Section_2221_-_Utility_Trench_Excavation.pdf
PDF 122 KB Posted
- Solicitation number
- PD 25-26.099
- Issued by
- Escambia County, Florida
About this file
This is an Engineering Manual specification document issued by the Escambia County Utilities Authority (ECUA) addressing utility trench excavation, backfill, and compaction procedures for pipeline installation projects in Florida. Section 2221 of the 2025 Edition Engineering Manual establishes comprehensive requirements for excavation, shoring, dewatering, pipe bedding, trench backfill, compaction, grading, and cleanup work. The specification applies to trenches exceeding five feet in depth and mandates compliance with OSHA Excavation Safety Standards per 29 C.F.R. Part 1926, Subpart P, and Florida Statute 553.63. Contractors are required to conduct pre-bid site visits to become familiar with existing conditions along the planned work route and must accept the site in its existing condition during the contract timeframe. The contractor assumes full responsibility for managing groundwater and surface water encountered during construction. Trench width shall be maintained at the pipe outer diameter plus 24 inches where soil conditions permit, with a maximum of 300 linear feet of open trench allowed at any time, and no trenches permitted to remain open overnight.
The specification delineates detailed product requirements including angular pipe bedding material, sand or fine aggregate backfill subject to engineer approval, crushed rock cradling meeting specified sieve requirements, and controlled density fill formulated as K-Krete or equivalent with minimum 28-day compressive strength of 70 psi. Initial backfill must be placed by hand in approximately four-inch layers to a minimum of 12 inches above pipe top, with subsequent backfill compacted in layers not exceeding 12 inches depth for non-vehicular areas. The contractor must contact Sunshine811 a minimum of two days prior to excavation to locate existing underground utilities and is responsible for any damage to utilities caused by construction operations. All sheeting, shoring, and bracing materials must be OSHA-compliant and maintained throughout the excavation period. The specification permits contractor discretion in compaction methods subject to engineer approval and prohibits the use of explosives for rock excavation. Trench excavation is considered incidental to pipeline installation with payment made at contract unit price per cubic yard only if a separate bid item is established, with no allowance for waste material.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Engineering Manual
2025 Edition Section 2221 – Trench Excavation, Backfill and Compaction Page 1 of 6
Section 2221
Utility Trench Excavation
PART 1: General
1.1 General Description of Work –
1.1.1 Topics Covered – Excavation, shoring, dewatering, pipe bedding, trench backfill, compaction, grading, and cleanup of all pipeline trenching for the project.
1.1.2 Requirements – Pursuant to Florida Statute 553.63, any trench or similar excavation having a depth in excess of five (5) feet will be subject to the Excavation Safety Standards established by the Occupational Safety and Health Administration, 29.C.F.R., Part 1926 -
Safety and Health Regulations for Construction, Subpart P – Excavations.
1.1.3 Contractor Visitation – Prior to submittal of bid, the Contractor shall visit the site and become thoroughly familiar with site conditions existing along the route of the planned work. The Contractor shall accept site in condition existing during Contract time frame.
1.1.4 Groundwater/Surface Water – Management of groundwater/surface water encountered during construction are conditions of the Contract and responsibility of Contractor.
PART 2: Products
2.1 Source Materials – Determination of source of materials for bedding and backfill shall be responsibility of Contractor, but use of such materials shall be subject to approval of Engineer.
2.2 Pipe Bedding and Backfill – Pipe bedding shall be angular material.
2.3 Sand Backfill – (Where specified on plans). Use sand or fine aggregate with source of material subject to approval of Engineer.
2.4 Cradling Rock – Use crushed rock or stone with 70-100 percent passing 1-inch sieve and no more than 50 percent passing ¾-inch sieve.
2.5 Controlled Density Fill –
2.5.1 Mixture – Use high slump mixture of portland cement, fly ash and fine aggregate formulated, licensed and marketed as K-Krete or equal.
2.5.2 Strength – Provide mixture with minimum 28-day compressive strength of 70 psi with no measurable shrinkage or surface settlement.
2.6 Sheeting, Shoring, and Bracing – All excavation and trench safety measures shall be OSHA compliant. Use sound timber or structural steel. Use shapes and sizes as required.
2025 Edition Section 2221 – Trench Excavation, Backfill and Compaction Page 2 of 6
PART 3: Execution
3.1 General –
3.1.1 Dewatering – See Section 2100.3.5. – General Earthwork
3.1.2 Protection of Existing Utilities –
3.1.2.1 Contact the Sunshine811 Call Center a minimum of two (2) days prior to beginning excavation operations to have existing underground utilities located in areas of excavation work.
3.1.2.2 Locations and elevations of utilities shown on plans are to be considered approximate only. Notify utility and Engineer of conflicts between existing and proposed facilities.
3.1.2.3 Repair or replace existing utilities damaged, destroyed, or disrupted by
Contractor’s equipment or forces during construction work. Unless specified otherwise, replacement will be at the Contractor's expense.
3.1.3 Stability of Excavations –
3.1.3.1 Sheeting, Shoring, and Bracing –
3.1.3.1.1 Provide materials for shoring and bracing, such as sheet piling, uprights, stringers, and cross braces, in good serviceable condition. Maintain shoring and bracing in excavations regardless of time period excavations will be open.
Extend shoring and bracing as excavation progresses.
3.1.3.1.2 Provide permanent steel sheet piling or pressure treated CCA timber sheet piling wherever subsequent removal of sheet piling might permit lateral movement of soil under adjacent structures. Cut off tops a minimum of 2.5 feet below final grade and leave permanently in place.
3.1.3.1.3 The Contractor shall provide all shoring necessary to hold walls of excavation, prevent damage to adjacent structures, and to protect workmen and property.
3.1.3.2 When moveable trench shield is used below spring line of pipe, it shall be lifted prior to any forward movement to avoid pipe displacement.
3.1.4 Changes in Grade – Minor adjustments to grades may be made from plan grades to suit unforeseen construction conflicts or conditions with approval from Engineer. No additional compensation will be made for such minor changes.
3.2 Excavation and Trenching –
3.2.1 General –
3.2.1.1 Method of excavation at the Contractor's option.
2025 Edition Section 2221 – Trench Excavation, Backfill and Compaction Page 3 of 6
3.2.1.2 The Contractor will use caution when excavating under and around tree roots, structures, and utilities.
3.2.1.3 Stockpile and replace topsoil equal to pre-existing depth for surface restoration in grassed or agricultural areas where specified or shown on plans.
3.2.2 Trench Characteristics –
3.2.2.1 Depth – As indicated for pipe installation to lines and grades required with proper allowance for thickness of pipe and type of bedding specified or indicated.
3.2.2.2 Width – Keep width of trench as narrow as possible and yet provide adequate room for backfilling and jointing. Trench width shall be pipe O.D. plus 24 inches where soil conditions permit.
3.3 Organic or Unstable Materials –
3.3.1 General – The site shall be stripped of all organic and deleterious materials in phases, so as to prevent and impede erosion and sedimentation.
3.3.2 Guidelines – Stop work and notify Engineer. Perform remedial work as directed.
3.3.3 Unsuitable and Waste Material – If material is judged unsuitable or waste and removal is authorized, remove and dispose of in a legal manner. Replace with trench stabilizing material as directed by Engineer.
3.4 Rock Excavation –
3.4.1 Guidelines – Excavate any rock to maintain a minimum 6-inch clearance around pipe.
Dispose of rock material not suitable for backfill as directed by Engineer.
3.4.2 Explosives – The use of explosives is not permitted.
3.5 Bedding –
3.5.1 Place after bottom of trench has been excavated to proper depth and grade. Place, compact and shape bedding material to conform to barrel of pipe for 90 degrees (bottom
¼ of the circumference) to insure continuous firm bedding for full length of pipe.
3.5.2 At each pipe joint, dig bell holes to relieve pipe bell of loads and ensure continuous bearing of pipe barrel on bearing surface.
3.5.3 Trench bottom shall be free of large stones and other foreign material.
3.6 Trench Backfilling –
3.6.1 Guidelines –
3.6.1.1 Use excavated material backfill unless otherwise specified or directed.
2025 Edition Section 2221 – Trench Excavation, Backfill and Compaction Page 4 of 6
3.6.1.2 Use suitable backfill for all trenches beneath walks, parking areas, paved streets or existing exposed utilities.
3.6.1.3 Additional compaction or density testing may be required per the authority having jurisdiction.
3.6.2 Initial Backfill –
3.6.2.1 Place after pipe has been bedded and checked for alignment, grade, and internal obstructions.
3.6.2.2 Carry out in an orderly fashion after authorization to cover pipe has been given.
3.6.2.3 Allow no more than 300 feet of trench to be open at one time.
3.6.2.4 Do not backfill until concrete or mortar has sufficiently cured.
3.6.2.5 Record location of connections and appurtenances before backfilling.
3.6.2.6 Place by hand and hand tamp to not less than 12 inches above top of pipe, in approximately 4-inch layers.
3.6.2.7 Backfill simultaneously on both sides of pipe to prevent displacement.
3.6.2.8 Place cushion of 4 feet above pipe envelope before using heavy compacting equipment.
3.6.3 Subsequent Backfill –
3.6.3.1 Place backfill into trench at an angle so that impact on installed pipe is minimized.
3.6.3.2 Compaction of all backfill material shall be performed in a manner that shall not crack, crush, and/or cause the installed pipe to be moved from the established grade and/or alignment.
3.6.3.3 Areas not subject to vehicular traffic shall be backfilled and compacted in layers not more than 12 inches in depth.
3.6.3.4 Compaction method at discretion of the Contractor with following exceptions:
3.6.3.4.1 If in the Engineer's opinion compaction method presents potential damage to pipe, it will not be allowed.
3.6.3.4.2 Compaction of any backfill material by flooding or jetting will require prior written authorization of Engineer.
3.6.3.5 Mound excavated materials no greater than 6 inches in open areas only.
3.6.3.6 Fill upper portion of trench with topsoil as specified hereinbefore.
3.6.3.7 No trench shall be open overnight.
2025 Edition Section 2221 – Trench Excavation, Backfill and Compaction Page 5 of 6
3.6.4 Controlled Density Fill –
3.6.4.1 Use where shown on plans or approved by Engineer.
3.6.4.2 Provide suitable forms to limit volume of controlled density fill material.
3.6.4.3 Protect exposed utility lines during placement.
3.6.4.4 Place material in accordance with suppliers' written recommendations unless directed otherwise by Engineer.
3.6.4.5 Where the backfill material is deposited in water the layer and density requirements shall not apply until a one-foot layer of comparatively dry material is obtained, but this one-foot layer shall be thoroughly compacted by tamping.
3.6.4.6 If the Contractor has compaction equipment with which the required density can be obtained in thicker lifts than permitted above and upon satisfactory evidence that the proposed equipment will produce work equal in quality to that produced by the specified methods, ECUA may permit placement of granular material of soil groups
A-1, A-2, or A-3 in lifts up to a maximum of three foot compacted thickness. The
Contractor will be required to furnish equipment and labor to excavate and backfill test pits to be dug for the performance of density tests.
3.6.4.7 Use of thick lift compaction procedures will not be allowed for first stage backfilling
(beneath the haunches) of pipe culverts and storm sewers.
PART 4: Measurement and Payment
4.1 Trench Excavation –
4.1.1 Guidelines –
4.1.1.1 Trench excavation shall be considered incidental to pipeline installation.
4.1.1.2 Payment shall be made at the contract unit price per cubic yard only if a bid item is established in the Contract.
4.2 Backfill –
4.2.1 Guidelines –
4.2.1.1 Payment for backfill shall be made at the contract unit price per cubic yard only if a separate bid item is established in the Contract.
4.2.1.2 No allowance for waste shall be made.
4.2.1.3 If Engineer orders an initial backfill material other than that specified in the
Contract, it shall be paid for as an extra in price per cubic yard as compacted in
2025 Edition Section 2221 – Trench Excavation, Backfill and Compaction Page 6 of 6 place, EXCEPT if a higher-class embedment is ordered by Engineer because the
Contractor has over-excavated the trench width.
4.2.1.4 If the Contractor over-excavates the trench width and the Engineer orders the next higher class of embedment to be used, the embedment shall be paid for as if the original specified embedment was used.
4.2.1.5 If the Engineer orders the excavated material to be removed and disposed of and replaced with another material and a separate bid item is not established as a bid item, the material shall be paid as an extra.
4.2.1.6 If the Contractor fails to compact the backfill to the density requirements, the
Engineer may order the material removed and replaced at no cost to the Owner.
File details come from the government source that posted it. Updated .