Seattle Patient Lift Replacement_Floor Plans.pdf
PDF 16 MB Posted
- Attached to
- 6530--Seattle VAMC Patient Lift Replacement
- Solicitation number
- 36C26026Q0561
About this file
This document contains architectural drawings and electrical plans for a patient lift replacement project at a Seattle VA facility across multiple buildings and floors.
The project encompasses replacement of patient lifts and slings across Building 100 (1st, 2nd, 5th, and 6th floors) and Building 102 (Emergency Department). Building 100 includes 19 patient lifts in the Spinal Cord Injury unit and 30 lifts in the Community Living Center on the 1st floor; 25 lifts (including 10 radiology lifts and tentative Dual CT replacements) on the 2nd floor; 20 lifts on the 5th floor; and 18 lifts on the 6th floor. Building 102's Emergency Department requires 22 tentative lifts. The total scope requires 144 lifts and slings with approximately 135 removals. Design requirements specify that lifts must avoid existing ceiling items including Centrak and sprinkler heads, with particular attention to accommodating new Dual CT layout drawings. The existing D lift on the 2nd floor requires urgent replacement, though the order must also be designed to meet the new Dual CT layout specifications. Detailed electrical floor plans, ceiling plans, equipment layouts, and stretcher path planning are provided for each area, with color-coded diagrams indicating lift locations throughout patient rooms, nursing units, and isolation areas. The drawings indicate specific room numbers, square footage, and equipment specifications for targeted installation areas.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C26026Q0561_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Seattle Patient Lift Replacement Drawings
EXISTING DOOR TO REMAIN
NEW DOOR
NE
266-0
NE
304-0
145°
CT CONTROL
S2.234
147 SF
PATIENT
HOLDING BAY
S2.278
513 SF
CT SCANNER
S2.276
SE
114-0
1"
7'
AE402
276.1
6.
4.
A
19' - 8"
BREAK
2D-125
HAC
2D-127
CT EQUIP
2D-127B
CT SCANNER
2D-150
ULTRA SOUND
2D-162
OFFICE
2D-163
CHIEF'S OFFICE
2D-196S
PROGRAM
OFFICER
2D-196R
LINEN
2D-122
BREAK
2D-127B
EQUIP STORAGE
2D-126
LOCKERS
2D-124
CORRIDOR
C2-28
CORRIDOR
C2-36
CORRIDOR
C2-32
CORRIDOR
C2-29
CONTROL
2D-125B
TEMPORARY ICRA
BARRIER, SEE ICRA PLAN
CORRIDOR
C2-25
PASSAGE
C2-34
RAD FLUORO
2D-143
AE401
AE401
PATCH FLOORING TO
MATCH ADJ EXISTING,
RESILIENT TILE FLOORING
A P
P R
O X
3'
APPROX
7' - 0"
3 4
1. THE CONTRACTOR SHALL FIELD VERIFY ALL EXISTING
CONDITIONS BEFORE BEGINNING WORK. ANY CONFLICTS
BETWEEN EXISTING CONDITIONS AND THE CONTRACT
DOCUMENTS SHALL BE BROUGHT IMMEDIATELY TO THE
ATTENTION OF THE COR.
2. DIMENSIONS SHOWN ARE FROM GRID LINES TO FACE OF
STUD, CENTERLINE OF STRUCTURAL COLUMNS,
CENTERLINE OF OPENINGS, UON
3. ANY DOORS NOT DIMENSIONED SHALL BE INSTALLED 6"
FROM THE INTERSECTING WALL OR CENTERED ON THE
WALL, UON.
4. ENSURE THAT ALL REQUIRED BACKING IS INSTALLED IN
WALLS PRIOR TO INTALLING DRYWALL.
5. ALL EQUIPMENT TO BE REMOVED & REINSTALLED SHALL
BE REINSTALLED AT THE SAME HEIGHT & LOCATION AS
THE EXISTING (UON).
6. DURING PHASE I, INSTALL NEW FLOORING UP TO THE
NEAREST WHOLE UNIT. DURING PHASE II, COMPLETE
FLOORING INSTALLATION.
SHOWN AREA
PROJECT
NORTH
NE
304-0
SE
114-0
AE402 4
8'
127°
0.
234.2
A
280.1
447 SF
CT SCANNER
S2.280
513 SF
CT SCANNER
S2.276
159 SF
CT CONTROL
S2.234
PATIENT
HOLDING BAY
S2.278
BREAK
2D-125
HAC
2D-127
TEMPORARY ICRA
BARRIER, SEE ICRA PLAN
PHASE I FLOOR FINISH
BOUNDARY. AS PART OF
PHASE II, CONTINUE
FLOORING THROUGHOUT
REMAINDER OF ROOM
AE401
AE401
AE401
AE402
03 03 03
VA PUGET SOUND HEALTH CARE SYSTEM - 1660 S
COLUMBIAN WAY, SEATTLE WA 98108
5/20/2022 MK MC
PROJECT
NORTH
1/4" = 1'-0"1
FLOOR PLAN - PHASE I
1/4" = 1'-0"2
FLOOR PLAN - PHASE II
PROJECT
NORTH
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
PAINT WALL TO MATCH EXISTING ADJACENT. INSTALL
NEW, 3'-0" TALL, RIGID WALL COVERING ACROSS ENTIRE
LENGTH OF WALL (EXCEPT BEHIND CASEWORK &
COUNTER). REINSTALL WALL MOUNTED EQUIPMENT.
AUTOMATIC DOOR PUSH PLATE
REINSTALL WALL MOUNTED SINK.
REINSTALL WALL / BASE CASEWORK & COUNTERTOP.
INSTALL NEW LEAD SHIELDING PER SHIELDING REPORT,
INSTALL NEW GWB, 1/A-602.
L3
L3
L4L4
L4L4
L4L4L4L4
L4L4
L4L4
OS
OS
OS
L3
L3
L3
L3
L4L4
L4L4
L4L4L4L4
L4L4
L4L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
L4
OS
OS
OS
OSOS
OS
OS
NE
266-0
NE
304-0
SE
114-0
85 SF
CT CONTROL
S2.234
513 SF
CT SCANNER
S2.276
AFF
ACT 2x2
8' - 0"
AFF
ACT 2x2
8' - 0"
CEILING LIFT PER
MANUFACTURER DRAWINGS
147 SF
PATIENT
HOLDING BAY
S2.278
BREAK
2D-125
HAC
2D-127
CT EQUIP
2D-127B
CT SCANNER
2D-150
ULTRA SOUND
2D-162
OFFICE
2D-163
CHIEF'S OFFICE
2D-196S
PROGRAM
OFFICER
2D-196R
LINEN
2D-122
BREAK
2D-127B
EQUIP STORAGE
2D-126
LOCKERS
2D-124
CORRIDOR
C2-28
CORRIDOR
C2-36
CORRIDOR
C2-32
CORRIDOR
C2-29
SKY FACTORY ECOSLIM LED
LUMINOUS SKYCEILING
CONTROL
2D-125B
RAD FLUORO
2D-143
PASSAGE
C2-34
CORRIDOR
C2-25
TEMPORARY ICRA
BARRIER, SEE ICRA PLAN
PATCH CEILING TO NEAREST WHOLE
TILE. MATCH ADJ EXISTING, ACT 2x2
TEMPORARY ICRA
BARRIER, SEE ICRA PLAN
A P
P R
O X
3'
APPROX
7' - 0"
2x2 ACOUSTICAL CEILING TILE
SUPPLY GRILLE PER MECHANICAL
(SIZE & PROPORTION MAY VARY)
LIGHT FIXTURE PER ELECTRICAL
RETURN GRILLE PER MECHANICAL
(SIZE & PROPORTION MAY VARY)
EXHAUST GRILLE PER MECHANICAL
(SIZE & PROPORTION MAY VARY)
LIGHT FIXTURE PER ELECTRICAL
SHOWN AREA
PROJECT
NORTH
NE
304-0
SE
114-0
AFF
ACT 2x2
8' - 0"
AFF
ACT 2x2
8' - 0"
AFF
ACT 2x2
8' - 0"
447 SF
CT SCANNER
S2.280
156 SF
PATIENT
HOLDING BAY
S2.278
CT SCANNER
S2.276
159 SF
CT CONTROL
S2.234
CEILING LIFT PER
MANUFACTURER DRAWINGS
SKY FACTORY ECOSLIM LED
LUMINOUS SKYCEILING
BREAK
2D-125
HAC
2D-127
TEMPORARY ICRA
BARRIER, SEE ICRA PLAN
PHASE I CEILING FINISH
BOUNDARY. AS PART OF PHASE II,
CONTINUE CEILING THROUGHOUT
REMAINDER OF ROOM
VA PUGET SOUND HEALTH CARE SYSTEM - 1660 S
COLUMBIAN WAY, SEATTLE WA 98108
5/20/2022 MK MC
PROJECT
NORTH
1/4" = 1'-0"1
CEILING PLAN - PHASE I
1/4" = 1'-0"2
CEILING PLAN - PHASE II
PROJECT
NORTH
1. ALL EQUIPMENT TO BE REMOVED & REINSTALLED SHALL BE
REINSTALLED AT THE SAME HEIGHT & LOCATION AS THE
EXISTING (UON).
2. IN PHASE I, INSTALL CEILING TO THE NEAREST WHOLE TILE
UP TO THE ICRA BARRIER. IN PHASE II, INSTALL THE REST OF
THE CEILING.
LEGEND
GENERAL NOTES
KEY NOTES (THIS SHEET ONLY)
KEY PLAN
REINSTALL ANY, PREVIOUSLY STORED, CEILING MOUNTED
EQUIPMENT
REINSTALL WALL MOUNTED LIGHT FIXTURE, CENTERED ON
LENGTH OF WALL.
FRAME WALL TO 6" ABOVE CEILING PER ASSEMBLY
SCHEDULE & TYPES, EXCEPT DRY WALL UP TO FINISH
CEILING ONLY. SILICONE CAULK JOINT WHERE GYP MEETS
CEILING.
AE402 4
A5108 SHARPS DISPOSAL
E0948CART,
STORAGE
M3073 INFECTIOUS
WASTE BASKET
A5145 GARMENT HOOK
M3150 DISTRIBUTION
SYSTEM, MEDS
F2000 WASTEPAPER
BASKET
M8810 MAYO STAND
A5077
HAND
SANITIZER
DISPENSER
M3070LINEN HAMPER
X3145X-RAY SCREEN
M4116 VITAL SIGNS
MONITOR
HAC
2D-127
BREAK
2D-125
S Y
S T
E M
C
A B
IN
E
T
P A
R T
IA
L
U P
S
POWER
DISTRIBUTION
UNIT
MAIN DISCONNECT PANEL
PATIE
NT TABLE
G
ANTRY
CEILING
MOUNTED
INJECTOR
LCD MONITOR 1
447 SF
CT SCANNER
S2.280
M4255IV STAND
A1132 ACCESSORY
MOUNTING RAIL
F0340 STOOL
F0360 FOOTSTOOL
AE402
E0906MOBILE LINEN
CABINET
NE
304-0
A5077 HAND SANITIZER
DISPENSER
M3070 LINEN HAMPER
M4116 VITAL SIGNS
MONITOR
A5075 SOAP DISPENSER
X3145X-RAY SCREEN
M8810MAYO STAND
F2000 WASTEPAPER
BASKET
M3150 DISTRIBUTION
SYSTEM, MEDS
M3073 INFECTIOUS
WASTE BASKET
A5145 GARMENT HOOK
A5108 SHARPS DISPOSAL
E0948CART,
STORAGE
A5080 PAPER TOWEL
DISPENSER
513 SF
CT SCANNER
S2.276
SERVICE
CABINETSYSTEM
CABINET
P A
R T
IA
L
U P
S
POWER
DISTRIBUTION
UNIT
MAIN DISCONNECT PANEL
PATIENT TABLE
G A
N
TR
Y
CLG MOUNTED INJECTOR
LED MONITOR
A1012 PHONE, WALL
F0340 STOOL
M4255 IV STAND
A1132 ACCESSORY
MOUNTING RAIL
F0360FOOTSTOOL
F3200 CLOCK
A-502
A5107 GLOVE DISPENSER
A-502
A-502
E0906 MOBILE LINEN
CABINET
NE
304-0
SE
114-0
4' - 6"
F2700 BAR CODE READER
A1015 PHONE, DESK
M1840COPIER / FAX
F2000 WASTEPAPER
BASKET
F3065 WHITE & BULLETIN
BOARD COMBO
A1015 PHONE, DESK
A1015 PHONE, DESK
A5077 HAND SANITIZER
DISPENSER
A5077
HAND
SANITIZER
DISPENSER
TYP
F0340 STOOL
AE402
A-502
SE
114-0
A1012 PHONE, WALL
PATIENT
HOLDING BAY
S2.278
M4655 STRETCHER
M3105BLANKET
WARMING
SE
114-0
PATIENT
HOLDING BAY
S2.278
M4655 STRETCHER, TYP
VA PUGET SOUND HEALTH CARE SYSTEM - 1660 S
COLUMBIAN WAY, SEATTLE WA 98108
5/20/2022 MK MC
1/2" = 1'-0"1
ENLARGED EQUIPMENT PLAN - S2.280
1/2" = 1'-0"2
ENLARGED EQUIPMENT PLAN - S2.276
1/2" = 1'-0"5
ENLARGED EQUIPMENT PLAN - S2.234
PROJECT
NORTH
PROJECT
NORTH
1/2" = 1'-0"3
ENLARGED EQUIPMENT PLAN - S2.278
PROJECT
NORTH
1/2" = 1'-0"4
STRETCHER PATH OF TRAVEL - S2.278
PROJECT
NORTH
PROJECT
NORTH
KEY NOTES (THIS SHEET ONLY)
1 GE PROVIDED EQUIPMENT. REFERENCE MANUFACTURER
SPECIFIC DRAWINGS.
GE PROVIDED EQUIPMENT TO BE INSTALLED BY THE
CONTRACTOR. REFERENCE MANUFACTURER SPECIFIC
DRAWINGS.
PAR EXCELLENCE SMART STORAGE SYSTEM FURNISHED
BY VA, INSTALLED CONTRACTOR. COORDINATE FINAL
PRODUCT WITH COR.
IMAGING EQUIPMENT POWER DATA MONITOR FURNISHED
BY VA, INSTALLED CONTRACTOR. COORDINATE FINAL
PRODUCT WITH COR.
22 lifts total