About this file
This document is a section on Measurement and Payment for a state and local contract opportunity in Chatham County and the City of Savannah, Georgia. The project involves the rehabilitation of up to ten (10) fairway bunkers and one (1) practice bunker at the Henderson Golf Club. The measurement and payment terms outline the methods for determining quantities and compensating the contractor for work such as removing existing sand and underdrain systems, cleaning and replacing outfall pipes, replacing inlets, installing underdrain pipe, and rehabilitating the bunkers with concrete and sand. Payment will be based on unit prices for the actual quantities of work performed in the field. The contract also includes provisions for sod installation. The overall contract opportunity is named "24-0040-2 Rehabilitation of Fairway Bunkers at Henderson Golf Course" and is located in Savannah, Georgia.
The document provides details on estimated quantities, which are approximate and not guaranteed. The contractor will not be paid for work exceeding 25% of the bid quantities without a change order. The contractor is required to provide assistance to the engineer to verify quantities and elevations as requested. Pricing for the various pay items is to be included in the contractor's bid proposal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01150-1
SECTION 01150
MEASUREMENT AND PAYMENT
1. SCOPE:
Under this heading shall be included the methods of measurement and payment for items of work under this Contract.
2. ESTIMATED QUANTITIES:
All estimated quantities for unit price items, stipulated in the Bid Proposal, or other
Contract Documents, are approximate and are to be used as a basis for estimating the probable cost of the work and for comparing the bids submitted for the Project. The actual amounts of work done and materials furnished under price items may differ from the estimated quantities. The basis of payment for work and materials will be the actual amount of work done and material furnished. The Contractor agrees to make no claim for damages, anticipated profits or otherwise on account of any difference between the amounts of work actually performed and materials actually furnished and the estimated amounts included in the Bid Proposal. The Contractor will not be paid for any work which exceeds 25 percent of the quantity set forth in the Bid Schedule without a change order issued before the work is performed unless specifically ordered in writing by the Engineer. The Contractor will provide assistance to the Engineer to check quantities and elevations when so requested.
3. REMOVAL OF EXISTING SAND AND UNDERDRAIN SYSTEMS IN BUNKERS:
Measurement of the removal of the existing sand and underdrain systems will be as determined by the actual area of each bunker to be restored as directed by the Owner.
Payment shall be at the unit price in the Bid Proposal and shall include all labor, materials and equipment required to remove all items.
4. CLEAN OUTFALL PIPE FROM BUNKER:
Measurement shall be on the basis of actual pipe cleaned in the field. Payment will be at the unit price in the bid proposal and will include all labor, materials and equipment required to clean the pipe.
5. REPLACE OUTFALL PIPE FROM BUNKER:
Measurement shall be on the basis of actual pipe replaced in the field. Payment will be at the unit price in the bid proposal and will include all grading, trenching, labor, materials and equipment required to replace the pipe.
6. REPLACE INLET:
Measurement shall be on the basis of actual inlets replaced in the field. Payment will be at the unit price in the bid proposal and will include removing existing inlet, installing new inlet, connecting pipes, grading, trenching, labor, materials and equipment required to replace the inlet.
01150-2
7. UNDERDRAIN PIPE:
Measurement of pipe will be on the basis of the number of linear feet of pipe of each size in place as measured in the field. Payment for furnishing and installing the pipe will be on the basis of the unit price for each size in the Bid Proposal and shall include the pipe, fittings, filter sock, stone backfill, filter fabric, and all work required for excavation and backfilling to properly installing the pipe.
8. BUNKER REHABILIATION:
Measurement will be on the basis of the actual area of bunker rehabilitated as determined in the field. Payment shall be at the unit price in the Bid Proposal and shall include all labor, materials and equipment required to install the concrete per manufacturer’s recommendation in a manner which provides positive drainage and to install the bunker sand above the concrete base.
9. SOD:
Measurement of sod shall be on the basis of the actual amount of sod furnished and installed in the field. Payment for furnishing and installing the sod shall be at the unit price in the
Bid Proposal.