Schedule_of_Values_(2).xlsx

XLSX spreadsheet 22 KB Posted

Attached to
Home Reconstruction at 205 Hays Drive, Sanford, FL 32771
Solicitation number
CC-7333-26/NBM
Issued by
Seminole County, Florida

About this file

This Schedule of Values document supports the Seminole County Board of County Commissioners' Invitation for Bid (Project CC-7333-26/NBM) for home reconstruction services at 205 Hays Drive, Sanford, Florida 32771. The project requires bidders to reconstruct a single-family home with a minimum of 1,100 square feet (±100 square feet) containing three bedrooms and two bathrooms. The project timeline spans 270 days total, consisting of 90 days for permitting, 150 days to substantial completion, and 30 days to final completion. All permitting, engineering, and related matters are included within this timeframe. Bidders are required to submit a schedule of values as part of their bid submission. Bid documents are available on the Seminole County website through the ProcureNow portal.

The Engineer's estimate for the project is $225,000.00, which includes costs incurred by the County for storing the client's property. Minority and Women-Owned Business Enterprises (M/WBEs) are encouraged to participate in the bidding process. All bid responses are considered public records under the Florida Constitution and Florida Statutes Section 119.011. Prospective bidders are instructed not to contact Seminole County staff or officials except through the specified contact person designated for the solicitation.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table 1

MASTER DRAW SCHEDULE
Project Address
AGREEMENT TITLEPAYMENT NO.
COUNTY CONTRACT NO. PERIOD ENDING:
CONTRACTOR CIP#
ABCDEFGHIJK
Item #Description of WorkQuanityUnit PriceScheduled ValueWORK
From Previous ApplicationCOMPLETE D
This PeriodMaterials Presently Stored
(Not in F or G)Total Completed and Stored To Date (F+G+H)% (I/E)Balance To Finish (E-I)Retainage
1House Plans and Mobilization Cost1--00
Draw 1 - Startup & Demo Cost---00
2Footer, Rebar, Stem Wall100
3Rough Grade Lot/Slad Compaction1-00
4Rough Plumbing Underground Slab1-00
5Slab Pour1-00
Draw 2 - Slab Install---00
6Block Walls/Lintels1-00
7Framing/Trusses Delivery1-00
8Roofing Dry-In1-00
Draw 3 - Framing---00
9Windows/Ext. Doors1-00
10Roofing1-00
11Rough Electrical1-00
12Rough Mechanical1-00
13Insulation Rough In1-00
Draw 4 - Rough In---00
14Drywall & Texture1-00
15Tile Bathroom1-00
16Lath/Stucco1-00
17Interior Paint1-00
18Exterior Paint1-00
19Flooring1-00
20Trim Molding1-00
21Int. Doors & Hardware1-00
22Cabinetry/Counter tops1-00
23Septic Started1-00
Draw 5 - Trim out---00
24Final Electrical1-00
25Final Plumbing1-00
26Final Mechanical1-00
27Driveway/Walkway1-00
28Final Insulation / Shelves1-00
29Appliances Installed Only1-00
30Landscape/Sod1-00
Draw 6 - Final & Driveway---00
311
Draw 7 - Retainage---00

Totals - - -