This is a Scope of Work document for a residential housing rehabilitation project issued by Escambia County's Neighborhood Enterprise Division under its SHIP (State Housing Initiatives Partnership) Housing Repair Program for owner Ashawni Hayes at 2414 W. Moreno Street, Pensacola, Florida. The project encompasses three primary work categories: roofing repairs and replacement including decking, framing, underlayment, vents, flashing, and installation of 30-year architectural shingles; foundation work involving leak detection, replumbing, wall support and stabilization, drywall repair, and flooring replacement in the hallway and bathrooms; and installation of new front stairs compliant with Escambia County Building Code and ADA standards. A mandatory on-site walkthrough is scheduled for October 6, 2026 at 10:00 AM, with quotes due by October 14, 2026 at 1:00 PM and quote review on October 15, 2026 at 1:00 PM at 221 Palafox Place, Pensacola, Florida. The project must be completed within 60 days, with liquidated damages assessed at $150 per day for work exceeding the contract period. Bids must be submitted exclusively through the OpenGov portal and must include completed cover sheets, all numbered scope pages, and an itemized pricing table with total cost; failure to comply will result in bid rejection.
Payment for projects under $15,000 is lump sum upon completion; projects exceeding $15,000 are eligible for a 40 percent draw upon 50 percent project completion, a substantial completion draw within 20 business days thereafter, and final payment upon completion of all work, inspections, homeowner acceptance, and submission of required documentation. Award will be made to the lowest and most responsible bidder. Contractors must have current W9, Sunbiz registration, Worker's Compensation insurance or exemption, and Commercial General Liability coverage of $1,000,000 with Escambia County listed as certificate holder and additional insured. Projects valued at $25,000 or higher require 100 percent Performance and Payment Bonds prior to Notice to Proceed. All contractors must be registered with sam.gov, hold state contractor licenses, possess Escambia County Competency Board and Business/Occupational licenses, and maintain EPA RRP Renovator certifications. The project includes no federal funding and will follow federal, state, and county laws and ordinances.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NED_Home_Rehab_-_2414_W._Moreno_St._(Addendum_#1_Revision).pdf | ||
| NED_Home_Rehab_-_2414_W._Moreno_St..pdf | ||
| Bid_Scope_Materials_List.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NEIGHBORHOOD ENTERPRISE DIVISION - ESCAMBIA COUNTY
SHIP HOUSING REPAIR – SCOPE OF WORK - COVERSHEET
| OWNER: |
| Ashawni Hayes |
| JOB NUMBER: |
| NED-S-2414-092926 |
| ADDRESS: |
| 2414 W. Moreno St |
| DATE PREPARED: |
| 09-29-2026 |
Pensacola, Fl. 32505
| WALK DATE: |
| 10-06-2026 10:00 am |
| PHONE: |
| 850.490.7417 |
| QUOTES DUE: |
| 10-14-2026 1:00 pm |
| QUOTE REVIEW: |
| 10-15-2026 1:00 pm |
I/(we) certify that I/(we) have carefully examined the Housing Repair Specifications and Contractor Requirements related to the above referenced job, as furnished by Escambia County, and I/(we) have also examined the site on which the proposed work is to be performed. Based on these examinations, We propose to furnish all materials, tools, machinery and labor necessary to complete the work in a professional, workmanship manner and to complete the work at the prices listed.
TOTAL JOB COST
CONTRACTOR’S SIGNATURE
TITLE
QUOTE REVIEW:
FIRM
| |_| ACCEPTED |
| |_| REJECTED |
FIRM PHONE NUMBER
QUOTE REPRESENTATIVE
Escambia County Building Code
REQUIRED PERMITS AND INSPECTIONS:
By signing this document, you are certifying that your firm is not currently suspended, debarred, or in any way disqualified from participating in any county, state, or federal funded housing rehabilitation programs.
All measurements are for reference only and should be confirmed by the bidder.
Mandatory ON-SITE walk-through: October 6, 2026, at 10:00AM
INSTRUCTIONS TO BIDDERS
The bidder must complete, sign, and upload the cover sheet and all numbered pages on the Scope of Work. The bidder must also complete the itemized pricing table and include a total cost. Failure to do any of these requirements will result in the bid being rejected. Hand delivered, emailed or faxed submissions will NOT be accepted. Submissions are only accepted online, via the OpenGov portal. All quotes must be received by the published “Quotes Due” deadline.
The quotes will be opened on the “Quotes Due” and awarded to the lowest and most responsible bidder. The opening of these quotes or the “Quote Review” will be held at 221 Palafox Place, Pensacola, FL 32502 on October 15, 2026. Should the total cost of this project exceed the funds available, then a removal of one or more of the optional pricing tables line items may be removed to maintain the program’s budgetary restrictions.
CONTRACTOR’S RESPONSIBILITIES AND OBLIGATIONS
All repair work performed must be inspected and conform to state laws, and the Escambia County building codes and ordinances. The contractor is responsible for proper reattachment or hook-up of any of the following that apply; appliances, existing coaxial cable, telephone and interface, electric, water, and sewage. The contractor will only assist in moving the larger furniture and the contractor is not responsible for the removal of the homeowner’s trash, discarded belongings or furnishings. Labor, overhead, permits, insurance, and profit must be included into each itemized line-item price and not listed as a separate itemized price or listed under “miscellaneous.” Non-compliance will result in rejection of bid. Review the “Bid Scope Materials List” for product lines and or their equivalents.
HOMEOWNER’S RESPONSIBILITIES AND OBLIGATIONS
The homeowner is responsible for maintaining existing utilities for the contractor use during the rehabilitation period and for the removal of all belongings and furnishings from the designated work areas prior to the start date. The homeowner is also to be given options when selecting colors and styles of the products being replaced.
PAYMENT SCHEDULE
The payment will be lump sum payment at the project completion for bids and under $15,000. For bids over $15,000, the contractor will be eligible for a 40% draw once the NED confirms that 50% of the work has been completed as determined by line-item costs. For a line item to be counted toward project completion, it must be fully completed; no partial credit will be given for incomplete work. Within 20 business days after the initial draw the contractor will be eligible for a substantial completion draw which is to be 150% less of any line-item costs that are not complete. The contractor will be eligible for final payment after the following conditions have been fulfilled:
*Completion of the Scope of Work
| *Inspection/Sign-off by Building Inspections and/or Health Department |
| *Acceptance by the Homeowner (Homeowner’s Release & Warranty) |
| *Contractor’s Final Affidavit |
| *Warranty Paper provided to the Homeowner |
| *Premises free from all construction debris |
| *Submission of RRP Checklist Form |
| *Original Invoice from Contractor |
*Surety’s Consent to Final Payment (if applicable)
COMPLETION DATE
There is a 60-day time limit on this rehabilitation project. For every day worked more than the contract period, liquidated damages of ONE HUNDRED and FIFTY DOLLAR ($150.00) per day will be assessed. During this timeline the homeowner is not to begin any new rehabilitation projects.
ESCAMBIA COUNTY NEIGHBORHOOD ENTERPRISE DIVISION
HOUSING REPAIR PROGRAMS
CONTRACTOR REQUIREMENTS
If your firm is awarded the bid for housing repair (SHIP or HUD programs), the following items must be current and on file to issue a Purchase Order.
| *Current W9 and Sunbiz registration (less than one year old). |
| *County Vendor Information sheet (less than one year old). |
| *Worker’s Compensation as required by State Law OR exemption form. |
| *Commercial General Liability, Automobile Liability and Pollution Liability at |
($1,000,000 coverage) and listing Escambia County as a certificate holder and a additional insured.
*Commercial General Liability, Automobile Liability and Pollution Liability certificates must state the following under Additional Interest:
Escambia County C/O Neighborhood Enterprise Division 221 Palafox Place Suite 304 Pensacola, FL 32502-5844
All correspondence should be directed to the Neighborhood Enterprise Division, 221 Palafox Place, Suite 304, Pensacola, FL 32502 for review.
*For jobs valued at $25,000 or higher, a 100% Performance and Payment Bonds will be needed prior to the Notice to Proceed date. If the Bond is not filed within 10 days after the contract is signed, then a letter of insurability will be required. A Consent of Surety will be required before final payment. The contractor will be responsible for the recording of all bonds with Pam Childers, Clerk of The Circuit Court of Escambia County Florida.
Refer to BCC Office of Purchasing Risk Management Guidelines Procedure No: PP-180 (Performance and Payment Bonds) and PP-185 (Risk Management Guidelines) for further details. [http://www.myescambia.com/business/purchasing-policies-and-procedures]
Additionally, the Neighborhood Enterprise Division will maintain the following info in the contractor’s file:
*www.sam.gov Contractor may not be federally debarred and participate in this program
| *State registered or State Certified Contractor License |
| *Escambia County Competency Board License |
| *Escambia County Business/Occupational License |
| *EPA RRP Renovator and Firm Certifications |
Firms quoting Lead Based Paint Abatement jobs must also submit proof of Lead Abatement firm certification.
All information must be current at the time of the award. IF INFORMATION CANNOT BE PRODUCED IN A TIMELY MANNER, THE COUNTY RESERVES THE RIGHT TO AWARD THE BID TO THE NEXT MOST RESPONSIVE BIDDER.
SHIP Housing Repair Program Specifications PAGE 1
Ashawni Hayes
2414 W. Moreno St
Pensacola, Fl. 32505
850.490.7417
SCOPE OF WORK
The rehabilitation of this owner-occupied, single-family, residence is to make the home safer, more energy efficient, and easier to access within the provisions of federal, state, and county laws and ordinances and the SHIP repair program. The rehabilitation of this home will include the following tasks as outlined below and the repaired areas are to match as close as possible to their existing surroundings. If additional tasks beyond those included in this scope are discovered, then additional funds may be allocated. Before any additional work is performed, written county approval will be needed. There is no federal funding for this project.
1. ROOFING:
Remove existing roof covering down to the decking and replace any deteriorated or damaged decking with like, kind, and quality of existing materials. Repair or replace any damaged roof framing to include rafter tails, rafters, and barge rafters. Refasten and certify decking attachment. Install a peel and stick underlayment water barrier. Replace the existing drip edge with a new metal drip edge. Install new slant-back vents, replace gas vent caps and all flashing as required. Replace all boots with new lead, EPDM, and or metal boots. Install 30-year architectural (CertainTeed Landmark or equivalent) roof shingle as per manufacturer’s specifications and/or a self-adhering modified bitumen roof system to any low sloped areas as per the Escambia County Building Code. Then install new shingle over the ridge vents. Then install new shingle over the ridge vents. Budget 320 square feet for damaged decking replacement. If they are missing or outdated install hurricane clips on every rafter or truss, with a minimum of 6 pictures illustrating said strapping. Trim any trees over hanging roof to clear roof by approximately 10’ and remove all debris from site. Repair or replace any damaged fascia and soffit with like material and match the finish as close as possible. Replace the existing gutters with new 6” seamless gutters only where gutters are currently installed. This is to include 4” downspouts, splash blocks, and diverters as needed.
Photographs are required for all stages of construction.
Total $_______________ Homeowner:_______________ Permit:_______________
2. FOUNDATION:
The foundation appears to be sinking or settling in the hallway between the two bathrooms. Preform a leak detection, replumb where needed, jack up or support the wall as needed, secure the hallway wall and repair the damaged drywall, replace the hallway and bathrooms flooring as needed, adjust, repair or replace the interior doors that are not closing.
Total $_______________ Homeowner:_______________ Permit:_______________
3. STAIRS:
Install new stairs to the front of the home as per the Escambia County Building Code. The ADA also provides details on landings, lengths, slope, and handrails.
Total $_______________ Homeowner:_______________ Permit:_______________
Review the “Bid Scope Materials List” for product lines and or their equivalents.
Mandatory H.O signoff on scopes when 100% completed and on permits when required.