This is a Scope of Work document for the City of St. Cloud, Florida's Chris Lyle Aquatics Center Pool Resurfacing Project (ITB #2025-227). The project involves comprehensive resurfacing and restoration services at the facility located at 2991 17th Street, St. Cloud, Florida 34769. The scope of work encompasses pre-construction site visits and scheduling, surface preparation including removal of existing finishes and repair of structural deficiencies, application of new exposed quartz finish, replacement of perimeter waterline tiles with ceramic/porcelain or clay tile, inspection and repair of coping stones, resealing of expansion and control joints, and reinstallation or replacement of pool fixtures and hardware including main drain covers, inlet fittings, skimmer components, lane anchors, handrails, and ladders. A mandatory pre-bid conference is scheduled for December 16, 2025, at 9:00 a.m. at the St. Cloud Civic Center, with written questions due by December 26, 2025, at 5:00 p.m. Bids must be submitted electronically through https://procurement.opengov.com/portal/stcloud by January 8, 2026, at 10:00 a.m. Work is scheduled to begin no earlier than February 23, 2026, with final completion required by April 6, 2026.

The estimated project cost is $302,750.00, funded through the City's General Fund. Contractors must submit a bid bond equal to five percent of the bid price, and the selected contractor must provide payment and performance bonds equal to one hundred percent of the total bid amount. Liquidated damages are set at $1,685 per calendar day for failure to meet the April 6, 2026 completion deadline. Contractor requirements include a minimum of three years of commercial pool resurfacing experience, current Florida Department of State registration, proof of surety bonding capability, general liability insurance of $1,000,000 per occurrence and $2,000,000 aggregate, workers' compensation insurance, and E-Verify compliance for all employees and subcontractors. The contractor must comply with 2 CFR Part 200 (Uniform Guidance) and the Davis-Bacon Act for prevailing wage compliance. A one-year warranty on all workmanship and materials is required, with extended manufacturer warranties where applicable. The procurement does not specify set-aside designations or restrictions on eligible organizations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work – City of St. Cloud Chris Lyle Aquatic Center Pool Resurfacing Project

1. Project Overview The purpose of this project is to restore and resurface the Chris Lyle Aquatics Center Pool located at 2991 17th Street St Cloud Florida 34769. The project will ensure the swimming pool meets current safety, health, and operational standards while extending the service life of the facility.

2. Project Location Site: Chris Lyle Aquatics Center Address: 2991 17th Street St Cloud Florida 34769.

Owner: City of St. Cloud

3. Objectives

· Repair and resurface the existing pool shell to eliminate cracks, delamination, and surface deterioration.

· Improve pool aesthetics and functionality.

· Ensure compliance with all applicable local, state, and federal codes

· Minimize pool downtime and disruption to facility operations.

4. Scope of Work

4.1 Pre-Construction

· Conduct site visit and field measurements.

· Provide a detailed work schedule and submittals for materials and finishes.

· Protect all existing structures, equipment, and landscaping during construction.

· Drain pool water per environmental and city regulations.

4.2 Surface Preparation

· Remove existing pool finish down to a sound substrate (plaster, paint, or concrete).

· Repair cracks, hollow spots, and structural deficiencies with approved patching compounds.

· Clean and acid-wash surfaces as required to ensure proper adhesion of new coating.

4.3 Resurfacing Application

· Apply new exposed quartz in accordance with manufacturer specifications.

· Ensure uniform color, texture, and thickness throughout the pool.

· Finish to smooth, non-slip, watertight surface suitable for public use.

4.4 Tile, Coping, and Joint Work

· Replace all perimeter waterline tiles with new ceramic/porcelain or clay tile (color and pattern approved by City).

· Inspect and repair coping stones or replace as directed

· Reseal all expansion and control joints with pool-grade elastomeric sealant.

4.5 Fixtures and Hardware

· Remove and reinstall or replace as needed:

· Main drain covers (VGB-compliant)

· Inlet fittings

· Skimmer throats and lids

· Lane anchors and rope hooks

· Handrails and ladders (inspect and polish or replace as required)

4.6 Filling and Start-Up

· Fill the pool with city water per standard procedures.

· Balance pool water chemistry.

· Cure and test the finish per manufacturer recommendations.

· Perform leak detection test to verify watertightness.

4.7 Clean-Up and Closeout

· Remove all debris and restore surrounding area to preconstruction condition.

· Provide as-built documentation and warranty certificates.

· Conduct final walk-through with City representative.

5. Deliverables

· Construction schedule and progress reports

· Material and product submittals

· Warranty (minimum one-year workmanship and materials)

· Final inspection report and acceptance form

6. Schedule

· Project Start Date:

· Substantial Completion:

· Final Completion:

7. Standards and References

· National Plasterers Council (NPC) guidelines

· ANSI/APSP/ICC-5 Standard for Residential Inground Pools

· Local Building and Health Codes

· ADA Accessibility Guidelines

8. Contractor Requirements

· Licensed and insured contractor with at least 10 years of commercial pool resurfacing experience.

· Provide proof of worker safety training and compliance with OSHA standards.

· Coordinate all inspections with the City’s representative.

9. Warranty

· Contractor shall provide a minimum one-year warranty on all workmanship and materials, with extended manufacturer warranties where applicable.