MCN_Weekly_Progress_Report_Template_-_Attachment__4.docx

DOCX document 28 KB Posted

Attached to
MCN Remediation Plan - Develop Databases and Training Services Federal contract opportunity
Solicitation number
SGE500-16-R-0010
Issued by
Department of State Office of Acquisition Management

About this file

MCN Weekly Progress Report and ActivitiesTemplates - Attachment 4

View the file

Other files for this federal contract opportunity

Other files attached to MCN Remediation Plan - Develop Databases and Training Services, newest first.
File Type Posted
Questions_and_Answers.pdf PDF
AMENDMENT_A001.pdf PDF
MCN_Statement_of_Work_-_Attachment__1.pdf PDF
SOLICITATION_SGE500-16-R-0010.pdf PDF
Public_Financial_Management_Risk_Assessment_of_the_MCN_-_Attachment__2.pdf PDF
MCN_Assessment_Remediation_Work_Plan_-_Attachment__3.pdf PDF
Cover_Letter_Solicitation_16R0010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Template INL Program Weekly Progress Report Date: Month Week, 2016

Requirement: Progress Report submitted every week Submitted to:

Submitted by: (Firm)

CONTRACT NUMBER: ________________

PERIOD OF PERFORMANCE OF WEEKLY PROGRESS REPORT:

· Week of ,2015 – Month, 2015 (i.e., Prior Week)

· Week of , 2015 – Month ,2015 (i.e., Current Week)

· Week of , 2015 – Month, 2015 (i.e., Following Week)

SUMMARY OF TASK STATUS

Task
Project Dates
Status

Task 1:

Task 2:

Task 3:

Task 4:

Task 5

ACTIVE TASKS

Task 1:

· Description of Work:

· Major Deliverables:

· Upcoming Milestone(s):

· Activities Completed in “Prior Week”

· Activities to be Completed During “Current Week”

· Activities Planned for “Following Week”

POTENTIAL RISKS

Description of Potential Risk
Impact on Work Performance
Perceived Severity
Recommended Solutions With Timelines
Status