This Scope of Work document outlines HVAC duct cleaning and related services for the Maryland Department of Natural Resources at the Tawes Building located at 580 Taylor Avenue in Annapolis, Maryland. The project encompasses comprehensive cleaning and restoration of HVAC ductwork, air handling components, and ventilation systems throughout the facility. Services include removal and cleaning of registers, vents, grilles, and diffusers; drop ceiling access and tile removal; selective insulation removal; installation of access ports; use of agitation devices such as industrial brushes and compressed air; HEPA vacuum collection with multi-stage filtration systems capable of 2,500-5,000 CFM at 4-5" static pressure; optional microbial treatment using EPA-registered products; protective coatings where required; cleaning of Variable Air Volume (VAV) boxes, reheat coils, and air handling units (AHUs); and post-cleaning inspections and access port sealing. All work must comply with industry standards established by the National Fire Protection Association (NFPA), North American Insulation Manufacturers Association (NAIMA), National Air Duct Cleaners Association (NADCA), Sheet Metal and Air Conditioning Contractors Association (SMACNA), and Underwriters Laboratories (UL). The contractor shall furnish all labor, materials, equipment, supervision, and tools necessary to complete the work, with coordination required with the Superintendent or designee. Areas requiring occupant evacuation may necessitate weekend or after-hours work scheduling.

The project includes comprehensive post-cleaning inspection and certification procedures, with contractors required to conduct final walk-throughs with the Building Manager and obtain sign-off on a Certificate of Completion. Access port closure requirements mandate airtight removable plates or doors mechanically fastened every 4 inches on center and sealed with UL-181A tape, gasket, or mastic. While completion of OSHA Outreach Training (10-hour and/or 30-hour) is desirable, it is not mandatory. No pricing information, set-asides, incumbent contractors, funding sources, or contract award dates are specified in this scope of work document. The related contract opportunity indicates the project has been cancelled.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Scope of Work Details Project: HVAC Duct System Cleaning and Related Services Location: 580 Taylor Avenue, Maryland Department of Natural Resources – Tawes Building, Annapolis, MD D-

POD

1. Project Overview This Scope of Work (SOW) outlines requirements for the cleaning and restoration of HVAC ductwork, air handling components, and ventilation systems throughout the Tawes Building. All work shall be performed in accordance with the following industry standards:

● National Fire Protection Association (NFPA)

● North American Insulation Manufacturers Association (NAIMA)

● National Air Duct Cleaners Association (NADCA)

● Sheet Metal and Air Conditioning Contractors Association (SMACNA)

● Underwriters Laboratories (UL)

Completion of OSHA Outreach Training (10-hour and/or 30-hour) is desirable but not mandatory.

The Contractor shall furnish all labor, materials, equipment, supervision, and tools necessary to complete the work.

2. Scope of Services

2.1 Removal and Cleaning of Registers, Vents, Grilles, and Diffusers

1. Remove all registers, vents, grilles, and diffusers as needed.

2. Vacuum and/or hand-wash all components to remove dust, dirt, and debris.

○ Cleaning shall improve appearance and indoor air quality.

2.2 Drop Ceiling Access

3. Remove drop ceiling tiles as required to gain access to the duct system.

4. Report damaged ceiling tiles to the Building Manager.

5. Reinstall ceiling tiles after work is completed.

2.3 Insulation Removal (As Needed)

6. Remove exterior insulation, where necessary, by cutting clean access points using appropriate tools.

2.4 Installation of Access Ports

7. Install access ports in ductwork as required for complete system access and source removal.

Ports shall comply with NFPA, NAIMA, NADCA, SMACNA, and UL guidelines.

Access Ports Shall Permit:

a. Full reach of internal duct surfaces

b. Complete source removal

2.5 Use of Agitation Devices

Industrial Brushes (If Applicable)

8. Utilize industrial brushes to loosen debris.

○ Brushes shall be selected based on duct size and type of surface.

Compressed Air (If Applicable)

9. Use compressed air to loosen debris within ductwork.

○ Main and side runs may be isolated and cleaned separately.

2.6 Vacuum Collection Requirements

All vacuum collection equipment must utilize High-Efficiency Particulate Arrestance (HEPA) filtration.

High-Powered HEPA Vacuum Systems

10. Use negative pressure equipment during brushing and compressed air cleaning.

○ Minimum capability: 2,500–5,000 CFM with 4–5" static pressure

○ Multi-stage filtration including pre-screen, bag filter, and HEPA filter

Portable HEPA Vacuums

11. Use industrial-grade portable HEPA vacuums for close-access cleaning.

2.7 Microbial Treatment (If Applicable)

12. Apply an EPA-registered bacteriostat/fungistat/deodorizer, such as EnviroCon, where applicable.

○ Non-aerosol formulations only

○ The application may require airless fogging equipment

Note: No product may be represented or applied as a ductwork “sanitizer,” as none are EPA-approved for that purpose.

2.8 Protective Coatings (If Applicable)

13. Apply protective coatings to interior insulation or metal duct surfaces when required.

○ Product data and application specifications must be submitted to the Owner for approval.

2.9 Variable Air Volume (VAV) Boxes (If Applicable)

14. Create access ports if needed.

a. HEPA vacuum interior surfaces

b. Secure loose wiring

c. Inspect insulation and report damage

2.10 Reheat Coils (If Applicable)

15. Access coils by creating ports if necessary.

a. HEPA vacuum or brush fins

b. Apply EPA-approved coil cleaner and rinse

c. Clear condensate drain

d. Report any damaged fins or insulation

2.11 Air Handling Unit (AHU) Cleaning (If Applicable)

16. Clean AHU components, including:

a. Interior surfaces (HEPA vacuuming, brushing, scraping, wiping)

b. Condensing coils

c. Filter racks

d. Blower compartment and blades

e. Dampers and louvers

f. Optional sanitizing per Section 12

g. Reporting of any damaged or deteriorated components

3. Inspections and Sealing

3.1 Post-Cleaning Inspection

17. Conduct post-cleaning inspection with the Building Manager

3.2 Access Port Closure Requirements

18. Install airtight removable plates or doors in compliance with industry standards.

Requirements:

● Metal panels shall match or exceed the existing duct gauge

● Mechanically fastened every 4" on center

● Sealed with UL-181A tape, gasket, or mastic

● Materials must be corrosion-resistant

● No installation may compromise duct structural, thermal, or functional integrity

● All materials must be UL- and NFPA-compliant

4. Restoration and Clean-Up

4.1 Reinstall Registers and Ceiling

19. Reinstall all registers, vents, grilles, diffusers, and ceiling tiles in original locations.

4.2 Clean-Up

20. Remove protective coverings. Sweep floors and vacuum carpets.

4.3 Final Inspection

21. Conduct a final walk-through with the Building Manager and verify that all work has been restored to its original condition.

○ Obtain sign-off on Certificate of Completion for Approval

5. Scheduling

● Work shall be coordinated with the Superintendent and/or designee

● Areas that are required to be unoccupied during cleaning may require weekends or after hours.

Scope of Work Details
1. Project Overview
2. Scope of Services
2.1 Removal and Cleaning of Registers, Vents, Grilles, and Diffusers
2.2 Drop Ceiling Access
2.3 Insulation Removal (As Needed)
2.4 Installation of Access Ports
2.5 Use of Agitation Devices
Industrial Brushes (If Applicable)
Compressed Air (If Applicable)
2.6 Vacuum Collection Requirements
High-Powered HEPA Vacuum Systems
Portable HEPA Vacuums
2.7 Microbial Treatment (If Applicable)
2.8 Protective Coatings (If Applicable)
2.9 Variable Air Volume (VAV) Boxes (If Applicable)
2.10 Reheat Coils (If Applicable)
2.11 Air Handling Unit (AHU) Cleaning (If Applicable)
3. Inspections and Sealing
3.1 Post-Cleaning Inspection
3.2 Access Port Closure Requirements
4. Restoration and Clean-Up
4.1 Reinstall Registers and Ceiling
4.2 Clean-Up
4.3 Final Inspection

5. Scheduling