Schedule_of_Values.pdf

PDF 98 KB Posted

Attached to
Home Reconstruction at 2250 Greenway, Sanford FL 32771
Solicitation number
CC-7282-26/NBM
Issued by
Seminole County, Florida

About this file

This is a Schedule of Values document related to a home reconstruction project bid invitation issued by the Seminole County Board of County Commissioners for property located at 2250 Greenway, Sanford, Florida 32771 (Project CC-7282-26/NBM). The project involves the reconstruction of a single-family home containing a minimum of 1,100 square feet (plus or minus 100 square feet) with three bedrooms and two bathrooms. The construction timeline spans 270 days total, comprising 90 days for permitting, 150 days to substantial completion, and 30 days to final completion. Bid documents are available through the Seminole County website at https://secure.procurenow.com/portal/seminolefl. All prospective bidders are required to submit a Schedule of Values with their bid submission. Minority and Women-owned Business Enterprises (M/WBEs) are encouraged to participate.

The Engineer's estimate for the project is $225,000, inclusive of fees the County must pay for storing the owner's belongings. Bidders must adhere to strict communication protocols and refrain from contacting Seminole County staff or officials except through the designated contact person. All bid responses are considered public records under Florida law, and any bidder claiming portions of their response are exempt from public records disclosure must follow established procedures. Bid documents are accessible through the County's online procurement portal, and interested parties should review all solicitation materials and attachments prior to submission.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item # Description of Work Quanity Unit Price Scheduled Value

Schedule of Values

A B C D E Project Address:

Startup & Demo Cost 1 House Plans and Mobilization Cost 1

4 Rough Plumbing Underground Slab 1

2 Footer, Rebar, Stem Wall 1 3 Rough Grade Lot/Slad Compaction 1

Slab Install 5 Slab Pour 1

7 Framing/Trusses Delivery 1 6 Block Walls/Lintels 1

Framing 8 Roofing Dry-In 1

9 Windows/Ext. Doors 1 10 Roofing 1

12 Rough Mechanical 1 11 Rough Electrical 1

Rough In 13 Insulation Rough In 1

16 Lath/Stucco 1

14 Drywall & Texture 1 15 Tile Bathroom 1

18 Exterior Paint 1 17 Interior Paint 1

19 Flooring 1 20 Trim Molding 21 Int. Doors & Hardware 1

23 Septic Started 1 22 Cabinetry/Counter tops 1

Trim out 24 Final Electrical 1

28 Final Insulation / Shelves 1

26 Final Mechanical 1 27 Driveway/Walkway 1

30 Landscape/Sod 1

25 Final Plumbing 1

29 Appliances Installed Only 1

Totals

Final & Driveway

Retainage

Table 1