About this file

This is a Statement of Work for completion of a previously installed water cistern and installation of a water service line at a residential property located at 356456 5600 Rd, Jennings, OK 74038.

The contractor shall furnish and install a submersible 3-wire pump sized to deliver at least 15 gpm at 20 ft head, a minimum 44-gallon pressure tank rated for 40–60 psi, piping, controls, a well house, and electrical infrastructure. The pump must be controlled by a float switch and pressure switch with an electrical box and breaker between the pressure switch and pump. The well house must measure 4 feet minimum in all dimensions, be constructed of 3/32" thick fiberglass with 1" insulation, and be anchored to the cistern slab with 4 stainless steel bolts. All piping between components shall be minimum 1" PVC with a gate valve after the pressure tank, a check valve before the pump, and a 100 psi pressure gauge after the pressure tank. Electrical wiring must be at least 10 AWG, 3-wire, designed for direct bury at a minimum depth of 18", and housed in PVC conduit at connections to a minimum depth of 18".

The contractor shall install water service lines using blue PEX pipe with a pressure rating of 160 psi at 73.4°F and copper tube size fittings compatible with AWWA C800 compression-joint brass valves per AWWA C904 standards. The pipe must be laid continuously from the cistern to the home in a trench at least 30 inches deep with proper bedding and backfill specifications. All work must be performed by state-licensed plumbing personnel, tested in the presence of a Construction Inspector prior to completion, and covered by a minimum one-year warranty. The contractor must contact the Construction Inspector three business days before work begins and provide 24-hour notice for any scheduling changes.

View the file

Other files

File Type Posted
IHS IEE Representation Form__508 Compliant_ BLANK.docx DOCX document
PAW WD OK20260030 Osage Pawnee .pdf PDF
OEH8 - SR 4467.pdf PDF
Bid Sheet.pdf PDF
246-26-Q-0026.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cistern and Water Service Line

STATEMENT OF WORK

1.01 SUMMARY OF WORK TO BE DONE BY CONTRACTOR

A. Complete previously installed water cistern and furnish and install water service line as shown on the drawing. Work shall include;

1. Topping off tank with pump, pressure tank, and controls,

2. Installing electrical wire and conduit from completed tank to disconnect box on home,

3. Installing water service line from completed tank to home.

1.02 SITE LOCATION

A. 356456 5600 Rd Jennings, OK 74038 36.202781748, -96.652207001

1.03 CONSTRUCTION SCHEDULE

A. Contact the Construction Inspector three business days before the start of any work.

B. Failure to perform work on the date scheduled will require 24-hour notice to rescheduling the work.

C. Leave all work exposed until inspected and approved. Work not inspected before it is covered will be re-exposed at the Contractor’s expense.

1.04 QUALITY ASSURANCE

A. Perform work under the direction of personnel licensed in the state including, but not limited to:

1. Plumbing.

1.05 WARRANTY

A. Provide a minimum one-year warranty for all materials and labor, covering defects in the materials or workmanship.

1.06 CISTERN TANK TOP-OFF

A. Contractor shall furnish and install pump, controls, piping, well house, and pressure tank, to allow the cistern to store and deliver water to the home.

B. Piping between components shall;

1. Be PVC material, and at least 1” PVC.

2. Be compatible with components and water service line.

3. Include a gate valve after pressure tank, and a check valve before pump.

4. Include a 100 psi pressure gauge after pressure tank.

C. Pump shall be;

1. Submersible, 3 wire,

2. Sized to deliver a flow of at least 15 gpm at a head of 20 ft,

3. Or approved equal, D. Well house shall be:

1. 4 feet minimum in height, width, and length,

2. Constructed of 3/32” thick fiberglass,

3. Accessible from a hinged door,

4. Have 1” of spray, styrofoam, or fiberglass insulation,

5. Anchored to cistern slab by 4 stainless steel bolts.

6. Or approved equal.

E. Pressure tank shall be:

1. Minimum 44 gal in volume,

2. Rated for 40-60 psi,

3. Or approved equal, F. Controls shall be installed such that;

1. Pump is activated by a pressure switch located just upstream of pressure tank,

2. Pump is controlled by a float such that pump will not activate if water level is below pumping level,

3. A box and breaker shall be included between pressure switch and pump. Breaker shall be designed to trip if associated pump draws excessive current.

G. Electrical wiring shall be;

1. At least 10 AWG, 3 wire, and designed for direct bury.

2. Installed at a minimum depth of 18”,

3. Housed inside PVC conduit at connections to home disconnect and cistern controls, to a minimum depth of 18”.

1.07 WATER SERVICE LINES

A. PEX pipe, roll type, blue in color, pressure rating 160 psi at 73.4oF.

B. Fittings:

1. Copper tube size (CTS), SDR9, and is compatible with CTS AWWA C800 compression-joint brass valves and fittings using stainless steel inserts at connections.

2. AWWA C904

a. F1807: Brass or Copper Insert Fittings with Copper Crimp Rings.

b. F1960: Cold Expansion Fittings with PEX Reinforcing Rings.

c. F2080: Cold Expansion Fittings with Metal Compression-Sleeves.

C. Install water service lines and appurtenances in the locations, sizes and materials shown on the drawings or staked in the field.

D. Lay one continuous pipe from the cistern to the home. Splices are not allowed unless approved by the inspector in advance.

1.08 TRENCH

A. Depth: Minimum 30 inches.

B. Bottom: Free from stones greater than 1-inch, large dirt clods, any frozen material.

C. Bedding: If the trench bottom is hardpan, rock, or has stones larger than 1-inch in diameter in the largest direction:

a. Over excavate 6 inches.

b. Place 6 inches of mechanically compacted imported bedding

c. Place pipe in trench.

d. Place 6 inches of mechanically compacted river sand over the pipe.

D. Backfill: restore trenches to initial grade.

1.09 TESTING

A. Test cistern pump and controls in presence of inspector prior to completion.

B. Before joints are covered, test pipe for leaks.

C. Visually inspect all connections and fittings for leaks in the presence of the Construction Inspector.

D. Repair all leaks before backfilling and completion.

1.10 CLOSEOUT ACTIVITIES

A. Restore the site as close as is practical to its original condition.

B. Any utility or facility damage is to be corrected in kind by the Contractor.