Summary of Section 4000 - As-Built and Record Drawing Requirements

This document establishes the as-built and record drawing requirements for the CDBG-DR Oakfield Palafox Stormwater Upgrades Phase III construction project administered by Escambia County Board of County Commissioners in Florida. The file specifies the procedures and standards that the successful bidder must follow for documenting project completion through comprehensive as-built and record drawings. These drawings must accurately reflect all construction work performed, modifications made during construction, and final conditions of the completed stormwater infrastructure improvements, roadway reconstruction, utility relocations, and sanitary sewer upgrades across the approximately 6,200 linear feet of improvements along the Palafox Street corridor and associated streets. The contractor must prepare these drawings in accordance with Escambia County Technical Specifications and ECUA's Engineering Manual standards, with submittal required prior to final project completion within the 365-day substantial completion deadline plus the additional 30-day final completion period. The as-built drawings serve as the official record of the constructed project and must be prepared to facilitate future maintenance, repairs, and modifications to the stormwater and utility systems installed.

The as-built and record drawing requirements ensure compliance with federal CDBG-DR program documentation standards and provide essential reference materials for Escambia County's management of the completed infrastructure assets. All drawings must be prepared by or under the direct supervision of a Florida-licensed professional engineer and submitted in formats acceptable to the County, typically including both paper copies and digital files compatible with the County's record management systems. The contractor bears full responsibility for the accuracy and completeness of these documents, and any deficiencies or omissions discovered during the County's review must be corrected at no additional cost to the project.

View the file

Other files

File Type Posted
CDBG-DR_Oakfield_Palafox_Stormwater_Upgrades_-_HS005_(Addendum_#3_Revision).pdf PDF
Section_4000_-_As-Built_and_Record_Drawing_Requirements.pdf PDF
Section_2651_-_Television_Inspection.pdf PDF
Section_2576_-_Wastewater_Forcemain_Systems.pdf PDF
Section_2570_-_Gravity_Sewer_Collection_Systems.pdf PDF
Section_2556_-_Water_Distribution_System.pdf PDF
Section_2310_-_Jack_and_Bore.pdf PDF
Section_2300_-_Horizontal_Directional_Drilling_(HDD).pdf PDF
Section_2221_-_Utility_Trench_Excavation.pdf PDF
TOC.pdf PDF
Oakfield_Palafox_Phase_III_-_Released_for_Bidding_Planset_-_07-27-2026.pdf PDF
CDBG-DR_Oakfield_Palafox_Stormwater_Upgrades_-_HS005_(Addendum_#1_Revision).pdf PDF
Heavy_Construction_Wage_Determination_5.18.26.pdf PDF
Oakfield_Palafox_-_Phase_3_-_Released_for_Bidding_-_Planset_07-10-2026.pdf PDF
10116-2023232_Oakfield-Palafox_Roadway_and_Drainage_Improvements_Project_-_NOVA_GEOTECHNICAL_ENGINEERING_REPORT_S&S.pdf PDF
HS005-A1_Executed_(6).pdf PDF
HS005_Escambia_County_Regional_Stormwater_Hurricane_Sally_Infrastructure_Repair_Agreement.pdf PDF
NWFWMD_1374115_Permit.pdf PDF
Specification_References.pdf PDF
Exhibit.FederalContractProvisions.HUD_with_signature_5.6.26.pdf PDF
Section-3-project-implementation-plan-template---forms-0-8.pdf PDF
Escambia_County_Section_3_Business_Application_CDBG-DR.pdf PDF
Escambia_County_Section_3_Contract_Clause_CDBG-DR.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Engineering Manual

2025 Edition Section 4000 – Record Drawings Page 1 of 6

Section 4000

As-Built and Record Drawing Requirements

PART 1: General

1.1 Applicability – These requirements apply to ECUA Capital Improvement Projects (CIP) and System Extension Projects (aka developer-sponsored projects) based on the following criteria:

1.1.1 All ECUA CIP projects and System Extension Projects that include a new ECUA lift station or an existing ECUA lift station receiving major upgrades.

1.1.2 All ECUA CIP projects and System Extension Projects that contain a combined 500’ or more of new ECUA mains shall follow this entire specification. For projects with less than 500’ of mains, the Survey Record Drawings portion of this specification becomes optional.

1.1.3 If there is a question regarding the applicability of these requirements to a certain project, then the ECUA Project Engineer assigned to that project shall make the determination as early as possible in the project.

1.1.4 For CIP projects, ECUA Project Engineer will require Engineer of Record to include a specific task/fee line item for Survey Record Drawings and a specific task/fee line item for Final Record Drawings, and will provide pay item for Contractor As-Builts in the project’s bid proposal form.

1.1.5 For System Extension Projects, these requirements are represented via paragraphs 7 and 8 of the Utility Service Agreement (USA).

1.2 Overview – The following chart represents an overview of the process required in order to develop Final Record Drawings for ECUA:

1.3 Terms Defined – The Record Drawing process requires various drawings to be developed by multiple parties along the way, with the following terms being defined and used as part of these requirements:

1.3.1 Surveyor of Record – The Florida registered PSM that performs the required surveying and then creates the Survey Record Drawings.

Contractor develops As-

Built Drawings per this

Specification

Surveyor of Record develops Survey Record

Drawings per this

Specification

Engineer of Record develops Final Record

Drawings per this

Specification and coordination with ECUA

Inspector

Engineer of

Record submits signed and sealed

Final Record

Drawings to ECUA

2025 Edition Section 4000 – Record Drawings Page 2 of 6

1.3.2 Engineer of Record (EOR) – The Florida registered PE that collects information from the Contractor As-Builts and Survey Record Drawings and creates the Final Record Drawings.

1.3.3 Contractor As-Builts – Drawings prepared by the Contractor and submitted to the EOR.

1.3.4 Survey Record Drawings – Drawings prepared by the Surveyor of Record and submitted to the EOR.

1.3.5 Final Record Drawings – Drawings prepared by the EOR and submitted to ECUA.

PART 2: Contractor’s As-Built Drawings Requirements

2.1 Prior to backfilling, the Contractor shall make and record measurements (recorded to nearest 1” or 0.1’) to all underground features (connections to mains, fittings, etc) that the Surveyor of Record will not have access to with his post-construction survey of surface features (i.e. manhole lids, valve boxes, etc). Contractor shall assemble all of the required information in a legible format on a clean set of plans. As-Builts that are illegible will be rejected by the EOR

2.2 The following underground features shall be measured with measurements being clearly annotated on plans:

Water System Sewer System

Service taps Service taps, stubouts (gravity and pressure)

FH taps ARV taps

WM fittings (tees, bends, elbows, etc) FM fittings (tees, bends, elbows, etc)

WM every 100’ if WM alignment meanders FM every 100’ if FM alignment meanders

2.3 Contractor shall take one measurement, referenced to valves, for features on straight sections of mains that are in-line with above-ground termination features such as valves. Contractor shall take two measurements, referenced to at least two above-ground features, for features on meandering sections of mains. Examples include:

2.4

124’

281’

196’

Upstream

MH

Downstream

MH

Notes:

1. Lateral stub-out locations to be measured at

ROW line

2. Measurements to lateral connections to mains shall be made from upstream MH

Gravity Sewer Water and Force Mains

Notes:

1. Service stub-out and/or meter locations to be surveyed by

Surveyor of

Record

2. Indicate valve used for main referencing measurements

185’

217’

268’

Ref.valve

124’

115’

83’

120’

190’

280’

2025 Edition Section 4000 – Record Drawings Page 3 of 6

2.5 Contractor shall provide detailed description of the feature (i.e. 6”x1” saddle tap for water service, 8” 45-degree bend for WM, 4” sewer lateral wye connection to main, etc).

2.6 Title sheet of As-Builts shall include:

2.6.1 Title “Contractor’s As-Builts”.

2.6.2 Name of the project, and ECUA CIP project number or System Extension number.

2.6.3 Contractor’s company name, address, and phone number.

2.6.4 Statement: “These As-Built Drawings have been prepared per the ECUA Engineering Manual.”, under which shall be signature and printed name of person that prepared drawings, along with phone number and e-mail address.

2.7 Provide as separate document all available photographs, clearly labeled, that show connections to existing mains, critical utility crossings, or other pertinent areas.

2.8 Contractor shall submit As-Built Drawings to the EOR, and shall be available to answer questions related to the drawings as well as supply additional information should there be missing/incorrect information. Insufficient As-Built Drawings as determined by either the EOR or ECUA will delay ECUA payments on CIP projects, and will delay Final Acceptance on System Extension Projects.

PART 3: Survey Record Drawings Requirements:

3.1 The Surveyor of Record is responsible for surveying property and easement boundaries as well as all at-grade and above-grade facilities per the following table:

Water System Sewer System

Valve boxes Manholes

Fire hydrants Lateral stub-outs

Water meters/boxes Valve boxes

Well and tank site fence and building corners, fence gates, SCADA tower, generator pad, driveway, power service pole, aerial power lines, etc

Lift station fence corners, fence gates, SCADA tower, control panel, hatches, concrete slab corners, water service/BFP, generator pad, driveway, influent piping, power service pole, aerial power lines, etc

All other at- or above- grade facilities All other at- or above- grade facilities

Parcels and easements

Property corners, edge of driveways, easement boundaries, encroachments, etc

3.2 Survey shall be prepared utilizing the Florida North Zone of the Florida State Plane Coordinate System, with horizontal measurements and coordinates accurate to within a tenth of a foot (0.1’).

All elevations (i.e. manhole rims, inverts of every gravity wastewater pipe and force main connections to manholes, lift station top of slab, bottom of wet well, influent pipe invert and control set points) will be based on the North American Vertical Datum of 1988 (NAVD88), and shall be accurate to within a hundredth of a foot (0.01’).

2025 Edition Section 4000 – Record Drawings Page 4 of 6

3.3 Show and dimension all rights-of-ways, ECUA parcels, and easements. Label easements based on type (i.e. public utility, ECUA, etc) and their origination (i.e. per plat named ______ located at book ___ and page ___ ).

3.4 Provide ample measurements from right-of-way lines, parcel boundaries, and easement boundaries to surveyed facilities such that it is clearly known if a facility is in its correct location or installed outside of ECUA’s property interests.

3.5 Surveyor of Record shall provide detailed description of the surveyed facility (i.e. valve box, 4” sewer lateral stub-out, etc.).

3.6 Title sheet of Survey Record Drawings shall include:

3.6.1 Title “Survey Record Drawings”.

3.6.2 Name of the project, and ECUA CIP project number or System Extension number.

3.6.3 Surveyor’s company name, address, and phone number.

3.6.4 Statement: “These Survey Record Drawings have been prepared per the ECUA Engineering Manual. I certify that the surveyed location information of the water and sewer facilities shown on these drawings conforms to the minimum technical standards for land surveying in the State of Florida and that said Record Drawings are true and correct to the best of my knowledge and belief.” under which shall be signature, date, and seal of Survey of Record, and printed name of Surveyor of Record, along with phone number and e-mail address.

3.7 Surveyor of Record shall submit Survey Record Drawings to the EOR, and shall be available to answer questions related to the drawings as well as supply additional information should there be missing/incorrect information. Insufficient Survey Record Drawings as determined by either the EOR or ECUA will delay ECUA payments on CIP projects, and will delay Final Acceptance on System Extension Projects.

PART 4: Final Record Drawings Requirements

4.1 The EOR shall assemble the information as provided by the Contractor’s As-Built Drawings and the Surveyor’s Record Survey Drawings, supplement with additional information provided by the EOR and the ECUA Project Inspector, and prepare a set of draft Final Record Drawings. The EOR shall retain the Contractor’s As-Built Drawings, the Survey Record Drawings, and a copy of the signed and sealed Final Record Drawings, all for future review by ECUA upon request. The EOR shall use the best available data between the information sources to form the Final Record Drawings.

4.2 Final Record Drawings shall be new drawings that show facilities as they are constructed, with drawings of new mains, appurtenances, labels and notes as needed. Design/construction plans with clouding, mark-outs, and strike-throughs that attempt to simply illustrate changes between design plans and record drawings will not be allowed. Any information, notes, or measurements from the design/construction plans that are no longer relevant from a Final Record Drawing perspective shall be deleted. Only installed facility information, notes, and measurements shall remain visible.

2025 Edition Section 4000 – Record Drawings Page 5 of 6

4.3 All water and sewer mains and services shall be labeled with the appropriate size, material, color, AWWA designation, pipe thickness, etc. Gravity mains shall be labeled with their diameter, pipe thickness, length, and slope. Each fitting shall be labeled with its material and size. Valves shall be labeled with their size and type. All service lines and sewer laterals shall be labeled with their diameter, material, etc.

4.4 Coordinates shall be provided for all surveyed facilities as well as measured locations of underground facilities from Contractor’s As-Builts.

4.5 Incorporate project photographs per paragraph 2.6.

4.6 Show all abandoned in-place facilities including the extent and method of abandonment (i.e.

capping ends of mains, grouting, etc).

4.7 Title sheet of Final Record Drawings shall include:

4.7.1 Title “Final Record Drawings”.

4.7.2 Name of the project, and ECUA CIP project number or System Extension number.

4.7.3 EOR’s company name, address, phone number, and Certificate of Authorization number.

4.7.4 Statement: “These Final Record Drawings have been prepared per the ECUA Engineering Manual. I certify these Final Record Drawings have been reviewed by me or by individual(s) under my direct supervision and to the best of my knowledge and belief these drawings substantially reflect the water and/or sewer facilities as constructed. Contractor’s As-Builts were provided by ________, dated ______; Survey Record Drawings were provided by __________, dated _______.” under which shall be signature, date, and seal of EOR, and printed name of EOR, along with phone number and e-mail address.

4.7.5 Contractor’s name and related information as listed on the Contractor’s As-Builts.

4.7.6 Surveyor of Record’s name and related information as listed on the Survey Record Drawings.

4.7.7 ECUA Project Inspector’s name and location for his signature granting approval of the Final Record Drawings.

4.7.8 ECUA Project Engineer’s name.

4.8 Upon development of a set of draft Record Drawings, the EOR shall:

4.8.1 Coordinate and hold mandatory meeting at EOR’s office with EOR and ECUA Project Inspector and together review the draft Record Drawings for completeness, accuracy, and conformance to this specification. Attendance by the Contractor or the Surveyor of Record is optional and at the discretion of the EOR.

4.8.2 Make corrections to all erroneous items as determined in meeting.

4.9 Final Record Drawings package shall include:

4.9.1 Two sets of Final Record Drawings (22" x 34" or 24" x 36" sheets), signed, dated, and sealed by the EOR

2025 Edition Section 4000 – Record Drawings Page 6 of 6

4.9.2 Thumb/Flash Drive labeled with project info, containing:

• ACAD version of the Final Record Drawings

• PDF version of the Final Record Drawings (full sheet size)

• PDF version of the Contractor’s As-Builts (full sheet size)

• PDF version of the Record Survey (full sheet size)

4.10 EOR shall submit Final Record Drawings package to ECUA Project Inspector per the following:

4.10.1 For CIP projects, Final Record Drawings package shall be submitted with or prior to Contractor’s Final Pay Application. Final Pay Application shall not be processed without proper project closeout paperwork, to include Final Record Drawings acceptable to ECUA.

4.10.2 For System Extension projects, Final Record Drawings shall be submitted at Project Closeout along with other required documents. Final Acceptance shall not be granted without proper project closeout paperwork, to include Final Record Drawings acceptable to ECUA.

4.11 ECUA Project Inspector will perform final review and if acceptable, sign the title sheet thereby approving the documents. Insufficient Final Record Drawings as determined by either the ECUA Project Inspector or ECUA Project Engineer will delay ECUA payments on CIP projects, and will delay Final Acceptance on System Extension Projects.

PART 5: Miscellaneous

5.1 On CIP projects, ECUA’s Standard General Conditions require Contractor’s draft As-Builts to be submitted with each monthly pay request. ECUA Project Engineer may waive this requirement based on project needs.

5.2 Occasionally, portions of partially completed projects may be required to be placed into service prior to project’s end. As part of the Certification of Completion of Construction for these portions, Contractor shall submit draft As-Builts with the request to ECUA to place any mains into service.