Section_108msp_Prosecution_and_Progress_I_7B_.pdf
PDF 176 KB Posted
- Attached to
- I-7B Hodgeville at Blue Jay Rd - Construction
- Solicitation number
- PE-65100-NONST-2025-000000021
- Issued by
- Early County, Georgia
About this file
This is a Special Provision document issued by the Effingham Board of Commissioners in the State of Georgia for Project ID 25-ITB-074, dated September 25, 2024. The document outlines specific requirements related to Section 108 - Prosecution and Progress, focusing on lane closure requirements and associated penalties.
The document establishes liquidated damages of $500.00 per hour (or any part thereof) for failure to reopen lanes at times specified in Section 150.11. These damages are cumulative and in addition to any other liquidated damages that may be assessed for failure to complete the overall project. The provision retains Sub-Section 108.08 and adds these specific requirements regarding lane closures and associated penalties.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| I_07B_ES_PC_112124 (1).pdf | ||
| I_07B_CONSTRUCTION_PLAN_SET_112224.pdf | ||
| I_07B_ROW_090524.pdf | ||
| Section_150msp_Traffic_Control_I_7B_Hodgevill.pdf | ||
| Bid_Bond_Form (4).pdf | ||
| Bidder_s_Checklist (3).pdf | ||
| SAMPLE_CONSTRUCTION_CONTRACT (6).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Date Submitted: September 25, 2024
EFFINGHAM BOARD OF COMMISSIONERS
STATE OF GEORGIA
SPECIAL PROVISION
Project ID: 25-ITB-074
County: EFFINGHAM
SECTION 108—PROSECUTION AND PROGRESS
Retain Sub-Section 108.08 and add the following:
For this project the following items of work and corresponding intermediate times are required:
1. Lane Closures
Failure to reopen the lanes at the times specified in Section 150.11 will result in the assessment of
Liquidated Damages at a rate of $500.00 per hour or any part thereof.
The above rates are cumulative and in addition to any Liquidated Damages which may be assessed for failure to complete the overall project.