Scope of Work Summary

This is a Scope of Work (SOW) document for the United States Coast Guard Sector Lake Michigan's storefront entry system replacement project (PN: 31514998), located at 2420 S Lincoln Memorial Drive, Milwaukee, WI 53207, with a target completion date of February 2026.

The contractor shall provide complete demolition and removal of the existing exterior storefront system, including all aluminum framing, glazing, doors, anchoring devices, thresholds, sealants, hardware, and electrical components, with full responsibility for debris disposal and site restoration. Installation requirements include a commercial-grade aluminum storefront system with minimum 0.125-inch extruded wall thickness and factory-applied black powder-coat finish, rated to withstand medium-to-high wind loads per ASCE 7 and local building codes with detailed engineering submittals required. Glazing shall be single-pane, laminated, impact-rated tempered glass with minimum 1/4-inch thickness. Commercial doors must feature full-length continuous hinges, surface-mounted hydraulic closers, full-perimeter weatherstripping with bottom sweeps, adjustable aluminum thresholds, and reinforced lock strike plates. The contractor must relocate and re-integrate existing electronic access control systems (intercom, key reader, electric strike, power supplies, and wiring) with comprehensive functional testing in the presence of a government representative prior to final acceptance. All exterior joints and seams shall be sealed with fire-rated spray foam and high-performance, commercial-grade weatherproof sealant in black finish to ensure a fully watertight, weather-resistant building envelope free of air infiltration and interior condensation.

Work must be completed within 45 calendar days from submittal approval, during normal hours of 7:00 am to 3:00 pm Monday through Friday, with prior COR approval required for extended hours. The contractor must submit all required documentation within 7 calendar days of award, including tradesman qualifications, reference photos, product data sheets, wind load rating documentation, and certificate of insurance, with the Coast Guard having 7 days to review and respond. The contractor assumes full liability for any property damage, assumes complete responsibility for electronic access control system functionality, and must maintain asset protection, daily site cleanup, and compliance with all local codes, environmental regulations (RCRA, VOC laws), safety requirements, and industry standards from AAMA, NFRC, and ASTM. Electrical power is available onsite; telephone services and restroom facilities are provided. Final acceptance is contingent upon structural integrity, watertight performance, full access system functionality, and site cleanliness approval by the Contracting Officer's Representative (Benjamin.r.syrstad@uscg.mil or 731-446-6467).

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Homeland Security

United States Coast Guard

Scope of Work

For

Replacement of Sector Lake Michigan

Storefront Entry System

PN:31514998

AT THE

U.S. Coast Guard Sector Lake Michigan

2420 S Lincoln Memorial Drive, Milwaukee, WI. 53207

Feb 2026

1. GENERAL

United States Coast Guard (USCG) is Planning to enter negotiations with a Contractor. The purpose of this project is to remove and replace the existing exterior storefront entry system.

Prior to submitting a quote, it is mandatory to examine this SOW, and it highly recommended to visit the facility to take field evaluations and become familiar with the existing condition under which the work will be performed. After the award of the contract, a pre-conference will be held prior to starting the work at the Unit.

2. BACKGROUND

Sector Lake Michigan currently has issues with the front entrance storefront system. The USCG intends to replace the entire storefront assembly including framing, glazing, and door systems.

3. SCOPE

The Contractor shall provide all supervision, labor, equipment, parts, materials, and disposal necessary to remove all old equipment and install the new storefront system. The Contractor is responsible for the disposal of all waste generated from this project. All local codes shall be followed and proper plumbing procedures to complete this installation. All work shall be performed to restore proper functionality, security, weather resistance, and aesthetic appearance of the entryway.

3a. Demolition and Removal

• Scope of Removal

✓ The Contractor shall execute the complete deconstruction, removal, and legal disposal of the entire existing exterior storefront system. This scope includes, but is not limited to, all aluminum framing, glazing, doors, anchoring devices, thresholds, sealants, hardware, and associated electrical components.

• Asset Protection

✓ The Contractor is responsible for implementing and maintaining robust protection for all surrounding finishes, walls, flooring, and adjacent structures to prevent damage during deconstruction activities.

• Site Maintenance & Debris Removal

✓ The Contractor shall furnish all necessary dumpster services for the containment of construction debris. The project site shall be cleared of all generated debris daily to maintain a clean and safe work environment.

• Remediation of Property Damage

✓ Any damage to Government property incurred because of the Contractor's operations shall be repaired or replaced to its original condition or better. All labor and material costs associated with such remediation will be the sole responsibility of the

Contractor.

3b. Substrate and Opening Preparation

• Site Inspection and Verification

✓ The Contractor shall conduct a thorough inspection of the existing rough openings to identify any pre-existing damage, deterioration, or defects in the substrate.

• Dimensional and Geometric Analysis

✓ The Contractor must field-verify all critical dimensions of the openings. It is the

Contractor's responsibility to confirm that the openings are level, plumb, and square to the tolerances required for the new system installation as specified in the manufacturer's installation documents.

• Substrate Remediation

✓ The base bid price shall be inclusive of all minor substrate repairs and corrections necessary to achieve a plumb, level, and true surface required for a watertight and structurally sound installation. Such preparatory work is considered an incidental obligation of the Contractor. No additional compensation will be authorized for routine substrate preparation that falls within the scope of industry-standard practice.

3c. Storefront and Door System - Technical Specifications & Installation

• Framing System

✓ Material: The system shall be a commercial-grade aluminum storefront with a minimum extruded wall thickness of 0.125 inches.

✓ Finish: All aluminum components shall receive a factory-applied, durable powder-coat finish in black.

• Performance and Structural Requirements

✓ Wind Load: The complete storefront and door system, as installed, must be structurally engineered and rated to withstand medium-to-high wind loads in accordance with all applicable local building codes and prevailing engineering standards (e.g., ASCE 7).Engineering Submittals: The Contractor shall submit for approval detailed engineering calculations for the proposed anchoring methods, demonstrating full compliance with the specified wind load requirements.

• Glazing Specifications

✓ Type: Glazing shall be single-pane, laminated, impact-rated tempered glass.

✓ Thickness: The minimum glass thickness shall be 1/4 inch.

• Commercial Door Assembly

✓ General: Doors shall be single-leaf, commercial-grade, full-flush aluminum door assemblies, fully compatible and integrated with the storefront framing system.

✓ Hardware Suite: Each door shall be outfitted with the following commercial-grade components:

✓ Hinge: Full-length continuous (piano) hinge.

✓ Closer: Surface-mounted hydraulic door closer.

✓ Seals: Full-perimeter weatherstripping and a bottom-of-door sweep.

✓ Threshold: Adjustable aluminum threshold.

✓ Locking: Reinforced lock strike plate integrated into the door frame.

• Installation and Weatherproofing

✓ Perimeter Seal: The contractor shall apply fire-rated spray foam insulation within the entire perimeter cavity between the storefront framing and the rough opening to create a continuous air and thermal barrier.

✓ Exterior Sealant: All exterior joints, seams, and junctures shall be sealed with a high-performance, commercial-grade, weatherproof sealant in a black finish, applied in accordance with the manufacturer's specifications.

• Final Performance Mandate

✓ Upon completion, the installed system must provide a fully watertight and weather-resistant building envelope. The assembly shall be free of air infiltration and shall not exhibit condensation on interior surfaces under normal operating conditions.

3d. Relocation and Re-Integration of Electronic Access Control Systems

• System Decommissioning and Removal

✓ The Contractor shall carefully decommission and remove all components of the existing electronic access control system. This includes, but is not limited to, the intercom unit, electronic key reader (e.g., card reader, keypad), electric strike, power supplies, and all associated wiring and conduit. Components shall be protected from damage during removal and stored securely for reinstallation.

• Reinstallation and Reconnection

✓ The Contractor shall professionally reinstall and reconnect the complete access control system onto the new door and frame assemblies. Installation shall be performed in a clean, workmanlike manner, ensuring all devices are securely mounted, and all wiring is properly concealed and terminated in accordance with low-voltage electrical best practices.

• Functional Verification and Acceptance

✓ Prior to final project acceptance, the Contractor must conduct a comprehensive operational test of the reinstalled system in the presence of a government representative. The Contractor shall demonstrate that all components, including the intercom, key access reader, and electric locking hardware—are fully functional and operate as intended.

• Assumption of Liability

✓ The Contractor assumes full and complete liability for any malfunction, damage, or failure of the electronic access control system that is a direct or indirect result of the removal and reinstallation process. The Contractor shall be responsible, at no cost to the Government, for all labor, materials, and diagnostic work required to restore the system to its original operational condition should such issues arise.

3e. Architectural Finishes and Site Restoration

• Installation of Trim

✓ The Contractor shall furnish and install all necessary interior and exterior architectural trim. The trim shall be installed to conceal all installation fasteners, shims, and gaps between the new storefront system and the adjacent construction, providing a clean, complete, and professionally finished appearance.

• Surface Restoration

✓ The Contractor shall be responsible for the complete restoration of any existing surfaces—including but not limited to paint, drywall, masonry, or flooring—that are altered, disturbed, or damaged during the course of the work. All repaired areas must be finished to seamlessly match adjacent, undisturbed surfaces in color, texture, and sheen, rendering the restoration work inconspicuous upon final inspection.

3f. Compliance and Quality Assurance

• Regulatory and Manufacturer Adherence

✓ All work performed under this Scope of Work, including the selection of materials, installation methodologies, and final system performance, shall strictly comply with:

✓ All applicable local, state, and federal building codes, ordinances, and regulations.

✓ The manufacturer's published installation instructions and specifications for all furnished products.

✓ Relevant industry standards for safety, performance, and environmental protection.

• Material and Workmanship Quality

✓ All materials supplied and workmanship rendered shall meet or exceed the highest industry standards for commercial exterior storefront and door installations. This includes, but is not limited to, standards set by organizations such as the American

Architectural Manufacturers Association (AAMA), the National Fenestration Rating

Council (NFRC), and the American Society for Testing and Materials (ASTM) where applicable.

4. GOVERNMENT FACILITIES AND UTILITIES

• Electrical power is available on the site. The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded.

• Telephone services will not be available for use by the contractor.

• Building restroom facilities are available for use.

5. MATERIALS AND LOCATIONS

• Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents.

• Storage shall be in accordance with manufacturers’ recommendations in a clean, dry, well-ventilated area.

• Store materials shall be protected from sunlight and kept away from excessive heat.

• The contractor shall not store any highly flammable materials in the work area.

• Sufficient area for staging is available on site; storage areas will be pre-approved by the

Contracting Officers’ Representative (COR).

• The Contractor is required to comply with local VOC laws and regulations.

• All applicable Material Safety Data Sheets shall be available upon request.

6. SCHEDULE OF WORK

• Completion of work shall be accomplished within 45 calendar days from acceptance of submittals.

• The Contractor shall perform all work during normal base work hours of 7:00 am to 3:00 pm, Monday through Friday.

• If the contractor is going to work outside normal working hours, prior permission must be obtained from the COR.

7. EXISTING CONDITIONS

• The contractor is expected to satisfy themselves as to the existing conditions and the work to be performed.

• The contractor shall verify all dimensions and equipment data prior to ordering materials and commencement of work.

8. LIABILITY OF CONTRACTOR

• Any damage to Government property caused by the contractor shall be repaired or replaced by the contractor at no cost to the Government.

• The contractor shall not disconnect any service without approval from the COR.

9. INSPECTION AND ACCEPTANCE

• The COR will accomplish inspection and acceptance of work.

• Final acceptance contingent upon structural integrity, watertight performance, full access system functionality, and site cleanliness.

10. SAFETY

The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. To accomplish this end, the Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with the requirements of all Federal, State and Local safety laws, rules and regulations.

11. ENVIRONMENTAL COMPLIANCE

Any waste generated because of the project shall either be recycled IAW CIM 16455.10 or be disposed of IAW the Resource Conservation and Recovery Act (RCRA). Any Hazardous Waste shall be manifested off site with Station listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored and disposed of IAW RCRA and all applicable federal, state (i.e. DOT) and local laws and ordinances. All solid waste/trash shall be removed from site and not disposed of in onsite dumpsters. All installation related solid waste shall be removed from the site after each working day. All extra chemicals and products shall be removed from the site upon work completion. Laydown areas will be approved on a case-by-case basis by the Contracting Officers Representative. Any damage to vegetated areas shall be repaired and reseeded by the Contractor. Nothing shall be discharged to a storm drain at any time during the project. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable CG policies/plans/permits/laws/ordinances.

All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence. Draining of chemicals/fluids/petroleum shall not be allowed onsite.

12. SITE RESTORATION & CLEAN UP

The work site shall be cleaned up at the completion of each workday. The Contractor shall take special care to contain dust while working. Upon completion of the job, the Contractor shall clean up the job site, returning it to a state of cleanliness equal to or exceeding that in which it was found. The Contractor shall properly dispose of all removed equipment, trash, extra materials, dirt, debris, or other litter that remain. There will be no final acceptance of the contract until the Contracting Officer’s Representative (COR) approves the appearance of the job site.

13. GOVERNMENT FACILITIES AND REGULATIONS:

The Contractor, their employees, and any sub-contractors shall become familiar with and obey all Unit regulations. All personnel employed on the project shall keep within the limits of the work area and shall not enter any other area outside of the work site unless to do so in the performance of their duties. There shall be No Smoking in any Coast Guard Building. All smoking must be done in the designated smoking area.

14. CONTRACT TIMELINE

• Provide all required submittals within 7 calendar days after contract award.

• The U.S. Coast Guard will have 7 calendar days to review submittals and respond.

• Contractor shall provide projected delivery schedule and firm delivery date within 21 calendar days after award.

• Contractor shall begin work within 14 calendar days of submittal approval and complete within 21 calendar days.

15. SUBMITTALS

Once awarded, the following list of submittals required for approval defines the specific minimum requirements for this contract. The submittal shall contain sufficient information that can be used to determine compliance with the material within these specifications and referenced specifications.

• Tradesman Qualifications/Certification.

• Reference Photos.

• Product data sheets for storefront systems, glazing, hardware, sealants, and anchoring calculations.

• Wind load rating documentation.

• Certificate of Insurance prior to mobilization.

16. POINT OF CONTACT

Site visit should be arranged with the Contracting Officer’s

Representative (COR) – Benjamin.r.syrstad@uscg.mil or 731-446-6467.

Reference. Photos

File details come from the government source that posted it. Updated .