Section_2310_-_Jack_and_Bore.pdf
PDF 169 KB Posted
- Solicitation number
- PD 25-26.099
- Issued by
- Escambia County, Florida
About this file
This document is Section 2310 of the ECUA (Escambia County Utilities Authority) Engineering Manual 2025 Edition, providing technical specifications for jack and bore operations used to install potable water pipe, reclaimed water pipe, and sanitary sewer pipe in areas where trenching is not feasible or permitted. The specification establishes requirements for steel casing, carrier pipes, spacers, and end seals, with casing sizes ranging from 8 inches to 72 inches depending on carrier pipe diameter. For installations requiring casing sizes of 8 inches or larger, steel casing must meet ASTM A-139 Grade B standards with minimum yield strength of 35,000 psi and tensile strength of 60,000 psi, with specified minimum wall thicknesses varying from 0.188 inches to 0.625 inches based on casing diameter. Smaller casing sizes of 8 inches or less may utilize steel, PVC, or PE materials and allow alternate installation methods such as pneumatic mole, punching, or pushing methods, subject to approval by the applicable transportation authority.
Execution requirements mandate that boring operations be performed to alignment and grade per construction drawings, with equipment capable of controlling line and grade and preventing void formation. The contractor bears full responsibility for protecting underground utilities and producing a sound, tight installation true to line and grade, with lateral or vertical variation not exceeding 0.1 feet per 50 linear feet for gravity flow installations. Personnel requirements specify that equipment operators must have at least three years of experience within the last five years, and a boring supervisor with minimum experience of 5,000 linear feet of similar diameter and material pipe must remain on site throughout operations. ECUA inspector and engineer notification is required a minimum of 48 hours in advance of work commencement. Measurement and payment are calculated per linear foot of installed casing, including all labor, materials, equipment, grouting, and associated work, while carrier pipe payment is handled separately according to applicable ECUA sections for water distribution, reclaimed water, gravity sewer, or wastewater force main systems.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Engineering Manual
2025 Edition Section 2310 – Jack and Bore Page 1 of 5
Section 2310
Jack and Bore
PART 1: General
1.1 General Description of Work – This work shall consist of boring and jacking operations related to the installation of potable water pipe, reclaimed water pipe, and sanitary sewer pipe (gravity or force mains), in areas where trenching is not feasible or permitted, or as designated on the plans.
PART 2: Products
2.1 Pipe –
2.1.1 Requirements – Steel casing shall be used for all installations requiring casing sizes 8- inches or larger.
2.1.1.1 The steel casing shall be seamless or electric resistance-welded tubing for sizes up to 24-inch O.D. and standard double-submerged arc-weld for sizes over 24 inches.
2.1.1.2 Steel pipe shall be new, unused, ASTM A-139, Grade B, straight seam, minimum yield strength of 35,000 psi, and minimum tensile strength of 60,000 psi, with one beveled end (to 37 degrees) and other end square cut.
2.1.1.3 The table provided on the next page represents ECUA minimum requirements.
The Engineer of Record shall review project specific requirements such as soil and loading conditions along with requirements of the applicable transportation authority having jurisdiction over the subject real estate to determine whether the specific project warrants heavier walled casing than the minimum depicted herein.
If heavier walled casing is required, the steel casing diameter shall increase to the next nominal size.
2025 Edition Section 2310 – Jack and Bore Page 2 of 5
Casing Size Versus Carrier Size
Carrier Pipe I.D. Steel Casing Diameter Minimum Wall Thickness
2” 8” .188”
3” 10” .188”
4" 12” .188”
6" 14” .188”
8" 18” .250”
10" 20” .250”
12" 24” .250”
14" 30” .312”
16" 30” .312”
18" 30” .312”
20" 36” .312”
24" 42” .375”
30" 48” .500”
36" 54” .500”
42" 60” .500”
48" 72” .625”
2.2 Smaller Casing Sizes – For casing sizes eight inches and smaller, install in accordance with Section 3.2; steel, PVC, or PE material may be used. PVC and PE casings shall have the same color-coding requirements as the carrier pipe.
2.3 Spacers – Acceptable spacers shall be non-corroding, non-rotting and non-settling. Spacers shall be of type to slide easily in casing without causing damage to casing.
2.4 End Seals – Both ends of bore shall be sealed watertight. Acceptable end seals shall be made using rubber seal with stainless steel band retainers.
Approved Manufacturers – Casing Spacers and End Seals
Manufacturer Casing Spacers End Seals
RACI Spacers North America ✓
BWM Company ✓ ✓
CCI Piping Systems ✓ ✓
Cascade Waterworks ✓ ✓
Others as approved by ECUA in writing.
PART 3: Execution
3.1 Requirements –
3.1.1 Boring shall be performed to alignment and grade as shown on the construction drawings.
3.1.2 Equipment shall be of adequate size and capability to install the product and in conformance with the equipment Manufacturer’s recommendations for all power equipment used in the installation. Equipment shall have a means for controlling line and grade and a means for centering the cutting head inside the borehole. Equipment shall provide a means for preventing voids by assuring:
2025 Edition Section 2310 – Jack and Bore Page 3 of 5
3.1.2.1 In stable, cohesive conditions, the rear of the cutting head must be prevented from advancing in front of the leading edge of the casing by more than 1/3 times the casing diameter, not to exceed 8 inches.
3.1.2.2 In unstable conditions, such as granular soil, loose or flowable materials, the cutting head must be retracted into the casing a distance that permits a balance between pushing pressure, pipe advancement and soil conditions.
3.1.3 Every effort shall be made to prevent formation of voids. Upon completion of the boring operations, voids around the outside face of the casing shall be filled by grouting.
3.1.4 The Contractor shall be responsible for protecting any underground utilities and for any damage resulting to located utilities.
3.1.5 The Contractor shall be fully responsible for producing a sound, tight installation, true to line and grade. All pipe shall be installed through the casing using casing spacers per the applicable ECUA Standard Detail.
3.1.6 Only workmen experienced in boring operation shall perform the work.
3.1.7 Joint restraint for all carrier pipe shall be provided in accordance with Standard Detail D- 65.
3.1.8 If the grade of the pipe at the jacking end is below the ground surface, suitable pits or trenches shall be excavated for the purpose of conducting the jacking operations and for placing end joints of the pipe. Such work shall be sheeted securely and braced in accordance with OSHA Trench Safety requirements.
3.1.9 Heavy duty jacks suitable for pushing the casing through the soil shall be provided. In operating jacks, even pressure shall be applied to all jacks used so that pressure will be applied to the casing uniformly around the ring of the casing.
3.1.10 A suitable jacking frame or back stop shall be provided. The pipe to be jacked shall be set on guides properly braced together, to support the section of the casing and to direct it in the proper line and grade.
3.1.11 The whole jacking assembly shall be placed so as to line up with the direction and grade of the casing. In general, soil material shall be excavated just at the leading edge of the casing and material removed through the casing and the casing forced through the soil with jacks, into the space thus provided.
3.1.12 The casing, preferably, shall be jacked from the low or downstream end. Lateral or vertical variation in the final position of the casing from the line and grade established by the Engineer shall not exceed 0.1 feet per 50 linear feet of pipe for gravity flow installations, provided that such variation shall be regular and only in one direction and that the final grade or flow line shall be in the direction indicated.
3.1.13 If the Contractor desires, he may use a cutting edge of steel plate around the head end of the casing extending a short distance beyond the end of the casing with inside angles or lugs to keep the cutting edge from slipping onto the casing.
3.1.14 When jacking of casing is once begun, the operation shall be carried on without interruption, insofar as practical, to prevent the casing from becoming firmly set in the soil.
2025 Edition Section 2310 – Jack and Bore Page 4 of 5
3.1.15 Any casing damaged in jacking operations shall be removed and replaced at Contractor’s entire expense.
3.1.16 Immediately after jacking is complete and the carrier or encasement pipe is accurately positioned and approved for line and grade, the clearance space between the pipe and soil shall be completely filled by pressure grouting for the entire length of the installation.
3.1.17 The pits or trenches excavated to facilitate jacking operations shall be backfilled immediately after the jacking of the casing has been completed.
3.1.18 Spacers shall be installed at spacing recommended by spacer manufacturer or minimum spacing to ensure that carrier pipe does not contact casing. If spacing requirements do not coincide, the closer spacing shall prevail. Casing or carrier pipe damaged during carrier pipe installation shall be replaced at Contractor’s expense.
3.1.19 If utilized as end seal, grout shall be minimum 4 inches thick and supported by interior soil “donut” sufficient to provide watertight seal.
3.1.20 If rubber end seal is utilized, install rubber end seal with stainless steel band retainers per manufacturer’s recommendation to ensure watertight seal.
3.2 Smaller Casing Sizes – For casing or sleeve sizes eight inches or smaller, alternate casing installation methods are allowed subject to the approval of the applicable transportation authority having jurisdiction over the subject real estate. These methods may include pneumatic mole, punching, or pushing methods.
PART 4: Personnel Requirements
4.1 Jack and bore equipment operators shall be trained to operate the specific drilling equipment for
ECUA’s project with at least 3 years experience obtained within the last five years. All pipe of similar type and material shall be furnished by a single manufacturer.
4.2 Perform jack and bore operations under the constant direction of a boring supervisor who shall remain on site and be in responsible charge throughout the boring operation. The supervisor shall have supervised jack and bore operations of a minimum of 5,000 linear feet of pipe of a similar or greater diameter, of similar material, over similar lengths, and with similar subsurface conditions.
4.3 Provide a competent and experienced supervisor that is thoroughly familiar with the equipment and type of work to be performed, and in direct charge and control of the operation at all times. In all cases, the supervisor must be continually present at the job site during the actual crossing operation. Provide a sufficient number of competent workers on the job at all times to ensure the jack and bore installation is made in a timely and satisfactory manner.
4.4 The ECUA inspector and engineer must be notified a minimum of 48 hours (2 business days) in advance of starting the work. In addition, the jack and bore operation shall not begin until ECUA is present at the job site and agrees that proper preparations for the crossing have been made.
ECUA’s approval for beginning the work shall in no way relieve the Contractor of the ultimate responsibility for the satisfactory completion of the work.
2025 Edition Section 2310 – Jack and Bore Page 5 of 5
PART 5: Measurement and Payment
5.1 Measurement –
5.1.1 Measurement shall be per linear foot of installed casing, and shall include furnishing all labor, materials, equipment, and work involved in the boring operations.
5.1.2 The unit measurement shall also include skids, steel ties, grouting, and other items associated with the boring and casing.
5.2 Payment –
5.2.1 The accepted quantities for boring and jacking will be paid at the unit bid price per linear foot of installed casing.
5.2.2 Payment for carrier pipe will be paid in accordance with Section 2556 – “Water Distribution Systems,” Section 2566 – “Reclaimed Water Systems,” Section 2570 – “Gravity Sewer Collection Systems,” and Section 2576 – “Wastewater Force Main Systems”.
5.2.3 When not listed as a separate Contract pay item, boring, drilling and jacking conduit or jacking shall be considered as incidental work, and the cost there of shall be included in such Contract pay item(s) as provided in the Contract proposal.
5.2.4 Compensation, whether by Contract pay item or incidental work will be for furnishing all materials, labor, equipment, tools and incidentals required for the work, all in accordance with the plans and these specifications.