This Statement of Work (SOW) details a contract for replacing four malfunctioning metal doors at the U.S. Coast Guard Station Cape Disappointment, located at 322 Coast Guard Rd. in Ilwaco, Washington. The contractor will be responsible for removing existing doors and installing new metal doors that meet USCG physical security standards, including appropriate locking mechanisms compatible with the station's security system. The work must ensure proper door alignment, sealing, and functionality, with doors requiring a 20-minute fire rating in compliance with NFPA 80.
Key requirements include performing all work in a workmanlike manner following OSHA safety standards, using materials free of defects and conforming to industry standards, and maintaining a clean and safe work area. The contractor must provide a one-year warranty on workmanship and materials, dispose of removed doors and debris according to environmental regulations, and conduct all operations within authorized areas of the government premises. Work is to be performed Monday through Friday between 8:00 am and 4:00 pm, with potential for adjusted schedules if approved in advance by the Contracting Point of Contact.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions and Answers.docx | DOCX document | |
| SF1449_Solicitation_STA Cape D_Metal Door Replacement.pdf | ||
| Smart Matrix _FAR Clauses_Acquisition.GOV.pdf | ||
| 15-5549_Wage Determination_Pacific County.txt | TXT text file | |
| IMG_0415.jpeg | JPEG file | |
| IMG_0418.jpeg | JPEG file | |
| IMG_0417.jpeg | JPEG file | |
| IMG_0414.jpeg | JPEG file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
USCG STA Cape Disappointment Replace Metal Doors
USCG STA Cape Disappointment 322 Coast Guard Rd. Ilwaco, WA 98624
PART 1 - GENERAL
1 - Scope Of Work
The intent of this Statement of Work (SOW) is to have the contractor replace four malfunctioning metal doors at USCG Station Cape Disappointment. The contractor will provide all necessary labor, materials, services, equipment, and supervision to remove the existing doors and install new, operational metal doors that meet industry specifications at
322 Coast Guard Rd., Ilwaco, WA 98624.
2 - Place of Performance
USCG STA Cape Disappointment 322 Coast Guard Rd. Ilwaco, WA 98624
Contractor Personnel
Contract Manager
• The contractor must provide a contract manager who must be responsible for the performance of the work.
• The contract manager or alternate(s) must have full authority to act for the contractor on all contract matters relating to daily operation of this contract
• The contact manager and alternate or alternates must be able to read, write, speak, and understand the English language.
Contractor employees
• The contractor must not employ persons for work on this contract if such employee is considered by the contracting officer to be a potential threat to the health, safety, security, general well-being, or operational mission of the installation and its population.
• Contactor personnel must present a neat appearance and be easily recognized as contractor employees.
• The contractor must not employ any person who is an employee of the U. S.
Government if employing that person would create a conflict of interest. Additionally, the contractor must not employ any person who is an employee of the U. S. Coast
Guard unless such person seeks and receives approval according to U. S. Coast Guard regulations.
Security requirements
Due to heightened Security at USCG Facilities, all contractor employees performing tasks related to this SOW, while onboard a Coast Guard facility, shall have proper valid identification. Time spent undergoing entrance to USCG facilities will not be considered a government delay of work or differing site condition.
Hours of Operation – Projected Date of Completion
• The contractor must perform the tasks as required by the SOW under this contract during the following hours:
• Monday through Friday between 08:00 am and 16:00 pm unless other time is specified.
• Holidays: If applicable.
• Special event, or adjusted work hours: If circumstances should arise wherein the contractor desires a different work schedule as required above, the contractor must request the same in writing. Submit written request to the Contracting Point of
Contact (POC) a minimum of 24 hours before the requested adjusted work schedule.
If the desired schedule change is to be effective on a Monday, the request must be submitted to the (POC) prior to 9:00am on the Friday prior to commencement of work.
Invoicing
In conjunction with the subject award, proper invoices will be submitted through the Invoice
Processing Platform (IPP) at https://www.ipp.gov/. IPP is a secure web-based electronic invoicing system provided by the U.S. Department of the Treasury’s Bureau of the Fiscal
Service in partnership with the Federal Reserve Bank of St. Louis (FRSTL). IPP is available at no cost to any commercial vendor or independent contractor doing business with a participating government agency.
Actions to take:
If you are already enrolled in IPP:
If your company is already registered to use IPP, you will not be required to re-register and you do not need to contact IPP.
If you are NOT already enrolled in IPP:
The point of contact you provided in your SAM.gov registration will receive two emails from ipp.noreply@mail.eroc.twai.gov. Please note that emails from this email address may filter into your spam or junk folder:
1. The first email will have the IPP Logon ID and a link to the IPP application.
2. A second email, which will be sent within 24 hours of the first email, contains a temporary password.
Once your contact receives these emails, please ensure they log into IPP and complete the registration process.
Once registered to use IPP, your company may submit invoices electronically, receive e-mail notifications when requests are paid, view payment history, and access remittance downloads.
The e-mail notification of payment is sent when a payment is distributed to your bank account and may include the following payment information: Date of payment, dollar amount, invoice number, paying agency, payee name, and ACH trace number.
Vendor training materials, including a first time login tutorial, are available on the https://www.ipp.gov/ website. Once you have logged in to the IPP application, you will have access to user guides that provide step-by-step instructions for all IPP capabilities, ranging from creating and submitting an invoice to setting up email notifications. Live webinars are held monthly and provide a great opportunity to learn the basic of the system and to call in and ask the IPP team questions about the IPP application.
IPP Customer Support is available to assist users of the system and can answer your questions related to accessing IPP or completing the registration process.
• Toll-free number: 866-973-3131
• Email address: IPPCustomerSupport@fiscal.treasury.gov
• Hours of operation: Monday through Friday (excluding bank holidays) from 8:00 am -
6:00 pm ET
PART 2 - DEFINITIONS
General Definitions
When the (SOW), solicitation provision or contract clause uses a word or term that is defined in the Federal Acquisition Regulations (FAR), the word or term has the same meaning as the definition as contained in section 2.101 of the FAR. The FAR index is available via the
Internet at http://www.acqnet.gov at the end of the FAR, after the FAR Appendix.
Defective Service: A service or commodity output that does not meet the standard of performance requirement specified in the contract for that service or commodity.
Quality Assurance: A planned and systematic pattern of all government actions necessary to provide confidence that adequate technical requirements are established; products and services conform to established technical requirements; and satisfactory performance is achieved. Quality assurance refers to actions by the government assurance functions for a contracted service.
Quality Control: Those actions taken by a contractor to control the production of outputs to ensure that they conform to the contract requirements.
Technical Definitions: Not applicable to contract.
PART 3 - GOVERNMENT FURNISHED PROPERTY AND SERVICES
General Information
The Government must provide the facilities, equipment, materials, and services listed here:
Government Furnished Equipment:
The following utilities are available for use at no cost by the contractor:
• 120v power supply
• Water supply
Government Furnished Material: None.
PART 4 - CONTRACTOR FURNISHED ITEMS AND SERVICES
Except for those items, services, or commodities specifically stated in part 3 above as government furnished, the contractor must furnish everything needed to perform this contract according to all its terms.
PART 5 - SPECIFIC TASKS
The contractor shall remove four malfunctioning metal doors at USCG STA Cape
Disappointment, 322 Coast Guard Rd., Ilwaco, WA 98624. The contractor shall supply and install four new metal doors, ensuring they meet or exceed USCG physical security standards. Installation should include appropriate locking mechanisms compatible with the station's existing security system and ensure proper alignment and sealing. The contractor is responsible for all necessary labor, materials, and disposal of debris, ensuring minimal disruption to station operations during the replacement process.
DETAILED TASKS
1. The contractor shall mobilize all necessary resources, equipment, and personnel to the project site.
2. The contractor shall remove and properly dispose of four malfunctioning metal doors.
3. The contractor shall remove and properly dispose of the existing door frames for the four malfunctioning metal doors.
4. The contractor shall provide and install new door frames for the four door locations.
5. The contractor shall provide and install new metal doors to the newly installed door frames, ensuring proper functionality and compliance with all safety and security standards.
6. The contractor shall dispose of all debris and materials resulting from the removal of the malfunctioning doors and door frames.
7. The contractor shall perform demobilization upon completion of the installation, including the removal of all equipment and excess materials from the project site.
OTHER
1. Doors shall have a 20-minute fire rating in compliance with NFPA 80.
2. All work shall be performed in a workmanlike manner utilizing OSHA Safety and
Health Standards to ensure a safe working environment.
3. Material used must conform to applicable industry standards and be free of defects.
4. Installation must ensure that doors align properly, operate smoothly, and are securely anchored to withstand regular use without sagging or failing.
5. Contractor is responsible for the disposal of removed doors and any related debris following environmental and local regulations.
6. Contractor shall provide a one-year warranty on workmanship and materials used in the replacement of the doors.
7. The work area shall be kept clean and safe during construction, and any damage caused to the surrounding area during installation must be repaired without additional cost to the Government.
Interferences:
The contractor shall be responsible for any/all interferences that may be encountered while completing this SOW.
Safety:
All work shall be conducted in a safe manner and shall comply with all applicable Federal, State, and local safety standards and requirements. The US Coast Guard reserves the right to inspect for compliance with safety standards and requirements. The Contractor shall comply with all Federal, State, and local laws, including OSHA.
Operations and Storage Facilities:
The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the on-site representative with the concurrence of the Contracting Officer. The Contractor shall hold and save the Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor’s performance.
PART 6 - TESTING AND ACCEPTANCE
Testing
The contractor shall document and certify operational functionality test.
Acceptance
Acceptance on behalf of the government will be made by the POC as attested to / witnessed by signatures on the contractor generated document / form per section 6 "Testing" above.
PART 7 - APPLICABLE PUBLICATIONS AND FORMS
Publications and forms that apply to the (SOW) are listed below. The publications and forms have been designated as either mandatory or informational. The contractor is obligated to follow those publications and use those forms designated as mandatory to the extent specified in other sections of this (SOW). The contractor must be guided by those publications or use those forms designated as informational to the extent necessary to accomplish requirement in this (SOW).
Publications
OSHA Safety and Health Standards, 29 CFR Part 1926 – Safety and Health Regulations for
Construction
END