This statement of work outlines the requirements for replacing corroded natural gas lines at US Coast Guard Station Sand Key. The scope of work involves demolishing existing gas pipes to the galley and living quarters, furnishing and installing approximately 250 feet of black iron gas pipe ranging from one to two inches in diameter, installing necessary fittings including elbows, unions, and a reducer, painting all new pipe yellow, marking all new pipe, and removing and replacing the existing galvanized lines to the water heaters and female bathroom with black iron pipe. The related federal contract opportunity is a solicitation issued by the US Coast Guard under solicitation number 30321PR240000003 to obtain these gas line replacement services at Station Sand Key.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Synopsis Solicitation 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #: TBD
STATEMENT OF WORK SSK REV.01 26OCT23
LAST UPDATED: 10/26/2023 PAGE 1/2
STATEMENT OF WORK
FOR
STATION SAND KEY GAS LINE REPLACEMENT
1.0 GENERAL
1.1 BACKGROUND
USCG Station Sand Key’s gas lines are severely corroded and detiorated.
1.2 SCOPE
1. Demo Natural Gas Pipe to Galley & Living Quarters
2. Furnish and Install 100’ of 2 ½” Black Iron
3. Furnish and Install 150’ of 1 ½” Black Iron
4. 6’ of ¾” Black Iron to Water Heater
5. (4) 2 ½” Cut Offs
6. (4) 1 ½” Cut Offs
7. (4) ¾” Cut Offs
8. (1) 2 ½” to 1 ½” Reducer
9. All Pipes and Fittings Must be Painted Yellow Before Installing
10. All Pipes will be Marked
11. (10) 2 ½” Ells
12. (10) 1 ½” Ells
13. Remove All Galvanized Pipe to Water Heaters and Female Bathroom-Replace with Black Iron
14. (2) 2 ½” Unions
15. (4) 1 ½” Unions
1.3 OBJECTIVE
Restore Station Sand Key’s heavily corroded natural gas lines.
1.4 APPLICABLE DOCUMENTS
TBD
1.4.1 Compliance Documents
The following documents provide specifications, standards, or guidelines that must be complied with in order to meet the requirements of this contract:
1.4.2 Reference Documents
The following documents may be helpful to the Contractor in performing the work described in this document:
file://///hqnas/SHARED/G-A/G-ACS/CAAT%20Team/TOOLBOX/SCOPE%20PARAGRAPHS.doc
PR #: TBD
STATEMENT OF WORK SSK REV.01 26OCT23
LAST UPDATED: 10/26/2023 PAGE 2/2
2.0 SPECIFIC REQUIREMENTS/TASKS
2.1 TASK ONE. Demo Natural Gas Pipe to Galley & Living Quarters
2.2 TASK TWO. Furnish and Install 100’ of 2 ½” Black Iron
2.3 TASK THREE. Furnish and Install 150’ of 1 ½” Black Iron
2.4 TASK FOUR. 6’ of ¾” Black Iron to Water Heater
2.5 TASK FIVE. (4) 2 ½” Cut Offs
2.6 TASK SIX. (4) 1 ½” Cut Offs
2.7 TASK SEVEN. (4) ¾ Cut Offs
2.8 TASK EIGHT. (1) 2 ½ to 1 ½ Reducer
2.9 TASK NINE. ALL PIPES MUST BE YELLOW BEFORE INSTALLING
2.10 TASK TEN. ALL PIPES WILL BE MARKED
2.11 TASK ELEVEN. (10) 2 ½ Ells
2.12 TASK TWELVE. (10) ½ Ells
2.13 TASK THIRTEEN. REMOVE ALL GALVANIZED PIPE TO WATER HEATERS AND FEMALE
BATHROOM-REPLACE WITH BLACK IRON
2.14 TASK FORTEEN. (2) 2 ½ Unions
2.15 TASK FIFTEEN. (4) 1 ½ Unions
File details come from the government source that posted it. Updated .