Scope of Works - Elastomeric coating of Roof.pdf

PDF 174 KB Posted

Attached to
Elastomeric Coating on roof of office buildings (labor Only)
Solicitation number
191N6525Q0097
Issued by

About this file

This document is a Scope of Work (SOW) for an elastomeric coating project at the US Embassy in New Delhi, India. The project involves applying a solvent-based elastomeric acrylic coating to approximately 10,000 square feet of a pitched corrugated roof on a prefab structure. Key requirements include extensive surface preparation, installation of metal scaffolding, and a multi-step coating process involving primer application, reinforcement fabric embedment, and multiple layers of grey and white elastomeric coating. The contractor must provide experienced labor, safety equipment, and comply with strict embassy security protocols. The project is scheduled for 30 days on-site, with working hours from 8:30 AM to 5:30 PM Monday through Saturday, and requires detailed safety and security clearance procedures, including background checks for workers and submission of transportation details for material deliveries.

View the file

Other files

File Type Posted
QA sheet (1).xls XLS spreadsheet
SF1442 Cover Page.pdf PDF
SOLICITATION-Elastomeric coating of roof.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Elastomeric Coating Scope of Work for office buildings at Enclave Compound

US Embassy, New Delhi

1.0 Background and Purpose:

Embassy of the United States of America in New Delhi has a requirement to hire services of a contractor to do elastomeric coating (labor only) on corrugated roof of office building.

Work involves erection of scaffolding and experience labor for carrying out the work of coating. Approximate area is 11,500 square feet.

2.0 GENERAL REQUIREMENTS

a. Contractor shall provide personnel, material, equipment, and supervision to complete the technical requirements in this Statement of Work. Contractor shall follow security and safety (please refer attached OSHA Guidance for Safety) directions as explained by the COR.

b. Contractor and his workers will have limited access to the work site and shall not go to any other place in compound until and unless approved by COR.

c. Contractor has to bring in the scaffolding material and stack them properly with barricading around to restrict any unauthorize entry into the space.

d. Any damage that occurs to the building, equipment, furnishings or landscaping due to the failure of Contractor to properly protect and secure the work site while the roof project is in progress shall be Contractor’s responsibility to repair or replace the damages that have taken place matching to existing at Contractor’s expense.

3.0 Scope of Work

Erection of Scaffolding:

3.1 Under this contract, contractor must provide and install metal scaffolding (cup loc scaffolding) to reach a pitched roof approximately 30 above the ground level on one side of the building and create anchoring points on the other side (length wise) to anchor the safety ropes to support attachment of safety belts. Contractor can verify the height and width during walk through. Any ambiguity later will not be considered. Below are the works which contractor must furnish:

3.1.1 Storage Area:

Contractor will be provided with a designated space for storage of tools and tackles to work on this project.

3.2 Contractor shall follow below steps to get the scaffolding erected:

Step 1: Contractor must get the scaffolding designed for its sturdiness and resistance against overturning moments from a certified third party. A certified copy of the scaffolding design will be required.

Step 2: Contractor shall share safety plan for entire work. Contractor shall get the scaffolding installation designed and inspected by a competent authority and obtained approval from COR.

Step 3: Upon approval of scaffolding design, contractor shall make barricading for the designated storage space on the compound.

Step 4: Upon approval of the barricading, contractor shall bring the scaffolding material on compound. All the material will be checked for its functionality and safe work performance.

Step 5: Once all scaffolding material is checked and approved contractor can start erection of scaffolding per requirement. Contractor must get the installed scaffolding inspected by a third-party inspector to certify its compliance with the design and safe for people to work on this scaffolding with inclined ladders inside the scaffolding.

Note: Scaffolding shall be covered from all three sides with a green construction fabric to make it opaque and restricting any entry into the scaffolding area. A door with locking facility shall be installed to restrict entry of unauthorized personnels into the construction space.

Step 6: The Contractor must provide a qualified English-speaking supervisor for the entire duration of work.

Step 7: It will be the Contractor Supervisor’s responsibility to check on the sturdiness of scaffolding each day before start of work and ensure that it is safe to work on it.

It is the responsibility of the Contractor to ensure that all scaffolding material is in sound condition, regularly inspected and kept on record.

Step 8: The Contractor shall supply his own transport of adequate size to move own labor, materials, tools, and equipment in order to provide an effective and efficient. service. No claims will be accepted for costs for additional equipment requirements, consumables and standing time.

Step 10: Inclined stair flights (45º) are mandatory as a means of access to and egress from work platforms, unless it is not practical to install inclined stairs flights such as where there is no space for the inclined stairs flights. An additional Risk Assessment should be carried out and recorded in these instances.

Step 11: For ease of installation, stair flights shall be of light construction but capable of withstanding imposed loads.

Step 12: The maximum load rating of scaffolding systems should be clearly indicated in the submission.

Step 13: Contractor shall tie a jute / PVC rope approximately 2” in diameter from one end to another end of the building (along the length of the building) for workers to tie in their safety harnesses while working. This is an advise to the contractor but contractor will be ultimately responsible for the safety and security of his workers. Contractor is liable to find a suitable and mutually acceptable way to tie the safety harnesses of workers during work timings.

4.0 Elastomeric Coating

4.1 SUMMARY:

A. Approximate area to be repaired / treated is approximately 10,000 square feet. The are where this coating has been proposed is a pitched corrugated roof above a prefab structure on second floor level. The proposed roof repair using a solvent-based elastomeric acrylic coating includes, but is not limited to, the following:

1. Clean/Pressure wash roof areas and allow to dry.

2. Perform minor repairs to masonry.

3. Begin coating repair work at low end around roof drains.

4. Apply one coat primer on all surfaces and allow to dry.

5. Apply grey base coat (first coat) and lay reinforcement fabric.

6. Apply second coat and embed reinforcement fabric (three layers on entire roof area) on all base flashings (up-turns) around roof perimeter or penetrations.

7. Allow to dry.

8. Apply elastomeric coating and fabric material to all projections, perimeter, and penetrations.

9. Apply a white finish topcoat over the first and second base coats on the entire roof area. Using a white coat over a grey base coat allows for a more uniform and thorough application.

4.2 PROJECT PROCEDURES:

A. Embassy will occupy premises during entire period of construction for the conduct of normal, daily operations. Contractor shall conduct his operations to ensure least inconvenience to Embassy’s operations.

B. Contractor shall take precautions to avoid excessive noise or vibration that would disturb Embassy’s operations. When directed by Embassy, Contractor shall perform certain operations at designated time of day or night to minimize disturbance.

C. Working hours shall be 8:30 AM to 5:30 PM Monday through Friday. No work shall be done on Saturday, Sunday and mission holidays unless otherwise approved.

4.3 Application:

4.3.1 PREPARATION OF SUBSTRATE

A. Contractor shall determine the condition of the existing structural deck/substrate. All defects in the deck or substrate shall be corrected before new solvent-based elastomeric coating commences. Areas of deteriorated deck/substrate, porous or other affected materials must be removed and replaced with new to match existing.

B. Surface preparation is the most critical procedural requirement in paint applied coating systems. Remove all loose particles, delaminated paint, oil, grease, laitance, efflorescence, mild, mildew, loose old coating, and other foreign materials. Areas shall be first scraped, swept clean, and then thoroughly power washed. Use high power adjustable pressure washer with a minimum 3500 PSI (Pounds per Square Inch) mechanical spray device.

C. Each individual container of elastomeric primer and topcoats shall be thoroughly mixed using a heavy-duty drill on slow RPM (Revolutions per Minute) with an elongated mixing paddle bit that will reach the bottom of the container. Coating shall be a uniform color, with no light or dark streaks present. Flashing Grade material typically does not require mixing.

D. Coatings shall be applied in temperatures of fifty degrees Fahrenheit (50°F / 10°C) or greater.

4.3.2 THINNING SOLVENT-BASED ELASTOMERIC FOR SPRAY EQUIPMENT

A. Thinning Mix: One-quart mineral spirits to 5 gallons solvent-based elastomeric.

1. Pour 1 gallon from a 5-gallon pail coating into another container. Add one-quart mineral spirits to 4 gallons and mix thoroughly. Use an electric drill and mixing paddle. Add portions of the removed 1 gallon and continue to mix until the coating is properly thinned.

2. Spray applies thinned elastomeric coating in two coats to meet minimum thickness.

B. Additional Thinning Mix: Maximum two quarts mineral spirits to 5 gallons elastomeric.

1. Spray applies thinned elastomeric coating in three coats to meet minimum thickness.

C. DO NOT thin elastomeric coatings for brush or roller applications except for primer application described below.

4.3.3 FIRST COAT PRIMER APPLICATION

A. If required by manufacturer to use Elastomeric coating as a priming coat; dilute with 20% water, mix well prior to application as a primer of existing coating.

B. Coverage rate: Apply primer at 0.7–1.4 gallons (2.65-5.30L) per 100 square feet (9 SM)

C. Brush, roll or spray the elastomeric primer evenly onto the surface to fully saturate the substrate in one application with brush or roller: multiple applications with sprayer. DO

NOT allow primer to pond or collect in low areas. Apply primer up to the perimeter roof edge of the flashing terminations and penetrations.

D. Areas observed with residual “bleed” through of prior surfacing causing discoloration shall be re-primed to prevent discoloration.

E. Allow standard primer to cure for a minimum of four (4) hours before reinforcing fabric embedment into base coat.

4.3.4 GREY BASE COAT APPLICATION and REINFORCING FABRIC EMBEDMENT

A. Coverage rate: Apply Base Coat at 0.7–1.4 gallons (2.65-5.30L) per 100 square feet (9 SM)

B. Reinforcing fabric embedment requires either a large hand brush or roller application to evenly lay the fabric within the coating. The coating shall be rolled or brushed liberally and evenly onto the surface using a broad, even strokes.

C. The fleece fabric can only hold so much coating and all excess shall be rolled forward to the unsaturated fleece, eliminating ponding or excessive build-up.

1. Reinforcing Fabric Full Coverage: Roll out polyester fleece with smooth side facing up (natural unrolling procedure) into the primer. The fleece will begin to rapidly saturate with the liquid coating.

2. Use a medium nap roller or brush to work the primer into the fleece, saturating from the bottom up, and eliminating air bubbles, folds and wrinkles.

3. The appearance of the saturated fleece shall be light opaque with no white spots.

White spots where fabric clearly shows through, are indications of unsaturated fleece or lack of adhesion.

4. Allow 75mm overlap for all side joints and 100mm overlap for all end joints.

D. Apply final coat of grey elastomeric coating on top of fleece fabric to finish the saturation of the fleece. Roll this final coating into the fleece, shall result in a semi-gloss appearance.

Be careful not to “pull up” the fabric. Allow first grey base coat to dry sufficiently to “hold” fabric.

E. Allow grey base to cure for a minimum of twenty-four (24) hours before finish coats.

F. DO NOT apply coating over primer prematurely. Primer exposed to excessive moisture, primer used as temporary waterproofing, or primer older than eight (8) days. Exposure of the coating more than eight (8) days may require removal and application of new primer.

4.3.5 FINISH WHITE TOPCOAT APPLICATION

A. Coverage rate: Apply White finish topcoats at 0.7–1.4 gallons (2.65-5.30L) per 100 square feet (9 SM). Based on first finish coat smooth texture, the second topcoat may be reduced to 0.5 gallons (2.50L) to 100 square feet (9 SM). Coating to be White in color.

B. Brush, roll or spray the elastomeric topcoat evenly onto the surface to fully saturate the primed surfaces in one application with brush or roller: multiple applications with sprayer.

DO NOT allow coating to pond or collect in low areas.

C. Apply elastomeric topcoat up to the perimeter roof edge of the flashing terminations and penetrations.

D. Allow to cure for a minimum of twenty-four (24) hours before second finish coat.

E. DO NOT allow any excess coating to remain on the surface, the correct amount of coating will leave no fibrous surface texture from the fleece fabric. The final coating should be smooth, uniform, and bright white.

F. Dry finish (2 prime coats + 2 topcoats) thickness: 48 mils.

G. The entire roof shall be flood tested following the installation of the new waterproofing system. Drains will be temporarily blocked to create a situation for standing water. Allow water to stand for a minimum of 1 hour while inspecting the lower floors for leaks.

Maximum water depth of 100mm.

5.0 Working Hours:

5.1 On site working hours will be from 0830 in the morning till 1730 in the evening.

Every day from Monday to Saturday. Vendor may get working permission on Sunday from COR upon request.

6.0 RESPONSIBILITY OF THE CONTRACTOR

6.1 PROJECT SAFTEY:

A. Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. Contractor shall prepare a Construction Accident Prevention Plan to cover total project safety.

B. The products being used for this roof coating repair give off vapors while curing. Close and seal all doors and windows near and around work area. Close off and seal all HVAC air intake points, goose necks, and vents with duct tape and polyethylene sheeting.

Shutting down the HVAC may be necessary during the work so as not to affect the equipment.

C. The Contracting Officer and the Post Occupational Safety and Health Officer [POSHO] reserve the right to suspend work when and where Contractor’s safety and health program is operating in an inadequate or non-complying manner.

6.2 PROJECT SECURITY:

A. Personnel Clearances: Labor Background checks will require a minimum of 21 days for clearance. Local labor may be used on this Project provided that they are escorted by local embassy employees or U.S. cleared citizens.

B. Vehicle Clearances: Submit authorization requests, to include dates, vehicle type, license number, and driver name, for each motorized vehicular implement used on-site.

C. Access to Site: Contractor shall have limited access to or be admitted into the compound outside the areas designated for the project except with permission by the Embassy.

D. Access to Work Area:

1. Local Labor shall access from the EXTERIOR of the building

2. Material loading/off-loading shall be from the EXTERIOR of the building.

E. Procurement/Storage: Materials shall be procured by NON-SECURE or local means and stored NON-SECURE. All materials may be inspected prior to use on the project.

6.3 The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The

Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.

6.4 The Contractor shall identify and appoint a Project Manager who should be qualified and have experience in the field of similar projects for the management of this Contract.

Project Manager shall always be present on the site. He / She shall be able to speak and write the English language.

6.5 The Contractor shall comply with all local labor laws, regulations, customs, and practices pertaining to labor, safety, and similar matters. The Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries. USG shall not be liable for any mishap or incident happened on site due to negligence on part of contractor.

6.6 All expenses towards mobilization at site and demobilization including bringing in equipment, workforce and materials, profit, and overheads, dismantling the equipment, clearing the site etc. should be included in the rates quoted by the Contractor. No separate payment on such expenses shall be entertained.

6.7 Contractor shall provide the necessary scaffolding, overhead protection barriers, construction lift, debris chute and associated equipment for the satisfactory completion of the project.

6.8 The Contractor should arrange for the site visit of the professional in his field from the manufacturer of materials used in this project that will be providing warranties to supervise the project during work in progress.

7.0 SECURITY CLEARANCE

7.1 After Contract Award: Contractor shall collect security forms within 2 days from the

Embassy. Contractor shall complete two types of forms for their cleared workers and daily workers. The cleared workers will escort the daily workers. Forms should be filled with residence proof, date of birth, place of birth and photograph. Duly filled forms shall be submitted to the Embassy within 10 days. It takes approximate 15 days to provide the security clearance. A Notice to Proceed cannot be issued unless security clearance is obtained.

7.2 The Contractor shall inform and provide in writing transportation details (vehicle registration number, drivers & associated helpers or labor name and date of delivery) to the Embassy at least 48 hours in advance for all material and equipment deliveries.

8.0 SAFETY

8.1 Contractor is responsible and shall continue management and implementation of a safety and health program throughout construction.

8.2 The Contracting Officer and the Post Occupational Safety and Health Officer [POSHO] reserve the right to suspend work when and where Contractor's safety and health program is operating in an inadequate or non-complying manner.

8.3 Contractor shall provide all Personal Protective Equipment for the workers as per the requirement to work on scaffolding and at height. Work will be stopped in case the proper protection equipment is not found with the workers and the lapse of time shall be at the Contractor’s expense.

9.0 PERIOD OF PERFORMANCE

9.1 Contractor shall submit crew security forms, construction bar chart of complete project schedule and material product data after Contract Award.

9.2 Working hours shall be 8:00 AM to 5:00 PM Monday through Saturday. No work shall be done on Sundays and holidays unless otherwise approved.

9.3 Milestones:

Pre-proposal Site Visit: ……………………………

Pre-Construction Submittals Within 10 days of Award

Notice to Proceed: Within 10 days of Submittal Approval

Construction: 30 days on-site

Final Clean-up and Acceptance: Within 10 days before Completion

Rainy Season Months: July - September

END OF STATEMENT OF WORK