SCO-25-29127-01A-NTB Add #2.pdf

PDF 1 MB Posted

Attached to
North Carolina Department of Transportation
Solicitation number
SCO-25-29127-01A
Issued by
Gaston County, North Carolina

About this file

This addendum document, issued May 1, 2026, clarifies and revises specifications for the North Carolina Department of Transportation's Gaston County Equipment Sub-Shop construction project (SCO ID# 25-29127-01A). The project involves construction of a 9,000 square foot pre-engineered metal building maintenance facility with a 3-bay shop, wash bay, tire change bay, offices, break room, toilets, parts storage, and mezzanine. Work hours are established as 7:00 AM to 4:00 PM, with after-hours work requiring NCDOT coordination. A mandatory pre-bid conference was held on May 12, 2026, at 11:00 AM, with 28 attendees from NCDOT, architectural firms, and construction companies documented on the attendance list. Formal bid submissions were due May 28, 2026, at 2:00 PM to 1710 E. Marion Street, Shelby, NC 28152. The construction schedule is 425 consecutive calendar days with liquidated damages assessed at $500 per day. Bids are to be held for 60 days following bid opening, with contract award anticipated within 4 to 6 weeks of bid opening. Notice to Proceed timing is contingent on award of bids.

The addendum includes seven project alternates addressing mezzanine expansion, high-performance coatings, rubber flooring, wall tile, site asphalt installation, fire hydrant installation, and owner-preferred hardware (Sargent 80 Series, 8800 rim exit devices). Three allowances are provided for unsatisfactory soil excavation and disposal, mass rock removal, and trench rock removal, with corresponding unit prices for additional quantities. The project requires a minimum 10 percent or greater minority business enterprise (MBE) participation goal, with bidders required to submit an Identification of HUB Certified/Minority Business Participation form and either Affidavit A or Affidavit B. Bid security must equal five percent of the proposal amount, submitted as cash deposit, certified check, or bid bond from a North Carolina-licensed surety. Requests for information (RFIs) must be submitted electronically in writing to the designer at thameed@morrisberg.com by May 18, 2026, at 5:00 PM, with final addenda issued May 21, 2026.

View the file

Other files

File Type Posted
SCO-25-29127-01A-NTB.pdf PDF
SCO-25-29127-01A-NTB Add #1.pdf PDF
SCO-25-29127-01A-NTB Add #3.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #

May 1 , 2026

SCO ID# 25-29127-01A

NCDOT – Gaston County Equipment Sub-Shop

The following Addendum clarifies, revises, and takes precedence over information previously published.

GENERAL ITEMS:

1. Pre-Bid Presentation

2. Pre-Bid Meeting Sign-In Sheet

3. Additional Information

a. Work hours are from 7am to 4pm. After hours work to be coordinated with

NCDOT.

ATTACHMENTS:

The following have been attached and included with addendum #

a. Pre-Bid Meeting Sign-In Sheet

b. Pre-Bid Presentation

END OF ADDENDUM #

2.

ATTENDANCE LIST

Pre-Bid Conference Tuesday, May 12, 2026 (11:00 AM)

NCDOT Gaston County Equipment Sub-Shop

SCO ID # 25-29127-01A

*PLEASE PRINT CLEARLY*

NAME COMPANY EMAIL

Hany Gorgui NCDOT hfgorgui@ncdot.gov

Gretchen Golz NCDOT ext-gmgolz@ncdot.com

William Jory NCDOT Equipment wwjory@ncdot.gov

Mark Hoyel Gaston Equipment mwhoyle@ncdot.gov

Mike Cabaniss NCDOT Equipment mcabaniss@ncdot.gov

Blake Guffey NCDOT cbguffey@ncdot.gov

Tarik Hameed Morris-Berg Architects thameed@morrisberg.com

Edgar Irakiza Morris-Berg Architects eirakiza@morrisberg.com

Justin Graves Hamlett Associates JGraves@hamlettai.com

Leland Bourque Pinnix LBourque@pinnix.com

Jesse Padgett Custom Building Systems jesse@custombuildingsystems.com

Sam Guptill Edison Foard sguptill@edisonfoard.com

Anna Freeman Ardmore Roderick afreeman@ardmoreroderick.com

Thadd Parker Smart Electric thaddeusparker@smartelectriccompanyinc.com

Eli Witherspoon Pinnix ewitherspoon@pinnix.com

Mark Reyes W.C. Construction Company bids@wcconstructionco.com

Mike Robinson Hostetter & Son Construction frank@hostetterandson.com

Chris Kearns Gen-Con Group chris@gencongroupse.com mailto:hfgorgui@ncdot.gov mailto:ext-gmgolz@ncdot.com mailto:wwjory@ncdot.gov mailto:mwhoyle@ncdot.gov mailto:mcabaniss@ncdot.gov mailto:cbguffey@ncdot.gov mailto:thameed@morrisberg.com mailto:eirakiza@morrisberg.com mailto:JGraves@hamlettai.com mailto:LBourque@pinnix.com mailto:jesse@custombuildingsystems.com mailto:sguptill@edisonfoard.com mailto:afreeman@ardmoreroderick.com mailto:thaddeusparker@smartelectriccompanyinc.com mailto:ewitherspoon@pinnix.com mailto:bids@wcconstructionco.com mailto:frank@hostetterandson.com mailto:chris@gencongroupse.com

Kirk Hunter Gais Construction estimating@gaisconstruction.com

Amy Michalesko AVM Construction amichalesko@avmcontractors.com

Shane Zello Concrete Core Drilling/ KanMan shanez@concretedrillsaw.com

Tyler Hannifan Nance Construction LLC thannifan@nancegc.com

Chris Wolf Neill Construction chris@neillinc.com

Obeol Guzman Alma HVAC obeol@almahvac.com

Fernando Salgado Dallas Electrical Contractors fernando@dallasncelectric.com

Eric Stroupe Dallas Electrical Contractors eric@dallasncelectric.com

William Goode Goode Disposal Services Inc. info@goodedisposalservices.com mailto:estimating@gaisconstruction.com mailto:amichalesko@avmcontractors.com mailto:shanez@concretedrillsaw.com mailto:thannifan@nancegc.com mailto:chris@neillinc.com mailto:obeol@almahvac.com mailto:fernando@dallasncelectric.com mailto:eric@dallasncelectric.com mailto:info@goodedisposalservices.com

NCDOT Gaston County Equipment Sub-Shop

Pre-Bid Conference

May 12, 2026

SCO ID# 25-29127-01A

AGENDA

INTRODUCTION OF PROJECT TEAM

BID PROCEDURES

MBE PARTICIPATION

SCHEDULE

SUBMISSIONS / BID CLARIFICATIONS

PROJECT SCOPE

QUESTIONS AND ANSWERS

PRESENTATION OF PREFERRED BRAND ALTERNATES

BID PROCEDURES

GENERAL INFORMATION

• BID DATE: MAY 28, 2026 – 2:00 PM

• DELIVER TO: 1710 E. MARION STREET, SHELBY, NC 28152

• MAIL TO: 1710 E. MARION STREET, SHELBY, NC 28152

• IF MAILED, PLEASE CONFIRM RECEIPT BY 12:00 PM. USE UPS OR FEDEX

BID SUBMISSION

• BID DOCUMENTS

• PLAN ROOMS

• thameed@morrisberg.com

BID FORMS

• FORM OF PROPOSAL

• MBE FORMS (EITHER A OR B)

• BID SECURITY

mailto:thameed@morrisberg.com

MBE PARTICIPATION

PROJECT GOAL

• 10% OR GREATER

BID FORMS

• IDENTIFICATION OF HUB CERTIFIED/ MINORITY BUSINESS

PARTICIPATION FORM

• AFFIDAVIT “A”

• AFFIDAVIT “B”

SCHEDULE

AWARD OF BIDS

• 4-6 WEEKS FOLLOWING BID OPENING

• HOLD BIDS FOR 60 DAYS

NOTICE TO PROCEED

• TBD – BASED ON AWARD OF BIDS

CONSTRUCTION TIME

• 425 CONSECUTIVE CALENDAR DAYS (14 MONTHS)

LIQUIDATED DAMAGES

• $500/DAY

SUBSTITUTIONS

SUBSTITUTIONS

• 10 DAYS PRIOR TO RECEIPT OF BIDS

• INSTRUCTION TO BIDDERS

• PROVIDE ALL REQUIRED INFORMATION TO DESIGNER

• CSI FORM 13.1A

RFI

• SUBMIT ELECTRONICALLY IN WRITING TO DESIGNER

thameed@morrisberg.com

• MAY 18, 2026 AT 5:00 PM

ADDENDA

• FINAL ADDENDA ISSUED MAY 21, 2026

• ISSUED TO ALL PLAN HOLDERS

Site Location

Site Location

Project Scope

Mary

Alexander

Road

• 9,000 square feet

• PEMB

• 3-Bay Maintenance Shop

• Wash Bay

• Tire Change Bay

• Offices/ Break Room

• Toilets

• Parts Storage

• Mezzanine

ALTERNATES

ALTERNATE #1

• Mezzanine Expansion: Provide structural framing (by PEMB supplier) and composite deck above Parts Storage and Break Room, adding 811 square feet of mezzanine. Remove GWB demising walls and replace with galvanized guardrail and pickets along the mezzanine edge.

ALTERNATE #2

• Add High Performance Coating: Provide a three-part epoxy textured vehicular coating at Work Bays, Tire Change, Tire Storage, and Machining, per the finish schedule (Sheet A1400), in lieu of the Base Bid.

ALTERNATE #3

• Replace Sealed Concrete with Rubber Flooring: Provide Rubber Tile Flooring

(RUF-1) at Corridor 101, Lead Workstation 102, Supervisor 103, Parts Storage

104 and Break Room 107 in lieu of sealed concrete.

ALTERNATE #4

• Replace Epoxy Paint with Wall Tile at Toilets: Provide wall tile (WT-1) on wet wall (behind toilet and lavatory) in Men and Unisex and add floor tile and tile base throughout.

ALTERNATE #5

• Install asphalt as indicated on plans denoted as “By Owner”: General

Contractor to provide and install site asphalt, in lieu of Owner.

ALTERNATE #6

• Install fire hydrant as indicated on plans denoted as “By Owner”: General

Contractor to provide and install fire hydrant and new line serving hydrant, in lieu of Owner.

ALTERNATE #7

• Provide Owner-Preferred Hardware Brand: Provide "Sargent" 80 Series, 8800 rim exit device and trim at all doors specified to receive this hardware type.

ALLOWANCES

ALLOWANCE #1

• INCLUDE 1,500 CU YD OF UNSATISFACTORY SOIL EXCAVATION AND

DISPOSAL OFF-SITE AND REPLACEMENT WITH SATISFACTORY SOIL

MATERIAL FROM OFF-SITE, AS SPECIFIED IN SECTION 312000

“EARTHWORK”

ALLOWANCE #2

• INCLUDE 200 CU YD OF MASS ROCK REMOVAL AND REPLACEMENT

WITH SATISFACTORY SOIL MATERIAL, AS SPECIFIED IN SECTION 312000

“EARTHWORK”

ALLOWANCES

ALLOWANCE #3

• INCLUDE 50 CU YD OF TRENCH ROCK REMOVAL AND REPLACEMENT

WITH SATISFACTORY SOIL MATERIAL FROM OFF-SITE, AS SPECIFIED IN

SECTION 312000 “EARTHWORK”

UNIT PRICES

UNIT PRICE #1

• REMOVAL OF UNSATISFACTORY SOIL AND REPLACEMENT WITH

SATISFACTORY SOIL MATERIAL (PER CU YD)

UNIT PRICE #2

• MASS ROCK EXCAVATION AND REPLACEMENT WITH SATISFACTORY

SOIL MATERIAL (PER CU YD)

UNIT PRICE #3

• TRENCH ROCK EXCAVATION AND REPLACEMENT WITH SATISFACTORY

SOIL MATERIAL (PER CU YD)

Q + A

PRESENTATION OF PREFERRED BRAND ALTERNATES

GENERAL STATUTE GS113-3

ALTERNATE #7

• Provide Owner-Preferred Hardware Brand: Provide "Sargent" 80 Series, 8800 rim exit device and trim at all doors specified to receive this hardware type.

Addendum 1 Cover - NCDOT GCESS
NCDOT Gaston County Equipment Sub-Shop Pre-Bid Presentation
Slide 1
Slide 2
Slide 3
Slide 4
Slide 5
Slide 6
Slide 7
Slide 8
Slide 9
Slide 10
Slide 11
Slide 12
Slide 13
Slide 14
Slide 15
Slide 16
Slide 17
Slide 18
Slide 19

File details come from the government source that posted it. Updated .