This is a Request for Quote (RFQ) issued by Collier County, Florida, through its Public Utilities Department (PUD) for the removal and installation of hurricane impact-rated windows and doors at the Public Utilities Operations Center (PUOC) located at 4375 and 4425 Progress Avenue, Naples, Florida. The project involves complete replacement of windows, doors, and glass frames at both the East Building (4425) and West Building (4375), including 32 commercial windows, 7 commercial storefront doors with sidelites, and associated interior and exterior repairs. The scope of work includes demolition of existing systems, procurement and installation of new hurricane impact-rated components with tinted glass, removal of exterior awnings and shutter channels, repairs to stucco and drywall, and provision of operation and maintenance manuals with user training. A non-mandatory pre-bid meeting is scheduled for Tuesday, April 21, 2026, at 10:00 a.m. at the project site, with all questions due by May 1, 2026, at 10:00 a.m. RFQs are due on Wednesday, May 6, 2026, no later than 3:00 p.m. The selected contractor will have 210 days from purchase order issuance to achieve final completion.
The contractor is responsible for performing all take-offs and measurements, obtaining all required permits (with permit fees paid by the county), coordinating work with occupied buildings, and ensuring compliance with all applicable codes and Collier County vertical standards. Collier County will provide paint and replacement blinds at no cost to the contractor. The county utilizes a three-quote competitive process for vendor selection, awarding to the responsive and responsible low bid. Specific pricing terms are not disclosed in the RFQ document. The project manager is Anthony Lupo, reachable at (239) 207-0248, with additional contact available through Paul A. Abbott at Paul.Abbott@collier.gov or (239) 252-5347. Collier County does not accept quotes with non-standard terms and conditions, requiring all bidders to comply with county procurement policies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| PUOC_HI_System_Install.pdf | ||
| Insurance_Requirements_Template.docx | DOCX document | |
| PO_Terms_and_Conditions.pdf | ||
| Quick_Quotes_Instructions_Version_1_.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pathway / Parking
Building Envelope
Life & Safety
REQUEST FOR QUOTE
PROJECT TYPE
Repairs
Renovation
Maintenance
PROJECT SUMMARY
The Scope of Work is the official description of the work that is to be completed during the contract. The scope of work must be consistent with the project timeline and contract price methodology.PROJEC PROJECT NAME
REQUIRED SIGNATURES
FUND/ COST CENTER
GL CODE/ Project #
PROJECT NAME PROJECT LOCATION & ADDRESS
QUOTE DUE DATE AUTHORIZED PROJECT
DECISION & BUDGET CONTACT
CONTRACT # REQUEST DATE
SCOPE OF WORK
PER OUR PROCUREMENT DIVISION, COLLIER COUNTY IS NOT ALLOWED TO ACCEPT QUOTES WITH TERMS AND CONDITIONS.
FOR MORE INFORMATION REFERENCING THE FOLLOWING, PLEASE CLICK THE LINK BELOW
COLLIER COUNTY TERMS AND CONDITIONS
DIVISION DESIGNEE (REQUESTING DIVISION)
ASSIGNED PROJECT MANAGER SITE VISIT
DATE & TIME
New Construction
Development
Consulting / Estimate
Other - _________________
PROJECT MANAGER
Attached Photos https://www.colliercountyfl.gov/home/showpublisheddocument/74077/636364888296470000
LS 1
LS 1
Date:
Collier County Public Utilities Department Water Division (PUOC)
Signature of Representative:
TOTAL BID $0.00
Public Utilities Operations Center (PUOC) Progress Ave East & West Buildings -Hurricane Resiliency Project
RFQ/Bid Tab Sheet SCOPE OF WORK (Detailed in separate document)
Utilizing the Collier County's 3 Quote process. The selected Responsive & Responsible Low Bid Vendor is to perform the following services for the Public Utilities Department (PUD).
Task 2
Removal & installation of complete system includes all interior & exterior, demo as needed, installation, including replacement of sills where applicable, and repairs to stucco & drywall. Paint will be provided by Collier County. All Glass must be tinted with dart tint; shade to be selected by Collier County from samples
Name of Company:
Task 1
• Progress East Building (4425) Windows & Doors (glass & frame)
Remove existing & install new Hurricane Impact-rated windows, doors, & sidelites COMPLETE (as detailed in SOW)
Remove existing & install new Hurricane Impact-rated windows & doors COMPLETE (as detailed in SOW)
• Progress West Building (4375) Windows & Doors (glass & frame)
Public Utilities Operations Center (PUOC) Progress Ave, Naples, FL 34104
PROJECT: Remove & Replace E & W Buildings SF Glass, Windows, doors, frames (Complete) with HI Glass System
Progress Ave, Naples FL 34104 East & West Buildings
N East West
West side of East Building
Utilizing the Collier County’s 3 Quote process. The selected Responsive & Responsible Low Bid Vendor is to perform the following services for the Public Utilities Department (PUD).
Task – Remove existing & install new Hurricane impact-rated windows & doors complete, of both the East & West buildings.
4425 Progress Avenue (East Building)
W-1 W-2 W-3 W-4 D-1 W-5 W-6 W-7 W-8
D-1 W-1 W-2 W-3 W-4 D-2 D-3 W-5 W-6 W-7 W-8 D-4
4425 Progress Avenue (West Building)
Scope of Work:
• Progress Ave. East Building (4425) Windows & Doors (glass & frame).
o West side of East Building Commercial Right Hand (RH) Storefront Door with Sidelites (x2) Commercial Panel Storefront Glass Windows (x3) o South end of East Building Commercial Windows (x8) Commercial Left Hand (LH) Storefront Door (x1)
• Progress Ave. West Building (4375) Windows & Doors (glass & frame).
o South end of West Building
Commercial Windows (x8) Commercial Left Hand Storefront Doors (x2) Commercial Right Hand Storefront Door (x2)
The Contractor’s Responsibilities (Including but not limited to):
1. Their own take-off quantities, measurements of all windows, doors, and openings as needed
2. The removal & disposal of the buildings’ existing windows; procure & install the new Hurricane Impact rated system. Remove exterior awning/frame & shutter channels. Do not reinstall.
3. Work will be performed with the building occupied and any window/door removed must be completed/secured each day. Contractor must coordinate with building staff to ensure those impacted directly (by the work) can be temporarily relocated.
4. Contractor will obtain all required permits for the upgrade to the Hurricane Impact System as may be required.
5. Include tinted glass (dark tint shade to be approved by Collier County).
6. Hurricane impact glass to have a sticker on the inside (hurricane impact rating).
7. Remove interior blinds and dispose of; Collier County will replace, if necessary, with new blinds at no cost to the contractor.
8. Any required repairs to stucco (exterior) and drywall (interior) including painting resulting from the construction activities. Collier County will provide the paint at no cost to the contractor. Interior windowsills affected by the windows replaced are to be included in the bid price by the contractor (Collier County to pre-approve the quality & color.
9. The complete removal, replacement and repair (as may be needed) of windows and doors systems.
10. Provide O & M manuals & User Training, and as built details, at the completion of the work.
11. Shipment, delivery, and unloading of all materials to job site.
12. The disposal of unused and demo/removed materials.
13. Maintaining a clean work area and a final cleaning when project is complete.
14. The Coordination/supervision of (the work) all trades including accessories furnished and installed by third-party vendors. Scheduling, cutouts, recesses, blocking, etc. is the responsibility of the Contractor.
15. A turnkey project providing or obtaining all labor, material, permits and permissions to complete this project. The county will pay all permit fees. Contractor responsible for cost of (if any) failed inspections (i.e., Re-inspections).
16. Ensure all work is done in strict compliance with all applicable Codes and standards requirements.
17. Contractor to follow collier county vertical standards.
NON-MANDATORY PRE-BID MEETING:
The PRE-BID meeting shall be held on Tuesday, April 21, 2026, at 10:00 am. Additional site visits will be allowed, but must be scheduled with Project Manager – Paul Abbott (at least 24 hours prior)
Location: 4425 Progress Ave Naples, FL 34104
• During meeting all inspections of site may be conducted.
• Please have all questions submitted by: May 1st 10:00 AM.
RFQ DUE DATE:
RFQs for the above project shall be due Wednesday, May 6, 2026, no later than 3:00 PM.
Contact Information:
Project Manager: Paul A. Abbott E-Mail address: Paul.Abbott@collier.gov Telephone #: (239) 252-5347 mailto:Paul.Abbott@collier.gov
| Untitled |
| PUOC Prog. E&W HI Glass-SOW.pdf |
| Task – Remove existing & install new Hurricane impact-rated windows & doors complete, of both the East & West buildings. |
| The Contractor’s Responsibilities (Including but not limited to): |
| 1. Their own take-off quantities, measurements of all windows, doors, and openings as needed |
| 2. The removal & disposal of the buildings’ existing windows; procure & install the new Hurricane Impact rated system. Remove exterior awning/frame & shutter channels. Do not reinstall. |
| 3. Work will be performed with the building occupied and any window/door removed must be completed/secured each day. Contractor must coordinate with building staff to ensure those impacted directly (by the work) can be temporarily relocated. |
| 4. Contractor will obtain all required permits for the upgrade to the Hurricane Impact System as may be required. |
| 5. Include tinted glass (dark tint shade to be approved by Collier County). |
| 6. Hurricane impact glass to have a sticker on the inside (hurricane impact rating). |
| 7. Remove interior blinds and dispose of; Collier County will replace, if necessary, with new blinds at no cost to the contractor. |
| 8. Any required repairs to stucco (exterior) and drywall (interior) including painting resulting from the construction activities. Collier County will provide the paint at no cost to the contractor. Interior windowsills affected by the windows replace... |
| 9. The complete removal, replacement and repair (as may be needed) of windows and doors systems. |
| 10. Provide O & M manuals & User Training, and as built details, at the completion of the work. |
| 16. Ensure all work is done in strict compliance with all applicable Codes and standards requirements. |
| Bid Tab Prog HI Glass.pdf |
| PUOC Merc HR Proj |
VCP Pathways
Project Name :
Scope of work
Task Description Quantity Total Price
Total $ - 0
** All quantities given are estimates. Contractor is responsible for final take off and quantities. **
Company:
Signature:
image1.png
| Check Box1: Yes | |
| Check Box2: Off | |
| Check Box3: Off | |
| Check Box4: Off | |
| Check Box5: Off | |
| Check Box6: Off | |
| Check Box7: Off | |
| Check Box8: Yes | |
| Check Box9: Off | |
| Check Box10: Off | |
| Text18: Pamela Libby | |
| Text19: 4012-273512-70113.1.4 | |
| Text20: | |
| 2026-04-13T13:55:04-0400 | |
| LupoAnthony |
| 2026-04-13T14:50:44-0400 | |
| libby_p |
| Date2_af_date: |
| Date3_af_date: |
| Date4_af_date: |
| Check Box11: Yes |
| Text11: N/A |
| Text13: PUOC-HI System Install |
| Text14: 4375 & 4425 Progress Ave, Naples, FL 34104 |
| Text17: ANTHONY LUPO |
| Text3: CALENDAR INVITE FOR SITE VISIT TO FOLLOW, IF APPROPRIATE |
| Text2: "REQUEST FOR QUOTE" RECEIVAL RESPONSE REQUIRED |
| Scope: Utilizing the Collier County’s 3 Quote process. The selected Responsive & Responsible Low Bid Vendor is to perform the following services for the Public Utilities Department (PUD). |
Task – Remove existing & install new Hurricane impact-rated windows & doors complete, of both the East & West buildings.
Additional Information:
1. Progress Ave. East Building (4425) Windows & Doors (glass & frame).
• West side of East Building o Commercial Right Hand (RH) Storefront Door with Sidelites (x2) o Commercial Panel Storefront Glass Windows (x3)
• South end of East Building o Commercial Windows (x8) o Commercial Left Hand (LH) Storefront Door (x1)
2. Progress Ave. West Building (4375) Windows & Doors (glass & frame).
• South end of West Building o Commercial Windows (x8) o Commercial Left Hand Storefront Doors (x2) o Commercial Right Hand Storefront Door (x2)
3. Upon issuance of purchase order contractor will provide Project Manager contact within 5 work days.
4. Collier County Project Manager is Anthony Lupo (239) 207-0248.
5. Contractor will have 210 days to final completion from issuance of the purchase order.
File details come from the government source that posted it. Updated .