SAMO – FC Doheny House Re-Roof

SOW

Part 1: General Information

A. Introduction

The purpose of this SOW is to perform the re-roofing at one of our housing locations. This housing unit is considered non-historic. NPS will require a quote to Reroof the building with an Option A of Red Clay Tile material and Option B for asphalt tile material.

B. Background

The Franklin Canyon Doheny House located at 1936 Lake Drive, Beverly Hills, CA 90210 is a wooden structure stucco 2050 sf housing unit built in 1920. This building’s slate roof shall be replaced with red clay tile or asphalt tile depending on price of material, availability and ultimately NPS decision on which material option to choose (option A or option B).

C. Scope

The overall project purpose is to replace the roof at said locations with Option A red clay tile or Option B asphalt tile.

1936 Lake Drive, Beverly Hills, CA 90210 was determined to have its roof replaced due to age and condition of existing roof (it is past its lifecycle).

• Remove and dispose of all existing roofing materials, and any rotten sheathing/decking.

• Repair or replace any rotten or damaged sheathing/decking with like material.

• Re-roof with red clay tiles or asphalt shingles depending upon NPS Option decision.

• Furnish and install 50# or recommended felt over the entire roof area including new drip edge flashing.

• Furnish and install new flashing for all roof penetrations, including curb flashings, chimney flashings, valley flashings, roof jacks and vents etc.

• Paint roof jacks and vents to match color of newly installed roofing material.

• Remove existing gutters and downspouts. Install new gutters and new downspouts.

• Remove and re-install any wireless rooftop internet or communication antennas.

D. Applicable Documents

None

Part 2: Work Requirements

A. Technical Requirements

The contractor must be licensed to provide roofing, electrical, carpentry, and painting services by the state of California. All work shall be completed in accordance with current

Federal and State Building Codes.

The contractor is responsible for taking their own measurements, dimensions, and quantity of materials required to complete the job.

The contractor will be responsible for removing and disposing of any debris generated during the workday. Contractor is to furnish trash/debris receptable and must be approved by the Contracting Officer’s Representative.

The contractor shall immediately notify the Contracting Officer of any ambiguities, inconsistencies, and errors discovered in this specification.

The contractor shall provide to the Contracting Officer a list of all Sub-Contractors, if any, prior to the commencement of work.

All work is subject to “Davis-Bacon” prevailing wage and will be performed Monday through

Friday, no earlier than 8:00 a.m.

Contractor shall take every precaution to prevent damage to government and personal property and vegetation at the sites. Should any damage result, the contractor shall complete repairs or replacement to the satisfaction of the COR, at no cost to the government.

Storage of materials and equipment shall be limited to areas designated by the COR during contractor’s operations. The contractor is responsible for daily clean-up.

The buildings will be occupied during the performance period of this contract. Provide and maintain adequate egress at all times, in accordance with the Life Safety Code (NEPA 101).

No corridor, aisle, stairway, door, or exist shall be obstructed or used in a manner that interferes with egress.

B. Deliverables

The contractor shall provide a written schedule within 5 days after award. The contractor shall complete work within 60 days of award.

Roofing warranty limited lifetime and a 5-year performance guarantee against a defective roofing system, including repairing to maintain a watertight condition. During the five-year period, the contractor shall repair all leaks without cost to the government.

Part 3: Supporting Information

A. Security

Contractor shall take all precautions to protect the public and all property during performance under this contract. The contractor will ensure buildings are always secure.

The contractor shall coordinate work schedules and locations with the Contracting Officer’s

Representative (COR) and shall erect barricades and appropriate signs while working to prevent harm to persons and property.

The contractor shall be responsible for maintaining an effective accident prevention program and providing a safe environment for all personnel and visitors. The contractor shall ensure that work is accomplished in compliance with Federal, State and local safety and health requirements. The contractor shall comply with all OSHA requirements.

The contractors will be provided with the North or South gate code for access to Franklin

Canyon while the site is closed to the public. Contractors are to secure code. Contractor is to use caution and obey all traffic laws while in Franklin Canyon.

B. Place of Performance

1936 Lake Drive

Beverly Hills, CA 90210

NOTE: Mulholland\Coldwater Canyon entrance gate is closed. Must use Beverly Drive to

Franklin Canyon entrance to access site.

C. Period of Performance

The period of performance for this contract will be 60 days after NTP.

All work shall be scheduled for weekdays (Monday-Friday) between 8:00 a.m. and 5:00 p.m.

D. Special Considerations

No NPS equipment will be provided.