SJPS Riley and Eureka Elementary Window Replacement Project Manual 20211104_Bidding.pdf

PDF 5 MB Posted

Attached to
Eureka and Riley Elementary Schools Window Replacement
Solicitation number
RFP SJP 220000000209 1
Issued by
Clinton County, Sterling Village, Michigan

About this file

St. Johns Public Schools Eureka and Riley Elementary Schools Window Replacement Project Manual

This project manual is a comprehensive bidding and contract document for the St. Johns Public Schools district in Michigan, prepared by Hobbs+Black Architects for the replacement of window systems at two elementary school locations: Eureka Elementary School at 7550 North Welling Road in St. Johns, Michigan, and Riley Elementary School at 5935 West Pratt Road in DeWitt, Michigan. The work includes removal of existing window systems and installation of new aluminum window systems with complete sealant, flashing, and trim as a single integrated system. Sealed proposals must be submitted no later than 9:00 a.m. on Thursday, November 18, 2021, at St. Johns Public Schools Business Office, with a public bid opening and posting of bid tab within 24 hours. Non-mandatory pre-bid site visits must be scheduled with the Director of Facilities (Rob Gleeson at 517-388-4036) by 5:00 p.m. on November 15, 2021. The contractor is responsible for all costs associated with bid assembly and submission. Construction is scheduled to commence on June 20, 2022, with project closeout and completion of as-built drawings and operations manuals required by August 12, 2022. The bidding documents are dated November 4, 2021, and are available in PDF format from the architect's project FTP site and multiple plan room locations.

Bidders must submit hard copy bids in duplicate (no electronic or faxed bids accepted) with a 5 percent bid bond (minimum) and proposal forms identifying all subcontractors and major material suppliers. Contract awards are contingent upon the Owner's consideration of material quality, contractor competency and solvency, and responsibility, with the Owner reserving the right to reject any or all bids and to contract within sixty days following bid opening. Performance and Payment Bonds of 100 percent of the contract amount are required per Michigan Public Act 213 of 1963, and insurance requirements include workers' compensation (minimum $1,000,000 per incident), general liability ($1,000,000 per occurrence/$2,000,000 aggregate), automobile ($1,000,000 per occurrence), and excess/umbrella liability ($5,000,000 occurrence/aggregate). This is a prevailing wage project subject to Michigan sales tax, with bid questions due by 5:00 p.m. on November 15, 2021, and final addenda issued by November 16, 2021. Post-bid interviews will occur immediately following the bid opening with the apparent low bidder.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

117 E. Allegan Street Lansing, Michigan 48933 P.517.484.4870 F.517.484.1369

H+B Project No. 21716

Project Manual for

St. Johns Public Schools

Riley and Eureka Elementary Window Replacement

Eureka Elementary 7550 North Welling Road

St. Johns, Michigan 48879

Riley Elementary

5935 West Pratt Road DeWitt, Michigan 48820

November 4, 2021

ST. JOHNS PUBLIC SCHOOLS

EUREKA AND RILEY ELEMENTARY SCHOOLS WINDOW REPLACEMENT

PROJECT NO. 21716

HOBBS+BLACK ARCHITECTS TABLE OF CONTENTS

11.04.2021 - 1

TABLE OF CONTENTS

DIVISION 0 BIDDING AND CONTRACT REQUIREMENTS

Section 00 1116 Invitation to Bid Section 00 2113 Instructions to Bidders Section 00 4113 Proposal Form Attachments A and B Section 00 6000 AIA Document A201 2017 General Conditions of the Contract for Construction Section 00 6001 Prevailing Wage Rates

DIVISION 1 GENERAL REQUIREMENTS

Section 01 1000 Summary Section 01 2100 Allowances Section 01 2300 Alternates Section 01 2500 Substitution Procedures Section 01 2500A Substitution Request Form Section 01 2600 Contract Modification Procedures Section 01 2900 Payment Procedures Section 01 3100 Project Management and Coordination Section 01 3200 Construction Progress Documentation Section 01 3233 Photographic Documentation Section 01 3300 Submittal Procedures Section 01 3300A Electronic Waiver Section 01 3300B Subcontractor and Major Material Suppliers List Section 01 4000 Quality Requirements Section 01 4200 References Section 01 5000 Temporary Facilities and Controls Section 01 6000 Product Requirements Section 01 6000A Substitution Request Form (After Bidding) Section 01 7300 Execution Section 01 7300A Request for Interpretation Section 01 7329 Cutting and Patching Section 01 7700 Closeout Procedures Section 01 7700A Punch List Section 01 7823 Operation and Maintenance Data Section 01 7839 Project Record Documents Section 01 7900 Demonstration and Training

DIVISION 6 WOOD, PLASTICS AND COMPOSITES

Section 06 1053 Miscellaneous Rough Carpentry

DIVISION 7 THERMAL AND MOISTURE PROTECTION

Section 07 9200 Joint Sealants

DIVISION 8 THERMAL AND MOISTURE PROTECTION

Section 08 5113 Aluminum Windows

TABLE OF CONTENTS HOBBS+BLACK ARCHITECTS

- 2 11.04.2021

PAGE INTENTIONALLY LEFT BLANK

HOBBS+BLACK ARCHITECTS INVITATION TO BID

11.04.2021 00 1116 - 1

SECTION 00 1116

INVITATION TO BID

PART 1 - GENERAL

1.1 PROJECT IDENTIFICATION

A. Project/Sites: Riley Elementary School

5935 West Pratt Rd.

DeWitt, MI 48820

Eureka Elementary School 7550 North Welling Rd.

St. Johns, MI 48879

B. Owner: St. Johns Public Schools

501 West Sickles St.

C. Architect: Hobbs+Black Architects 117 E. Allegan St.

Lansing, MI 48933

1.2 TYPES OF PROPOSALS

A. Contractor bids shall be submitted in one single lump sum category entitled General Construction which shall include all portions of the work. Proposals shall be made on unaltered copies of Proposal Forms as herein enclosed, furnished by the Architect. The Bidder shall fill in all blank spaces and the proposal shall be signed by a legal officer or agent who is authorized to bind the bidder to a contract.

B. Hard Copies of Bids must be submitted in duplicate. Electronic or faxed bids will not be accepted.

C. The Contractor(s) are wholly responsible for any and all costs associated with assembling and submitting a bid and assembly of information and participating in a Post Bid Interview.

1.3 TIME AND PLACE OF BID RECEPTION

A. Sealed proposals will be received by the Owner no later than 9:00 a.m. Local Time; Thursday, November 18, 2021, at St Johns Public Schools, 501 West Sickles Street, St. Johns, MI 48879. Proposals shall be opened and publicly read aloud; a bid tab will be posted within 24 hours to all bidders. Faxed or electronically submitted bids will not be accepted.

B. The bidders sealed envelope shall be addressed as follows:

Lower Right Hand Corner:

TO: Director of Business and Finance

Ms. Kelly Corbett St. Johns Public Schools

501 West Sickles St.

St. Johns, MI 48879

Lower Left Hand Corner:

BID: EUREKA and RILEY ELEMENTARY SCHOOLS WINDOW REPLACEMENT

Addenda Received: #__________________ (identify on outside of envelope).

1.4 EXAMINATION AND PROCUREMENT OF DOCUMENTS

A. Bidding Documents: Dated November 4, 2021.

Bidding Documents will be available on or about November 4, 2021. Printed documents will not be provided.

PDF files may be provided to a printer of choice at the bidder’s expense.

Bidding documents are downloadable in .pdf format from the Architect’s project FTP site via the following link:

https://hobbsblack.exavault.com/share/view/2q2x2-2fyenfu9

Bidding Documents are also on file at the following locations:

INVITATION TO BID HOBBS+BLACK ARCHITECTS

00 1116 - 2 11.04.2021

1. Hobbs+Black Architects, 117 E. Allegan St., Lansing, MI 48933

2. St. Johns Public Schools, 501 West Sickles Street, St. Johns MI 48879

3. SIGMA https://sigma.michigan.gov/webapp/PRDVSS2X1/AltSelfService

4. WCA Plan Room, 3135 South State Street, Suite 350-H, Ann Arbor, MI 48108

5. Builders Exchange of Michigan_Grand Rapids, 678 Front Ave NW, Ste 330, Grand Rapids, MI 49504

6. Builders Exchange of Kalamazoo, 3431 E. Kilgore Rd., Kalamazoo, MI 49001

7. Builders Exchange of NW Michigan, 1373 Barlow, Ste 4, Traverse City, MI 49686.

8. Builders Exchange of Lansing & Central Michigan, 1240 E. Saginaw, Lansing, MI 48906

9. CAM - Construction Association of Michigan, 43636 Woodward Avenue, Southfield MI 48302.

1.5 NON MANDITORY PRE-BID SITE VISITS

A. All bidders who wish to visit each site must schedule their site visits with the Director of Facilities, Mr. Rob

Gleeson, (517) 388-4036. All site visits must be conducted on or before 5:00 p.m. Local Time, November 15, 2021. Pre-Bid Site Visits are not mandatory for bidders but are strongly encouraged.

1.6 OWNER'S RIGHT TO REJECT PROPOSALS

A. The Owner reserves the right to reject any or all proposals.

The Owner reserves the right to contract within sixty (60) days following the bid opening. The Owner reserves the right to allow a Bidder to withdraw their bid within 24 hours of bid opening. Bidders cannot withdraw their bid without the written consent of the Owner. Enforcement of the Bid Bond will be at the sole discretion of the Owner, the Owner reserves the right to exercise the Bid Bond or not if a Bidder is allowed to withdraw their bid. If the Owner elects to not exercise their option on the Bid Bond they will do so in writing to the Bidder.

The Owner reserves the right to waive any irregularities, reject any or all proposals, in whole or in part or accept any proposals in whole or part, including scope and pricing clarifications made during the Post Bid Interview process that, in the opinion of the Owner, will serve its best interest.

1.7 REFERENCES HEREIN

A. Participation in this project is open to both genders regardless of ethnicity or orientation or identification. The use of the pronoun he/his throughout this document is to be considered interchangeable for either gender.

END OF SECTION 00 1116

HOBBS+BLACK ARCHITECTS INSTRUCTIONS TO BIDDERS

11.04.2021 00 2113 - 1

SECTION 00 2113

INSTRUCTIONS TO BIDDERS

PART 1 - GENERAL

1.1 EXAMINATION OF DOCUMENTS AND SITE

Bidders shall carefully examine the Contract Documents and visit the construction site to obtain first-hand knowledge of existing conditions. Contractor will not be given extra payments for conditions which can be determined by visually examining the site and Contract Documents.

1.2 QUESTIONS, INTERPRETATIONS, AND ADDENDA

A. Should any bidder find discrepancies between the Drawings and Specifications, or should he be in doubt as to their exact meaning, he should notify the Architect-Engineer at once. The Architect-Engineer may then, at his option, issue Addenda clarifying same. The Architect-Engineer will not be responsible for oral instructions or for the Contractor's misinterpretations of Drawings and Specifications.

1. Pre-Bid Requests for Information shall be submitted via email to mruiter@hobbs-black.com, or via fax to the attention of Martin Ruiter at (517) 484-1369.

B. The Architect-Engineer reserves the right to issue Addenda at any time prior to the bid opening. All such addenda shall become, upon issuance, an inseparable part of the Contract Documents. Each bidder shall incorporate within his bid proposal all costs for items listed in the Addenda; and shall acknowledge receipt and the identifying number of each Addendum on the Bid Proposal Form and on the outside of the sealed bid envelope.

1.3 BID SECURITY, BONDS, AND INSURANCE

A. Bid Security, Performance, and Payment Bonds will be required on this project.

1. A Bid Bond is required in the amount of 5% of total Bid, minimum.

2. Performance Bond, Payment Bond (100% of total Bid, minimum) and Insurance requirements are described below and in the General and Supplementary Conditions.

Performance and Payment Bonds as required by Public Act 213 of 1963

100% of Contract Amount

Workers Compensation As required by the State of Michigan, but not less than $1,000,000 per incident for bodily injury by accident or disease.

General Liability Each Occurrence: $1,000,000 Aggregate: $2,000,000

Automobile Each Occurrence: $1,000,000 Excess/Umbrella Liability Occurrence/Aggregate: $5,000,000

1.4 MODIFICATION AND WITHDRAWAL

A. Proposals may be withdrawn and/or changed any time prior to the bid opening. Proposals may not be withdrawn or changed after the bid opening time; and shall be deemed a firm offer continuing for sixty (60) days. Bids received after the time and date of the bid opening will be returned unopened to the proposer.

1.5 SUBSTITUTION OF SPECIFIED PRODUCTS

A. See substitution requirements described in the General Conditions.

B. Requests for substitutions during the bidding period shall be made seven (7) days prior to the established bid date.

1.6 CODES, ORDINANCES, REGULATIONS, ETC.

A. All labor and materials shall be furnished and installed in strict accordance with the latest to bid date applicable codes, ordinances, and regulations of any governing body that has jurisdiction over this project.

B. If the quality of the labor and materials required by the Drawings and Specifications exceeds the requirements of the applicable codes, ordinances, and regulations, the Drawings and Specifications shall take precedence.

C. If the quality of the labor and materials required by the applicable codes, ordinances, and regulations exceed the requirements of the Drawings and Specifications the applicable codes, ordinances, regulations, etc., shall take precedence.

INSTRUCTIONS TO BIDDERS HOBBS+BLACK ARCHITECTS

00 2113 - 2 11.04.2021

1.7 SUB-CONTRACTOR AND MATERIAL SUPPLIER

A. The successful bidder shall submit to the Architect-Engineer, before the contracts are tendered to him for signature, a complete list of all sub-contractors, all material suppliers, and all superintendents (General Construction and principal sub-contractors) he proposes to engage on the work. Sub-contracts and material contracts shall not be awarded until after they have been approved by the Architect-Engineer and Owner. Superintendents (General Construction and Principal Sub-Contractors) shall not be changed during the construction on this project without prior approval in writing from the Architect-Engineer and Owner.

B. The successful bidder will be required to submit the list of sub-contractors within 24 hours after bid opening.

C. Names of major trades sub-contractors must be listed on the Proposal Form.

1.8 AWARD OF CONTRACT

A. The material proposed to be used for the completion of work, and the competency, solvency, and responsibility of the bidders will receive due considerations before the awarding of this contract. In the reception of proposals for the work, the Owner incurs no obligation to accept the lowest or any proposal submitted. The right to accept or reject any and all bids is reserved by the Owner. The Owner reserves the right to require testimonial or legal documents pertaining to the solvency of a Contractor.

1.9 WAGE RATE

A. This is a Prevailing Wage Project.

1.10 USE & SALES TAX

A. Michigan Sales Tax applies to this Project.

1.11 COMMUNICATIONS

A. Communications, written or verbal, with the Owner relating to this Project during the bidding phase will be considered non-binding.

1.12 ANTICIPATED PROJECT TIMELINE

Project Issued for Bids November 4, 2021

Cut-off for Bidder Questions 5:00 p.m. Local Time, November 15, 2021

Last Addenda Issued November 16, 2021

Bids Due 9:00 a.m. Local Time, November 18, 2021

@ The Business Office of St. Johns Public Schools Attn: Kelly Corbett (hard copy only no fax or e-file bids allowed)

Post-Bid Interview(s) Immediately following the bid opening with the apparent low bidder.

Construction Start June 20, 2022

Project Close-Out Complete

(As-built Drawings, Operations & Maintenance Manuals) August 12, 2022

END OF SECTION 00 2113

HOBBS+BLACK ARCHITECTS PROPOSAL FORM

11.04.2021 00 4113 - 1

SECTION 00 4113

PROPOSAL FORM

FOR ALL WORK OF ALL TRADES

BIDDING DOCUMENTS DATED: PROPOSAL DATED:

November 4, 2021

BIDDER:

(Address)

(City) (State) (Zip Code)

(Area Code) (Telephone Number)

� Corporation - State of

� Sole Proprietor � Partnership

PROJECT: EUREKA AND RILEY ELEMENTARY SCHOOLS WINDOW REPLACEMENT

HOBBS + BLACK PROJECT NUMBER: 21716

The Bidder, in compliance with the Invitation to Bid for the Construction Work on subject project has received and examined the Contract Documents and all conditions regarding the project, and having visited the site of the proposed project, hereby submits to the Owner this proposal, including the following documents: Attachment A – Iran Affidavit & Attachment B – Familial Disclosure, for all labor and materials of all trades for the Project and proposes for a complete and fully functional facility:

1. To hold my bid open for a maximum period of sixty (60) days.

2. To enter into and execute a contract, if awarded on the basis of this proposal, and to furnish guaranty bonds in accordance with the Supplementary General Conditions.

3. To accomplish the work in accordance with all the Contract Documents.

4. To complete the work by the time stipulated in the Proposal Form and under the conditions as outlined in the General and Supplementary General Conditions.

5. To accept the provisions of the Instructions to Bidders regarding disposition of Bid Security.

BASE BID:

The Bidder, in compliance with the Bidding Documents of the Project, hereby proposes to furnish all labor, materials, supplies and other expenses necessary to construct both Projects at Riley and Eureka Elementaries in accordance with the Bidding Documents, for the Total Base Bid Amount of:

(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)

ARCHITECT:

Hobbs+Black Architects 117 E. Allegan Street Lansing, MI 48933

OWNER:

St. Johns Public Schools 501 West Sickles Street

PROPOSAL FORM HOBBS+BLACK ARCHITECTS

00 4113 - 2 11.04.2021

The Bidder, shall also in compliance with the Bidding Documents of the Project, hereby proposes to furnish all labor, materials, supplies and other expenses necessary to construct the Project in accordance with the Bidding Documents for the Eureka Elementary portion of the scope only, for the Base Bid Amount of:

(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)

The Bidder, shall also in compliance with the Bidding Documents of the Project, hereby proposes to furnish all labor, materials, supplies and other expenses necessary to construct the Project in accordance with the Bidding Documents for the Riley Elementary portion of the scope only, for the Base Bid Amount of:

(Amount shall be shown in both words and figures. In case of discrepancy, the amount shown in words will govern.)

CONTRACT TIME:

The Bidder hereby agrees to schedule and complete all work to allow for 100% Completion of the entire Project no later than the August 12, 2022. The Bidder agrees to start work upon notice to proceed and continuously make progress in the work until completion per the schedule in 00 2113, Instructions to Bidders.

EXPERIENCE MODIFICATION RATING (EMR):

List the EMR for your company as determined by your insurance carrier for the past three (3) years:

2021 __________ 2020__________ 2019 ___________

ALTERNATES:

The scope of the work may be changed by the Owner to include some, or all of the work described as alternates. For each alternate included as part of the work, the base bid shall be adjusted as follows. (Refer to Section 01 2300, Alternates for complete descriptions)

1. Alternate No. 1 Integral Window Blinds: Provide a cost to remove existing blinds/shades and not re-install them, and to add integral blinds to all new window units. Patch and repair all holes from previous hardware with color matched caulk.

Eureka Add/Deduct $

Riley Add/Deduct $

ALLOWANCES:

1. The amount of $5,000 is ____ is not _____ included in the Base Bid for Owner/Construction Contingency.

ADDITIONAL WORK:

Additional Work will not be paid without written authorization from the Owner and Architect prior to the work being executed.

Additional work may be authorized on a lump sum or a cost-plus basis. In computing the charges for the Contractor's overhead and profit, the following shall be used.

For additional work performed by any subcontractor, the sub contractor's fee, including overhead and profit shall be not more than 7.5 percent of the subcontractor's cost of the work.

For additional work performed by subcontractors, the Contractor's fee, including overhead and profit shall be not more than 7.5 percent of the subcontractor's cost.

For additional work self-performed by the Contractor, the fee, including overhead and profit shall be not more than 10 percent of the actual cost of labor and materials. All discounts shall accrue to the Owner. To this sum shall be added the actual cost of insurance and taxes.

HOBBS+BLACK ARCHITECTS PROPOSAL FORM

11.04.2021 00 4113 - 3

ADDENDA:

Receipt of the following Addenda is acknowledged:

# Dated # Dated

# Dated # Dated

5% BID SECURITY:

Attached is a certified check, bank draft or bid bond in the amount of:

payable to the Owner. It is agreed that the amount of the certified check, bank draft or bid bond shall become the property of the Owner as liquidated damages if the undersigned fails to enter into the contract within ten days from receipt of the notice of award.

REFERENCES

Please provide a minimum of three references (K-12 institutions preferred) where work has been completed within the past five years, or is being completed. This list must include names, addresses and phone numbers of the individuals at the place of business to be contacted.

1. School District/Company Name

Address

Contact Name Phone Number

2. School District/Company Name

Address

Contact Name Phone Number

3. School District/Company Name

Address

Contact Name Phone Number

Upon notification of the acceptance of the proposal, the Undersigned agrees to execute a contract for the above work, for the above stated compensation. The Undersigned further agrees, if awarded the contract, to execute and deliver to the Architect-Engineer within 10 days after the signing of the contract, satisfactory bonds, in the form of 100% "Performance Bond" and 100% "Labor and Material Payment Bond," according to the laws of the State of Michigan governing this construction work, in the amount equal to the contract sum. The Undersigned hereby agrees to complete all the work and improvements as specified in the contract documents.

PROPOSAL FORM HOBBS+BLACK ARCHITECTS

00 4113 - 4 11.04.2021

The Owner will consider the qualification and experience of the Contractor, the amount of the bid, and the completion date when determining the award of the contract.

Respectfully submitted, Name of Contracting Firm Address

BY:

Seal -- if bid is by a corporation.

END OF PROPOSAL FORM

The undersigned, the owner or authorized officer of

Name of Bidder

By

Date

State of )

County of )

This instrument was acknowledged before me on the day of , date month year by

Bidder Signature Name

Notary Signature

Notary Name

County, My Commission Expires

Acting in the County of

Attachment A - Iran AffidavitAttachment A - Iran AffidavitAttachment A - Iran AffidavitAttachment A - Iran Affidavit

Eureka and Riley Elementary Schools Window ReplacementEureka and Riley Elementary Schools Window ReplacementEureka and Riley Elementary Schools Window ReplacementEureka and Riley Elementary Schools Window Replacement

Notarized SignatureNotarized SignatureNotarized SignatureNotarized Signature

SS.

(the “Bidder”), pursuant to the compliance certification requirement provided in the St Johns School

District Eureka and Riley Elementary Schools Window Replacement Invitation to Bid, hereby certifies, represents and warrants that the Bidder (including its officers, directors and employees) is not an “Iran Linked Business” within the meaning of the Iran Economic Sanctions Act, Michigan Public

Act No. 517 of 2012 (the “Act”), and that in the event Bidder is awarded a Contract as a result of the aforementioned Request for Proposal, the Bidder will not become an “Iran Linked Business” at any time during the course of performing under the Contract.

The Bidder further acknowledges that any person who is found to have submitted a false certification is responsible for a civil penalty of not more than $250,000.00 or 2 times the amount of the Contract or proposed Contract for which the false certification was made, whichever is greater, the cost of

District's investigation, and reasonable attorney fees, in addition to the fine. Moreover, any person who submitted a false certification shall be ineligible to bid on an Invitation To Bid for three (3) years from the date the it is determined that the person has submitted the false certification.

AFFIDAVIT OF COMPLAINT - IRAN ECONOMIC SANCTIONS ACT AFFIDAVIT OF COMPLAINT - IRAN ECONOMIC SANCTIONS ACT AFFIDAVIT OF COMPLAINT - IRAN ECONOMIC SANCTIONS ACT AFFIDAVIT OF COMPLAINT - IRAN ECONOMIC SANCTIONS ACT

Michigan Public Act No. 517 of 2012Michigan Public Act No. 517 of 2012Michigan Public Act No. 517 of 2012Michigan Public Act No. 517 of 2012

Vendor InformationVendor InformationVendor InformationVendor Information

1.

2.

3.

4.

5.

Signature(s):

Title:

Name of Firm:

) SS

On this , before me a Notary agent of the said firm

State of

County of and who acknowledged the same to be his free act and deed as such agent.

day of

My Commission Expires

Notarized SignatureNotarized SignatureNotarized SignatureNotarized Signature

Vendor InformationVendor InformationVendor InformationVendor Information

Public in and for said county, personally appeared

Notary Public

Owner/ Employee Name Related To: Relationship

The following are familial relationships as described above (provide employee name, family contact name, family contact position, and familial relationship or NONE).

Attachment B - Familial DisclosureAttachment B - Familial DisclosureAttachment B - Familial DisclosureAttachment B - Familial Disclosure

Eureka and Riley Elementary Schools Window ReplacementEureka and Riley Elementary Schools Window ReplacementEureka and Riley Elementary Schools Window ReplacementEureka and Riley Elementary Schools Window Replacement

All bidders must complete the following disclosure form in compliance with MCL 380.1267 and attach this information to their proposal.

By the attached sworn and notarized statement, we are disclosing the following familial relationship(s) that exists between the owner or any employee of the Vendor and any member of the Districts’ Board or the superintendent.

Disclose any familial relationship and complete the form below in its entirety:

AIA

Document A201TM – 2017

General Conditions of the Contract for Construction

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

Order No.0528487069 which expires on 03/12/2019, and is not for resale.

User Notes: (1966036069)

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an attorney is encouraged with respect to its completion or modification.

For guidance in modifying this document to include supplementary conditions, see AIA Document A503™, Guide for Supplementary

Conditions.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

for the following PROJECT:

(Name and location or address)

«ST. JOHNS PUBLIC SCHOOLS»

«EUREKA AND RILEY ELEMENTARY SCHOOLS WINDOW REPLACEMENT

REROOF

EUREKA ELEMENTARY

7550 N. WELLING ROAD

ST. JOHNS, MICHIGAN 48879

and

RILEY ELEMENTARY

5935 WEST PRATT RD

DEWITT, MICHIGAN 48820»

THE OWNER:

(Name, legal status and address)

« ST. JOHNS PUBLIC SCHOOLS »« »

«501 WEST SICKLES STREET

ST. JOHNS, MICHIGAN 48879»

THE ARCHITECT:

(Name, legal status and address)

«HOBBS + BLACK ASSOCIATES, INC.»« »

«117 EAST ALLEGAN STREET

LANSING, MICHIGAN 48933»

TABLE OF ARTICLES

1 GENERAL PROVISIONS

2 OWNER

3 CONTRACTOR

4 ARCHITECT

5 SUBCONTRACTORS

6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS

7 CHANGES IN THE WORK

8 TIME

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

9 PAYMENTS AND COMPLETION

10 PROTECTION OF PERSONS AND PROPERTY

11 INSURANCE AND BONDS

12 UNCOVERING AND CORRECTION OF WORK

13 MISCELLANEOUS PROVISIONS

14 TERMINATION OR SUSPENSION OF THE CONTRACT

15 CLAIMS AND DISPUTES

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

INDEX

(Topics and numbers in bold are Section headings.)

Acceptance of Nonconforming Work

9.6.6, 9.9.3, 12.3

Acceptance of Work

9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3

Access to Work

3.16, 6.2.1, 12.1

Accident Prevention

Acts and Omissions

3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.3.2, 14.1, 15.1.2, 15.2

Addenda

1.1.1

Additional Costs, Claims for

3.7.4, 3.7.5, 10.3.2, 15.1.5

Additional Inspections and Testing

9.4.2, 9.8.3, 12.2.1, 13.4

Additional Time, Claims for

3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.6

Administration of the Contract

3.1.3, 4.2, 9.4, 9.5

Advertisement or Invitation to Bid

1.1.1

Aesthetic Effect

4.2.13

Allowances

3.8

Applications for Payment

4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.5.4, 9.6.3, 9.7, 9.10

Approvals

2.1.1, 2.3.1, 2.5, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10.1, 4.2.7, 9.3.2, 13.4.1

Arbitration

8.3.1, 15.3.2, 15.4

ARCHITECT

Architect, Definition of

4.1.1

Architect, Extent of Authority

2.5, 3.12.7, 4.1.2, 4.2, 5.2, 6.3, 7.1.2, 7.3.4, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.4.1, 13.4.2, 14.2.2, 14.2.4, 15.1.4, 15.2.1

Architect, Limitations of Authority and Responsibility

2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.4, 9.6.4, 15.1.4, 15.2

Architect’s Additional Services and Expenses

2.5, 12.2.1, 13.4.2, 13.4.3, 14.2.4

Architect’s Administration of the Contract

3.1.3, 3.7.4, 15.2, 9.4.1, 9.5

Architect’s Approvals

2.5, 3.1.3, 3.5, 3.10.2, 4.2.7

Architect’s Authority to Reject Work

3.5, 4.2.6, 12.1.2, 12.2.1

Architect’s Copyright

1.1.7, 1.5

Architect’s Decisions

3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.4.2, 15.2

Architect’s Inspections

3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.4

Architect’s Instructions

3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.4.2

Architect’s Interpretations

4.2.11, 4.2.12

Architect’s Project Representative

4.2.10

Architect’s Relationship with Contractor

1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.3.2, 13.4, 15.2

Architect’s Relationship with Subcontractors

1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3

Architect’s Representations

9.4.2, 9.5.1, 9.10.1

Architect’s Site Visits

3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4

Asbestos

10.3.1

Attorneys’ Fees

3.18.1, 9.6.8, 9.10.2, 10.3.3

Award of Separate Contracts

6.1.1, 6.1.2

Award of Subcontracts and Other Contracts for

Portions of the Work

5.2

Basic Definitions

1.1

Bidding Requirements

1.1.1

Binding Dispute Resolution

8.3.1, 9.7, 11.5, 13.1, 15.1.2, 15.1.3, 15.2.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.3.3, 15.4.1

Bonds, Lien

7.3.4.4, 9.6.8, 9.10.2, 9.10.3

Bonds, Performance, and Payment

7.3.4.4, 9.6.7, 9.10.3, 11.1.2, 11.1.3, 11.5

Building Information Models Use and Reliance

1.8

Building Permit

3.7.1

Capitalization

1.3

Certificate of Substantial Completion

9.8.3, 9.8.4, 9.8.5

Certificates for Payment

4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.4

Certificates of Inspection, Testing or Approval

13.4.4

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

Certificates of Insurance

9.10.2

Change Orders

1.1.1, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.7, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.2, 11.5, 12.1.2

Change Orders, Definition of

7.2.1

CHANGES IN THE WORK

2.2.2, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.5

Claims, Definition of

15.1.1

Claims, Notice of

1.6.2, 15.1.3

CLAIMS AND DISPUTES

3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4

Claims and Timely Assertion of Claims

15.4.1

Claims for Additional Cost

3.2.4, 3.3.1, 3.7.4, 7.3.9, 9.5.2, 10.2.5, 10.3.2, 15.1.5

Claims for Additional Time

3.2.4, 3.3.1, 3.7.4, 6.1.1, 8.3.2, 9.5.2, 10.3.2, 15.1.6

Concealed or Unknown Conditions, Claims for

3.7.4

Claims for Damages

3.2.4, 3.18, 8.3.3, 9.5.1, 9.6.7, 10.2.5, 10.3.3, 11.3, 11.3.2, 14.2.4, 15.1.7

Claims Subject to Arbitration

15.4.1

Cleaning Up

3.15, 6.3

Commencement of the Work, Conditions Relating to

2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.2, 15.1.5

Commencement of the Work, Definition of

8.1.2

Communications

3.9.1, 4.2.4

Completion, Conditions Relating to

3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 14.1.2, 15.1.2

COMPLETION, PAYMENTS AND

Completion, Substantial

3.10.1, 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2

Compliance with Laws

2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3

Concealed or Unknown Conditions

3.7.4, 4.2.8, 8.3.1, 10.3

Conditions of the Contract

1.1.1, 6.1.1, 6.1.4

Consent, Written

3.4.2, 3.14.2, 4.1.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 13.2, 15.4.4.2

Consolidation or Joinder

15.4.4

CONSTRUCTION BY OWNER OR BY

SEPARATE CONTRACTORS

1.1.4, 6

Construction Change Directive, Definition of

7.3.1

Construction Change Directives

1.1.1, 3.4.2, 3.11, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1

Construction Schedules, Contractor’s

3.10, 3.11, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2

Contingent Assignment of Subcontracts

5.4, 14.2.2.2

Continuing Contract Performance

15.1.4

Contract, Definition of

1.1.2

CONTRACT, TERMINATION OR

SUSPENSION OF THE

5.4.1.1, 5.4.2, 11.5, 14

Contract Administration

3.1.3, 4, 9.4, 9.5

Contract Award and Execution, Conditions Relating to

3.7.1, 3.10, 5.2, 6.1

Contract Documents, Copies Furnished and Use of

1.5.2, 2.3.6, 5.3

Contract Documents, Definition of

1.1.1

Contract Sum

2.2.2, 2.2.4, 3.7.4, 3.7.5, 3.8, 3.10.2, 5.2.3, 7.3, 7.4, 9.1, 9.2, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.5, 12.1.2, 12.3, 14.2.4, 14.3.2, 15.1.4.2, 15.1.5, 15.2.5

Contract Sum, Definition of

9.1

Contract Time

1.1.4, 2.2.1, 2.2.2, 3.7.4, 3.7.5, 3.10.2, 5.2.3, 6.1.5, 7.2.1.3, 7.3.1, 7.3.5, 7.3.6, 7, 7, 7.3.10, 7.4, 8.1.1, 8.2.1, 8.2.3, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 12.1.2, 14.3.2, 15.1.4.2, 15.1.6.1, 15.2.5

Contract Time, Definition of

8.1.1

CONTRACTOR

Contractor, Definition of

3.1, 6.1.2

Contractor’s Construction and Submittal

Schedules

3.10, 3.12.1, 3.12.2, 4.2.3, 6.1.3, 15.1.6.2

Contractor’s Employees

2.2.4, 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11.3, 14.1, 14.2.1.1

Contractor’s Liability Insurance

11.1

Contractor’s Relationship with Separate Contractors and Owner’s Forces

3.12.5, 3.14.2, 4.2.4, 6, 11.3, 12.2.4

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

Contractor’s Relationship with Subcontractors

1.2.2, 2.2.4, 3.3.2, 3.18.1, 3.18.2, 4.2.4, 5, 9.6.2, 9.6.7, 9.10.2, 11.2, 11.3, 11.4

Contractor’s Relationship with the Architect

1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5.1, 3.7.4, 3.10, 3.11, 3.12, 3.16, 3.18, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.4, 15.1.3, 15.2.1

Contractor’s Representations

3.2.1, 3.2.2, 3.5, 3.12.6, 6.2.2, 8.2.1, 9.3.3, 9.8.2

Contractor’s Responsibility for Those Performing the

Work

3.3.2, 3.18, 5.3, 6.1.3, 6.2, 9.5.1, 10.2.8

Contractor’s Review of Contract Documents

3.2

Contractor’s Right to Stop the Work

2.2.2, 9.7

Contractor’s Right to Terminate the Contract

14.1

Contractor’s Submittals

3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 9.2, 9.3, 9.8.2, 9.8.3, 9.9.1, 9.10.2, 9.10.3

Contractor’s Superintendent

3.9, 10.2.6

Contractor’s Supervision and Construction

Procedures

1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.4, 7.3.6, 8.2, 10, 12, 14, 15.1.4

Coordination and Correlation

1.2, 3.2.1, 3.3.1, 3.10, 3.12.6, 6.1.3, 6.2.1

Copies Furnished of Drawings and Specifications

1.5, 2.3.6, 3.11

Copyrights

1.5, 3.17

Correction of Work

2.5, 3.7.3, 9.4.2, 9.8.2, 9.8.3, 9.9.1, 12.1.2, 12.2, 12.3, 15.1.3.1, 15.1.3.2, 15.2.1

Correlation and Intent of the Contract Documents

1.2

Cost, Definition of

7.3.4

Costs

2.5, 3.2.4, 3.7.3, 3.8.2, 3.15.2, 5.4.2, 6.1.1, 6.2.3, 7.3.3.3, 7.3.4, 7.3.8, 7.3.9, 9.10.2, 10.3.2, 10.3.6, 11.2, 12.1.2, 12.2.1, 12.2.4, 13.4, 14

Cutting and Patching

3.14, 6.2.5

Damage to Construction of Owner or Separate

Contractors

3.14.2, 6.2.4, 10.2.1.2, 10.2.5, 10.4, 12.2.4

Damage to the Work

3.14.2, 9.9.1, 10.2.1.2, 10.2.5, 10.4, 12.2.4

Damages, Claims for

3.2.4, 3.18, 6.1.1, 8.3.3, 9.5.1, 9.6.7, 10.3.3, 11.3.2, 11.3, 14.2.4, 15.1.7

Damages for Delay

6.2.3, 8.3.3, 9.5.1.6, 9.7, 10.3.2, 14.3.2

Date of Commencement of the Work, Definition of

8.1.2

Date of Substantial Completion, Definition of

8.1.3

Day, Definition of

8.1.4

Decisions of the Architect

3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4, 9.5.1, 9.8.4, 9.9.1, 13.4.2, 14.2.2, 14.2.4, 15.1, 15.2

Decisions to Withhold Certification

9.4.1, 9.5, 9.7, 14.1.1.3

Defective or Nonconforming Work, Acceptance, Rejection and Correction of

2.5, 3.5, 4.2.6, 6.2.3, 9.5.1, 9.5.3, 9.6.6, 9.8.2, 9.9.3, 9.10.4, 12.2.1

Definitions

1.1, 2.1.1, 3.1.1, 3.5, 3.12.1, 3.12.2, 3.12.3, 4.1.1, 5.1, 6.1.2, 7.2.1, 7.3.1, 8.1, 9.1, 9.8.1, 15.1.1

Delays and Extensions of Time

3.2, 3.7.4, 5.2.3, 7.2.1, 7.3.1, 7.4, 8.3, 9.5.1, 9.7, 10.3.2, 10.4, 14.3.2, 15.1.6, 15.2.5

Digital Data Use and Transmission

1.7

Disputes

6.3, 7.3.9, 15.1, 15.2

Documents and Samples at the Site

3.11

Drawings, Definition of

1.1.5

Drawings and Specifications, Use and Ownership of

3.11

Effective Date of Insurance

8.2.2

Emergencies

10.4, 14.1.1.2, 15.1.5

Employees, Contractor’s

3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3.3, 11.3, 14.1, 14.2.1.1

Equipment, Labor, or Materials

1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 4.2.6, 4.2.7, 5.2.1, 6.2.1, 7.3.4, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2

Execution and Progress of the Work

1.1.3, 1.2.1, 1.2.2, 2.3.4, 2.3.6, 3.1, 3.3.1, 3.4.1, 3.7.1, 3.10.1, 3.12, 3.14, 4.2, 6.2.2, 7.1.3, 7.3.6, 8.2, 9.5.1, 9.9.1, 10.2, 10.3, 12.1, 12.2, 14.2, 14.3.1, 15.1.4

Extensions of Time

3.2.4, 3.7.4, 5.2.3, 7.2.1, 7.3, 7.4, 9.5.1, 9.7, 10.3.2, 10.4, 14.3, 15.1.6, 15.2.5

Failure of Payment

9.5.1.3, 9.7, 9.10.2, 13.5, 14.1.1.3, 14.2.1.2

Faulty Work

(See Defective or Nonconforming Work)

Final Completion and Final Payment

4.2.1, 4.2.9, 9.8.2, 9.10, 12.3, 14.2.4, 14.4.3

Financial Arrangements, Owner’s

2.2.1, 13.2.2, 14.1.1.4

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

GENERAL PROVISIONS

Governing Law

13.1

Guarantees (See Warranty)

Hazardous Materials and Substances

10.2.4, 10.3

Identification of Subcontractors and Suppliers

5.2.1

Indemnification

3.17, 3.18, 9.6.8, 9.10.2, 10.3.3, 11.3

Information and Services Required of the Owner

2.1.2, 2.2, 2.3, 3.2.2, 3.12.10.1, 6.1.3, 6.1.4, 6.2.5, 9.6.1, 9.9.2, 9.10.3, 10.3.3, 11.2, 13.4.1, 13.4.2, 14.1.1.4, 14.1.4, 15.1.4

Initial Decision

15.2

Initial Decision Maker, Definition of

1.1.8

Initial Decision Maker, Decisions

14.2.4, 15.1.4.2, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5

Initial Decision Maker, Extent of Authority

14.2.4, 15.1.4.2, 15.2.1, 15.2.2, 15.2.3, 15.2.4, 15.2.5

Injury or Damage to Person or Property

10.2.8, 10.4

Inspections

3.1.3, 3.3.3, 3.7.1, 4.2.2, 4.2.6, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 12.2.1, 13.4

Instructions to Bidders

1.1.1

Instructions to the Contractor

3.2.4, 3.3.1, 3.8.1, 5.2.1, 7, 8.2.2, 12, 13.4.2

Instruments of Service, Definition of

1.1.7

Insurance

6.1.1, 7.3.4, 8.2.2, 9.3.2, 9.8.4, 9.9.1, 9.10.2, 10.2.5, 11

Insurance, Notice of Cancellation or Expiration

11.1.4, 11.2.3

Insurance, Contractor’s Liability

11.1

Insurance, Effective Date of

8.2.2, 14.4.2

Insurance, Owner’s Liability

11.2

Insurance, Property

10.2.5, 11.2, 11.4, 11.5

Insurance, Stored Materials

9.3.2

INSURANCE AND BONDS

Insurance Companies, Consent to Partial Occupancy

9.9.1

Insured loss, Adjustment and Settlement of

11.5

Intent of the Contract Documents

1.2.1, 4.2.7, 4.2.12, 4.2.13

Interest

13.5

Interpretation

1.1.8, 1.2.3, 1.4, 4.1.1, 5.1, 6.1.2, 15.1.1

Interpretations, Written

4.2.11, 4.2.12

Judgment on Final Award

15.4.2

Labor and Materials, Equipment

1.1.3, 1.1.6, 3.4, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 5.2.1, 6.2.1, 7.3.4, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1, 10.2.4, 14.2.1.1, 14.2.1.2

Labor Disputes

8.3.1

Laws and Regulations

1.5, 2.3.2, 3.2.3, 3.2.4, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 9.9.1, 10.2.2, 13.1, 13.3.1, 13.4.2, 13.5, 14, 15.2.8, 15.4

Liens

2.1.2, 9.3.1, 9.3.3, 9.6.8, 9.10.2, 9.10.4, 15.2.8

Limitations, Statutes of

12.2.5, 15.1.2, 15.4.1.1

Limitations of Liability

3.2.2, 3.5, 3.12.10, 3.12.10.1, 3.17, 3.18.1, 4.2.6, 4.2.7, 6.2.2, 9.4.2, 9.6.4, 9.6.7, 9.6.8, 10.2.5, 10.3.3, 11.3, 12.2.5, 13.3.1

Limitations of Time

2.1.2, 2.2, 2.5, 3.2.2, 3.10, 3.11, 3.12.5, 3.15.1, 4.2.7, 5.2, 5.3, 5.4.1, 6.2.4, 7.3, 7.4, 8.2, 9.2, 9.3.1, 9.3.3, 9.4.1, 9.5, 9.6, 9.7, 9.8, 9.9, 9.10, 12.2, 13.4, 14, 15, 15.1.2, 15.1.3, 15.1.5

Materials, Hazardous

10.2.4, 10.3

Materials, Labor, Equipment and

1.1.3, 1.1.6, 3.4.1, 3.5, 3.8.2, 3.8.3, 3.12, 3.13, 3.15.1, 5.2.1, 6.2.1, 7.3.4, 9.3.2, 9.3.3, 9.5.1.3, 9.10.2, 10.2.1.2, 10.2.4, 14.2.1.1, 14.2.1.2

Means, Methods, Techniques, Sequences and

Procedures of Construction

3.3.1, 3.12.10, 4.2.2, 4.2.7, 9.4.2

Mechanic’s Lien

2.1.2, 9.3.1, 9.3.3, 9.6.8, 9.10.2, 9.10.4, 15.2.8

Mediation

8.3.1, 15.1.3.2, 15.2.1, 15.2.5, 15.2.6, 15.3, 15.4.1, 15.4.1.1

Minor Changes in the Work

1.1.1, 3.4.2, 3.12.8, 4.2.8, 7.1, 7.4

MISCELLANEOUS PROVISIONS

Modifications, Definition of

1.1.1

Modifications to the Contract

1.1.1, 1.1.2, 2.5, 3.11, 4.1.2, 4.2.1, 5.2.3, 7, 8.3.1, 9.7, 10.3.2

Mutual Responsibility

6.2

Nonconforming Work, Acceptance of

9.6.6, 9.9.3, 12.3

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

Nonconforming Work, Rejection and Correction of

2.4, 2.5, 3.5, 4.2.6, 6.2.4, 9.5.1, 9.8.2, 9.9.3, 9.10.4, 12.2

Notice

1.6, 1.6.1, 1.6.2, 2.1.2, 2.2.2., 2.2.3, 2.2.4, 2.5, 3.2.4, 3.3.1, 3.7.4, 3.7.5, 3.9.2, 3.12.9, 3.12.10, 5.2.1, 7.4,

8.2.2 9.6.8, 9.7, 9.10.1, 10.2.8, 10.3.2, 11.5, 12.2.2.1, 13.4.1, 13.4.2, 14.1, 14.2.2, 14.4.2, 15.1.3, 15.1.5, 15.1.6, 15.4.1

Notice of Cancellation or Expiration of Insurance

11.1.4, 11.2.3

Notice of Claims

1.6.2, 2.1.2, 3.7.4, 9.6.8, 10.2.8, 15.1.3, 15.1.5, 15.1.6, 15.2.8, 15.3.2, 15.4.1

Notice of Testing and Inspections

13.4.1, 13.4.2

Observations, Contractor’s

3.2, 3.7.4

Occupancy

2.3.1, 9.6.6, 9.8

Orders, Written

1.1.1, 2.4, 3.9.2, 7, 8.2.2, 11.5, 12.1, 12.2.2.1, 13.4.2, 14.3.1

OWNER

Owner, Definition of

2.1.1

Owner, Evidence of Financial Arrangements

2.2, 13.2.2, 14.1.1.4

Owner, Information and Services Required of the

2.1.2, 2.2, 2.3, 3.2.2, 3.12.10, 6.1.3, 6.1.4, 6.2.5, 9.3.2, 9.6.1, 9.6.4, 9.9.2, 9.10.3, 10.3.3, 11.2, 13.4.1, 13.4.2, 14.1.1.4, 14.1.4, 15.1.4

Owner’s Authority

1.5, 2.1.1, 2.3.32.4, 2.5, 3.4.2, 3.8.1, 3.12.10, 3.14.2, 4.1.2, 4.2.4, 4.2.9, 5.2.1, 5.2.4, 5.4.1, 6.1, 6.3, 7.2.1, 7.3.1, 8.2.2, 8.3.1, 9.3.2, 9.5.1, 9.6.4, 9.9.1, 9.10.2, 10.3.2, 11.4, 11.5, 12.2.2, 12.3, 13.2.2, 14.3, 14.4, 15.2.7

Owner’s Insurance

11.2

Owner’s Relationship with Subcontractors

1.1.2, 5.2, 5.3, 5.4, 9.6.4, 9.10.2, 14.2.2

Owner’s Right to Carry Out the Work

2.5, 14.2.2

Owner’s Right to Clean Up

6.3

Owner’s Right to Perform Construction and to

Award Separate Contracts

6.1

Owner’s Right to Stop the Work

2.4

Owner’s Right to Suspend the Work

14.3

Owner’s Right to Terminate the Contract

14.2, 14.4

Ownership and Use of Drawings, Specifications and Other Instruments of Service

1.1.1, 1.1.6, 1.1.7, 1.5, 2.3.6, 3.2.2, 3.11, 3.17, 4.2.12, 5.3

Partial Occupancy or Use

9.6.6, 9.9

Patching, Cutting and

3.14, 6.2.5

Patents

3.17

Payment, Applications for

4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5, 9.6.3, 9.7, 9.8.5, 9.10.1, 14.2.3, 14.2.4, 14.4.3

Payment, Certificates for

4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4

Payment, Failure of

9.5.1.3, 9.7, 9.10.2, 13.5, 14.1.1.3, 14.2.1.2

Payment, Final

4.2.1, 4.2.9, 9.10, 12.3, 14.2.4, 14.4.3

Payment Bond, Performance Bond and

7.3.4.4, 9.6.7, 9.10.3, 11.1.2

Payments, Progress

9.3, 9.6, 9.8.5, 9.10.3, 14.2.3, 15.1.4

PAYMENTS AND COMPLETION

Payments to Subcontractors

5.4.2, 9.5.1.3, 9.6.2, 9.6.3, 9.6.4, 9.6.7, 14.2.1.2

PCB

10.3.1

Performance Bond and Payment Bond

7.3.4.4, 9.6.7, 9.10.3, 11.1.2

Permits, Fees, Notices and Compliance with Laws

2.3.1, 3.7, 3.13, 7.3.4.4, 10.2.2

PERSONS AND PROPERTY, PROTECTION OF

Polychlorinated Biphenyl

10.3.1

Product Data, Definition of

3.12.2

Product Data and Samples, Shop Drawings

3.11, 3.12, 4.2.7

Progress and Completion

4.2.2, 8.2, 9.8, 9.9.1, 14.1.4, 15.1.4

Progress Payments

9.3, 9.6, 9.8.5, 9.10.3, 14.2.3, 15.1.4

Project, Definition of

1.1.4

Project Representatives

4.2.10

Property Insurance

10.2.5, 11.2

Proposal Requirements

1.1.1

PROTECTION OF PERSONS AND PROPERTY

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

Regulations and Laws

1.5, 2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 9.9.1, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14, 15.2.8, 15.4

Rejection of Work

4.2.6, 12.2.1

Releases and Waivers of Liens

9.3.1, 9.10.2

Representations

3.2.1, 3.5, 3.12.6, 8.2.1, 9.3.3, 9.4.2, 9.5.1, 9.10.1

Representatives

2.1.1, 3.1.1, 3.9, 4.1.1, 4.2.10, 13.2.1

Responsibility for Those Performing the Work

3.3.2, 3.18, 4.2.2, 4.2.3, 5.3, 6.1.3, 6.2, 6.3, 9.5.1, 10

Retainage

9.3.1, 9.6.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3

Review of Contract Documents and Field

Conditions by Contractor

3.2, 3.12.7, 6.1.3

Review of Contractor’s Submittals by Owner and

Architect

3.10.1, 3.10.2, 3.11, 3.12, 4.2, 5.2, 6.1.3, 9.2, 9.8.2

Review of Shop Drawings, Product Data and Samples by Contractor

3.12

Rights and Remedies

1.1.2, 2.4, 2.5, 3.5, 3.7.4, 3.15.2, 4.2.6, 5.3, 5.4, 6.1, 6.3, 7.3.1, 8.3, 9.5.1, 9.7, 10.2.5, 10.3, 12.2.1, 12.2.2, 12.2.4, 13.3, 14, 15.4

Royalties, Patents and Copyrights

3.17

Rules and Notices for Arbitration

15.4.1

Safety of Persons and Property

10.2, 10.4

Safety Precautions and Programs

3.3.1, 4.2.2, 4.2.7, 5.3, 10.1, 10.2, 10.4

Samples, Definition of

3.12.3

Samples, Shop Drawings, Product Data and

3.11, 3.12, 4.2.7

Samples at the Site, Documents and

3.11

Schedule of Values

9.2, 9.3.1

Schedules, Construction

3.10, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2

Separate Contracts and Contractors

1.1.4, 3.12.5, 3.14.2, 4.2.4, 4.2.7, 6, 8.3.1, 12.1.2

Separate Contractors, Definition of

6.1.1

Shop Drawings, Definition of

3.12.1

Shop Drawings, Product Data and Samples

3.11, 3.12, 4.2.7

Site, Use of

3.13, 6.1.1, 6.2.1

Site Inspections

3.2.2, 3.3.3, 3.7.1, 3.7.4, 4.2, 9.9.2, 9.4.2, 9.10.1, 13.4

Site Visits, Architect’s

3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4

Special Inspections and Testing

4.2.6, 12.2.1, 13.4

Specifications, Definition of

1.1.6

Specifications

1.1.1, 1.1.6, 1.2.2, 1.5, 3.12.10, 3.17, 4.2.14

Statute of Limitations

15.1.2, 15.4.1.1

Stopping the Work

2.2.2, 2.4, 9.7, 10.3, 14.1

Stored Materials

6.2.1, 9.3.2, 10.2.1.2, 10.2.4

Subcontractor, Definition of

5.1.1

SUBCONTRACTORS

Subcontractors, Work by

1.2.2, 3.3.2, 3.12.1, 3.18, 4.2.3, 5.2.3, 5.3, 5.4, 9.3.1.2, 9.6.7

Subcontractual Relations

5.3, 5.4, 9.3.1.2, 9.6, 9.10, 10.2.1, 14.1, 14.2.1

Submittals

3.10, 3.11, 3.12, 4.2.7, 5.2.1, 5.2.3, 7.3.4, 9.2, 9.3, 9.8, 9.9.1, 9.10.2, 9.10.3

Submittal Schedule

3.10.2, 3.12.5, 4.2.7

Subrogation, Waivers of

6.1.1, 11.3

Substances, Hazardous

10.3

Substantial Completion

4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2

Substantial Completion, Definition of

9.8.1

Substitution of Subcontractors

5.2.3, 5.2.4

Substitution of Architect

2.3.3

Substitutions of Materials

3.4.2, 3.5, 7.3.8

Sub-subcontractor, Definition of

5.1.2

Subsurface Conditions

3.7.4

Successors and Assigns

13.2

Superintendent

3.9, 10.2.6

Supervision and Construction Procedures

1.2.2, 3.3, 3.4, 3.12.10, 4.2.2, 4.2.7, 6.1.3, 6.2.4, 7.1.3, 7.3.4, 8.2, 8.3.1, 9.4.2, 10, 12, 14, 15.1.4

Suppliers

1.5, 3.12.1, 4.2.4, 4.2.6, 5.2.1, 9.3, 9.4.2, 9.5.4, 9.6, 9.10.5, 14.2.1

AIA Document A201™ – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017 by

The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and International

Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at 13:07:06 on 04/17/2018 under

Surety

5.4.1.2, 9.6.8, 9.8.5, 9.10.2, 9.10.3, 11.1.2, 14.2.2, 15.2.7

Surety, Consent of

9.8.5, 9.10.2, 9.10.3

Surveys

1.1.7, 2.3.4

Suspension by the Owner for Convenience

14.3

Suspension of the Work

3.7.5, 5.4.2, 14.3

Suspension or Termination of the Contract

5.4.1.1, 14

Taxes

3.6, 3.8.2.1, 7.3.4.4

Termination by the Contractor

14.1, 15.1.7

Termination by the Owner for Cause

5.4.1.1, 14.2, 15.1.7

Termination by the Owner for Convenience

14.4

Termination of the Architect

2.3.3

Termination of the Contractor Employment

14.2.2

TERMINATION OR SUSPENSION OF THE

CONTRACT

Tests…

This is the start of the file's text. The full file is on GovTribe.