Seal_Specs-Plans_Combined.pdf
PDF 2 MB Posted
- Solicitation number
- S-C01010-00018361
- Issued by
- Oregon
About this file
This is a Special Provisions and Plans document for the Cherryville-Welches Area Chip Seal Project issued by the Clackamas County Department of Transportation and Development in Oregon. The project consists of placing approximately 330,000 square yards of chip seal with county-furnished aggregate across multiple roads in the Cherryville and Welches areas, removing existing thermoplastic pavement markings, installing and maintaining temporary work zone traffic control measures, and performing incidental work as specified. The project is estimated at $1,455,000.00 and is not federally funded. The contract follows the 2024 Oregon Standard Specifications for Construction. Work must not begin before July 1, 2027, and must be completed by September 3, 2027. The contractor is required to hold a preconstruction conference with utilities representatives and submit a three-week look-ahead schedule weekly. Traffic lane closures are restricted to Monday through Friday, 7:00 a.m. to 6:00 p.m., with additional restrictions on Redland Road limiting work hours to 9:00 a.m. to 3:00 p.m. weekdays. The contractor must provide homeowner and business notifications at least three days before significant traffic impacts and must obtain approval of traffic control plans at least 14 days before any closure begins.
Payment will be made on a unit price basis for chip seal application (measured in square yards) and asphalt in chip seal (measured in tons), with a retainage rate of 5.0 percent held until final payment. Liquidated damages are calculated at 15.0 percent of the contractor's bid amount divided by total calendar days. Lane closure violations incur liquidated damages of $500 per 15-minute interval per lane, in addition to costs for required traffic control measures. The contractor must furnish either PMCRS-2H or CRS-3P polymer-modified emulsified asphalt and is responsible for all testing costs, equipment, labor, and incidentals. The county will stockpile chip aggregate at specified locations near Boring, Oregon, and will assist with signage and moisture control. The contractor must maintain current as-built drawings and deliver a complete set upon project completion as a condition of final payment. Insurance requirements include Commercial General Liability ($1,000,000 per occurrence/$2,000,000 aggregate), Commercial Automobile Liability ($1,000,000), and Pollution Liability ($1,000,000/$2,000,000), with the county and its officers listed as additional insureds. No asphalt cement cost adjustment or steel material price escalation clauses apply to this project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID 2026-83 Cherryville welches Chip Seal Project Bid Docs.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS FOR
CHERRYVILLE/WELCHES AREA
CHIP SEAL PROJECT
CLACKAMAS COUNTY DEPARTMENT OF TRANSPORTATION AND
DEVELOPMENT
CLACKAMAS COUNTY, OREGON
ASPHALT CONCRETE PAVING AND OILING (ACP – CHIP SEAL/FOG COAT) & TEMPORARY
TRAFFIC CONTROL (TTC)
CHERRYVILLE/WELCHES CHIP SEAL
Cherryville/Welches Area Chip Seal Project
Page intentionally blank
SPECIAL PROVISIONS
WORK TO BE DONE
CHERRYVILLE/WELCHES CHIP SEAL
PROJECT, CLACKAMAS COUNTY, OREGON
The Cherryville/welches area Project is a Chip Seal Project.
This contract will include, but not be limited to: placing approximately 330,000 square yards of Chip Seal with County furnished aggregate in the Cherryville/welches areas; removing existing thermoplastic pavement markings; installing, maintaining, and removing temporary work zone traffic control measures;
and performing additional incidental work as called for by the specifications and plans. The project estimate for this contract is $1,455,000.00
APPLICABLE SPECIFICATIONS
The Specification that is applicable to the Work on this Project is the 2024 edition of the "Oregon Standard Specifications for Construction" produced by the Oregon Department of Transportation and the Oregon Chapter of the APWA.
All number references in these Special Provisions shall be understood to refer to the Sections and subsections of the Standard Specifications and Supplemental Specifications bearing like numbers and to Sections and subsections contained in these Special Provisions in their entirety.
CLASS OF PROJECT
This is a Clackamas County Project and it is not federally funded.
CLASS OF WORK
Asphalt Concrete Paving & Oiling (ACP – Chip Seal/Fog Coat) Temporary
Traffic Control (TTC)
Section 00110 – Organization, Conventions, Abbreviations and Definitions
Comply with Section 00110 of the Standard Specifications modified as follows:
00110.05(d) References to Laws, Acts, Regulations, Rules, Ordinances, Statutes, Orders, and Permits
Add the following to the first bullet (Statutes and Rules):
• Clackamas County’s Local Contract Review Board (LCRB) Rules are accessible online on the
County’s website https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b-9bd8-c69ee7334685.
00110.05(e) Reference to Websites - Add the following bullet list to the end of this subsection:
• Bid Locker https://bidlocker.us/a/clackamascounty/BidLocker
• Clackamas How to Bid Vendor’s Guide https://www.clackamas.us/how-to-bid-on-county-projects
• OregonBuys https://oregonbuys.gov/bso/
• Oregon Temporary Traffic Control Handbook https://www.oregon.gov/odot/engineering/pages/ottch.aspx
• ODOT Construction Section - Qualified Products List (QPL) www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx
• Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD) https://mutcd.fhwa.dot.gov/
00110.10 Abbreviations
Add the following:
CCDA - Clackamas County Development Agency DTD - Clackamas County Department of Transportation and Development LCRB
- Local Contract Review Board ODFW - Oregon Department of Fish and Wildlife UNS - Utility Notification System WES - Water Environment Services of Clackamas County
00110.20 Definitions-Add the following to this subsection:
Agreement Form – The written agreement between the Owner and Contractor covering the work to be performed under the contract.
https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b-9bd8-c69ee7334685 https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b-9bd8-c69ee7334685 https://dochub.clackamas.us/documents/drupal/ef976bc9-14f4-495b-9bd8-c69ee7334685 https://bidlocker.us/a/clackamascounty/BidLocker https://www.clackamas.us/how-to-bid-on-county-projects https://oregonbuys.gov/bso/ https://www.oregon.gov/odot/engineering/pages/ottch.aspx http://www.oregon.gov/ODOT/Construction/Pages/Qualified-Products.aspx https://mutcd.fhwa.dot.gov/
Amendment – A contract modification for Additional Work, Changed Work, Extra Work, Field Directives, or other changes. An Amendment changes the contract value, scope, and/or time.
Amendments require formal approval by the Board of County Commissioners, pursuant to LCRB Rule Division C-049-160, prior to approval of such work.
Approved Equal - Materials or services proposed by the contractor and approved by the County as equal substitutes for those materials or services specified.
Award – Same as “Notice to Intent to Award”.
BCC – The Clackamas County Board of County Commissioners
Bid - A written offer by a bidder on forms furnished by the County to do work stated in the bid documents at the prices quoted. "Bid" is synonymous with "proposal" in these bid documents.
Bid Closing - The date and time for Bid Closing is the same as the date and time for Bid Opening.
Bid Documents- The following documents together comprise the Bid Documents:
• Invitation to Bid, Instructions to Bidders, Bid Form, Bid Proposal, Schedule of Prices, Bid
• Bond, Performance Bond
• Certificate of Insurance, Prevailing Wage Rates
• The "Oregon Standard Specifications for Construction" by ODOT and APWA, 2021 edition.
• Plans and drawings
• Other bid documents included or referenced in the bid documents
• Addenda, if any
• The Agreement Form and Special Provisions
Bonds -The bond or surety bond is a written document given by the surety and principal to the obligee to guarantee a specific obligation.
Change Order - A price agreement for Extra Work, Changed Work, field directives or other changes. A Change Order does not change the contract value, scope, or time until it is incorporated into an Amendment. Change Orders will be agreed upon, in writing, by the County Project Manager and the Contractor’s designated representative.
Contract - The written contract agreement, including amendments, signed by the Contractor and Clackamas County, which describes the work to be done, the contract amount, and defines the relationships and obligations of the Contractor and the County.
Contract Documents - The Invitation to Bid, the Instructions to Bidders, the accepted Bid Proposal and Schedule of Prices, the Subcontractor List, the Bid Bond, the Performance and Payment Bond, the Certificate of Insurance, the Prevailing Wage Rates, the Standard Specifications and Special Provisions, Amendments, the Plans and Drawings, the Agreement, as well as all documents incorporated by reference therein, and any and all addenda prepared by or at the direction of and adopted by the County and further identified by the signature of the parties and all modifications thereof incorporated in the documents before their execution.
County - The term "County" shall mean Clackamas County, including the Board of County Commissioners, employees and agents of the County authorized to administer the conditions of these contract documents.
Department – A subdivision of the Agency.
Engineer - The County's Project Manager either acting directly or through an authorized representative(s). When referring to approval of extra work or other Contract modifications, “Engineer” also refers to the County’s legal authority according to the LCRB rules.
Invitation to Bid - The public announcement (Notice to Contractors) inviting bids for work to be performed or materials to be furnished.
Legal Holiday - As defined in ORS 279C.540.
Lump Sum - A method of payment providing for one all-inclusive cost for the work or for a particular portion of the work.
Notice of Intent to Award - A written notice from the County notifying bidders that the County intends to award to the responsible bidder submitting lowest responsive bid.
ODOT Procurement Office – Clackamas County Procurement Division.
Owner – Synonymous with Agency.
Plan Holder’s List – A list of contractor’s names, contact names, phone and fax numbers that the County’s Purchasing Department creates during bidding of the Project.
Project Manager – The Owner’s representative who directly supervises the engineering and administration of the contract.
Shop Drawings – Synonymous with Working Drawings.
Solicitation Document – Synonymous with Bid Documents.
Standard Drawings – The Agency-prepared detailed drawings for Work or methods of construction that normally do not change from project to project. The Standard Drawings include the ODOT Standard Drawings.
Standard Specifications - "Oregon Standard Specifications for Construction", current edition, published by the Oregon Department of Transportation and as amended by the Agency.
State - Where the term “State” or “State of Oregon” or “ODOT” appears in the contract documents it shall mean “Clackamas County”, “State of Oregon”, or “ODOT” as applicable because of context.
Work Day - Any and every calendar day from January 1 to December 31 of every year, excluding Saturdays, Sundays and Legal Holidays.
END OF SECTION
Section 00120 – Bidding Requirements and Procedures
Comply with Section 00120 of the Standard Specifications supplemented and/or modified as follows:
00120.00 Prequalification of Bidders - Delete and replace with the following: See
Instructions to Bidders.
00120.01 General Bidding Requirements – Delete and replace with the following: See
Instructions to Bidders.
00120.05 Request for Plans, Special Provisions, and Bid Booklets: – Delete and replace with the following:
See Notice of Public Improvement Contract and Instructions to Bidders.
Copies of the 2024 Oregon Standard Specifications for Construction and Supplements might be found on the Oregon Department of Transportation website at:
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
00120.15 Examination of Work Site and Solicitation Documents; Consideration of Conditions to be Encountered – Delete the third paragraph.
00120.17 Use of Agency-Owned Land for Staging or Storage Areas – Add the following:
If no County-owned adjacent property is available for the Contractor, no changes here are necessary. If there is County-owned adjacent property but it won’t be available, a specific restriction should be mentioned in 00120.17 (b) and (c).
http://www.oregon.gov/ODOT/Business/Pages/Standard_Specifications.aspx
00120.30 Changes to Plans, Specifications, or Quantities before Opening of Bids - Delete and replace with the following:
See Instructions to Bidders.
00120.40 Preparation of Bids – Delete and replace this section with the following: See Instructions to Bidders.
00120.45 Submittal of Bids - Delete and replace with:
See Instructions to Bidders.
00120.50 Submitting Bids for More than One Contract – Delete this subsection.
00120.60 Revision or Withdrawal of Bids - Delete and replace with the following: See Instructions to Bidders.
00120.70 Rejection of Nonresponsive Bids – Delete and replace with the following: See
00120.95 Opportunity for Cooperative Arrangement – Delete this section.
Section 00130 – Award and Execution of Contract
Comply with Section 00130 of the Standard Specifications supplemented and/or modified as follows:
00130.00 Consideration of Bids - Delete third paragraph.
00130.10 Award of Contract - Delete and replace with the following: See
Instructions to Bidders.
00130.15 Right to Protest Award – Delete and replace with the following: See
Instructions to Bidders.
00130.30 Contract Booklet – Add the following:
Other documents are part of the contract documents by reference. These include, but are not limited to:
• The "Oregon Standard Specifications for Construction", 2021 Edition, as published by the
Oregon Department of Transportation (ODOT).
• “Oregon Standard Drawings” latest edition, as published by ODOT.
• Clackamas County Service District No. 1 "Surface Water Standard Specifications", latest edition.
00130.40 Contract Submittals - Delete and replace with the following: See
Instructions to Bidders.
00130.70 Release of Bid Guaranties – Delete and replace with the following: See
Section 00140 – Scope of Work
Comply with Section 00140 of the Standard Specifications supplemented and/or modified as follows:
00140.30 Agency-Required Changes in the Work – Replace the last paragraph with the following:
Upon receipt of an Engineer’s written order modifying the Work, the Contractor shall perform the Work as modified via Change Order, which may be subject to approval as an Amendment.
If an Amendment incorporating changes to the Work increases the Contract amount, the Contractor shall notify its Surety of the increase and shall provide the Agency with a copy of any resulting modification to bond documents. The Contractor’s performance of Work pursuant to Amendments shall neither invalidate the Contract nor release the Surety. Payment for changes in the Work shall be made in accordance with
00195.20. Contract Time adjustments shall be made in accordance with 00180.80.
00140.31 "As-Built" Records - Add the following section:
Maintain a current and accurate record of the work completed during the course of this contract. This may be in the form of "as-built" drawings kept by accurately marking a designated set of the contract plans with the specified information as the Work proceeds. Accurate, complete and current "as-built" drawings are a specified requirement for full partial payment of the work completed. At project completion and as a condition of final payment, the Contractor shall deliver to the Project Manager a complete and legible set of "as-built" drawings.
The "as-built" drawings must show the information listed below. Where the term "locate" or "location" is used, it shall mean record of position with respect to both the construction vertical datum and either construction horizontal datum or a nearby permanent improvement.
1) Record location of underground services and utilities as installed.
2) Record location of existing underground utilities and services that are to remain and that are encountered during the course of the work.
3) Record changes in dimension, location, grade or detail to that shown on the plans.
4) Record changes made by change order.
5) Record details not in the original plans.
6) Provide fully completed shop drawings reflecting all revisions.
Section 00150 – Control of Work
Comply with Section 00150 of the Standard Specifications modified as follows:
00150.00 Authority of the Engineer – Delete and replace the first sentence with the following:
Except as indicated elsewhere in the Contract (e.g., Amendment approval by the BCC), the Engineer has full authority over the Work and its suspension.
00150.05 Cooperative Arrangements – Delete this section.
00150.10 Coordination of Contract Documents
(a) Order of Precedence – Delete this section and replace with the following:
The Engineer will resolve any discrepancies between these documents in the following order of precedence:
• Approved Amendments;
• Approved Change Orders
• Bid Schedule with Schedule of Prices;
• Permits from governmental agencies
• Special Provisions;
• Agency-prepared drawings specifically applicable to the Project and bearing the Project title;
• Reviewed and accepted, stamped Working Drawings;
• Agreement Form;
• Standard Drawings;
• Approved Unstamped Working Drawings;
• Standard Specifications;
• All other Contract Documents not listed above.
Notes on a drawing shall take precedence over drawing details.
Dimensions shown on the drawings, or that can be computed, shall take precedence over scaled dimensions.
00150.50 Cooperation with Utilities: Add the following to the end of Paragraph (a):
There may be other utility servers who are not specifically listed in these Special Provisions or on the Plans that may be adjusting or inspecting their facilities within the project limits.
00150.50(c) Contractor Responsibilities – Add the following to the bulleted list:
• Follow applicable rules adopted by the Oregon Utility Notification Center;
• Contact Utility owners during Bid preparation and after Contract is awarded to verify all Utilities involvement on the Project Site;
• Hold a utility scheduling meeting and monthly utility coordination meetings (see also
00180.42);
• Maintain and re-establish utility location marks according to OAR 952-001-0090(3)(a).
Coordinate re-establishment of the location marks with the associated Utility;
• Determine the exact location before excavating within the tolerance zone according to OAR 952-
001-0090(3)(c);
• Backfill any exposed utilities as recommended and approved by the Utility representative.
Obtain utility locate warning tape from the Utility and replace damaged or removed warning tape.
Utility locate warning tape may not be present at all existing utilities;
• Stake, place warning tape, and maintain no work limits around critical Utility facilities as shown or directed by the Engineer and the Utility; and
• In addition to the notification required in OAR 952-001-0090(6), notify the Engineer and the Utility as soon as the Contractor discovers any previously unknown Utility conflicts or issues. Contrary to the OAR, stop excavating until directed by the Engineer and allow the Utility a minimum of two weeks to relocate or resolve the previously unknown utility issues.
Subject to the Engineer's approval, the Contractor may adjust the Utilities by asking the Utility owners to move, remove, or alter their facilities in ways other than as shown on the Plans or in the Special Provisions.
The Contractor shall conduct all negotiations, make all arrangements, and assume all costs that arise from such changes.
The existing underground utilities shown on the Plans have been determined by as-built records and field surveys, but are not guaranteed to be complete or accurate. The Contractor shall be responsible for contacting the individual utility companies to mark locations, and arranging with them for any relocation work that should be required.
The Contractor shall make excavations and borings ahead of the work where necessary to determine the exact location of underground pipes or other features, which might interfere with construction. The Contractor shall support and protect pipes or other services where they cross the trench and shall be responsible for all damages incidental to interruptions of service that may be caused by Contractor operations. Where a new utility line crosses an existing pipeline or other conduit, the trench backfill shall be well compacted in a manner that provides for the required backfill and compaction standards while protecting the utility in question.
00150.70 Detrimental Operations – Add the following:
Portions of this project might be constructed in close proximity to existing private improvements. All private improvements disturbed by the Contractor’s operations shall be repaired or replaced to equal or better condition at the Contractor’s expense. The Engineer may withhold from future payments to the Contractor an amount equal to the costs reasonably estimated by the Engineer to repair or replace, as the case may be, those private improvements disturbed by the Contractor’s operations. Engineer shall release the retained amount once Engineer has determined that the Contractor has completed the repair consistent with the requirements of this provision. In addition, prior to construction, the Contractor shall provide to the Engineer videotape showing private property, if any, which may be disturbed during construction.
Section 00160 – Source of Materials
Comply with Section 00160 of the Standard Specifications.
Section 00165 – Quality of Materials
Comply with Section 00165 of the Standard Specifications modified as follows:
00165.04 Costs of Testing – Replace this section with the following sentence: All testing required to be performed by the Contractor will be at the Contractor’s expense.
00165.10(a) Field-Tested Materials – Add the following sentence: The County follows the most current version of the MFTP on its projects:
00165.10(b) Nonfield-Tested Materials - Add the following sentence: The
County follows the most current version of the NTMAG on its projects.
Section 00170 – Legal Relations and Responsibilities
Comply with Section 00170 of the Standard Specifications supplemented and/or modified as follows:
00170.00 General - Replace the first sentence of the first paragraph in this section with the following:
The Contractor shall comply with all laws, ordinances, codes, regulations, executive orders, and administrative rules (collectively referred to as "Laws" in this Section) that relate to the Work or to those engaged in the Work.
00170.02 Permits, Licenses, and Taxes – Add the following:
This project is to be constructed in Clackamas County road right of way and streets. There are no separate road opening permits required from Clackamas County to perform the work required under this contract.
00170.61(a) Workers' Compensation - In the paragraph, replace "00170.70(d)" with "the Agreement".
Add the following subsection:
00170.67 Fees - The fee required by ORS 279C.825(1) will be paid by the Agency to the Commissioner of the Oregon Bureau of Labor and Industries under the administrative rules of the Commissioner.
00170.70(a) Insurance Coverages - Add the following to the end of this subsection:
The following insurance coverages and dollar amounts are required pursuant to this subsection:
Insurance Coverages
Combined Single Limit per Occurrence
Annual Aggregate Limit
Commercial General Liability $1,000,000 $2,000,000
Commercial Automobile Liability $1,000,000 (aggregate limit not required)
Pollution Liability $1,000,000 $2,000,000
00170.70(d) Additional Insured - Add the following paragraph at the beginning of the section and add the bullets to the end of this subsection:
The liability insurance coverages of 00170.70(a) shall include the Agency, the Agency's governing body, board, or Commission and its members, and their respective officers, agents, and employees as Additional Insureds, but only with respect to the Contractor's activities to be performed under the Contract.
• Clackamas County and its officers, agents, and employees
• Clackamas County Board of Commissioners
00170.70(h) Agency Acceptance – Delete the paragraph in this section and replace with the following:
All insurance and insurance providers are subject to Agency acceptance. In addition, all of the following are subject to Agency acceptance and, if requested by Agency, the Contractor shall provide complete copies of the following to Agency’s representatives responsible for verification of the insurance coverages required by the Contract: insurance policies, endorsements, self-insurance documents and related insurance documents.
00170.70(k) Builder’s Risk Installation Floater – Delete the paragraph in this section and replace with the following:
If specified by Special Provision, the Contractor shall obtain, at its expense, and keep in effect during the term of the Contract, Builder’s Risk Installation Floater Insurance covering the Contractor's Materials and Equipment to be used for completion of the Work performed under the Contract. The minimum amount of coverage to be carried shall be equal to the full amount of the Contractor´s Equipment, Materials, or fixtures to be installed, in-transit, or stored off-site during the performance of the Contract. This insurance shall include as loss payees the Agency, State of Oregon, the building or structure owner, the Contractor and Subcontractors as their interests may appear.
00170.72 Indemnity/Hold Harmless – Delete and replace with the following: Clackamas
County Public Improvement Contract.
Extend indemnity and hold harmless to the Agency and the following:
• Clackamas County and its officers, agents, and employees
• Clackamas County Board of Commissioners
00170.79 Third Party Beneficiary – Replace the text of this section with the following:
• Third-party beneficiaries to the Contract include the Oregon Department of Transportation and its officers, agents, and employees.
00170.85(b-1) Contractor Warranty for Specific Items – This subsection does not apply:
Section 00180 – Prosecution and Progress
Comply with Section 00180 of the Standard Specifications supplemented and/or modified as follows:
00180.06 Assignment of Funds Due Under the Contract - Delete first bulleted item.
00180.21(a) Subcontracting - Add the following subsection (a):
All contracts with subcontractors or suppliers shall have provisions making the contract assignable to the County, at the option of the County, if the Contractor terminates, goes out of business, declares bankruptcy, or otherwise is unable to perform provided that the County gives the subcontractor notice of assignment within fourteen (14) days of learning of the inability of the Contractor to perform.
The Engineer may revoke consent to subcontract. If the Engineer revokes consent to subcontract, the subcontractor shall be immediately removed from the Project Site.
00180.40 Limitation of Operations - Add the following to subsection (a):
The Contractor must provide, at a minimum, a 48-hour notice to the Clackamas County Project Manager in order to perform any work on Saturdays.
00180.40(b) On-Site Work - Add the following paragraph to the end of the subsection:
The Contractor shall not begin On-Site Work before July 1, 2027, unless approved by the Engineer.
Add the following subsection:
00180.40(c) Specific Limitations - Limitations of operations specified in these Special Provisions include, but are not limited to, the following:
Limitations Subsection
Cooperation with Utilities ........................................................ 00150.50 Cooperation with Other Contractors ....................................... 00150.55 Railway Work ................................................................... 00170.01(e) On-Site Work ................................................................... 00180.40(b) Contract Completion Time ............................................... 00180.50(h) Right-of-Way and Access Delays ........................................... 00180.65 Traffic Lane Restrictions .................................................. 00220.40(e) Special Events ................................................................. 00220.40(e) In-water Work Restrictions .............................................. 00290.34(a) Noise Control .......................................................................... 00290.32 Maintenance Under Traffic ..................................................... 00620.43 Opening Sections to Traffic .................................................... 00744.51 Opening Sections to Traffic .................................................... 00745.51
Be aware of and subject to schedule limitations in the Standard Specifications that are not listed in this Subsection.
00180.41 Project Work Schedules – Add the following:
A Type B schedule as detailed in the Supplemental Specifications is required on this Contract. In addition, a three-week look ahead schedule shall be prepared by the Contractor on a weekly basis and submitted to the Engineer. It shall include all construction activities planned for the following three-week period. The three-week look ahead schedule can be hand-written and shall be in a format agreed upon by the Contractor and the Engineer.
The Contractor shall notify the County 2 weeks before the first substantial work activity commences on the project sites.
00180.42 Preconstruction Conference - Add the following:
Before beginning On-Site Work and before meeting with the Engineer for the preconstruction conference, hold a group utilities scheduling meeting with representatives from the utility companies involved with this project. Incorporate the utilities time needs into the Contractor's schedule submitted prior to the preconstruction conference.
Submit the following during the preconstruction conference unless otherwise directed:
• The names, addresses, and telephone numbers of two or more persons employed by the Contractor who can be reached day or night to handle emergency matters.
• Subcontractor's list including contact list for each subcontractor with phone numbers and addresses and work to be performed.
• List of personnel authorized to sign change orders and receive progress payment warrants.
• Video recording of private properties affected by construction per 00150.70.
A representative of each subcontractor shall be required to attend the pre-construction conference.
A representative of each subcontractor shall be required to attend the pre-construction conference.
00180.43 Commencement and Performance of Work - Add the following bullet item:
• Conduct the work at all times in a manner and sequence that will ensure minimal interference with traffic. The Contractor shall not begin work that will interfere with work already started. If it is in the County's best interest to do so, the County may require the Contractor to finish a portion or unit of the project on which work is in progress or to finish a construction operation before work is started on an additional portion or unit of the project.
• The Contractor shall minimize impacts to school bus routes. If work will impact a school bus route, the Contractor shall notify and coordinate with the appropriate school district prior to starting work.
• At the time Substantial Completion is reached, the Contractor shall submit a Notice of Substantial Completion.
Add the following subsection:
00180.50(h) Contract Time - Complete all Work to be done under the Contract not later than September 3, 2027.
00180.70 Suspension of Work - Add the following to the first bullet item:
If the Inspector has reason to believe that any safety provisions are not being adhered to, the Inspector will immediately notify the Contractor’s site foreman and/or the appropriate person and the County Project Manager. The purpose of this discussion is to determine the validity of the alleged violation. This will also allow the Contractor a reasonable amount of time to correct or improve any of the provisions for the safety on this project. If the County Project Manager finds the problem still unresolved or uncorrected, they will notify the Contractor’s Project Manager and the County’s Risk Management Safety Analyst. If the County’s Risk Management Safety Analyst finds that the job site contains any unresolved safety issues, they will take appropriate action up to and including suspension of the Contractor’s operations on all or part of the Work.
00180.85(b)(1) Single Contract Time - Replace this subsection, except for the subsection number and title, with the following:
The Liquidated Damages per Calendar Day* are 15.0 percent of C divided by T as defined in this Section.
C = The Contractor’s Bid amount for the Contract.
T = The total Calendar Days between the latest completion date or time listed under 00180.50(h) in the Solicitation Documents and the Bid Opening that will result in the greatest value for T.
* Calendar Day amounts are applicable when the Contract time is expressed on the Calendar Day or fixed date basis.
Add the following subsection:
00180.85(c) Lane Closures and Road Closures - Lane closures and road closures beyond the limits specified will inconvenience the traveling public and will be a cost to the Agency.
(1) Lane Closures - It is impractical to determine the actual damages the Agency will sustain in the event traffic lanes are closed beyond the limits listed in 00220.40(e). Therefore, the Contractor shall pay to the Agency, not as a penalty, but as liquidated damages, $500 per 15 minutes, or for a portion of 15 minutes, per lane, for any lane closure beyond the limits listed in 00220.40(e). In addition to the liquidated damages, all added cost for traffic control measures, including flagging, required to maintain the lane closures beyond the allowed time limits, will be at no additional cost to the Agency. The required traffic control measures will be as determined by the Engineer.
The Engineer will determine when it is safe to reopen lanes to traffic. Assessment of liquidated damages will stop when all lanes have been safely reopened. Any liquidated damages assessed under these provisions will be in addition to those listed in 00180.85(b).
00180.88 Workplace Harassment Prevention Plan – Submit a workplace harassment prevention plan for review 10 days before the preconstruction conference. The plan shall ensure all workers are guaranteed a safe and respectful work environment regardless of their identity or status. The plan applies to, but is not limited to, a worker’s race, gender, creed, or any protected characteristic under state or federal law. At a minimum, the plan shall include:
• A Statement that the Contractor shall provide a safe and respectful workplace on the jobsite for all workers, subcontractors, suppliers, and other persons performing work.
• A description of how the plan will be implemented and monitored during the project duration.
• A list of the in-person trainings that will be conducted for workers of all ranks working on the project to support, promote, and grow a positive jobsite culture.
• A list of meaningful policies including procedures for aggrieved workers in need of recourse.
• How incidents involving bullying or harassment will be investigated and resolved in a prompt, thorough, and impartial manner.
Contractor shall post on the jobsite and make available copies of policies about hate, intimidation, or harassment including how to report incidents and how to receive support. Materials will be provided in all languages necessary to be inclusive of the workforce.
00180.89 Measurement – No measurement of quantities will be made for workplace harassment prevention plan.
00180.95 Payment – Payment for workplace harassment prevention plan will be for developing and implementing the plan during construction of the project, in-person training, developing meaningful policies, and investigating incidents.
Section 00190 – Measurement of Pay Quantities
Comply with Section 00190 of the Standard Specifications supplemented and/or modified as follows:
00190.20(a) Contractor to Provide Vehicle Weigh Scales: Delete and replace the last paragraph in this section with the following:
Unless otherwise provided in the Contract, Pay Items to be measured by weight shall include all Contractor costs for providing, maintaining, inspecting, and testing scales; for furnishing appropriate weigh tickets; for self-printing scales; for electronic weigh memo system(s); and for transporting Materials to the scales or to check weighing.
00190.20(f)(1) Scale with Automatic Printer: Delete and replace the first sentence in this section with the following:
If the scales have an automatic weigh memo printer or an approved electronic weigh memo system that does not require manual entry of gross weight information, the Agency may periodically have a representative at the scales to observe the weighing procedures.
00190.20(f)(1) Scale with Automatic Printer: Delete and replace the last bullet in this section with the
• Furnish a legible, serially numbered weigh memo for each load of Materials to the Agency's Materials receiver at the point of delivery, or as directed by the Engineer. The memo shall identify the Project, the Materials, the date, net weight (gross and tare as appropriate), and identification of the vehicle and weigh technician. If approved by the Engineer an electronic weigh memo system may be used. Requests to use an electronic weigh memo system shall be submitted to the Engineer according to 00150.37, providing sufficient detail for the Engineer to perform an evaluation. If approved, the Contractor shall provide training, technical support, reports, and weigh memo information to the Engineer at no additional cost to the Agency. The electronic weigh memo system shall be:
• Capable of recording and securely retaining the same required “weigh memo” information identified above. For retention see 00170.07(c).
• Fully integrated with the provided weigh scale system.
• Designed in such a way that the data electronically read from scales cannot be altered by the
Contractor, Subcontractor, Supplier, Engineer, or other system users.
• Designed to allow the Engineer remote access to all the weigh memo data in real-time and allow the Engineer to add comments to the individual weigh memo regarding waste, temperature, stations, yield or other information. The system shall identify the system user or individual that adds comments to the electronic weigh memo or otherwise access the system. The Contractor shall provide the Engineer a means to access the data if the Engineer cannot use an Agency provided hand held device for access.
• Capable of providing all the weigh memo information, including any added comments, in an electronic data file the Engineer can easily access without proprietary software.
00190.20(g) Agency-Provided Weigh Technician: Delete and replace subsection (g) with the following:
The Contractor must provide a weigh technician. The Agency will not provide one for the Contractor.
00190.30 Plant Scales: Add the following sentence after the bulleted list:
If approved by the Engineer an electronic weigh memo system may be used in place of a printer system.
See 00190.20(f)(3).
Section 00195 – Payment
Comply with Section 00195 of the Standard Specifications supplemented and/or modified as follows:
00195.10 Payment for Changes in Material Costs - Delete and replace with the following: No asphalt cement cost adjustment shall be used on this project.
00195.12 Steel Material Price Escalation/De-Escalation Clause – Add the following sentence:
No steel material price escalation/de-escalations shall be used on this project. There is no option for Contractor participation.
00195.20(b) Significant Changed Work – Add the following:
Significant is defined as:
a) An increase or decrease of more than 25 percent of the total cost of the Work calculated from the original proposal quantities and the unit contract prices; or,
b) An increase or decrease of more than 25 percent in the quantity of any one major contract item.
For condition b) above, a major item is defined as any item that amounts to 10 percent or more of the original total contract price.
00195.50(a) Progress Payments - Delete and replace the last sentence in the second paragraph as follows:
All estimated quantities are subject to correction in the final estimate. If the Contractor uses these estimates as a basis for making payments to Subcontractors and Suppliers, the Contractor assumes all risk and bears any losses that result.
00195.50(a)(1) Progress Estimates - Delete the first sentence and replace with the following:
At a regular period each month to be determined at the Preconstruction Conference, the Contractor will make an estimate of the amount and value of pay item work completed and in place. This estimate will be submitted to the Project Manager for review and approval.
(2) Value of Material on Hand - Delete the section and replace with the following:
(2) Value of Material on Hand - The Contractor will make an estimate of the amount and value of acceptable material to be incorporated in the completed work which has been delivered and stored as given in 00195.60(a) for review and approval.
(4) Limitations on Value of Work Accomplished - In the first sentence, change "Engineer's estimate" to “Contractor’s reviewed estimate”.
00195.50 (b) Retainage - Delete the first paragraph and replace with:
The amount to be retained from progress payments will be 5.0% of the value of payments made, and will be retained in one of the forms specified in Subsection (c) below. The County will withhold Retainage from all force account and change order work.
00195.50(c) Forms of Retainage – Delete first paragraph and replace with:
Forms of acceptable retainage are set forth below in Subsections (1) through (3). “Cash, Alternate A” or “Cash, Alternate B” (Retainage Surety Bond) are the Agency-preferred forms of retainage. Unless the Contractor notifies the County otherwise in writing, the County will automatically hold retainage per paragraph (2) “Cash, Alternate B (No Interest Earned). If the Agency incurs additional costs as a result of the Contractor’s election to use “Bonds and Securities”, the Agency may recover such costs from the Contractor by a reduction of the final payment.
Delete and replace paragraph (2) with the following:
(2) Cash, Alternate B (No Interest Earned) – Retainage will be deducted from progress payments and held by the Agency until final payment is made in accordance with 00195.90, unless otherwise specified in the Contract.
00195.50(d) Release of Retainage – Delete this section and replace with the following:
(d) Release of Retainage - As the Work progresses, release of the amounts to be retained under (b) of this Subsection will only be considered for Pay Items that have been satisfactorily completed. For purposes of this Subsection, a Pay Item will be considered satisfactorily completed only if all of the Work for the Pay Item is complete and all contractual requirements pertaining to the Pay Item and Work have been satisfied. Work not included in a Pay Item, or which constitutes part of an uncompleted Pay Item, will not be regarded as satisfactorily completed Work for the purposes of this Subsection.
When the Work is 50% completed and upon written application of the Contractor and written approval of the Surety, the Engineer or Project Manager may reduce or eliminate retainage on remaining progress payments if the Work is progressing satisfactorily.
A determination of satisfactory completion of Pay Items or Work or release of retainage shall not be construed as acceptance or approval of the Work and shall not relieve the Contractor of responsibility for defective Materials or workmanship or for latent defects and warranty obligations.
Section 00196 – Payment for Extra Work
Comply with Section 00196 of the Standard Specifications modified as follows:
00196.91 Extra Work Allowance – Add the following section:
The Bid schedule of prices contains a bid item for a pre-determined amount of Engineer ordered extra work.
All Bidders shall reflect this same amount in their total Bid. No Bidder shall presume in the preparation of the bid or in the course of contract work that there will be a certain payment under that item or a certain order for extra work.
Section 00197 – Payment for Force Account Work
Comply with Section 00197 of the Standard Specifications.
Section 00199 – Disagreements, Protests and Claims
Comply with Section 00199 of the Standard Specifications supplemented and/or modified as follows:
00199.40 Claim Decision; Review; Exhaustion of Administrative Remedies - Replace the entire section with the following:
The Contractor must properly submit a claim as detailed in 00199.30.
(a) Engineer Claim Review - The Engineer or Project Manager will, as soon as practicable, consider and investigate a Contractor's properly submitted claim for additional compensation, Contract Time, or for a combination of additional compensation and Contract Time. Once the Engineer or Project Manager determines the Agency is in receipt of a properly submitted claim, the Engineer or Project Manager will arrange a meeting, within 28 Calendar Days, or as otherwise agreed by the parties, with the Contractor in order to present the claim for formal review and discussion. A person authorized by the Contractor to execute Change Orders on behalf of the Contractor must be present and attend all claim meetings.
If the Engineer or Project Manager determines that the Contractor must furnish additional information, records, or documentation to allow proper evaluation of the claim, the Engineer will schedule a second meeting, to be held within 14 calendar days, or as otherwise agreed by the parties, at which the Contractor shall present the requested information, records and documentation.
The Engineer or Project Manager will advise the Contractor of the decision to accept or reject the claim.
If the Engineer or Project Manager finds the claim has merit, an equitable adjustment will be offered. If the Engineer or Project Manager finds the claim has no merit, no offer of adjustment will be made and the claim will be denied. The County intends to resolve claims at the lowest possible level.
If, at any step in the claim decision or review process, the Contractor fails to promptly submit requested information or documentation that the Agency deems necessary to analyze the claim, the Contractor is deemed to have waived its right to further review, and the claim will not be considered properly filed and preserved.
If the Engineer or Project Manager has denied a claim, in full or in part, for Contract Time only according to 00180.80, or has denied a claim, in full or in part, for correction of final compensation according to 00195.95, those disputed claims may then be resolved, in full or in part, at either of the two progressive steps of claim review procedure as specified in this
Subsection. For all claims, all of the actions and review under each step of the review process shall occur before the review can be advanced to the next higher step.
(b) Director Claim Review - Upon request by the Contractor, the Department Director will review the Engineer or Project Manager’s decision on the claim and advise the Contractor of the decision in writing.
If the Director finds the claim has merit, and equitable adjustment will be offered. If the Director finds the claim has no merit, no offer of adjustment will be made and the claim will be denied.
Once the Engineer determines the Agency is in receipt of a properly submitted claim, the Engineer will arrange a meeting, within 21 Calendar Days or as otherwise agreed by the parties, with the Contractor in order to present the claim for formal review and discussion.
If the Engineer determines that the Contractor must furnish additional information, records or documentation to allow proper evaluation of the claim, the Engineer will schedule a second meeting, to be held within 14 Calendar Days or as otherwise agreed by the parties, at which the Contractor shall present the requested information, records and documentation.
The Director shall evaluate the claim based on the information provided by the Contractor to the Engineer or Project Manager. However, if the Department Director (or designee) determines that the Contractor must furnish additional information, records or documentation to allow proper evaluation of the claim, the Department Director (or designee) will schedule a meeting, to be held within 14 Calendar Days, or as otherwise agreed by the parties, at which the Contractor shall present the requested information, records and documentation.
The claim is subject to records review, if not all of the records requested by the Department Director (or designee) were furnished. If applicable, advancement of the claim is subject to the provisions regarding waiver and dismissal of the claim or portions of the claim.
The decision of the Department Director shall be the final decision of the Agency.
(c) Commencement of Litigation - If the Contractor does not accept the Director’s decision, then the Contractor shall commence any suit or action to collect or enforce any claim filed in accordance with
00199.30 within a period of one (1) year following the mailing of the decision or within one (1) year following the date of "Second Notification", whichever is later. If said suit or action is not commenced in said one (1) year period, the Contractor expressly waives any and all claims for additional compensation and any and all causes of suit or action for the enforcement thereof that he might have had.
The Contractor must follow each step in order, and exhaust all available administrative remedies before resorting to litigation. Litigation of a claim that cannot be resolved through the process described above shall be initiated by filing a complaint in the Clackamas County Circuit Court for the State of Oregon.
In any litigation, the entire text of any order or permit issued by the County or any other governmental or regulatory authority, as well as any documents referenced or incorporated therein by reference, shall be admissible for purposes of Contract interpretation.
The Contract shall not be construed against either party regardless of which party drafted it. Other than as modified by the Contract, the applicable rules of contract construction and evidence shall apply. This Contract shall be governed by and construed according to the laws of the State of Oregon without regard to principles of conflict of laws.
The Contractor shall comply with 00170.00.
00199.50 Mediation - Delete the entire section.
00199.60 Review of Determination Regarding Records - Delete the entire section.
SECTION 00210 – Mobilization
Comply with Section 00210 of the Standard Specifications.
END SECTION
Section 00220 – Accommodations for Public Traffic
Comply with Section 00220 of the Standard Specifications supplemented and/or modified as follows:
00220.03 Work Zone Notifications - Add the following to the end of this subsection:
Notify emergency services, school districts, police department(s), fire department(s), TriMet, and garbage and recycling services 10 calendar days in advance of street closures.
00220.40 General Requirements - Add the following:
(e) Lane Restrictions – This project must remain open to traffic during non-work hours. The appropriate road surface and road width will be evaluated by the Project Manager each evening prior to allowing the traveling public thru the project site without continuous traffic control. If unsafe conditions exist, contractor must correct the problem or provide continuous traffic control at his own expense.
(1) Closed Lanes – Replace all bullets with the following:
• Monday through Friday 7:00 a.m. to 6:00 p.m.
• Work hours/traffic impacts on Redland Rd from Holcolm Blvd/Abernethy Rd to Holly Lane shall be restricted to 9am – 3pm during weekdays.
Traffic control devices at a physical street closure point shall include Type II barricades spaced at a maximum of 3-feet apart across the full width of the roadway with “NO
PARKING OR DRIVING” signage and link chain or rope with yellow caution tape connecting the barricades. Where necessary as directed and approved by the Inspector, the Contractor shall spread a thin pathway of sand across the fresh slurry at pedestrian crossings and high pedestrian traffic street…
This is the start of the file's text. The full file is on GovTribe.