SECTION 32 16 13 – CONCRETE CURBS AND GUTTERS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections, apply to this section.

1.2 SUMMARY

A. Provide all labor, materials, and equipment as necessary to complete all work as indicated on the

Drawings and specified herein.

B. This section includes:

1. Curb and gutters.

C. Related sections include the following:

1. Division 01 Section 015000-TEMPORARTY FACILITIES AND CONTROLS

2. Division 31 Section 312300-EARTHWORK

3. Division 32 Section 321218-BITUMINOUS PAVEMENT

4. Division 32 Section 321313-CONCRETE PAVEMENT

1.3 QUALITY ASSURANCE

A. Provide the required testing and inspection as indicated in Division 01 Section “General Requirements

- Temporary Facilities and Controls.” Concrete sampling, testing, and inspection shall conform to the requirements found in Division 32 Section “Concrete Pavement.”

1.4 WARRANTY

A. Furnish and sign 2-year written warranty (last page of this section) which shall cover cracking, spalling, settling, finishing, and forming.

PART 2 - PRODUCTS

A. Reinforcement: Shall be No. 4 bar reinforcement of new billet stock of intermediate grade in accordance with ASTM A615.

PART 3 - EXECUTION

3.1 PLACING FORMS

A. Steel or wood forms of an approved section shall be used throughout the construction. On radii 3 feet or less, 1/4-inch plywood or masonite shall be used. All forms shall have a height equal to concrete thickness. Built-up, battered, bent, twisted, or broken forms shall be removed from the work. Expansion joint materials shall not be used.

B. Forms shall be so constructed and set as to resist, without springing or settlement, the pressure of the concrete. On curbs of sharp radius, plywood or other approved flexible material shall be used in sections short enough to form a smooth, uninterrupted curb which shall not vary form the true radius by more than 1/4-inch. Forms shall not deviate more than 1/8-inch in 10 feet from the true horizontal alignment and no more than 1/8-inch in vertical alignment.

C. Where forms are set above general surrounding area, earth shall be placed along outside edges of forms to ensure stability.

D. Forms shall be cleaned and oiled each time they are used.

E. Forms must be approved by the COR prior to placing concrete.

3.2 PLACING REINFORCEMENT

A. Place 2 bars in gutter pan as specified in Drawings and in the following areas:

1. Where curb crosses a recently filled trench and extending a minimum of 5 feet beyond trench wall.

2. Where fill soil of 18 inches or more occurs.

3. In all valley gutter pans. (Exception – 3 bars as shown on the detail drawing)

4. In all path ramps and extending a minimum of eighteen inches beyond the bottom of the curb taper or curb transition.

5. As directed by the COR.

3.3 JOINTING

A. Control (contraction) joints shall be perpendicular to the curb edge, 1-1/2-inch deep, open and free of all excess concrete. Control joints shall be placed at intervals of not more than 10 feet as indicated on the Drawings.

B. Expansion joints shall be placed at all points of curvature, tangency, and at intervals of not more than 100 lineal feet.

3.4 FINISHING

A. Concrete shall be struck off true to cross section, after which it shall be finished smooth and even.

Face forms, if used, shall be left in place until the concrete has set sufficiently so that they can be removed without injury to the curb. The remaining forms shall be rounded with an edging tool. No tool marks are to be left on exposed edges.

B. A straight edge check is to be made while concrete is still plastic. Irregularities exceeding 1/8-inch shall be corrected. Finish surfaces shall not vary from the required cross section as indicated on Drawings by more than 1/8-inch. They shall not vary from the true horizontal alignment by more than 1/4-inch in 10 lineal feet. Sections exceeding those limitations are subject to rejection and replacing at Contractor’s expense.

C. Adding water to the surface of the concrete to assist in finishing operations is not permitted. If a finishing aid is permitted by the COR, it shall only be an approved product for that intended purpose and then applied according to the product recommendations.

PART 1 - GENERAL
1.2 SUMMARY
1.3 QUALITY ASSURANCE
1.4 WARRANTY
PART 2 - PRODUCTS
PART 3 - EXECUTION
3.2 PLACING REINFORCEMENT
3.3 JOINTING
3.4 FINISHING