Summary

Labor CategoryRate
Project Manager$ - 0
Supervisory Auditor$ - 0
Senior Auditor$ - 0
Auditor$ - 0
Escalation0.00%
Labor CategoryHoursRateTotal
Project Manager350.00$ - 0$ - 0
Supervisory Auditor900.00$ - 0$ - 0
Senior Auditor1,400.00$ - 0$ - 0
Auditor1,980.00$ - 0$ - 0
4,630.00$ - 0
Travel$ 8,200.00
$ 8,200.00
Escalation0.00%
Labor CategoryHoursRateTotal
Project Manager350.00$ - 0$ - 0
Supervisory Auditor900.00$ - 0$ - 0
Senior Auditor1,400.00$ - 0$ - 0
Auditor1,980.00$ - 0$ - 0
4,630.00$ - 0
Travel$ 8,323.00
$ 8,323.00
Escalation0.00%
Labor CategoryHoursRateTotal
Project Manager350.00$ - 0$ - 0
Supervisory Auditor900.00$ - 0$ - 0
Senior Auditor1,400.00$ - 0$ - 0
Auditor1,980.00$ - 0$ - 0
4,630.00$ - 0
Travel$ 8,447.85
$ 8,447.85
Escalation0.00%
Labor CategoryHoursRateTotal
Project Manager350.00$ - 0$ - 0
Supervisory Auditor900.00$ - 0$ - 0
Senior Auditor1,400.00$ - 0$ - 0
Auditor1,980.00$ - 0$ - 0
4,630.00$ - 0
Travel$ 8,574.56
$ 8,574.56
Escalation0.00%
Labor CategoryHoursRateTotal
Project Manager350.00$ - 0$ - 0
Supervisory Auditor900.00$ - 0$ - 0
Senior Auditor1,400.00$ - 0$ - 0
Auditor1,980.00$ - 0$ - 0
4,630.00$ - 0
Travel$ 8,703.18
$ 8,703.18
LaborTravelTotal
Base Year$ - 0$ 8,200.00$ 8,200.00
Option Year 1$ - 0$ 8,323.00$ 8,323.00
Option Year 2$ - 0$ 8,447.85$ 8,447.85
Option Year 3$ - 0$ 8,574.56$ 8,574.56
Option Year 4$ - 0$ 8,703.18$ 8,703.18
Total$ - 0$ 42,248.59$ 42,248.59

File details come from the government source that posted it. Updated .