must successfully integrate all work under the contract and respond promptly to government requests. Installation must be completed between the hours of 0800-1700 local UK time, Monday through Friday excluding UK and US holidays.

The related federal contract opportunity posted by the 48th Contracting Squadron seeks a Smartrack equipment tracking system utilizing RFID for the 321st Special Tactics Squadron at RAF Mildenhall. Interested parties should respond to solicitation number FA558721Q0064. The Department of the Air Force and United States Air Forces in Europe - Air Forces Africa are listed as the contracting agencies.

View the file

Other files for this federal contract opportunity

Other files attached to Smartrack System, newest first.
File Type Posted
Combined- FA558721Q0064 Update.pdf PDF
Brand Name Smartrack_Redacted.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

(SOW)

321 STS Smartrack Install at

Royal Air Force (RAF) Lakenheath

Rev. 1, 1 Feb 2021

1.0 Introduction

1.1 Mission: The 321 STS provides a Quick reaction, Rapid deployment force to establish and provide air-to-ground control during special operations or conventional missions. Its combat controllers and pararescuemen conduct the reconnaissance, surveillance, assessment, and creation of assault zone sites and provide air traffic control and long-range secure command and control missions. They also provide combat trauma medical care, personnel recovery and terminal attack control of munitions delivered by fixed- and rotary-wing aircraft. The highly deployable requirements of the operators and the quantity of the equipment needed in their support requires a digital means of tracking the equipment. We expect the contractor to provide the same or similar tracking system they have provided to the stateside STS units.

1.2 Background: The installation of the Smartrack will replace the already removed EPAS equipment tracking system.

It will provide accountability for over $20M of COMSEC, CA/CRL, and other equipment/inventory in 4 work-centers. It will also provide a routine maintenance tracker as well as keep historical records on all equipment. The system will also meet the requirement for the 720th OSS to be able to view our inventory and pull a report at any time.

1.3 Scope: “Williams Software Associates Corp” will install the Smartrack system. To include all hardware and software, scanners, cabling, and RFID sensors. They will input the STS equipment into the software and train the work-centers on its use.

2.0 General Requirements

2.1 Business Relations: The Contractor shall successfully integrate and coordinate all activity needed to execute this requirement. The Contractor shall manage the timeliness, completeness, and quality of problem identification. The Contractor shall promptly identify issues to the Government and take timely corrective action. The Contractor shall seek to ensure mission partner satisfaction and professional and ethical behavior of all contractor personnel.

2.2 Contract Management & Administration

2.2.1 Contract Management: The Contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of resources assigned to the requirement. The Contractor must maintain continuity between the mission partner and the contractor’s corporate offices.

2.2.2 Contract Administration: The Contractor shall establish processes and assign appropriate resources to effectively administer the contract. The Contractor shall respond to the Governments requests for contractual actions in a timely fashion. The Contractor shall have a single point of contact between the Government and contractor personnel assigned to support the contract. The Contractor shall assign resources in order to maintain proper and accurate records related to this contract.

2.3 Subcontract Management: If applicable, the Contractor shall be responsible for any subcontractor and any subcontractor management necessary to integrated work executed under this contract.

2.4 Hours of Work: Work days are from Monday through Friday excluding US federal holidays and UK bank holidays.

Work hours are from 0800 to 1700 local UK time.

3.0 Product Specifications & Installation Requirements

3.1 The contractor must provide all personnel, equipment, tools, materials, supervision, transportation, safety equipment, any other items and services necessary to install the Smartrack system. To include all hardware and software, scanners, cabling, and RFID sensors. They will input the STS equipment into the software and train the work-centers on its use.

4.3.1.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either include the shipping in the costs of the items, or outline it in a separate line item).

4.3.1.3 The Government will provide the shipping address as part of the solicitation document. Additionally, the Government will provide the vendor with the point of contact at the physical destination delivery address.

4.3.2 For vendors located outside of the United Kingdom.

4.3.2.1 Option One: United States Postal Service.

4.3.2.1.1 Shipping shall be FOB Destination.

4.3.2.1.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either included the shipping in the costs of the items, or outline it in a separate line item).

4.3.2.1.3 Weight of individual shipments must not exceed 70lbs.

4.3.2.1.4 Dimensions of individual shipments must not exceed 119 inches in length, and/or 72 inches in width or height.

4.3.2.1.5 Hazardous material is not submitted.

4.3.2.1.6 The Government will provide the APO shipping address as part of the solicitation.

4.3.2.2 Option Two: Commercial small parcel carrier.

4.3.2.2.1 Shipping shall be FOB Destination.

4.3.2.2.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either included the shipping in the costs of the items, or outline it in a separate line item).

4.3.2.2.3 Weight of individual shipments must not exceed 300lbs.

4.3.2.2.4 Dimensions of individual shipments must not exceed 119 inches in length, and/or 72 inches in width or height.

4.3.2.2.5 The Contractor is responsible for arranging and performing all shipping actions from origin to final destination.

4.3.2.2.6 The Government will provide the shipping address as part of the solicitation document. Additionally, the Government will provide the vendor with the point of contact at the physical destination delivery address.

4.3.2.3 Option Three: Consolidated Shipping Point.

4.3.2.3.1 Shipping shall be FOB Destination.

4.3.2.3.2 All shipping and transit costs must be included as part of the total purchase price submitted to the Government (vendor may either included the shipping in the costs of the items, or outline it in a separate line item).

4.3.2.3.3 Weight of individual shipments must exceed 300lbs.

4.3.2.3.4 Dimensions of individual shipments must exceed 72 inches of any one dimensions (length, width, height).

4.3.2.3.5 Hazardous material may be shipped via this method.

4.3.2.3.6 The Contractor must complete a DD Form 1139 “XXX” to determine if the cargo can be shipped via MILAIR.

4.3.2.3.7 The Contractor shall ensure all cargo is marked “UNITED

STATES AIR FORCE” in order to ensure shipments clear customs.

4.3.2.3.8 48 FW logistics points of contact are provided for in 4.3.3.

4.3.3 Contact Information; 48th Logistical Readiness Squadron (48 LRS)

4.3.3.1 48 LRS/Inbound Customs; 48lrs.lgrddc.inboundcustoms@us.af.mil.

4.3.3.2 48 LRS/Inbound Cargo; 48lrs.inboundcargo@us.af.mil.

4.3.3.3 Commercial phone number; +44 01638 52620.

4.4 Government Furnished Material: The US Government/321 STS will not provide any material for the installation.