This document is a Questions and Answers (Q&A) file for a Sitework and Paving Indefinite Delivery/Indefinite Quantity (IDIQ) contract (Solicitation FA283525B0001). The solicitation is for a single-award IDIQ with an estimated ceiling of $35 million, covering a 5-year period with an optional 6-month to 1-year extension of services. The proposal due date has been extended to December 8, 2025, through Amendment 005, with a minimum order guarantee of $2,500.
Key details include requirements for unit pricing on all items (including zero-quantity items), use of Highway Davis-Bacon wages, and specific clarifications on various line items in the bid schedule. The contract will require Performance/Payment Bonds for individual project awards ranging from $30,000 to $1,000,000. Contractors must provide all-inclusive unit pricing covering labor, materials, equipment, and mobilization, with no additional reimbursement for means and methods of completing work. The government will not provide a plan holder list, and the final evaluation will include pricing for five years plus the extension of services.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25 November 2025 Sitework and Paving (FA283525B0001) Questions and Answers:
Q: What is the magnitude for this IDIQ Solicitation? The only reference that I located in the solicitation was greater than $10,000,000. Can you provide some further clarification?
A: The estimated or approximate ceiling for this IDIQ is $35M consistent with the DFARS 236.204 Disclosure of magnitude for construction projects, of “(ii) Between $25,000,000 and $100,000,000.” Information will be updated via amendment to the solicitation documentation, and the estimated or approximate IDIQ ceiling will be added to the solicitation CLIN description. All prospective bidders are reminded that IDIQ ceiling is not a guarantee of work, but rather the max estimated OR approximate potential for this effort document. All orders placed of this IDIQ will be priced out using the bid schedule provided with their proposal.
Q: Is there a seed project for this IDIQ?
A: As outlined in Solicitation Block 10 and IFP Cover Letter paragraph 3, there is a minimum order guarantee of $2,500.
Q: Has any other company reached out regarding the accessibility of the documents posted to Sam.gov for this solicitation? It seems Attachment 01 and 13 that are posted on Sam.gov under this solicitation are password protected and our team is having trouble accessing them.
A: I have not received any notification of issues and have confirmed that they are accessible. An additional version of the SOW has been uploaded.
Q: Would it be possible to re-issue Attachment 01 SOW without being protected? When trying to open we get a request to sign in using Purview and when we use our Microsoft email, it still doesn't allow us to view the doc.
A: Additional version has been provided to remove any potential locks.
Q: Since Attachment 1 is unable to be opened and it contains the SOW - it is likely that upon being able to actually view the SOW that we will have additional questions. Will there be a second RFI period offered to accommodate this?
A: As of amendment 0002 the proposal due date has been extended to 6 November 2025 at 1400 EST. Further extension has been provided.
Q: How many awards will be made for this IDIQ?
A: This will be a single award IDIQ.
Q: Can we qualify our quote for ambiguous lines with what our understanding of the line is.
Ex - line 29 - we would assume this is just general debris, non-hazardous, non e-waste.
A: All vendors will need to ask specific questions about any line that they are unsure
of. All pricing for the IDIQ will be based on the winning offeror’s price sheet.
Q: Will the bid still be due next Friday or is there any expectation that it may be delayed?
A: As of amendment 0002 the proposal due date has been extended to 6 November 2025 at 1400 EST. Further extension has been provided.
Q: Regarding Location Coefficient percentage in attachment 13, please advise how the location coefficient percentage inputted directly relates to and affects the unit rates provided by the contractor.
A: As Stated in Para 3.4 of the SOW, the location coefficient accounts for additional costs to perform work at other locations. The coefficient itself does not affect individual line items. It is a below the line markup.
Q: No Quantity is provided for Item E11 for years 2 thru EOS in Attachment 13 A: Quantity should be 5 Each for years 2 through 5 and 2 for EOS.
Q: No Quantity is provided for Item J22 thru J26 for years 2 thru EOS in Attachment 13 A: For years 2 through EOS use:
J22 Light pole, round, 20' 1 EA J23 Light pole, round, 12' 1 EA J24 Light pole, square, 30' 1 EA J25 Light pole, square, 20' 1 EA J26 Light pole, square, 12' 1 EA
Q: Attachment 13 Item A09 is listed as per each quantity, however, in description tab A09 unit is Caliper-Unch, please advise A: Unit of Measure should be caliper-inch
Q: Attachment 13 Item A22, provide max pipe size and confirm if this item includes excavation & backfill or if that will be paid for in other units A: The maximum pipe size would be 12”, for excavation and backfill lines B01, B02, or B05 would be applicable.
Q: Attachment 13 Item A23, is this combined with A22, does it include excavation/backfill, provide max pipe size.
A: Yes, this would be in conjunction with Line Item A22. This is an added cost for a short load. Excavation and backfill is not included in this line.
Q: Attachment 13 Item A24, provide max pipe size and confirm if this item includes excavation & backfill or if that will be paid for in other units A: The maximum pipe size would be 12”, for excavation and backfill lines B01, B02, or B05 would be applicable.
Q: Attachment 13 Item A25, what diameter should be assumed for core?
A: Contractor shall assume a maximum diameter of 15”.
Q: Attachment 13 Item A27, should we assume this material is clean and unregulated, or provide level of contamination.
A: This is for clean unregulated material
Q: Attachment 13 for Item A27, does this item include sampling, characterization and profiling of soils?
A: Yes
Q: Attachment 13 for Item B01, confirm note 3 is erroneous and all disposal of unsatisfactory material is paid under other units A: Note 3 is not erroneous. Contractor shall dispose of unsatisfactory material.
Disposal costs are covered under Line Item A26.
Q: Attachment 13 for Item C08 unit is in SF, C08 in description tab the unit is LF, please advise.
A: Unit should be SF
Q: Attachment 13 for Item D01, provide drawing detail showing reinforcement required for equal bidding purposes A: Assume not more than 100 lbs per cubic yard of concrete.
Q: Attachment 13 for Item D07 will base course material be covered in this item or by B09/B12?
A: Base course should be included in this line item.
Q: Attachment 13 for Item E08, description tab states 8" pipe in item and 6" pipe in description, please advise.
A: Should be 6”
Q: For all utilities, will bedding be paid under utility unit rate or unit rates in section B A: Paid for under the utility unit rate
Q: Attachment 13, items F01 thru F05, description says to include fittings. Provide specific type and quantity for equal bidding purposes or exclude from unit rate.
A: Contractor will have to make assumptions as to the type and quantity of fittings.
Type of fittings must be compatible with the type of pipe being installed and approved by the pipe manufacturer.
Q: Attachment 13, items I18 thru I24, description says to include fittings. Provide specific type and quantity for equal bidding purposes or exclude from unit rate.
A: Contractor will have to make assumptions as to the type and quantity of fittings.
Type of fittings must be compatible with the type of pipe being installed and approved by the pipe manufacturer.
Q: What item will grease hoods, detail 3/C510 be paid under?
A: Items I-04 thru I-07
Q: How will contractors be paid for temp fence, office trailers, portajohns?
A: This is part of your coefficient
Q: Attachment 13 for Item C08, provide drawing detail, does this include sand bedding and polymeric sand infill?
A: This item will include all materials and labor to install this item, to include sand bedding and polymeric sand infill. Updated detail sheet to be provided.
Q: Attachment 13 for Item E10, provide specific model number for bollards A: TrafficGuard 10 MPH Removable Bollard – 304 Stainless, #4 Brushed Finish (HL 2005 S S10}
Q: Provide detail for L07 and L08 vehicle gates A: Updated detail sheets will be provided.
Q: Please clarify whether unit prices in the schedule will be binding for future task orders or used solely for evaluation purposes.
A: The unit prices are binding, this is a 5-year task order and there are 5 tabs to include pricing for year 1 through year 5. The pricing will be binding for all future task orders.
Q: Please confirm whether zero-quantity items should be priced for install even though extended totals remain $0.
A: Provide unit pricing for all zero-quantity items even though extended totals remain $0.
Q: Please advise on RFI response timeline given current shutdown, and confirm if proposal extension will be granted.
A: Amend 005 extends the proposal due date to Dec 8th. Please view SAM.gov to confirm dates and instructions.
Q: We understand “EOS” tab in bid schedule is for “extension of service” beyond the 5-year contract period that would be for another six months to a year, please advise. Because this will add good amounts of the cost to total evaluated proposal price.
A: The EOS pricing will be added to the evaluation summary and will be included in the overall evaluated price. Contractor will be evaluated on total price of five years, plus the extension of services (EOS).
Q: Please advise if each line item unit price should include, labor, material, equipment, mobilization, and any other cost involved to perform that line SOW? this will help to calculate the cost for each line item, if the quantity is less than provided in the bid schedule.
A: Unit pricing for each line item shall be all inclusive to include labor, material, equipment, and mobilization and any other costs to perform each line item without any other costs to complete the work. Example, if you need nuts and bolts for fittings, you need to include in the line item cost and not charge separately as there is no line item for nuts and bolts. Contractor will not charge for additional fees and materials to complete work under each line item.
Q: Will the contractor be entitled to reimbursement for any additional work, equipment, or resources required to complete tasks under any line item? For example, if a vacuum truck is needed or rigging is required for demolition or installation activities.
A: No, contractor is responsible for means and methods to complete work for each line item without requesting modification for additional work, equipment or resources. All work is be completed in accordance with contract specifications.
Contractor to make assumptions of means and methods and include in line item pricing.
Q: For Item B16 "Directional Drilling of Pipes up to 12 Inches", there is no item description in the description tab. Please advise.
A: Description: 1. Equipment mobilization, 2. Site preparation, 3. Labor and materials,
4. Any other requirements to complete work
Q: For items J57 through J92 the quantity is set to 0 EA. Can we assume that a unit price does not need to be provided for these items?
A: Provide unit pricing for all zero-quantity items even though extended totals remain $0.
Q: In the bid schedule, Items J57 through J92 are still quantity zero. Should we populate a unit price or leave it blank? If we do put a unit price, it will not calculate a total in the spreadsheet. Please advise.
Provide unit pricing for all zero-quantity items even though extended totals remain $0.
Q: The pricing schedule shows a quantity of zero for the transformers, but the descriptions tab references installation. Should we update the quantities to one and include pricing for the installation of all listed transformers? Please advise.
A: Provide unit pricing for all zero-quantity items even though extended totals remain $0.
Q: We received an automated email on Nov 11, 2025, notifying us of McKenzie Construction being added to the notice. Is there access to a plan holder list for all interested parties for this solicitation?
A: No, the Govt does not provide a plan holder list for this solicitation.
Q: Currently, bids are due on Nov 27, 2025, which is Thanksgiving. Will this be revised or should we consider submitting bids in advance of that date?
A: Amend 005 extends the proposal due date to Dec 8th. Please view SAM.gov to confirm dates and instructions.
Q: Should there be quantities for items J57 through J92 on the bid schedule? (Attachment 13, updated Nov 5) If not, should pricing be entered that will not affect the value of the bid?
A: Provide unit pricing for all zero-quantity items even though extended totals remain $0.
Q: The Davis-Bacon wages included with the solicitation are for “Building” construction type. Should the wages be for “Heavy” or “Highway” based on the anticipated work of this
IDIQ?
A: This was an error on the Govt’s part. Highway Davis-Bacon wages will be used and are attached in Amend 005. Current Highway Davis-Bacon wages will be at the issuance of every Task Order off this IDIQ.
Q: Will the Davis-Bacon included with the solicitation remain the same throughout performance of the IDIQ contract, or is the successful offeror responsible for adopting new wages each time they are revised?
A: The offeror is responsible for adopting and forecasting new wages each time, escalate as necessary for each of the Annual Pricing, Tab “1” is for Year 1 of the IDIQ, Tab “2” is for Year 2 of the IDIQ, etc.
Q: Proposals are currently due on Thanksgiving. Will the government extend the due date to Tuesday, December 2, 2025?
A: Amend 005 extends the proposal due date to Dec 8th. Please view SAM.gov to confirm dates and instructions.
Q: Please confirm the following
1. There is not a Bid Bond requirement to submit with bid package
2. If awarded, there will be Performance/Payment Bonds required for each individual project award (roughly between $30K - $1,000,000 each) A: Confirmed