SGHC Emergency Request for Bids Dishwashwer Replacement 10.2023.pdf
PDF 535 KB Posted
- Solicitation number
- BPM040837
- Issued by
- Baltimore County, Maryland
About this file
This document is an Invitation for Bids (IFB) issued by the Maryland Department of Health, Spring Grove Hospital Center (SGHC) for a Commercial Dishwasher with Installation Services. SGHC is seeking a single contractor to provide a new commercial dishwasher, model EUCCW8 or approved equivalent, along with installation, removal, disposal, and training services. The equipment must be delivered within 30 days of contract award and installed within 7 days of delivery. A pre-bid site visit is scheduled for October 5, 2023, and bids are due by October 9, 2023. The resulting contract will be a firm fixed-price award with a term of approximately 14 months, starting on November 1, 2023 and ending on December 31, 2024.
The IFB includes detailed requirements and specifications for the commercial dishwasher, as well as mandatory qualifications for the contractor. Pricing must be submitted on the provided Attachment B Bid Form, and the contract will be awarded to the responsible bidder submitting the most favorable total bid price. The procurement will be conducted under the Emergency Procurement method, and no renewal options are included. Minority Business Enterprises are encouraged to respond to this solicitation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Maryland Department of Health
EMERGENCY PROCUREMENT
Spring Grove Hospital Center
THIS SOLICITATION SHALL BE MADE IN ACCORDANCE WITH THE SMALL PROCUREMENT
REGULATIONS DESCRIBED IN COMAR 21.05.07.
INVITATION FOR BIDS
SOLICITTION 24-22184
Issue Date: October 5, 2023
Commercial Dishwasher and Installation at
Spring Grove Hospital Center
NOTICE
A Prospective Bidder that has received this document from the Department of General Services’ website or procurement.maryland.gov or that has received this document from a source other than the
Procurement Officer, and that wishes to assure receipt of any changes or additional materials related to this IFB, should immediately contact the Procurement Officer and provide the Prospective Bidder’s name and mailing address so that addenda to the IFB or other communications can be sent to the Prospective
Bidder.
Minority Business Enterprises Are Encouraged to Respond to this Solicitation https://procurement.maryland.gov/
STATE OF MARYLAND
NO BID NOTICE
In order to help us improve the quality of State solicitations, and to make our procurement process more responsive and business friendly, we ask that you take a few minutes and provide comments and suggestions regarding this solicitation. Please return your comments with your response. If you have chosen not to respond to this Contract, please email or fax this completed form to the attention of the Procurement Officer
(see the Key Information Sheet below for contact information).
Title: Commercial Dishwasher and Installation
Solicitation No: OPASS# 24-22184. If you have chosen not to respond to this solicitation, please indicate the reason(s) below:
( ) Other commitments preclude our participation at this time.
( ) The subject of the solicitation is not something we ordinarily provide.
( ) We are inexperienced in the work/commodities required.
( ) Specifications are unclear, too restrictive, etc. (Explain in REMARKS section.)
( ) The scope of work is beyond our present capacity.
( ) Doing business with the State of Maryland is simply too complicated. (Explain in REMARKS section.)
( ) We cannot be competitive. (Explain in REMARKS section.)
( ) Time allotted for completion of the Bid/Proposal is insufficient.
( ) Start-up time is insufficient.
( ) Bonding/Insurance requirements are restrictive. (Explain in REMARKS section.)
( ) Bid/Proposal requirements (other than specifications) are unreasonable or too risky.
(Explain in REMARKS section.)
( ) MBE or VSBE requirements. (Explain in REMARKS section.)
( ) Prior State of Maryland contract experience was unprofitable or otherwise unsatisfactory. (Explain in REMARKS section.)
( ) Payment schedule too slow.
( ) Other:__________________________________________________________________
2. If you have submitted a response to this solicitation, but wish to offer suggestions or express concerns, please use the REMARKS section below. (Attach additional pages as needed.).
REMARKS:
Vendor Name: ___________________________________________ Date: _______________________
Contact Person: _________________________________ Phone (____) _____ - _________________
Address: ______________________________________________________________________
E-mail Address: ________________________________________________________________
ATTENTION: PLEASE FAX OR EMAIL ONLY
STATE OF MARYLAND
SPRING GROVE HOSPITAL CENTER
IFB KEY INFORMATION SUMMARY SHEET
Invitation for Bids: Commercial Dishwasher and Installation
Solicitation Number: OCMP# 24-22184
IFB Issue Date: October 5, 2023
IFB Issuing Office: MARYLAND DEPARTMENT OF HEALTH
SPRING GROVE HOSPITAL CENTER
Procurement Officer: Melane’ Boltz
Office of Contract Management and Procurement
Phone: 410-543-4084 e-mail: Melane.boltz@maryland.gov
Contract Monitor: Jorel Fleming
Spring Grove Hospital Center
55 Wade Avenue, Catonsville, MD 21228
Phone: 410-402-7301 e-mail: jorel.fleming@maryland.gov
Term of Service: November 1, 2023, through December 1, 2024
Options 0
Bids are to be sent to: Melane’ Boltz, Procurement Officer e-mail: melane.boltz@maryland.gov
Pre-Bid/Site Visit Thursday, Oct 5, 2023, at 1:00 pm
Closing Date and Time: Monday, October 9, 2023, at 10:00 am Local Time
1.SUMMARY STATEMENT AND GENERAL INFORMATION
1.1 Summary Statement
The Maryland Department of Health, Spring Grove Hospital Center (SGHC) is seeking is seeking a Contractor a Contractor to provide a Commercial Dishwasher with Installation
Services to support Spring Grove Hospital Center (SGHC) in maintaining compliance with Food
Service Operational requirements.
The Department intends to make a single award as a result of this IFB.
1.2 Contract Type
The Contract resulting from this IFB shall be a firm fixed price award as defined in COMAR 21.06.03.02
1.3 Term of Contract
The contract resulting from this solicitation shall be for two years beginning on or about November 1, 2023, and ending on December 31, 2024 , with 0 renewal option.
1.4 Procurement Officer
The Procurement Officer is the sole point of contact in the State for purposes of this solicitation prior to the award of any Contract. The name and contact information of the Procurement Officer are indicated in the IFB Key Information Summary Sheet.
The Department may change the Procurement Officer at any time by written notice.
1.5 Contract Monitor
The Contract Monitor is the State representative for this Contract who is primarily responsible for
Contract administration functions after Contract award.
The name and contact information of the Contract Monitor are indicated in the IFB Key Information
Summary Sheet.
The Department may change the Contract Monitor at any time by written notice.
1.6 eMaryland Marketplace Advantage eMMA is an electronic commerce system for the State of Maryland. The solicitation and Bidder questions and the Procurement Officer’s responses, addenda, and other solicitation-related information will be provided via eMMA. In order to receive a contract award, a vendor must be registered on eMMA.
Registration is free. Go to emma.maryland.gov click on “Register” to begin the process, and then follow the prompts.
1.7 Questions and Inquiries
Written questions from prospective Bidders will be accepted by the Procurement Officer and shall be submitted via eMMA to the Procurement Officer indicated in the IFB Key Information Summary Sheet.
https://emma.maryland.gov/page.aspx/en/usr/login?ReturnUrl=%2fpage.aspx%2fen%2fbuy%2fhomepage
Questions are requested to be submitted at least seven (7) days prior to the Bid due date. The Procurement
Officer, based on the availability of time to research and communicate an answer, shall decide whether an answer can be given before the Bid due date.
1.8 Procurement Method
This Contract will be awarded in accordance with the Emergency Procurement method under
COMAR 21.05.06.02.D)https://dsd.maryland.gov/regulations/Pages/21.05.06.02.aspx.
1.9 Bids – Closing/Due Date
Bids must be received by the Procurement Officer no later than the Bid Due date and time indicated in the
IFB Key Information Summary Sheet in order to be considered.
Bids may only be submitted to the Procurement Officer’s email. Please DO NOT hand delivery any replies to the facility.
Requests for an extension of this time or date will not be granted.
Bids may be modified or withdrawn by written notice received by the Procurement Officer before the time and date set for the opening.
Bid amounts will not be eligible for increases unless it is specified on the bid page that an annual change in rate is allowable.
1.10 Pre-Bid/Site Visit
There will be a site visit on Thursday, October 5, 2023, at 1:00pm at the facility located at 55 Wade
Avenue, Catonsville, MD 21228
1.11 Award Basis
The Contract shall be awarded to the responsible Bidder submitting a responsive Bid with the most favorable Total Bid Price as referenced in COMAR 21.05.02.13) for providing the services as specified in this IFB. The most favorable Total Bid Price will be the lowest price total. This will be a single bid award.
1.12 Tie Bids
Tie Bids will be decided pursuant to COMAR 21.05.02.14.
1.13 Duration of Bid
Bids submitted in response to this IFB are irrevocable for 120 days following the closing date of the Bids.
This period may be extended at the Procurement Officer’s request only with the Bidder’s written agreement.
1.14 Revisions to the IFB
If it becomes necessary to revise this IFB before the due date for Bids, the Department shall provide addenda to all prospective Bidders through eMMA. Addenda will be placed on eMMA within a reasonable time to allow Bidders to consider them in preparing their bids. It remains the responsibility of all prospective Bidders to check eMMA for any addenda issued prior to the submission of Bids. If the due date for submission of bids does not permit adequate time for consideration of the addenda by
Bidders, the bid due date will be extended.
https://dsd.maryland.gov/regulations/Pages/21.05.06.02.aspx
Bidders should acknowledge receipt of all addenda to this IFB issued before the Bid due date. Failure to acknowledge receipt of an addendum does not relieve the Bidder from complying with the terms, additions, deletions, or corrections set forth in the addendum, and may cause the Bid to be rejected as being non-responsive to the requirements of the IFB.
1.15 Cancellations
The State reserves the right to cancel this IFB, or accept or reject any and all Bids, in whole or in part, received in response to this IFB.
1.16 Incurred Expense
The State will not be responsible for any costs incurred by any Bidder in preparing and submitting a Bid or in performing any other activities related to submitting a Bid in response to this solicitation.
1.17 Mandatory Contractual Terms
By submitting a Bid in response to this IFB, a Bidder, if selected for award, shall be deemed to have accepted the terms and conditions of this IFB and the Contract, attached herein as Attachment M.
Attachment C Bid Proposal Affidavit, Attachment H Conflict of Interest Affidavit, Attachment I Non-
Disclosure Agreement and Attachment N Contract Affidavit. If additional Attachments are required the vendor will have 24 hours to comply with the request to complete and return the attachments. Any exceptions to this IFB or the Contract must be raised prior to Bid submission. Changes to the solicitation, including the Bid Form or Contract, made by the Bidder may result in Bid rejection.
1.18 Protest/Disputes
Any protest or dispute related, respectively, to this solicitation or the resulting Contract shall be subject to the provisions of COMAR 21.10 (Administrative and Civil Remedies).
1.19 Bidder Responsibilities
The selected Bidder shall be responsible for rendering goods and services for which it has been selected as required by this IFB. All subcontractors shall be identified and a complete description of their role relative to the Bid shall be included in the Bidder’s Bid.
If a Bidder that seeks to perform or provide the services required by this IFB is the subsidiary of another entity, all information submitted by the Bidder, such as but not limited to, references, financial reports, or experience and documentation (e.g. insurance policies, bonds, letters of credit) used to meet minimum qualifications, if any, shall pertain exclusively to the Bidder, unless the parent organization will guarantee the performance of the subsidiary. If applicable, the Bidder’s Bid shall contain an explicit statement that the parent organization will guarantee the performance of the subsidiary.
1.20 Substitution of Personnel
If the solicitation requires that particular individual(s) or personnel be designated by the Bidder to work on the Contract, any substitution of personnel after the Contract has commenced must be approved in writing by the Contract Monitor prior to the substitution. If the Contractor substitutes personnel without the prior written approval of the Contract Monitor, the Contract may be terminated for default which shall be in addition to, and not in lieu of, the State’s remedies under the Contract or which otherwise may be available at law or in equity.
1.21 Compliance with Laws/Arrearages
By submitting a Bid in response to this IFB, the Bidder, if selected for award, agrees that it will comply with all Federal, State, and local laws applicable to its activities and obligations under the Contract.
By submitting a response to this solicitation, each Bidder represents that it is not in arrears in the payment of any obligations due and owing the State, including the payment of taxes and employee benefits, and that it shall not become so in arrears during the term of the Contract if selected for Contract award.
1.22 Verification of Registration and Tax Payment
Before a business entity can do business in the State it must be registered with the State Department of
Assessments and Taxation (SDAT). SDAT is located at State Office Building, Room 803, 301 West
Preston Street, Baltimore, Maryland 21201. The SDAT website is http://www.dat.state.md.us/sdatweb/services.html .
It is strongly recommended that any potential Bidder complete registration prior to the due date for receipt of Bids. A Bidder’s failure to complete registration with SDAT may disqualify an otherwise successful
Bidder from final consideration and recommendation for Contract award.
1.23 False Statements
Bidders are advised that Md. Code Ann., State Finance and Procurement Article, § 11-205.1 provides as follows:
In connection with a procurement contract a person may not willfully:
(a) Falsify, conceal, or suppress a material fact by any scheme or device;
(b) Make a false or fraudulent statement or representation of a material fact; or
(c) Use a false writing or document that contains a false or fraudulent statement or entry of a material fact.
A person may not aid or conspire with another person to commit an act under subsection (1) of this section.
A person who violates any provision of this section is guilty of a felony and on conviction is subject to a fine not exceeding $20,000 or imprisonment not exceeding five years or both.
1.24 Payment
The Contractor shall choose one method of submission, USPS, or email. The Contractor shall submit an original of each invoice and signed authorization to invoice to the Contract Monitor and the Accounts
Payable office.
All invoices for services shall be verified by the Contractor as accurate at the time of submission.
An invoice not satisfying the requirements of a Proper Invoice (as defined in COMAR 21.06.09) cannot be processed for payment. To be considered a Proper Invoice, invoices must include the following information, without error:
1) Contractor name and address;
2) Remittance address;
3) Federal taxpayer identification (FEIN) number, social security number, as appropriate;
4) Invoice period (i.e., time period during which services covered by invoice were performed);
http://www.dat.state.md.us/sdatweb/services.html
5) Invoice date;
6) Invoice number;
7) State assigned Contract number;
8) State assigned (Blanket) Purchase Order number(s);
9) Goods or services provided;
10) Amount due; and
11) Any additional documentation required by regulation or the Contract.
The facility reserves the right to reduce or withhold Contract payment in the event the Contractor does not provide the facility with all required deliverables within the time frame specified in the Contract or otherwise breaches the terms and conditions of the Contract until such time as the Contractor brings itself into full compliance with the Contract.
Any action on the part of the facility, or dispute of action by the Contractor, shall be in accordance with the provisions of Md. Code Ann., State Finance and Procurement Article §§ 15-215 through 15-223 and with COMAR 21.10.04.
Invoices for final payment shall be clearly marked as “FINAL” and submitted when all work requirements have been completed and no further charges are to be incurred under the Contract. In no event shall any invoice be submitted later than 60 calendar days from the Contract termination date.
For the purposes of the Contract an amount will not be deemed due and payable if:
1) The amount invoiced is inconsistent with the Contract;
2) The proper invoice has not been received by the party or office specified in the Contract;
3) The invoice or performance is in dispute, or the Contractor has failed to otherwise comply with the provisions of the Contract;
4) The item or services have not been accepted;
5) The quantity of items delivered is less than the quantity ordered;
6) The items or services do not meet the quality requirements of the Contract; or
The Contractor has not submitted satisfactory documentation or other evidence reasonably required by the Procurement Officer or by the Contract concerning performance under the Contract and compliance with its provisions.
THE REMAINDER OF THIS PAGE IS INTENTIONALLY LEFT BLANK.
SECTION 2 -MINIMUM QUALIFICATIONS
2.1 Bidder Minimum Qualifications
2.1.1 Contractor is responsible for having and demonstrating an understanding of the work to be performed along with proposed services including a work plan, methodology, experience, skills and qualified staff.
2.1.2 Contractor shall have the necessary financial, technical and technological resources to furnish and install goods. Contractor shall accomplish all work in strict accordance to the regulations and requirements as set forth by Engineering, Electrical and Mechanical Best Practice Standards
2.1.3 Contractor shall maintain documents that each person deployed possesses the requisite training, qualifications, and competence to perform the duties to which they are assigned.
2.1.4 Contractor shall possess at the time of the response verifiable work experience for three (3) to five (5) years providing for the same or similar commercial equipment delivery and installation under
Healthcare, Correctional or Academic Institutional environments.
2.1.5 Contractor shall perform the activities required to successfully complete the SGHC requirements and submit each Deliverable to the contract manager or their designee.
Item Description Format Due Date
Work
Schedule
Contractor shall provide the CONTRACT MONITOR OR DESIGNEE schedule that shows key milestones, material delivery, demolition, installation, clean up and close out.
Simple bar or Gnatt chart schedule - Soft Copy
Within 10 Days from
Contract Award
Drawings/Cut
Sheets
Contractor shall submit for CONTRACT MONITOR OR DESIGNEE approval cut sheets that shows detailed specifications and installation requirements
Customized and Final Drawing/Cut Sheets Required prior to Installation
Hard and Soft
Within (ten) 10 business days from Contract
Award
Activity
Hazard
Analysis (AHA):
Contractor shall submit for CONTRACT MONITOR OR DESIGNEE approval AHA’s for each definable features of work associated with this project. Purpose: The purpose of activity hazard analysis (AHA) is to identify potential risks that exist around the worksite premises.
Soft Copy Within 15 Days of
Contract Award
Permits and
Licenses
Equipment compliance certifications that the equipment conforms to ANSI, NEC or other Standardization Authority. Copy of DC Trade
Permits and Applicable Licenses
Soft and Hard
Prior to
Equipment
Installation
Material
Safety Data
Sheets (MSDS)
MSDS sheets applicable for the installation and operation of equipment. Soft and Hard
Copy
Prior to MDH
Acceptance of
Final Work
SECTION 3 – SCOPE OF WORK
3.1 Background and Purpose
The MARYLAND DEPARTMENT OF HEALTH Spring Grove Hospital Center requires a new
Champion Dishwasher, Model EUCCW8 or Approved Equivalent Commercial Dishwasher
(“Warewasher”) which shall operate on electrical power. Contractor shall provide installation, removal, disposal and training services under the Contract resulting from this Solicitation. Equipment Delivery should arrive within thirty (30) days of Contract Award notification and installation shall be completed seven (7) days of delivery to the facility.. Equipment Training and demonstrations shall be provided as described in Section 3.2.
SGHC requires a replacement Commercial Dishwasher as a result of Food Service Operations compliance requirements.
3.2 Scope of Work Requirements
It is the State’s intention to obtain services, as specified in this IFB, from a Contract between the selected
Bidder and the State.
Spring Grove Hospital Center requires a new Champion Dishwasher, Model EUCCW8 or Approved
Equivalent Commercial Dishwasher (“Warewasher”) which shall operate on electrical power. Contractor shall provide installation, removal, disposal, and training services under the Contract resulting from this
Solicitation. Equipment Delivery should arrive within thirty (30) days of Contract Award notification and installation shall be completed seven (7) days of delivery to the facility. Equipment Training and demonstrations shall be provided as described in Section 3.2
3.2.1 ORDERING PROCEDURES
The items ordered under this Contract resulting from this Solicitation are covered under the Attachment B
Bid Tab Form. All orders against this Contract are subject to the Terms and Conditions specified and for the period stated.
3.2.2 ATTACHMENT B – PRICING SHEET
The Attachment B Bid Form must be priced at the unit level provided and must include cost per unit and extended cost. There shall be no alterations to the Attachment B Price Sheet.
3.2.3 Contractor shall provide all necessary supervision, labor, adequate staffing, new equipment, materials, supplies, installation accessories, personal protection equipment and debris/dust control measures for the installation of new equipment along with removal/disposal of existing equipment as described.
Operations &
Maintenance
Manuals
(O&Ms)
Operations and Maintenance (O&Ms) manuals. Two (2) hard copies and one (1) soft copy on disc or other MDH approved removable storage media
Hard and Soft
Prior to MDH
Acceptance of
Final Work
Warranties Manufacturer’s, Extended Labor/Parts Warranty and
Other Warranties as Applicable under the Procurement
TBD
Prior to MDH
Acceptance of
Final Work
3.2.4 Contractor shall attend a Kick-Off Meeting within Seven (7) Business Days of the MDH executed Contract Award Notification.
3.2.5 Contractor/Subcontractor’ Staff shall attend a mandatory project orientation which shall be conducted by SGHC Facilities Management to discuss Hospital policies, security, safety, access and utility connections and population served at the facility.
3.2.6 Contractor shall provide all electrical, plumbing, and mechanical work associated with the proper installation of the new equipment in accordance to all applicable Federal and State of Maryland regulations. The new equipment shall be installed in accordance with Manufacturer’s installation specifications and industry standards to include but not limited NEC, NEIS, ANSI.
3.2.7 Contractor shall perform the necessary pre and post installation inspections and operating tests.
Contractor shall have third party licensed electrician verify that all installations meet industry standards and codes and provide a written copy of the inspection to the Contract Monitor or Designee
3.2.8 Contractor shall inspect all areas for the performance of this project to determine any defects that may prevent the proper completion of the project. Any such defects shall be immediately reported to the Contracting Officer’s Technical Representative (COTR) and the Contractor shall not proceed with work until such defects are corrected.
3.2.9 Contractor shall be responsible for all necessary permits, inspection cost, offsite storage, shipping, insurance, and freight where required for delivery, installation, removal and disposal.
3.2.10 WORKING HOURS: Contractor working hours shall be performed during the hours of 7:30
AM through 4:00 PM Monday through Friday. Contractor shall provide installation and removal services which require utility shut off or excessive noise Monday through Friday during the hours of
5:00pm through 4:00am. Weekend Work shall be Exempt unless approved in writing via the Contracting
Officer’s Technical Representative (COTR) along with a MDH executed Contract Modification.
3.2.11 TRAINING SERVICES AND DEMONSTRATIONS: Contractor shall provide a minimum of three (3) training sessions for onsite Workers.
a. Contractor shall provide In-service training and demonstrations for SGHC Food Service worker on the proper use and specific care of the machine to include but not limited to removal of the scrap screens, water jet arms for cleaning, interval cleaning, etc.
b. Contractor shall provide In-service training to SGHC Facilities staff on the proper maintenance of the machine.
3.2.12 Contractor shall furnish and install a new Champion Model CW Series Upright Conveyor Type
Dishwasher.
a. The new Commercial Grade Dishwasher equipment shall be equivalent in durability and capacity as Commercial Dishwashers utilized in Private Hospitals and Correctional Facilities.
b. Commercial Dishwasher shall be a Champion Brand, Model # EUCCW8 or Equal Commercial
Dishwasher with the necessary connection, sanitizing and electrical accessories that meet the following Specifications:
I. 29" wide peg belt
II. Dual Rinse feature
III. automatic tank fill
IV. vent fan control
V. electric eye idle pump shut-off & rinse saver
VI. stainless steel base & legs
VII. push-button start-stop station - load end
VIII. stainless-steel front end enclosure panels
IX. SST pumps impellers
X. re-circulating flushing nozzles - load end
XI. vent openings with 7" stainless steel stacks & locking dampers - both ends
XII. anti-jam & reverse switch
XIII. cULus
XIV. NSF
XV. ENERGY STAR®
XVI. 2-year parts and labor warranty
c. Reconditioned or Refurbished Equipment shall not be accepted.
d. Contractor(s) shall be responsible to verify all measurements, connection locations, loading dock measurements and quantity prior to submitting Bids. The contractor shall place an order with the Manufacturer or Manufacturer’s authorized dealer immediately upon Contract
Award and provide the SGHC the delivery lead timetable in writing.
e. Provide supervision of reassembly, installation, start up, and training by a certified company representative.
f. The contractor shall on a daily basis remove, and dispose of all protection items, tools, discarded equipment, excess materials and debris from the job site without any delay.
Contractor shall not utilize any dumpster on the SGHC campus grounds
g. The contractor shall exercise extreme caution and care to avoid and prevent any damages to adjacent equipment, surfaces, and existing structures which are excluded from the Scope of
Work. Any and all damages to such adjacent equipment, surfaces, and existing structures shall be fully restored or replaced by the contractor at no cost to the State of Maryland
Government within five (5) working days
3.2.13 DEMOLITION: Contractor shall safely and responsibly remove and discard the existing
Commercial Dishwasher.
3.2.14 The Contract Monitor or Designee shall receive all Contractor reports, schedules, final drawings along with being responsible for monitoring performance of the Contractors’ services to be performed under the Contract resulting from this Solicitation.
3.2.15 Contractor shall obtain written approval from COTR approval prior to placing order for equipment and commencing installation services. The contractor shall obtain written approval from the
Contract Monitor or Designee approval prior to placing order for equipment and commencing installation services.
3.2.16 Contractor and/or Contractor’s deployed Staff performing onsite services shall be required to comply with facility security check point requirements which includes but not limited to Federal and/or
State Issued Photo Identification verification. Contractor(s) shall immediately leave the premises after the completion of on-site work or meetings
3.2.17 GUARANTEE OF WORK: Contractor shall accomplish all work in strict accordance to the regulations and requirements as set forth by Best Practice and Standard Specifications and other applicable codes, and standard engineering practices.
a. The Contractor guarantees, for a Period of One (1) Year after Date of Acceptance to repair or replace any work in which any Defects in material or workmanship appear within said period and to repair or replace any and all work damaged by reasons thereof, to the satisfaction of the COTR and without cost to the District.
b. In any case where in fulfilling the requirements of the Contract or any guarantee, embraced in or required thereby, the Contractor disturbs any work guaranteed under another contract, he shall restore such disturbed work to a condition comparable to its original condition and guarantee such restored work to the same extent as it was guaranteed under such other contracts.
c. Upon the Contractor’s failure to proceed promptly to comply with the terms of any guarantee under the contract or still running upon work originally executed by other Contractors, the
District may (1) either have such work performed as the Director/ACCO deems necessary to fulfill such guarantee, or (2) allow all such damaged or defective work to remain in such unsatisfactory condition; provided that the Contractor shall promptly pay the District the sum estimated by the Director/ACCO under the provision of paragraphs above to represent the amount which would have been necessary to expend to fulfill such guarantee. Everything done in the fulfillment of any guarantee shall be without additional expense to the Government of the District of Columbia.
3.3 Department Obligations
3.3.1 The State will provide normal office working facilities and equipment reasonably necessary for
Contractor performance under the Contract. Any special requirements (e.g., reprographic services, computer time, key data entry) shall be identified.
3.3.2 The State is responsible for providing required information, data, documentation, and test data to facilitate the Contractor’s performance of the work and will provide such additional assistance and services as is specifically set forth.
3.3.3 Holly Center’s Program Services Director/Contract Manager will provide scheduling for weekly
Dental Clinic appointments.
3.3.4 The Contract Monitor will give written notice of performance issues to the Contractor, clearly describing the problem and delineating remediation requirement(s). If performance issues persist, the Contract Monitor may request the immediate removal of persons(s) whose performance is an issue and determine whether a substitution is required.
3.3.5 Before any of the work shall begin, the Contractor shall confer with the State’s representative at the site and agree on times, a sequence of procedure, means of access to the premises, space for storage of materials and equipment, use of approaches, use of facilities, etc.
3.3.6 If it becomes necessary to perform work on days or at times other than those indicated above or on holidays, special permission must be obtained in advance from the State’s representative in writing.
3.3.7 State holidays shall be observed by the Contractor and shall include:
● New Year’s Day
● Martin Luther King Day Columbus Day
● Presidents Day
● Veterans Day
● Memorial Day Thanksgiving Day
● Juneteenth Christmas Day
● Independence Day
● Labor Day
● Election Day
● Thanksgiving Day
● Native American Heritage Day
● Christmas Day and all other additional days authorized by the Governor, plus official general election holidays.
3.4 Contract Term
The term of this contract is for a period of twelve months beginning in November 2023 and ending in December 2024.
3.5 Contractor’s Liability Insurance
Responsibility for Damage Claims
The Contractor shall indemnify and save harmless and defend the State and all of its representatives from all suits, actions, or claims, of any character brought on account of any injuries or damages sustained by any person or property in consequence of any work performed under this Contract either by the Contractor or any subcontractor, or their employees, agents, or representatives.
Liability Insurance
1. The Contractor and its subcontractors shall maintain such insurance as shall protect the Contractor from claims under Workmen’s Compensation Act and the
Federal Employers Liability Act by coverage with insurance companies or by methods acceptable to the State Insurance Commissioner and by no other method, for damages which may arise from operations under this Contract, whether such operations be by the Contractor or by any subcontractor or anyone directly or indirectly employed by either of them.
2. The Contractor shall protect the Contractor self and the State from any claims from Bodily Injury, Liability, and Property Damage Liability.
3. The limits for Bodily Injury Liability shall be not less than
$1,000,000/$2,000,000; that is, $1,000,000 is the limit for injury per occurrence and $2,000,000 in the aggregate. The minimum limit for Property Damage
Liability shall be $1,000,000 per occurrence and $2,000,000 for aggregate.
4. The above policies for Bodily Injury and Property Damage Liability Insurance shall be so written as to include Contingent bodily Injury and Property Damage
Liability Insurance to protect the Contractor against claims from the operations of subcontractors.
5. Certificates of the Contractor’s insurance containing evidence of the Hold
Harmless Clause protecting the State of Maryland shall be filed with the
Procurement Coordinator and shall be subject to the approval of the Procurement
Officer for adequacy of protection. No work shall be started at the site until appropriate certificates of insurance are filed and approved by the Procurement
Coordinator.
3.6 Responsibility for damage.
The Contractor shall repair and restore to its original condition any equipment, materials, or surfaces damaged or disturbed by his operations. The Contractor shall be entirely responsible for any loss or damage to his own materials, supplies, and equipment, and to the personal property of his employees while they are on State premises. The Contractor shall be solely responsible for any damage to the building or its contents and for any loss or damage to any property belonging to the owner or the owner’s employees when such loss or damage may be attributable to his actions or negligence or the actions of his employees.
SECTION 4 – ATTACHMENTS
ATTACHMENT B BID INSTRUCTIONS
B-1 Bid Instructions
To assist each Bidder in the preparation of its Bid and to comply with the requirements of this solicitation, Bid
Instructions have been prepared. Each Bidder shall submit its Bid in accordance with the instructions as specified herein. All bids should be submitted in the eMMA solicitation bid tab section.
The Bid is used to calculate the Bidder’s TOTAL BID PRICE. Follow these instructions carefully when completing your Bid Form:
A) All Unit and Extended Prices must be clearly entered in dollars and cents, e.g., $24.15.
B) All Unit Prices must be the actual price per unit the State will pay for the specific item or service identified in this IFB and may not be contingent on any other factor or condition in any manner.
C) Except as instructed on the Bid Form, nothing shall be entered on or attached to the Bid Form that alters or proposes conditions or contingencies on the prices. Alterations and/or conditions may render the Bid not responsive.
D) It is imperative that the prices included on the Bid Form have been entered correctly and calculated accurately by the Bidder and that the respective total prices agree with the entries on the Bid Form.
Any incorrect entries or inaccurate calculations by the Bidder will be treated as provided in
COMAR 21.05.02.12 and may cause the Bid to be rejected.
E) All Bid prices are to be fully loaded prices that include all costs/expenses associated with the provision of services as required by the IFB. The Bid price shall include, but is not limited to, all: labor, profit/overhead, general operating, administrative, and all other expenses and costs necessary to perform the work set forth in the solicitation. No other amounts will be paid to the Contractor. If labor rates are requested, those amounts shall be fully loaded rates; no overtime amounts will be paid.
F) Unless indicated elsewhere in the IFB, sample amounts used for calculations on the Bid Form are typically estimates for evaluation purposes only. Unless stated otherwise in the IFB, the Agency does not guarantee a minimum or maximum number of units or usage in the performance of the Contract.
G) Failure to adhere to any of these instructions may result in the Bid being determined not responsive.
H) Bid amounts will not be eligible for increases unless it is specified on the bid page that an annual change in rate is allowable.
Contract Line Item Number
(CLIN)
SERVICES/GOODS Est.
Quantity
Unit Unit Price Extended Price
Signature of Authorized Personnel Print Name of Business/Organization
Date
Print Name of Authorized Personnel
Title
***END OF SECTION B***
B) All Unit Prices must be the actual price per unit the State will pay for the specific item or service identified in this IFB and may not be contingent on any other factor or condition in any manner.
C) Except as instructed on the Bid Form, nothing shall be entered on or attached to the Bid Form that alters or proposes conditions or contingencies on the prices. Alterations and/or conditions may render the Bid not responsive.
MDH has a need for an experienced
Contractor to provide Commercial
Dishwasher Equipment and services as described in Section C.
Description of Services
001 New Commercial Dishwasher – CW Series
Upright Conveyor Type Dishwasher .
Champion Brand or MDH Approved Equal Power Source: Electric
1 EACH
002 Installation Services for Commercial
Dishwasher/Booster Equipment including mechanical and trade services
003 Equipment Removal: Disconnect and Seal
Existing non-operating plumbing, electrical and mechanical connections.
004 Permits and Drawings –Inspections, Drawings (soft/hard copy) and Permit Costs for New Equipment Installation.
005 Existing Equipment Disposal– Removal/Disposal of Existing Commercial Dishwasher and Water Booster Equipment.
006 Training Services including training aid materials. Up to three (3) sessions.
007 Extended Warranty – Labor/Parts Coverage. Includes diagnostic, testing, repair, re-calibration and transportation fees.
TOTAL CONTRACT AMOUNT
D) It is imperative that the prices included on the Bid Form have been entered correctly and calculated accurately by the Bidder and that the respective total prices agree with the entries on the Bid Form.
Any incorrect entries or inaccurate calculations by the Bidder will be treated as provided in
COMAR 21.05.02.12 and may cause the Bid to be rejected.
E) All Bid prices are to be fully loaded prices that include all costs/expenses associated with the provision of services as required by the IFB. The Bid price shall include, but is not limited to, all: labor, profit/overhead, general operating, administrative, and all other expenses and costs necessary to perform the work set forth in the solicitation. No other amounts will be paid to the Contractor. If labor rates are requested, those amounts shall be fully loaded rates; no overtime amounts will be paid.
F) Unless indicated elsewhere in the IFB, sample amounts used for calculations on the Bid Form are typically estimates for evaluation purposes only. Unless stated otherwise in the IFB, the Agency does not guarantee a minimum or maximum number of units or usage in the performance of the Contract.
G) Failure to adhere to any of these instructions may result in the Bid being determined not responsive.
H) Bid amounts will not be eligible for increases unless it is specified on the bid page that an annual change in rate is allowable.
ATTACHMENT C BID PROPOSAL AFFIDAVIT
Attachment C: Bid Proposal Affidavit http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/AttachmentC-Bid_Proposal-Affidavit.pdf.
ATTACHMENT H CONFLICT OF INTEREST AFFIDAVIT
Attachment H: Conflict of Interest Affidavit https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/05/AttachmentH-Conflict-of-InterestAffidavit.pdf
ATTACHMENT I NON DISCLOUSRE AGREEMENT
chrome-extension://efaidnbmnnnibpcajpcglclefindmkaj/https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-I-Non-DisclosureAgreementContractor.pdf
ATTACHMENT M CONTRACT
See attached.
ATTACHMENT N CONTRACT AFFIDAVIT
Attachment N: Contract Affidavit http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-N-ContractAffidavit.pdf
APPENDIX 3 VENDOR PERFORMANCE FEEDBACK FORM
Appendix 3 Vendor Performance Feedback Form (References) (Due with Bids)
This form will be a separate document attachment in the solicitation on eMMA. Please be sure to download, complete and return the form.
http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/AttachmentC-Bid_Proposal-Affidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/AttachmentC-Bid_Proposal-Affidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/05/AttachmentH-Conflict-of-InterestAffidavit.pdf https://procurement.maryland.gov/wp-content/uploads/sites/12/2018/05/AttachmentH-Conflict-of-InterestAffidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-N-ContractAffidavit.pdf http://procurement.maryland.gov/wp-content/uploads/sites/12/2018/04/Attachment-N-ContractAffidavit.pdf
File details come from the government source that posted it. Updated .