Scope of Work (SOW) Summary
This is a Scope of Work document for the replacement of the front exterior entry door at the U.S. Coast Guard Sector Lake Michigan facility located at 2420 S Lincoln Memorial Drive, Milwaukee, WI 53207. The project number is PN: 31514998, with work anticipated to begin in January 2026. The contractor shall provide all supervision, labor, equipment, parts, and materials necessary to remove the existing exterior door assembly, prepare the opening, install a new commercial-grade exterior door and frame, and complete finishing work. The new door must be an exterior-grade single prehung door with full frame, sized and configured to match existing conditions, with factory-finished surfaces matching the existing color. Required specifications include an adjustable aluminum threshold, full perimeter weatherstripping for air and water tightness, insulated energy-efficient glazing, pre-drilled hardware preparation, and heavy-duty hinges with a reinforced lock area.
The contractor must complete work within 45 calendar days from acceptance of submittals, performing work during normal base hours of 7:00 a.m. to 3:00 p.m., Monday through Friday (with prior COR approval for extended hours). The contract timeline requires submission of all required submittals within 7 calendar days of award, with USCG review and response within 7 calendar days. The contractor must provide a firm delivery date within 21 calendar days of award and begin work within 14 calendar days of submittal approval, completing the project within 21 calendar days thereafter. A mandatory pre-award site visit must be arranged with the Contracting Officer's Representative (COR), Benjamin R. Syrstad (Benjamin.r.syrstad@uscg.mil or 731-446-6467). Required submittals include tradesman qualifications and certifications. The contractor is responsible for all waste disposal, environmental compliance including RCRA adherence for hazardous materials, site restoration, and compliance with all federal, state, and local safety regulations and building codes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW_Storefront_Sector Lake Michigan Updated.pdf | ||
| Wage Determination.txt | TXT text file | |
| 70Z03026QCLEV0060 - RFQ for Construction.docx | DOCX document | |
| Solicitation 70Z03026QCLEV0060 - SF 1442.pdf | ||
| Reference Information Sheet.pdf | ||
| Request for Information (RFI).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Homeland Security
United States Coast Guard
Scope of Work
For
Replacement of Sector Lake Michigan Front
Exterior Entry Door
PN: 31514998
AT THE
U.S. Coast Guard Sector Lake Michigan
2420 S Lincoln Memorial Drive, Milwaukee, WI. 53207
JAN 2026
1. General: United States Coast Guard (USCG) is Planning to enter negotiations with a
Contractor. The purpose of this project is to troubleshoot, identify, and correct any faults, blockages, damage or other issues with the exterior entry door. Prior to submitting a quote, it is mandatory to examine this SOW, and it highly recommended to visit the facility to take field evaluations and become familiar with the existing condition under which the work will be performed. After the award of the contract, a pre-conference will be held prior to starting the work at the Unit.
2. Background: Sector Lake Michigan currently has issues with the front entrance door.
Looking to having whole door group replaced.
3. SCOPE: The Contractor shall provide all supervision, labor, equipment, parts, and materials to remove all old equipment, electrical components and any other not required for the proper operation of the newly installed equipment. The contractor is responsible for the disposal of all waste generated from this project. All local codes shall be followed and proper plumbing procedures to complete this installation. All work shall be performed to restore proper functionality, security, weather resistance, and aesthetic appearance of the entryway.
3a. Scope of work detail:
• Demolition and Removal:
✓ Carefully remove and dispose of the existing exterior door, door frame, and related hardware.
✓ Protect surrounding finishes, walls, flooring, and adjacent structures during removal
• Preparation of Opening:
✓ Inspect the existing rough opening for damage or deterioration
✓ Repair or replace minor damaged framing as necessary to ensure proper installation
✓ Verify opening dimensions and ensure the opening is level, plumb, and square.
• Door and frame Installation:
✓ Furnish and install a new exterior-grade entry door and matching frame
✓ Install door frame securely into existing rough opening
✓ Ensure proper alignment, operation, and clearances
✓ Install weather stripping, thresholds, and seals to provide weather-tight performance
✓ Contractor shall provide a new commercial-grade exterior door meeting the following minimum requirements:
Type: Exterior entry door
Material: To match existing (verify on site prior to fabrication\installation)
Configuration: Single prehung door with full frame
Size: To match existing opening (verify on site prior to fabrication\installation)
Swing: To match existing (verify on site prior to fabrication\installation)
Finish: Factory-finished (To match existing color)
Frame: Exterior-grade prehung frame with weather-resistant components
Glazing: Insulated, energy-efficient glass insert
Threshold: adjustable aluminum threshold
Weatherstripping: Full perimeter weatherstripping for air and water tightness
Hardware Prep: Pre-drilled for handle set and deadbolt
Security: Reinforced lock area and heavy-duty hinges
• Insulation and Sealing:
✓ Insulate gaps between the door frame and rough opening with appropriate insulation material
✓ Apply sealant\caulking around the perimeter (as required) to prevent air and water infiltration
• Finishing work:
✓ Install interior and exterior trim as required
✓ Touch up or finish surfaces affected by installation to match existing conditions
• Standards and Compliance:
✓ All work shall comply with applicable local building codes and manufacturer installation requirements
✓ Materials and workmanship shall meet industry standards for exterior door installations
Site visit should be arranged with the Contracting Officer’s
Representative (COR) – Benjamin.r.syrstad@uscg.mil or 731-446-6467.
4. GOVERNMENT FACILITIES AND UTILITIES:
i. Electrical power is available on the site. The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded.
ii. Telephone services will not be available for use by the contractor.
iii. Building restroom facilities are available for use.
5. MATERIALS AND LOCATIONS: Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents. Storage shall be in accordance with manufacturers’ recommendations in a clean, dry, well-ventilated area. Store materials shall be protected from sunlight and kept away from excessive heat. The contractor shall not store any highly flammable materials in the work area. Sufficient area for staging is available on site; storage areas will be pre-approved by the Contracting Officers’ Representative
(COR).
The Contractor is required to comply with local VOC laws and regulations. All applicable Material Safety Data Sheets shall be available upon request.
6. SCHEDULE OF WORK: Completion of work shall be accomplished within 45 calendar days from acceptance of submittals. The Contractor shall perform all work during normal base work hours. The base normal working hours are 7:00 am to 3:00 pm, Monday through Friday, but the contractor is not limited to these hours. If the contractor is going to work outside normal working hours, prior permission must be obtained from the COR.
7. EXISTING CONDITIONS: The contractor is expected to satisfy himself as to the existing conditions and the work to be performed. The contractor shall verify all dimensions and equipment data prior to ordering materials and commencement of work.
8. LIABILITY OF CONTRACTOR: Any damage to government property caused by the contractor shall be repaired or replaced by the contractor at no cost to the government.
The contractor shall not disconnect any service without approval from the COR.
9. INSPECTION AND ACCEPTANCE: The COR will accomplish inspection and acceptance of work.
10. SAFETY: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. To accomplish this end, the Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with the requirements of all Federal, State and
Local safety laws, rules and regulations.
11. ENVIRONMENTAL COMPLIANCE: Any waste generated because of the project shall either be recycled IAW CIM 16455.10 or be disposed of IAW the Resource Conservation and Recovery Act (RCRA). Any Hazardous Waste shall be manifested off site with
Station listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored and disposed of IAW RCRA and all applicable federal, state (i.e.
DOT) and local laws and ordinances. All solid waste/trash shall be removed from site and not disposed of in onsite dumpsters. All installation related solid waste shall be removed from the site after each working day. All extra chemicals and products shall be removed from the site upon work completion. Laydown areas will be approved on a case-by-case basis by the Contracting Officers Representative. Any damage to vegetated areas shall be repaired and reseeded by the Contractor. Nothing shall be discharged to a storm drain at any time during the project. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable CG policies/plans/permits/laws/ordinances. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence. Draining of chemicals/fluids/petroleum shall not be allowed onsite.
12. SITE RESTORATION & CLEAN UP: The work site shall be cleaned up at the completion of each workday. The Contractor shall take special care to contain dust while working. Upon completion of the job, the Contractor shall clean up the job site, returning it to a state of cleanliness equal to or exceeding that in which it was found. The
Contractor shall properly dispose of all removed equipment, trash, extra materials, dirt, debris, or other litter that remain. There will be no final acceptance of the contract until the Contracting Officer’s Representative (COR) approves the appearance of the job site.
13. GOVERNMENT FACILITIES AND REGULATIONS: The Contractor, their employees, and any sub-contractors shall become familiar with and obey all Unit regulations. All personnel employed on the project shall keep within the limits of the work area and shall not enter any other area outside of the work site unless to do so in the performance of their duties. There shall be No Smoking in any Coast Guard Building. All smoking must be done in the designated smoking area.
14. CONTRACT TIMELINE: The Contractor shall provide all required information and complete this contract within this time schedule, unless approved by the Contracting
Officer.
i. Provide all required submittals to the Contracting Officer within 7 calendar days after the contract award.
ii. The U.S. Coast Guard will have 7 calendar days to review the submittals and respond to Contractor.
iii. The Contractor shall provide projected delivery schedule during proposal and provide a firm delivery date within 21 calendar days after the contract has been awarded.
iv. The Contractor, upon receiving notification that the U.S. Coast Guard has approved the submittals and having received the Contractors firm delivery date schedule, will have 14 Calendar days to begin work on the project and have the project completed within 21 calendar days. The Contractor shall notify the Contracting Officer of any long lead time delivery of equipment, so that the Contracting Officer can modify the delivery date of the contract.
15. SUBMITTALS: Once awarded, the following list of submittals required for approval defines the specific minimum requirements for this contract. The submittal shall contain sufficient information that can be used to determine compliance with the material within these specifications and referenced specifications.
❖ Tradesman Qualifications/Certification
Reference. Photos