SECTION F: DELIVERIES OR PERFORMANCE
DELIVERABLES
Annex/ Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.3.4
N/A Permits and Licenses
Before work commences and as requested by the KO.
KO 1 As specified
0200000/ 2.3.5
N/A Certificate of Insurance
Within 15 calendar days after award.
KO 1 As specified
0200000/ 2.6.7.1
N/A Quality Management Plan
Within 15 calendar days after award and within seven calendar days of changes.
KO 1 As specified
0200000/ 2.6.7.2
N/A QC Inspection File Within five calendar days of completion/ termination of the contract.
KO 1 As specified
0200000/ 2.6.7.3
N/A Contractor Quality Inspection and Surveillance Report
First work day of each month.
KO 1 Monthly
0200000/ 2.7.1
N/A List of Key Personnel and Qualifications
Within 15 calendar days after award.
KO 1 As specified
0200000/ 2.7.1
N/A Organizational Chart
Within 15 calendar days after award.
KO 1 As specified
0200000/ 2.7.2.6
N/A Proof of Legal Residency
Prior to be admitted to site of work.
KO 1 As specified
0200000/ 2.7.3
N/A Contractor Labor Hours (eCMRA) Report
No later than 31 October
KO 1 Annually for labor executed during the period of performance during each Government fiscal year
(FY)
0200000/
2.8.1 N/A Employee List Upon request. KO 1 As required
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.9.1
N/A Accident Prevention Plan
Within 15 calendar days after award and within seven calendar days of changes.
KO 1 As specified
0200000/ 2.9.2
N/A Activity Hazard Analysis
Together with the Accident
Prevention Plan and for changes.
KO 1 As specified
0200000/ 2.9.3
N/A Compliance Plans, Programs, and Procedures
Together with the Accident
Prevention Plan and for changes.
KO 1 As specified
0200000/ 2.9.5
J-0200000-05-
NAVFAC
Contractor Incident Reporting System
(CIRS)
Within five calendar days of accident.
KO 1 As required
0200000/ 2.9.5
J-0200000-05-
Weight Handling Equipment Accident Report
Within 15 working days of accident.
KO 1 As required
0200000/ 2.9.5
J-0200000-05-
Crane and Rigging Gear Near Miss Report
Within 15 working days of accident.
KO 1 As required
0200000/ 2.9.7
N/A Monthly On-Site Labor Report
First work day of each month.
KO 1 Monthly
0200000/ 2.9.8
N/A OSHA Citations and Violations Corrective Action Report
Within 48 hours after receiving a citation.
KO 1 As required
0200000/ 2.9.10
N/A Safety Certifications
Within 15 calendar days after award and as old certifications expire.
KO 1 As specified
0200000/ 2.10.1.1
N/A Water Conservation Plan
Within 15 calendar days after award and for changes.
KO 1 As specified
0200000/ 2.10.2.1
N/A Class I ODS Report
Within 24 hours following delivery of refrigerant to
DLA
KO 1 As required
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
0200000/ 2.10.2.5
J-0200000-05-
Emergency Planning and Community Right- To-Know Act (EPCRA) Report
Within 15 calendar days after contract award and not less than 10 working days prior to planned use of hazardous material.
KO 2 As specified
0200000/ 2.10.2.5
N/A Contractor Hazardous Material Inventory Log
Within 15 calendar days after the end of each calendar year and at termination of the contract.
KO 2 Annually
0200000/ 2.10.3
N/A Sustainable Procurement and Practices Plan
Within 15 calendar days after award and within 15 calendar days after exercised option periods.
KO 1 Annually
0200000/ 2.10.3
N/A Sustainable Delivery of Services Report
Within five calendar days after each contract period.
KO 1 Annually
0200000/ 2.10.3.2
N/A Recovered Material Certification
As specified KO 1 When a product containing recovered materials is equal to or better than the original and could be used.
1503020/2 .2.1
N/A Copy of State Certification for Contractor Personnel
15 calendar days prior to start of work. Copies of renewed certifications shall also be submitted.
KO 2 As required
1503020/2 .3.1
N/A Copy of Local/State Business License
Prior to contract award. Copies of renewed licenses shall also be submitted.
KO 2 1 per state
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
1503020/2 .3.2
N/A Permits 5 days prior to the start of work requiring permits.
KO 2 As required
1503020/2 .3.5
J-1503020-02 Planned Pesticide Use Sheets including Pesticide Labels and Safety Data Sheets (SDS)
With the proposal.
Note: Any proposed changes in pesticide usage shall be submitted for KO approval at least 5 business days in advance of pesticide use.
KO 2 1 for each pesticide per pest as required
1503020/3 J-1503020-05 Contractor's Work Plan
With the proposal.
KO 2 1 per proposal
1503020/3 N/A Report of Conditions Conducive to Pest Infestation
1 working day after citing conditions.
KO 2 As required
1503020/3 .1.1
N/A Mole Cricket Survey Report (per the appropriate Pest Group Sheet)
Within 1 day of the survey.
KO 2 As required
1503020/3 .3
J-1503020-08 Report of Pest Management Operations
Electronically within 1 day of each pest management operation.
KO 2 As required
1503020/3 .3
J-1503020-08 Report of Pest Management Operations
Electronically once per month by the 15th of the following month (Example: July data must be submitted by August 15).
KO 2 Monthly
1503050 / 2.3.7.1
N/A Water Conservation Plan
As specified KO 2 15 days after award/Annua lly 1503050 /
J-1503050-04 Recycling Report
Form As specified KO 3 With each invoice 1503050 /
N/A SDS sheets and catalog cut sheets or samples for fertilizer and mulch
As specified KO 2 As required
Spec Item
Form Attachment
Number Deliverable Title Date (s) of Submission
Distribution
Frequency Original
Copies (including original)
1503050 / 3.1
N/A Soil Analysis test results and proposed fertilizer
As specified KO 2 15 days after receipt of the test results by the Contractor
1503050 / 3.1.2, 3.2.3, 3.3.1
N/A Vegetation Control Schedule
As specified KO 2 15 days after award/Annua lly
1503050 / 3.1.4
N/A Debris Removal Schedule
As specified KO 2 15 days after award/Annua lly 1503050 /
3.1.14 N/A Artificial Turf
Maintenance As specified KO 2 15 days after award/Annua lly
1503060 / 3.1.1.3
N/A Deicing Material Container Plan
With proposal, revised and resubmitted within 15 days of any changes.
KO 2 As specified.
1503060 / 3.2.1.1, 3.2.2.1
N/A Snow Removal Plan
15 working days after award and 15 working days after the start of each option year
KO 4 Annually
File details come from the government source that posted it. Updated .