Scope of Work Large~5.docx

DOCX document 39 KB Posted

Attached to
DNR-Donnelly-Control structures
Solicitation number
21-422DNR-DIREC-B-16297
Issued by
Putnam County, Illinois

About this file

This document is a Scope of Work issued by the Illinois Department of Natural Resources for a small purchase procurement to replace a water control structure at the Donnelley/DePue State Fish and Wildlife Areas. The Vendor is required to provide, deliver, and off-load all aluminum components and appurtenances for four 48-inch diameter stop-log risers, thirty-six-inch diameter culvert pipes, fabricated aluminum stoplogs, stoplog lifting hooks, and other related materials. The project must be completed by October 31, 2020. Bids may be submitted electronically or via email, with a bid submittal date and time specified in the BidBuy solicitation. The contract will be awarded to the responsible and responsive bidder with the lowest total price. The procurement is not subject to a small business set-aside, but does include requirements related to prevailing wage rates, certified payroll, performance/payment bonds, insurance, and the use of U.S. steel products.

View the file

Other files

File Type Posted
Material_Specifications.pdf PDF
SMALL CONSTRUCTION BID FORM~71.docx DOCX document
Standard Certifications V.18.1~100.doc DOC document
Standard Terms and Conditions~12.pdf PDF
DeliveryLocation.pdf PDF
Plans_US-IL-174-13_COLEMAN_LAKE_STRUCTURE_FINAL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ILLINOIS DEPARTMENT OF NATURAL RESOURCES

SMALL PURCHASE PROCUREMENT

SCOPE OF WORK & PROJECT REQUIREMENTS

Date: July 15, 2020 File# 1-19-024

LOCATION: Donnelley/DePue SFWA

PROJECT TITLE: Replace Coleman Lake Water Control Structure

PROJECT NARRATIVE:

The Donnelley/DePue State Fish and Wildlife Areas complex is managed primarily for migratory waterfowl. Frank C. Bellrose, world-renown waterfowl expert, designated this area as an important North American waterfowl migration corridor.

Over the years, the primary water control structure at the Coleman Lake waterfowl area has deteriorated to the point of having to be replaced. In a coordinated effort with Ducks Unlimited, this repair effort is currently planned to take place this year. As a first step, materials to replace the water control structure shall be purchased.

SCOPE OF WORK:

The Vendor shall provide, deliver and off-load all the aluminum cmp (corrugated metal pipe) components and appurtenances, fabricated and non-fabricated, identified in the verbiage below and detailed in the attachments.

· Four (4) forty-eight-inch (48”) diameter, 12 gage, aluminum cmp stop-log riser(s) with an overall height measuring 6’-6”. Each cmp riser shall be fabricated to include: three inch (3”) channel gate frame extending four inches (4”) above the riser, three inch (3”) angle facing down for concrete placement, three inch (3”) angle interior brace (2@top, every 2’ down), 1/8” water seal, interior bracket for lifting hook, 3/16” 5052 aluminum plate security cover with ¼’ x 2” trap door and ¾” locking rod, two (2) 36” diameter x two-foot (2’) long inlet and outlet stubs with flanged ends located six inches up from the bottom. See attached specifications and drawings for details.

· Four (4) thirty-six-inch (36”) diameter, 12 gage, aluminum corrugated metal culvert pipes each measuring fourteen feet (14’) in length with one end flanged. See attached specifications and drawings for inlet details.

· Four (4) thirty-six-inch (36”) diameter, 12 gage, aluminum corrugated metal culvert pipes each measuring thirty feet (30’) in length with one end flanged. See attached specifications and drawings for outlet details.

· One (1) complete set of fabricated aluminum stoplogs, with lifting pins, for each aluminum cmp raiser. Each fabricated riser shall contain a total of fifteen (15) stoplogs; thirteen (13) 2”x6”x3/4” x 48” aluminum stoplogs, one (1) 2”x3”x1/4 x 48” aluminum stoplog and one (1) 2”x2”x1/4” x 48” aluminum stoplog. See attached specifications and drawings for details.

· Two pair (4 each) stoplog lifting hooks.

· Stainless steel bolt sets and gaskets for flange connection. Bolt sets and flange gaskets shall correspond to the number of flanged connections.

· Four beaver control device guards

· Culvert anchors and stainless-steel cables per the drawings. Minimum of two (2) complete sets for each structure.

ATTACHMENTS:

The following documents are included:

1) Material and Product Specifications

2) Design Drawings and Details

3) Delivery location aerial photos

PROJECT SPECIFICATIONS & REQUIREMENTS:

A.Project Specifications:
1)The awarded Vendor must have 5 years of experience in the commercial aluminum corrugated metal culvert fabrication industry and be able to provide documentation of providing similar products and materials for projects similar in size and scope to this one prior to Bid Award.

2) The awarded Vendor shall provide for the delivery and off-loading of the finished products and materials identified in the scope of work.

B.Project Instructions and Notes:
1)Work Completed by Prime Contractor:

A minimum of thirty percent (30%) of the work shall be completed by the Prime Contractor on this project. Pursuant to (30 ILCS 500/1-15.17) the Contractor is the person having a contract with the Illinois Department of Natural Resources.

2) Coordination of Work Activities:

All work activities and entry to the site must be coordinated with the site superintendent whose contact information is listed in the Project Contacts. Notice of product/material delivery shall be provided a minimum of forty-eight (48) hours prior. Vendor shall provide for all transportation and off-loading of products and materials without any assistance from site staff.

3) Deliverables:

N/A

4) Independent Testing:

The Contractor shall pay all independent laboratory testing, if needed.

5) Contractor’s Licensing and/or Certifications:

Contractor shall be responsible for compliance with all applicable contractor and trades person licensing with the appropriate State agency.

6) Shop Drawings:

Submit for the approval of the DNR Project Architect/Engineer, shop drawings and product data for the following items prior to Bid Award:

a. Aluminum Water Control Structure

b. Aluminum CMP

c. Aluminum Stoplogs

C.Project Requirements:
1)Project Meeting
PROJECT MEETING TO BE HELD: NO
MANDATORY ATTENDANCE: NO
2)Duration
Bids shall be good for ninety (90) calendar days after the Bid Opening Date.
3)Prevailing Wage Rates
This contract [or agreement] calls for the construction of a “public work,” within the meaning of the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires contractors and subcontractors to pay laborers, workers and mechanics performing services on public works projects no less than the current “prevailing rate of wages” (hourly cash wages plus amount for fringe benefits) in the county where the work is performed. The Illinois Department of Labor (IDOL) publishes the prevailing wage rates on its website at https://www2.illinois.gov/idol/laws-rules/conmed/pages/rates.aspx. IDOL revises the prevailing wage rates and the contractor/subcontractor has an obligation to check the IDOL’s web site for revisions to prevailing wage rates. For information regarding current prevailing wage rates, please refer to IDOL’s website. All contractors and subcontractors rendering services under this contract must comply with all requirements of the Act, including but not limited to, all wage requirements and notice and record keeping duties.
4)Certified Payroll
State law 820 ILCS 130/5 requires all contractors and sub-contractors working on state
construction projects to submit certified payroll records to the Department of Natural
Resources. The payroll records must include all workers employed by contractors on the
project.

In accordance with 820 ILCS 130/5, the contractor and sub-contractor(s) shall make and keep, for a period of 5 years from the date of the last payment made on or after January 1, 2014 (the effective date of Public Act 98-328) on a contract or subcontract for public works, records of all laborers, mechanics, and other workers employed by them on the project.

No later than the 15th day of each calendar month, the contractor shall file a certified payroll for the immediately preceding month with the Department of Natural Resources.

5) Small Business Set-Aside N/A

6)Subcontractors
The Contractor shall identify the names of all subcontractors to be utilized by them in the
performance of this contract, together with the anticipated amount of money that each
subcontractor is expected to receive pursuant to this contract. Pursuant to Illinois Procurement
Code (30 ILCS 500/1-15-108), a person or entity is not a “subcontractor” if that person only
Provides goods or supplies that are incidental to the performance of a contract by a person
who has a contract subject to the Code.
7)Insurance
Contractor shall, at all times during the term of this contract and any renewals or extensions, maintain and provide a Certificate of Insurance naming the State as an additionally insured for all required bonds and insurance. Certificates may not be modified or canceled until at least thirty (30) days’ notice has been provided to the State. Contractor shall provide: (a) General Commercial Liability insurance in the amount of $1,000,000 per occurrence (Combined Single Limit Bodily Injury and Property Damage) and $2,000,000 Annual Aggregate; (b) Auto Liability, including Hired Auto and Non-owned Auto (Combined Single Limit Bodily Injury and Property Damage), in amount of $1,000,000 per occurrence; and (c) Worker’s Compensation Insurance in the amount required by law. Insurance shall not limit Contractor’s obligation to indemnify, defend, or settle any claims.

8) Performance Bond/Labor and Material Payment Bond Pursuant to the Public Construction Bond Act (30 ILCS 550/), a performance bond and a labor and material payment bond covering the faithful performance of the contract and the payment of all obligations arising thereunder, shall be required if the project cost exceeds $50,000. Each bond shall be in the full amount of the contract. The bond must be from a surety licensed to do business within the State of Illinois and acceptable to IDNR.

9) Minority Contractor Opportunity Initiative The State requires a fee of $15 to cover Expenses related to the administration of the Minority Contractor Opportunity Initiative. Any Vendor awarded a contract under Section 20-10, 20-15, 20-25 or 20-30 of the Illinois Procurement Code (30 ILCS 500) of $1000 or more is required to pay a fee of $15. The Comptroller shall deduct the fee from the first check issued to the Vendor under the contract and deposit the fee in the Comptroller’s Administrative Fund.

10) Permits and Licenses Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.

11) Utilities Before starting excavation, establish location and extent of underground utilities occurring in the work area. Contractor shall contact Joint Utility Locating Information for Excavators (J.U.L.I.E.) 800-892-0123.

12) Highway Permits The Contractor is responsible for contacting the appropriate County Superintendent(s) of Highways and/or other appropriate local officials concerning the proposed work activities on the project as they may relate to use of the County and local road system. Coordination of any activities of concern to the County or Township shall be the responsibility of the Contractor. Special attention shall be given to load limits and seasonal restrictions.

13) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.

14)Steel Products
Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/).

15) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.

16) Final Cleaning Contractor shall clean-up all work related debris and construction materials and properly dispose off-site. The Contractor shall repair and otherwise make good any damage caused by the work and leave the premises in the equivalent of the original condition.

17) Warranties The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of one year from the goods acceptance date. See Section B. Project Instructions and Notes, for any extended warranties that may apply.

18) Change Orders Change order shall be defined as a change in a contract term, other than as specifically provided for in the contract, which authorizes or necessitates any increase or decrease in the cost of the contract or the time for completion. A change order shall be executed by the State agency and vendor evidencing the change. All changes shall be approved by the CPO, or designee, and be accompanied by a written determination that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed and the change is germane to the original contract as signed. Change orders that increase or decrease the cost of a contract or an estimated contract by a total of $10,000 or more or the time of completion by more than 30 days shall be published on the Illinois Procurement Bulletin, pursuant to Section 15-25 of the Code and documented pursuant to Section 33E-9 of the Criminal Code of 2012, in advance of execution of the change order.

19) Inducement Resolution All or a portion of this project may be paid or reimbursed from the proceeds of tax-exempt bonds subsequently issued by the State.

20) Payment Payments, including late payment charges, will be paid in accord with the State Prompt Payment Act and rules when applicable, 30 ILCS 540/; 74 III. Adm. Code 900. This shall be the Contractor’s sole remedy for late payments by the State. Payment terms contained in Contractor’s invoice(s) shall have no force or effect.

21)Contract Award
Contract award will be made to the responsible and responsive bidder with the lowest total price. The Department of Natural Resources reserves the right to reject any or all bids.
22)Term of Contract
All work shall be completed by October 31, 2020.

23) Bid Submittal Bids may be submitted electronically on BidBuy or by submitting the attached Bid Form to Frederick.Murphy@illinois.gov .

24)Bid Submittal Date and Time
Refer to the BIDBUY solicitation for the bid date and time.

25) Questions

ALL QUESTIONS PERTAINING TO THE SCOPE OF WORK OR THE BIDBUY PROCEDURES, MUST

BE DIRECTED TO Frederick.Murphy@Illinois.gov ALL QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN THREE (3) BUSINESS DAYS BEFORE THE BID DATE.