Scope of Work Gate with Cipher Lock.pdf

PDF 190 KB Posted

Attached to
Gate with Cipher Lock
Solicitation number
FA4600GateCipherLock
Issued by

About this file

This document is a Unit Developed Scope of Work for the Delta Fence Project by the 55th AMXS (Air Maintenance Squadron) at Offutt Air Force Base. The project requires installing a gate with a cipher lock in the hallway between Deltas 1 and 2 at the Bennie Davis Maintenance Facility to restrict unauthorized personnel access. The specific construction requirements include securing fence posts to the ground/walls, installing a chain-link fence, and implementing a KABA Simplex 1021B cipher lock or similar government-approved lock with a changeable code.

The contractor responsibilities encompass obtaining all necessary security and safety clearances, permits, and approvals, performing a mandatory pre-bid site visit, breaking down the bid into materials and labor line items, and completing the installation in compliance with federal safety standards. Additional requirements include cleaning and restoring the site within 10 workdays after project completion, removing debris, repairing any government property damage, and ensuring all work meets environmental and civil engineering regulations. Bonding may be required, and contractors must coordinate closely with the facility manager to schedule and execute the work.

View the file

Other files

File Type Posted
B457 Proposed Gate Map.pdf PDF
E21 Power Plan Area J.PDF PDF
E20 Power Plan Area H.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Unit Developed Scope of Work

FOR

Delta Fence Project 55th AMXS

Objectives: The 55th AMXS is requesting a gate with a cipher lock be put up in the hallway between Deltas 1&2. The gate will be next to the opening closest to Delta 1.

Justification: The gate would block unauthorized personnel from reaching restricted areas of the Bennie Davis Maintenance Facility. Delta 1 is a “free zone” used for various functions around the base, and currently, personnel can get into restricted areas with minimal restriction; this would add a barrier for them to get into restricted areas

Description of services: Project includes, but not limited to the following work elements. Use system components below to define scope of requirements.

1. Interior Construction Requirement

a. Fence posts secured to the ground and/or walls in a fashion that they could not be manipulated to move

b. Chain-link fence to fill in the space between gate and the walls/fence posts.

c. Install gate with cipher lock KABA Simplex 1021B or similar equipment approved by the government that code can be changed.

Acceptance Criteria: Work will be considered acceptable after all the following conditions are met

1. When a gate is installed with a cipher lock that can be changed.

2. All loose and unnecessary supplies and items associated with the work contained in this SOW have been removed from the work site and properly disposed of.

Other Requirements

1. Ensure all construction meets federal regulations for safety standards.

2. Bonding is required (if applicable).

3. The contractor is required to perform a site visit prior to and must coordinate with the facility manager to schedule work to be performed.

4. All security requirements must be met to include times of demolition and construction.

5. The contractor is required to perform a site visit prior to bid. Contractor who are not present will not be in consideration.

6. Bid shall be broken down to materials and labor as individual line items.

7. The Contractor shall furnish all required services, labor, tools, material, and equipment necessary to complete the installation and integration of the prime mission equipment in accordance with the approved site design and installation plan. In addition, the Contractor shall be responsible for the following actions:

a. Obtaining all necessary security and safety clearances for facilities and personnel. This includes obtaining escort badges necessary for unaccompanied work within the area.

b. Obtaining necessary certifications for installation equipment and technologies to be installed.

c. Obtaining environmental and life safety approvals.

d. Acquiring all necessary federal, state, local and base environmental and civil engineering permits and approvals.

e. Cleaning-up and restoring the site to its original or better condition within 10 workdays after project completion.

f. Repairing damage to Government property resulting from contractor activities, assuring the property is returned to its original or better condition.

g. Removing all debris at the end of each shift or more frequently if required to keep the work area safe and useable.

h. Disposing of excess equipment and materials in accordance with General Requirements.