Scope of Work - Large~41.docx
DOCX document 45 KB Posted
- Solicitation number
- 23-422DNR-DIREC-B-33504
- Issued by
- St. Clair County, Illinois
About this file
The document is a Scope of Work provided by the Illinois Department of Natural Resources (IDNR) for a small purchase procurement to replace two existing above ground fuel storage tanks at the Sangchris Lake State Park in Sangamon County, Illinois. The project involves removing the existing 1,000-gallon diesel and 1,300-gallon dual compartment gasoline tanks, and installing two new 1,000-gallon double walled steel tanks, one for diesel and one for gasohol, along with all required piping, pumps, meters, and safety equipment. The contractor must obtain the necessary permits and approvals from the Office of the State Fire Marshal prior to installation. The work must be completed within 180 days of contract execution, and the contractor must provide training to IDNR staff and a one-year warranty on the equipment and installation.
The contract will be awarded to the lowest responsive and responsible bidder. It is subject to the Illinois Prevailing Wage Act, and the contractor must utilize a minimum of 50% of the work with their own forces. Bidders must also comply with requirements related to COVID-19, subcontractor reporting, minority contractor initiatives, and use of Illinois-manufactured steel products. Payment will be made in accordance with the State Prompt Payment Act.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Location Map and Site Photos~1.pdf | ||
| 2Standard Terms and Conditions 20.1~7.pdf | ||
| 2SMALL CONSTRUCTION BID FORM1~24.docx | DOCX document | |
| Attachment 2 - 33 56 13 Aboveground Storage Tank Istallation.pdf | ||
| 1Standard CertificationsV.18.1~98.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINOIS DEPARTMENT OF NATURAL RESOURCES
SMALL PURCHASE PROCUREMENT
SCOPE OF WORK & PROJECT REQUIREMENTS
Date: November 28, 2022 File # 4-23-022
| LOCATION: | Sangchris Lake State Park | |
| 9898 Cascade Rd., Rochester, IL 62563 | ||
| Sangamon County |
PROJECT TITLE: Replace Above Ground Fuel Storage Tanks
PROJECT NARRATIVE:
This project will consist of replacing the two (2) existing double walled fuel storage tanks, due to inaccurate data plates, moisture concerns, and issues with fuel reconciliation. The tanks are located at the Sangchris Lake State Park main office/shop area. Sangchris Lake SP is located approximately 9.5 miles southeast of Rochester, Illinois, in Sangamon County.
The project will include removal of the existing tanks and equipment, and installing two (2) steel, double walled vented fuel storage tanks: 1 – 1,000 gallon diesel tank and 1 – 1,000 gallon gasohol tank and all pertinent piping, pumps, meters and hardware. The fuel storage system must be installed per the National Electric Code (NEC) and the Office of the State Fire Marshal (OSFM) requirements for aboveground fuel dispensing storage tanks per Title 41 of the Illinois Administrative Code, Ch. I, Section 180.20 “Aboveground Storage – Dispensing”.
SCOPE OF WORK:
The contractor will provide all labor, equipment and materials needed to install a new fuel storage system in accordance with 41 Ill. Adm. Code, Ch. I, Section 180.20 “Aboveground Storage – Dispensing”. The Contractor is required to file a permit application with the OSFM prior to installation and have the tanks inspected by the OSFM prior to filling. Copies of all sign-offs and approvals by the OSFM should be provided for DNR’s files.
The following items shall be addressed:
| 1) | The existing tanks – one 1,000 gallon diesel and one 1,300 gallon dual compartment gasoline – shall have their fuel temporarily offloaded into suitable containers until the new tanks are installed, and then be dismantled and properly disposed of per the Office of the State Fire Marshal Code and per EPA. Dispensing equipment, including pumps and meters, shall be turned over to IDNR. | |
| 2) | The new tanks will be installed on the existing reinforced concrete pad in the same location and orientation as the current tanks. The Contractor shall provide the proper and required equipment to lift from above and vertically remove and install the new tanks without damaging the existing bollards. A crane or high lift boom equipment may be required. | |
| 3) | Provide one (1) single compartment double walled steel aboveground storage tank (AST) that meets all requirements per Section 180.20 of the State Fire Marshal Code and referenced sections that may apply to fuel storage and dispensing of 1,000 gallons of diesel fuel. The pump for this tank shall have vanes specifically designed for the use with diesel fuel. | |
| 4) | Provide one (1) single compartment double walled steel above ground storage tank (AST) that meets all requirements per Section 180.20 of the State Fire Marshal Code and referenced sections that may apply to fuel storage and dispensing of 1,000 gallons of gasohol fuel. | |
| 5) | All associated metering devices, pumps, dispensers, safety equipment and on/off devices shall be installed as new equipment and be calibrated by the installer for the individual fuel types. All appurtenant devices shall be installed per manufacturer’s recommendations. | |
| 6) | The existing electrical service and safety switch for emergency shut-off are to remain up to the existing rigid metal conduit stub-up location in center of existing concrete pad. Contractor to extend new wiring in rigid metal conduit from that location to new equipment and reconnect existing light. Bond and ground all tanks and equipment to existing ground rod(s), and install additional rods if necessary. | |
| 7) | All electrical connections must have seal-offs per NFPA and Fire Marshal Code requirements. | |
| 8) | Provide all new emergency shut-off signage for existing disconnect. Sign shall say “EMERGENCY DISCONNECT SWITCH | FUEL PUMPS”. Letters on sign shall be 2” high and meet State Fire Marshal requirements. |
| 9) | Vent pipe size & height, top-fill with lockable enclosures, labeling size & color, off-set distance from other buildings, anti-siphoning devices, dispensing hoses & handles, break-away connections, and all pertinent components of the fueling systems must all meet the State Fire Marshal Codes and requirements for this installation. | |
| 10) | Ladders shall be provided on the exterior of the fuel pumps for safe access to the fill location, pump maintenance and meter readings. | |
| 11) | Provide one new 20 lb. Tri-Class dry chemical fire extinguisher and system on/off indicator light. | |
| 12) | Vapor lock preventers shall be installed per manufacturer’s recommendations. | |
| 13) | All permitting, calibration, inspections, and coordination with OSFM required to provide a fully functional commissioned system. | |
| 14) | Site cleanup and restoration to pre-construction conditions. |
ATTACHMENTS:
The following documents are included:
1) Location Map and Existing Site Photos
2) Specification Section 33 56 13 Aboveground Storage Tank Installation.
PROJECT SPECIFICATIONS & REQUIREMENTS:
| A. | Project Specifications: |
| 1) Contractor is responsible to verify all measurements and access prior to bidding. |
2) Contractor is responsible for locating and verifying the location of all utilities.
3) The Contractor is responsible for completing and filing for an AST Dispensing Application with the Office of the Illinois State Fire Marshal. The application can be found on the State Fire Marshal’s website.
B. Project Instructions and Notes:
1) Work Completed by Prime Contractor:
A minimum of fifty percent (50%) of the work shall be completed by the Prime Contractor on this project. Pursuant to (30 ILCS 500/1-15.17) the Contractor is the person having a contract with the Illinois Department of Natural Resources.
| 2) | Coordination of Work Activities: |
| All work activities and entry to the site must be coordinated with the Site Superintendent. |
3) Deliverables and Staff Training:
Two (2) sets of operating and maintenance manual and start-up procedures shall be provided to DNR. DNR staff shall receive one hour proper training and instruction on the operation and maintenance of all new equipment, prior to payment of work.
| 4) | Independent Testing: |
| The Contractor shall pay to have the pumps calibrated prior to closing out the project; results | must be provided to the Site Superintendent. |
5) Contractor’s Licensing and/or Certifications:
Contractor shall be responsible for compliance with all applicable contractor and trades person licensing with the appropriate State agency. This includes, but is not limited to:
a. AST Storage Tanks - Office of the State Fire Marshal
b. Licensed Electrician - for installation
6) Product Data:
Submit for the approval of the DNR Project Engineer and Site Superintendent shop drawings and product data for the following items prior to starting work and ordering: tanks, piping, hoses, vents, break-aways, top-fill equipment, disconnects, ladders, liquid level gauge, fill ports, leak detector, ground rod, emergency fuel shut-off switch and explosion proof seal-off.
| 7) | Warranty: | |
| The tanks, equipment, installation and miscellaneous equipment will have a one-year warranty, | unless otherwise specified by the manufacturers. |
C. Project Requirements:
| 1) | Project Meeting |
| PROJECT MEETING TO BE HELD: NO | |
| MANDATORY ATTENDANCE: NO |
| 2) | COVID-19 Requirements |
| In response to the COVID-19 pandemic, Governor J.B. Pritzker issued Executive Order 2021-22 and 2021-23. These Executive Orders mandate certain contractors shall use face coverings, have COVID-19 vaccinations, or undergo testing for COVID-19 when in indoor public places, Health Care Facilities, Schools, Institutions of Higher Education, and State-owned and operated congregate facilities. Vendor shall adhere to the requirements of these Executive Orders as applied by the Agency. The Agency may also implement vaccination or testing requirements that exceed those in the Executive Orders. |
3) Duration Bids shall be good for ninety (90) calendar days after the Bid Opening Date.
| 4) | Prevailing Wage Rates |
| This contract [or agreement] calls for the construction of a “public work,” within the meaning of the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires contractors and subcontractors to pay laborers, workers and mechanics performing services on public works projects no less than the current “prevailing rate of wages” (hourly cash wages plus amount for fringe benefits) in the county where the work is performed. The Illinois Department of Labor (IDOL) publishes the prevailing wage rates on its website at https://www2.illinois.gov/idol/laws-rules/conmed/pages/rates.aspx. IDOL revises the prevailing wage rates and the contractor/subcontractor has an obligation to check the IDOL’s web site for revisions to prevailing wage rates. For information regarding current prevailing wage rates, please refer to IDOL’s website. All contractors and subcontractors rendering services under this contract must comply with all requirements of the Act, including but not limited to, all wage requirements and notice and record keeping duties. |
| 5) | Certified Payroll |
| State law 820 ILCS 130/5 requires all contractors and sub-contractors working on state construction projects to submit certified payroll records to the Department of Natural Resources. The payroll records must include all workers employed by contractors on the project. |
In accordance with 820 ILCS 130/5, the contractor and sub-contractor(s) shall make and keep, for a period of 5 years from the date of the last payment made on or after January 1, 2014 (the effective date of Public Act 98-328) on a contract or subcontract for public works, records of all laborers, mechanics, and other workers employed by them on the project.
No later than the 15th day of each calendar month, the contractor shall file a certified payroll for the immediately preceding month with the Department of Natural Resources.
6) Employment of Public Workers on Public Works:
In a period of excessive unemployment rates, State contractors (1) constructing or building any public works or (2) cleaning-up and disposing on-site of hazardous waste, and that clean-up or on-site disposal is funded or financed in whole or in part with State funds or funds administered by the State, are required to employ at least 90% Illinois laborers on such project. For projects involving clean-up and on-site disposal of hazardous waste, emergency response or immediate removal activities are excluded. This requirement applies to all labor whether skilled, semi-skilled or unskilled, whether manual or non- manual.
A period of excessive unemployment rates is defined as any month immediately following two consecutive calendar months during which the level of unemployment in the State of Illinois has exceeded 5% as measured by the United States Bureau of Labor Statistics in its monthly publication of employment and unemployment figures.
Any public works project financed in whole or in part by federal funds administered by the State of Illinois is covered under the provisions of this requirement, to the extent permitted by any applicable federal law or regulation. 30 ILCS 570.
Contractors may receive an exception from this requirement by submitting a request and supporting documents certifying that Illinois laborers are either not available or are incapable of performing the particular type of work involved. The certification must: (a) be submitted to the agency within the first quarter of the Contract Term; (b) provide sufficient support that demonstrates the exception is met; (c) be signed by an authorized signatory of the contractor; and (d) be approved by the agency.
7) Small Business Set-Aside N/A
8) Apprenticeship-in-Training When applicable, the contractor and all subcontractors must be participants in apprenticeship and training programs that are both approved by and registered with the U.S. Department of Labor’s Bureau of Apprenticeship and Training. The program(s) must be in the same trade(s) in which the contractor or subcontractor performs work. For information on how to participate in or set up a program, contractors may call the U.S. Department of Labor at 312/596-5508 or visit their website http://www.doleta.gov/oa/ .
9) Illinois Office The bidder must certify that the bidder will maintain an Illinois office as the primary place of employment for persons employed in the construction authorized by the contract.
| 10) | Subcontractors |
| The Contractor shall identify the names of all subcontractors to be utilized by them in the performance of this contract, together with the anticipated amount of money that each subcontractor is expected to receive pursuant to this contract. Pursuant to Illinois Procurement Code (30 ILCS 500/1-15-108), a person or entity is not a “subcontractor” if that person only Provides goods or supplies that are incidental to the performance of a contract by a person who has a contract subject to the Code. |
| 11) | Insurance |
| Contractor shall, at all times during the term of this contract and any renewals or extensions, maintain and provide a Certificate of Insurance naming the State as an additionally insured for all required bonds and insurance. Certificates may not be modified or canceled until at least thirty (30) days’ notice has been provided to the State. Contractor shall provide: (a) General Commercial Liability insurance in the amount of $1,000,000 per occurrence (Combined Single Limit Bodily Injury and Property Damage) and $2,000,000 Annual Aggregate; (b) Auto Liability, including Hired Auto and Non-owned Auto (Combined Single Limit Bodily Injury and Property Damage), in amount of $1,000,000 per occurrence; and (c) Worker’s Compensation Insurance in the amount required by law. Insurance shall not limit Contractor’s obligation to indemnify, defend, or settle any claims. |
12) Performance Bond/Labor and Material Payment Bond Pursuant to the Public Construction Bond Act (30 ILCS 550/), a performance bond and a labor and material payment bond covering the faithful performance of the contract and the payment of all obligations arising thereunder, shall be required if the project cost exceeds $50,000. Each bond shall be in the full amount of the contract. The bond must be from a surety licensed to do business within the State of Illinois and acceptable to IDNR.
13) Minority Contractor Opportunity Initiative The State requires a fee of $15 to cover Expenses related to the administration of the Minority Contractor Opportunity Initiative. Any Vendor awarded a contract under Section 20-10, 20-15, 20-25 or 20-30 of the Illinois Procurement Code (30 ILCS 500) of $1000 or more is required to pay a fee of $15. The Comptroller shall deduct the fee from the first check issued to the Vendor under the contract and deposit the fee in the Comptroller’s Administrative Fund.
14) Permits and Licenses Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.
15) Utilities Before starting excavation, establish location and extent of underground utilities occurring in the work area. Contractor shall contact Joint Utility Locating Information for Excavators (J.U.L.I.E.) 800-892-0123.
16) Highway Permits The Contractor is responsible for contacting the appropriate County Superintendent(s) of Highways and/or other appropriate local officials concerning the proposed work activities on the project as they may relate to use of the County and local road system. Coordination of any activities of concern to the County or Township shall be the responsibility of the Contractor. Special attention shall be given to load limits and seasonal restrictions.
17) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.
| 18) | Steel Products |
| Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/). |
19) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.
20) Final Cleaning Contractor shall clean-up all work related debris and construction materials and properly dispose off-site. The Contractor shall repair and otherwise make good any damage caused by the work and leave the premises in the equivalent of the original condition.
21) Warranties The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of one year from the goods acceptance date. See Section B. Project Instructions and Notes, for any extended warranties that may apply.
22) Change Orders Change order shall be defined as a change in a contract term, other than as specifically provided for in the contract, which authorizes or necessitates any increase or decrease in the cost of the contract or the time for completion. A change order shall be executed by the State agency and vendor evidencing the change. All changes shall be approved by the CPO, or designee, and be accompanied by a written determination that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed and the change is germane to the original contract as signed. Change orders that increase or decrease the cost of a contract or an estimated contract by a total of $10,000 or more or the time of completion by more than 30 days shall be published on the Illinois Procurement Bulletin, pursuant to Section 15-25 of the Code and documented pursuant to Section 33E-9 of the Criminal Code of 2012, in advance of execution of the change order.
23) Inducement Resolution All or a portion of this project may be paid or reimbursed from the proceeds of tax-exempt bonds subsequently issued by the State.
24) Payment Payments, including late payment charges, will be paid in accord with the State Prompt Payment Act and rules when applicable, 30 ILCS 540/; 74 III. Adm. Code 900. This shall be the Contractor’s sole remedy for late payments by the State. Payment terms contained in Contractor’s invoice(s) shall have no force or effect.
| 25) | Contract Award |
| Contract award will be made to the lowest, responsible, responsive bidder. The Department of Natural Resources reserves the right to reject any or all bids. |
| 26) | Term of Contract |
| All work shall be completed with 180 days of contract execution. |
27) Bid Submittal Bids may be submitted electronically on BidBuy or by submitting the attached Bid Form.
| 28) | Bid Submittal Date and Time |
| Refer to the BIDBUY solicitation for the bid date and time. |
29) Questions ALL QUESTIONS PERTAINING TO THE SCOPE OF WORK OR THE BIDBUY PROCEDURES, MUST BE DIRECTED TO Frederick.Murphy@Illinois.gov ALL QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN THREE (3) BUSINESS DAYS BEFORE THE BID DATE.
30) Project Contacts: The following individuals are listed as project contacts during the construction phase. The Bidder may not communicate directly with any of these individuals during the bidding process. All communication during the bidding phase must be directed to the Frederick.Murphy@Illinois.gov email address.