About this file
This document is the Scope of Work for a small purchase procurement issued by the Illinois Department of Natural Resources (DNR) for flood repair work at Castle Rock State Park in Oregon, Illinois. DNR is seeking bids to repair a box culvert, stream bank, and asphalt pavement that were damaged during an August 2022 flood event. The scope of work includes removing the existing concrete wingwall and footing, completing earthwork, installing a new concrete wingwall and footing, placing controlled low-strength flowable fill, installing a concrete shoulder, removing and reinstalling riprap, and installing a wood guardrail. Bidders must have 3 years of highway/bridge construction experience, complete the work within 28 days of the notice to proceed, and comply with prevailing wage requirements. The contract is valued at less than $50,000, so a performance bond and labor/material payment bond are not required. DNR will award the contract to the lowest responsive, responsible bidder.
Pricing for the project will be evaluated on a lump sum basis. The contract includes a Small Business Set-Aside requirement. All work must conform to Illinois Department of Transportation standards and specifications. Contractor licensing and insurances are required, and the contractor must provide submittals for concrete, asphalt, and other materials prior to starting work. Payment will be made in accordance with the State Prompt Payment Act.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Flood photos.docx | DOCX document | |
| Location map~1.pdf | ||
| wingwll and footing details.PDF | ||
| Special Provisions~1.docx | DOCX document | |
| Plan view.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ILLINOIS DEPARTMENT OF NATURAL RESOURCES
SMALL PURCHASE PROCUREMENT
SCOPE OF WORK & PROJECT REQUIREMENTS
Date: September 12, 2022 File# 1-23-018
| LOCATION: | Castle Rock State Park | |
| Oregon, Illinois | ||
| Ogle County |
PROJECT TITLE: August 2022 Flood Repairs
PROJECT NARRATIVE:
The Illinois Department of Natural Resources, hereinafter referred to as DNR, is seeking bids to make needed repairs and replacement for flooding damage on a box culvert, stream bank and HMA pavement. On August 8, 2022, A 8” rain event from Sunday evening through Monday morning caused the stream to erode the bank adjacent to the box culvert. This caused the wingwall on the box culvert to fail and fall into the stream. The stream then proceeded to erode the embankment and undermine the park road pavement. See photos of erosion.
SCOPE OF WORK:
DNR is requesting a bid to perform all work described below and as shown on the attached plans.
· Remove existing concrete wingwall and footing from site.
· Complete all earthwork needed to complete the repairs per attached documents.
· Install new concrete wingwall and footing per attached documents.
· Install Controlled Low Strength flowable fill (CLS) as backfill behind new wingwall per attached documents.
· Install concrete shoulder per attached documents.
· Remove existing riprap and reuse as stream bank stabilization per attached documents.
· Install new RR4 riprap as stream bank stabilization per attached documents.
· Install two wood posts and boards with concrete foundation for wood guardrail.
· The contractor is required to clean-up all construction debris and haul off site.
· The contractor to provide all labor, material, and equipment to complete the work as shown on the construction documents.
ATTACHMENTS:
The following documents are included:
1) Location map
2) Plan view
3) Special Provisions
4) Wingwall and Footing details
5) Flood Photos
| A. | Project Specifications: |
| 1) | The awarded contractor must have 3 years of highway and bridge construction and be able to provide documentation of completion of at least 5 projects similar in size and scope to this one if requested. |
2) The awarded contractor must be able to complete work with 28 days of the Notice to Proceed (NTP).
3) CONSTRUCTION INSPECTION
Any work performed without the presence of an Owner’s designated representative to inspect said construction shall not be accepted for payment as directed by the Owner. Contractor shall notify Ownership a minimum of 24 hours in advance of the start of construction or the continuation of construction following a pause in work.
4) QUALITY ASSURANCE
A. Where reference is made to the "Standard Specifications" it shall mean "Standard Specifications for Road and Bridge Construction", adopted January 1, 2022, including all supplements, by the Department of Transportation, State of Illinois, insofar as the specifications apply. All reference to measurement and payment made in the "Standard Specifications" shall not apply to this contract.
All references to Engineer in the "Standard Specifications" shall mean Architect/Engineer.
B. Where reference is made to "ACI", it shall mean the "American Concrete Institute", Specifications and Tests.
C. Where reference is made to "ANSI" it shall mean the American National Standards Institute, Inc.
D. Where reference is made to "ASTM", it shall mean American Society for Testing and Materials Specifications, edition current as of date of bidding documents, unless otherwise specified.
E. Where reference is made to "AASHTO", it shall mean "American Association of State Highway and Transportation Officials" Specifications and Tests.
F. If, in the opinion of the Contractor, any part of the Specifications or Drawing(s) does not comply with the laws, codes, regulations, and specifications; that matter shall be referred to the attention of the Architect/Engineer for a decision before proceeding with that part of the work. There shall be no changes in the Drawing(s) and Specifications made without the approval of the Architect/Engineer.
B. Project Instructions and Notes:
1) Work Completed by Prime Contractor:
A minimum of seventy percent (70%) of the work shall be completed by the Prime Contractor on this project. Pursuant to (30 ILCS 500/1-15.17) the Contractor is the person having a contract with the Illinois Department of Natural Resources.
2) Coordination of Work Activities:
All entry to the site must be coordinated with the site superintendent and all work activities must be coordinated with the Region Engineer.
3) Independent Testing:
The Contractor shall pay all independent laboratory testing.
4) Contractor’s Licensing and/or Certifications:
Contractor shall be responsible for compliance with all applicable contractor and trades person licensing with the appropriate State agency. This includes, but is not limited to:
a. IL Dept. of Transportation qualified
5) Shop Drawings:
Submit for the approval of the DNR Project Architect/Engineer, shop drawings and product data for the following items before any work can be started:
a. Concrete (IDOT Mix design, and material certs)
b. CLSM (IDOT mix design)
c. Hot Mix Asphalt (IDOT mix design, and material certs)
d. Aggregates (IDOT material certs)
e. Epoxy Coated Reinforcement Bars (material certs, American made)
6) As-Built Markups:
The Contractor shall hand mark one set of drawings with corrections, dimensions, and "As-Built" notes. These Drawings shall be delivered to the DNR Project Architect/Engineer upon construction completion and prior to final payment request.
7) Lines, Grades, and Levels
a. The Contractor shall construct the project to the lines, grades and levels as shown on the Drawings and as described herein. Reasonable modifications from the Drawings will be permitted to take advantage of favorable topography or as warranted by unforeseen field conditions, but only as approved in writing by the Regional Engineer.
b. The regional Engineer shall furnish all location and control stakes reasonably necessary to define the outlines of the project. The Contractor shall be responsible for all other lines, levels, and grades necessary for the proper execution of the Work.
| 8) | Pre-Construction Meeting |
| Prior to initiating the Work, the Contractor shall contact the Regional Engineer for the purpose of scheduling a pre-construction meeting on the project site. The purpose of the meeting shall be to review contract requirements and working procedures. |
9) Utilities The Contractor shall be responsible for verifying the locations of existing utilities. Where unmarked utility lines, underground obstructions or piping may be uncovered on the premises, the Contractor shall notify the Utility Company having jurisdiction thereof and take all necessary measures to prevent interruption of services that may be damaged or interrupted through Contractor's own negligence and be responsible for immediate repair and/or restoration at his expense.
Prior to trenching or excavating, contact JULIE (Joint Utility Locating Information for Excavation 1-800-892- 0123) and the site manager to aid in locating all existing utilities.
| C. | Project Requirements: |
| 1) | Project Meeting |
| PROJECT MEETING TO BE HELD: YES NO X | |
| MANDATORY ATTENDANCE: YES |_| NO X |
2) COVID-19 Requirements In response to the COVID-19 pandemic, Governor J.B. Pritzker issued Executive Order 2021-22 and 2021-23. These Executive Orders mandate certain contractors shall use face coverings, have COVID-19 vaccinations, or undergo testing for COVID-19 when in indoor public places, Health Care Facilities, Schools, Institutions of Higher Education, and State-owned and operated congregate facilities. Vendor shall adhere to the requirements of these Executive Orders as applied by the Agency. The Agency may also implement vaccination or testing requirements that exceed those in the Executive Orders.
| 3) | Duration |
| Bids shall be good for ninety (90) calendar days after the submittal date, or | |
| for an extended period, if agreed to in writing by the Bidder and DNR. |
| 4) | Prevailing Wage Rates |
| This contract [or agreement] calls for the construction of a “public work,” within the meaning of | |
| the Illinois Prevailing Wage Act, 820 ILCS 130/.01 et seq. (“the Act”). The Act requires | |
| contractors and subcontractors to pay laborers, workers and mechanics performing services on | |
| public works projects no less than the current “prevailing rate of wages” (hourly cash wages | |
| plus, amount for fringe benefits) in the county where the work is performed. The Illinois | |
| Department of Labor (IDOL) publishes the prevailing wage rates on its website at | |
| http://labor.illinois.gov/. IDOL revises the prevailing wage rates and the | |
| contractor/subcontractor has an obligation to check the IDOL’s web site for revisions to | |
| prevailing wage rates. For information regarding current prevailing wage rates, please refer to | |
| IDOL’s website. All contractors and subcontractors rendering services under this contract must | |
| comply with all requirements of the Act, including but not limited to, all wage requirements and | |
| notice and record keeping duties. |
| 5) | Certified Payroll |
| State law 820 ILCS 130/5 requires all contractors and sub-contractors working on state | |
| construction projects to submit certified payroll records to the Department of Natural | |
| Resources. The payroll records must include all workers employed by contractors on the | |
| project. |
In accordance with 820 ILCS 130/5, the contractor and sub-contractor(s) shall make and keep, for a period of 5 years from the date of the last payment made on or after January 1, 2014 (the effective date of Public Act 98-328) on a contract or subcontract for public works, records of all laborers, mechanics, and other workers employed by them on the project.
No later than the 15th day of each calendar month, the contractor shall file a certified payroll for the immediately preceding month with the Department of Natural Resources.
6) Small Business Set-Aside The contractor awarded the bid must be registered as a small business, as required by the Small Business Set-Aside program. (For complete requirements, to become registered, or certify your business in the Small Business Set-Aside Program, visit http://www.sell2.illinois.gov/sbsp/set_aside.htm. or contact the Department of Central Management Services’ small business coordinator at 1-866-455-2897.)
7) Apprenticeship-in-Training When applicable, the contractor and all subcontractors must be participants in apprenticeship and training programs that are both approved by and registered with the U.S. Department of Labor’s Bureau of Apprenticeship and Training. The program(s) must be in the same trade(s) in which the contractor or subcontractor performs work. For information on how to participate in or set up a program, contractors may call the U.S. Department of Labor at 312/596-5508 or visit their website http://www.doleta.gov/oa/ .
8) Illinois Office The bidder must certify that the bidder will maintain an Illinois office as the primary place of employment for persons employed in the construction authorized by the contract.
| 9) | Subcontractors |
| The Contractor shall identify the names of all subcontractors to be utilized by them in the | |
| performance of this contract, together with the anticipated amount of money that each | |
| subcontractor is expected to receive pursuant to this contract. Pursuant to Illinois Procurement | |
| Code (30 ILCS 500/1-15-108), a person or entity is not a “subcontractor” if that person only | |
| Provides goods or supplies that are incidental to the performance of a contract by a person | |
| who has a contract subject to the Code. |
| 10) | Insurance |
| Contractor shall, at all times during the term of this contract and any renewals or extensions, maintain and provide a Certificate of Insurance naming the State as an additionally insured for all required bonds and insurance. Certificates may not be modified or canceled until at least thirty (30) days’ notice has been provided to the State. Contractor shall provide: (a) General Commercial Liability insurance in the amount of $1,000,000 per occurrence (Combined Single Limit Bodily Injury and Property Damage) and $2,000,000 Annual Aggregate; (b) Auto Liability, including Hired Auto and Non-owned Auto (Combined Single Limit Bodily Injury and Property Damage), in amount of $1,000,000 per occurrence; and (c) Worker’s Compensation Insurance in the amount required by law. Insurance shall not limit Contractor’s obligation to indemnify, defend, or settle any claims. |
11) Performance Bond/Labor and Material Payment Bond Pursuant to the Public Construction Bond Act (30 ILCS 550/), a performance bond and a labor and material payment bond covering the faithful performance of the contract and the payment of all obligations arising thereunder, shall be required if the project cost exceeds $50,000. Each bond shall be in the full amount of the contract. The bond must be from a surety licensed to do business within the State of Illinois and acceptable to IDNR.
12) Minority Contractor Opportunity Initiative The State requires a fee of $15 to cover Expenses related to the administration of the Minority Contractor Opportunity Initiative. Any Vendor awarded a contract under Section 20-10, 20-15, 20-25 or 20-30 of the Illinois Procurement Code (30 ILCS 500) of $1000 or more is required to pay a fee of $15. The Comptroller shall deduct the fee from the first check issued to the Vendor under the contract and deposit the fee in the Comptroller’s Administrative Fund.
13) Permits and Licenses Permits and licenses necessary for the execution of the work shall be secured and paid for by the Contractor.
14) Utilities Before starting excavation, establish location and extent of underground utilities occurring in the work area. Contractor shall contact Joint Utility Locating Information for Excavators (J.U.L.I.E.) 800-892-0123.
15) Highway Permits The Contractor is responsible for contacting the appropriate County Superintendent(s) of Highways and/or other appropriate local officials concerning the proposed work activities on the project as they may relate to use of the County and local road system. Coordination of any activities of concern to the County or Township shall be the responsibility of the Contractor. Special attention shall be given to load limits and seasonal restrictions.
16) New Products Unless otherwise specifically provided in the contract documents, all materials, equipment and products incorporated in the work under the contract shall be new and of a suitable grade for the purpose intended.
| 17) | Steel Products |
| Any steel product(s) used or supplied in the performance of this contract shall be manufactured or produced in the United States, in accordance with the Steel Products Procurement Act, unless a waiver is granted by IDNR (30 ILCS 565/). |
18) Specified Materials Bids shall be based on providing all products/materials exactly as required by the project specifications. Contractor may select from the list of acceptable manufacturers, offer an “equal” product and provide proof of its capabilities to meet the project specifications or, for products specified only by reference or performance standards, select any product which meets or exceeds the specified standards, by any manufacturer, subject to the approval of DNR.
19) Final Cleaning Contractor shall clean-up all work related debris and construction materials and properly dispose off-site. The Contractor shall repair and otherwise make good any damage caused by the work and leave the premises in the equivalent of the original condition.
20) Warranties The Contractor warrants that all work provided under the contract will be in conformance with the contract and free from defects in workmanship, materials, and equipment for a period of one year from the goods acceptance date. See Section B. Project Instructions and Notes, for any extended warranties that may apply.
21) Change Orders Change order shall be defined as a change in a contract term, other than as specifically provided for in the contract, which authorizes or necessitates any increase or decrease in the cost of the contract or the time for completion. A change order shall be executed by the State agency and vendor evidencing the change. All changes shall be approved by the CPO, or designee, and be accompanied by a written determination that the circumstances said to necessitate the change in performance were not reasonably foreseeable at the time the contract was signed and the change is germane to the original contract as signed. Change orders that increase or decrease the cost of a contract or an estimated contract by a total of $10,000 or more or the time of completion by more than 30 days shall be published on the Illinois Procurement Bulletin, pursuant to Section 15-25 of the Code and documented pursuant to Section 33E-9 of the Criminal Code of 2012, in advance of execution of the change order.
The DNR Architect/Engineer shall determine if the change was unforeseeable and/or germane to the original contract and that the price is fair and reasonable. When changes in or modifications to the work become necessary, the Contractor shall submit an itemized cost for the work and shall include appropriate documentation to support the cost for the labor, material, and equipment.
22) Inducement Resolution All or a portion of this project may be paid or reimbursed from the proceeds of tax-exempt bonds subsequently issued by the State.
23) Payment Payments, including late payment charges, will be paid in accord with the State Prompt Payment Act and rules when applicable, 30 ILCS 540/; 74 III. Adm. Code 900. This shall be the Contractor’s sole remedy for late payments by the State. Payment terms contained in Contractor’s invoice(s) shall have no force or effect.
| 24) | Contract Award |
| Contract award will be made to the lowest, responsible, responsive bidder. The Department of Natural Resources reserves the right to reject any or all bids. |
| 25) | Term of Contract | |
| All work shall be completed within 28 days after the notice to proceed, unless agreed to by both the Contractor and DNR, that a time extension is warranted. |
26) Bid Submittal Bids may be submitted electronically on BidBuy or by submitting the attached Bid Form.
| 27) | Bid Submittal Date and Time |
| Refer to the BIDBUY solicitation for the bid date and time. |
28) Questions
ALL QUESTIONS PERTAINING TO THE SCOPE OF WORK OR THE BIDBUY PROCEDURES, MUST
BE DIRECTED TO Frederick.Murphy@Illinois.gov ALL QUESTIONS MUST BE SUBMITTED IN WRITING NO LATER THAN THREE (3) BUSINESS DAYS BEFORE THE BID DATE.
29) Project Contacts: The following individuals are listed as project contacts during the construction phase. The Bidder may not communicate directly with any of these individuals during the bidding process. All communication during the bidding phase must be directed to the Frederick.Murphy@Illinois.gov email address.
| Project Engineer: | ||
| Engineer: Michael Bauling | ||
| Illinois Department of Natural Resources |
Address: 1365 W. Castle Road Oregon, IL 61061
| Phone: (815) 631-3765 |
| E-mail: Michael.Bauling@illinois.gov |
File details come from the government source that posted it. Updated .