Schedule A Attachments.M-32 Signal Work.pdf

PDF 4 MB Posted

Attached to
PMC Project - Traffic Signal repairs M-32 Otsego County
Solicitation number
RFP - 591 - 220000002934
Issued by
Otsego County, Michigan

About this file

The document is a set of special details related to a traffic signal improvement project in Otsego County, Michigan. The project involves the removal and replacement of traffic signals and related equipment at the intersection of M-32 (Main Street) and Murner Road/McVannel Drive in Livingston Township. Key items of work include the removal of existing traffic signal equipment and the installation of new traffic signals, strain poles, foundations, wiring, detection systems, and other related items. The project also includes temporary traffic control measures during construction. The document provides detailed specifications and drawings for the various components of the traffic signal infrastructure.

The pricing for this project will be based on unit prices for the various pay items, with a total bid amount. There is no indication of any set-asides or incumbent contractors. The project is being funded by the Michigan Department of Transportation, but the specific funding sources are not provided. The contract duration is not explicitly stated, but typical traffic signal projects of this nature have a completion timeframe of 3-6 months.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ONLY

N

EX. ROW

EX. ROW

EX. ROW

EX. ROW

E X

R O

W

E X

R O

W

E X

R O

W

E X

R O

W

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

CAUTION - CRITICAL

UNDERGROUND UTILITY

HAZARDOUS OR

FLAMMABLE MATERIAL

WATERMAIN

CAUTION

WATERMAIN

CAUTION

HAZARDOUS OR

FLAMMABLE MATERIAL

HAZARDOUS OR

FLAMMABLE MATERIAL

103' (EX. ROW)

(E

X

R O

W

(E

X

R O

W

66' (EX. ROW)

HAZARDOUS OR

FLAMMABLE MATERIAL CAUTION - CRITICAL

UNDERGROUND UTILITY

SA

T

G

T

W

W

G

T

CS:

JN:

TSC:

DATE:

DESIGN UNIT:

DRAWING SHEET

69021

213873 EPE

TWA#18157

6/23/22

STEADY WATTS:

PLAN:

0 30'

HORZ. (FT)

SIGNAL

GAYLORD

M-32 (MAIN ST) @ MURNER RD/MCVANNEL DR

LIVINGSTON TOWNSHIP, OTSEGO COUNTY

TRAFFIC SIGNAL REMOVAL SHEET

OPENINGS:

CYCLIC WATTS:

69021-01-002

EX SIGNALS

Michigan Department of Transportation

SECT

DESCRIPTIONAUTH

DATE NO. DATENO.

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: )

FILE:xxxxxx_6902101002_CON001.dgn

SAN

SAN

SAN

SAN

SAN

SAN

0.

0.

0.

0.

.5

0.

.4

.7

HH

HH

PS#2

PS#3

PS#4

PS#1

EAST (CS#4)

NORTH (CS#3)

WEST (CS#2)

SOUTH (CS#1)

FACING:

EX. 40' WOOD POLE

EX. 55' WOOD POLE

HH, ROUND, 3' DIA.

= 55 MPH)

(SPEED LIMIT

MURNER ROAD

= 25 MPH)

(SPEED LIMIT

McVANNEL DRIVE

WIRELESS VEHICLE DETECTION SYSTEM

WIRELESS INTERCONNECT SYSTEM (REMOTE)

CONTROLLER FDN, BASE MOUNT

& 16 LOAD SWITCH BAY BASE MOUNTED CABINET

DIGITAL TYPE ACTUATED CONTROLLER (MOD 50)

(CROSSING M-32; FACING EAST)

PUSHBUTTON & R10-3b(L) SIGN

PEDESTAL, FDN

PUSHBUTTON PEDESTAL, ALUM

POCH=27'-8" (SPAN #4)

POCH=23'-1" (SPAN #3)

CASING (13')

STRAIN POLE FDN, 6 BOLT (42"Ø, 16.5')

STRAIN POLE, 30', STEEL, 6 BOLT

(CROSSING M-32; FACING EAST)

PUSHBUTTON & R10-3b(R) SIGN

PEDESTAL, FDN

PEDESTAL, ALUM

= 40 MPH)

(SPEED LIMIT

M-32 (MAIN ST.)

= 55 MPH)

(SPEED LIMIT

M-32 (MAIN ST.)

9'2' 10'

VAR.

VAR.12'VAR.

32'9'

21'

VAR.

VAR.

11' VAR.

9'

9' 2'

20'

14' 11'

REMOVE HH & CONDUIT

29'

9'

12'

49'

34'

12'

11'

65'

21'

11'

10'

43'

40'

12'

9'

17'

SENSOR NODE (TYP.)

WIRELESS VEHICLE

(CROSSING M-32; FACING WEST)

PUSHBUTTON & R10-3b(R) SIGN

POCH=24'-5" (SPAN #2)

POCH=25'-5" (SPAN #1)

CASING (10')

STRAIN POLE FDN, 6 BOLT (42"Ø, 13.5')

STRAIN POLE, 30', STEEL, 6 BOLT

SERIAL PORT PROTOCAL (SPP) RADIO

EX YAGI ANTENNA (FACING EAST)

SERVICE DISCONNECT (NEMA 4X-STAINLESS STEEL)

EX ELECTRIC SERVICE (BY C.E. CO.)

POCH=26'-0" (SPAN #4)

POCH=25'-0" (SPAN #1)

CASING (12')

STRAIN POLE FDN, 6 BOLT (42"Ø, 15')

STRAIN POLE, 30', STEEL, 6 BOLT

NO. ITEM QUANTITIES

LIST OF MATERIAL

Fdn, Rem 1 Ea

Hh, Rem 1 Ea

Conduit, Rem 10 Ft

REGION ELECTRICIAN, (989) 370-1181

EQUIPMENT TO OWEN WERTH, MDOT NORTH

RETURN ALL REMOVED TRAFFIC SIGNAL

REMOVE SPAN#4

REMOVE SPAN#1

REMOVE SPAN#2

REMOVE SPAN#3

TS#3

REM

TS#4

REM

TS#5

REM

TS#6

REM

TS#7

REM

TS#8

REM

TS#1

REM

TS#2

REM

CS#1

REM

CS#2

REM

CS#3

REM

TS#4

REM

TS, Span Wire Mtd, Rem 8 Ea

Case Sign, Rem 4 Ea

Span Wire, Rem 4 Ea

Steel Pole, Rem 1 Ea 1

TS, Pedestrian, Bracket Arm Mtd, Rem 1 Ea

Pushbutton, Rem 1 Ea 8

POCH=25'-5" (SPAN #3)

POCH=24'-5" (SPAN #2)

(CROSSING M-32; FACING WEST)

REMOVE PUSHBUTTON & R10-3b(L) SIGN

REMOVE 2W LED CD PED SIGNAL

TO CASING (13'), MIN 2' BELOW GRADE

REMOVE FDN, 6 BOLT (42"Ø, 16.5'), DOWN 3.5'

REMOVE STRAIN POLE, 30', STEEL, 6 BOLT

R

Y

G

TS#7, TS#8

TS#5, TS#6,

TS#3, TS#4,

TS#1, TS#2,

LED TS

1W-3C-SA

REMOVE

LED CASE SIGN

24" X 30"

ONE-WAY

REMOVE

PhillipsK7 Text Box Schedule A - Attachment 1 Removal Items of Work

EX. ROW

EX. ROW

EX. ROW

EX. ROW

E X

R O

W

E X

R O

W

E X

R O

W

E X

R O

W

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

STEADY

FLASHING

START CROSSING

Watch For Vehicles

DON'T START

Finish Crossing If Started

DON'T CROSS

TO CROSS

PUSH BUTTON

CAUTION - CRITICAL

UNDERGROUND UTILITY

HAZARDOUS OR

FLAMMABLE MATERIAL

WATERMAIN

CAUTION

WATERMAIN

CAUTION

HAZARDOUS OR

FLAMMABLE MATERIAL

HAZARDOUS OR

FLAMMABLE MATERIAL

103' (EX. ROW)

(E

X

R O

W

(E

X

R O

W

66' (EX. ROW)

HAZARDOUS OR

FLAMMABLE MATERIAL CAUTION - CRITICAL

UNDERGROUND UTILITY

SA

T

G

T

W

W

CS:

JN:

TSC:

DATE:

DESIGN UNIT:

DRAWING SHEET

69021

213873 EPE

TWA#18157

6/23/22

STEADY WATTS:

PLAN:

0 30'

HORZ. (FT)

SIGNAL

GAYLORD

M-32 (MAIN ST) @ MURNER RD/MCVANNEL DR

LIVINGSTON TOWNSHIP, OTSEGO COUNTY

TRAFFIC SIGNAL CONSTRUCTION SHEET

OPENINGS:

CYCLIC WATTS:

69021-01-002

SIGNALS

Michigan Department of Transportation

SECT

DATE NO. DATENO.

FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: )

FILE:xxxxxx_6902101002_CON001.dgn

TS

SAN

SAN

SAN

SAN

SAN

SAN

0.

0.

0.

0.

.5

0.

.4

.7

HH

HH

PS#2

PS#3

PS#4

PS#1

EAST (CS#4)

NORTH (CS#3)

WEST (CS#2)

SOUTH (CS#1)

FACING:

EX. 40' WOOD POLE

EX. 55' WOOD POLE

HH, ROUND, 3' DIA.

= 55 MPH)

(SPEED LIMIT

MURNER ROAD

= 25 MPH)

(SPEED LIMIT

McVANNEL DRIVE

WIRELESS VEHICLE DETECTION SYSTEM

WIRELESS INTERCONNECT SYSTEM (REMOTE)

CONTROLLER FDN, BASE MOUNT

& 16 LOAD SWITCH BAY BASE MOUNTED CABINET

DIGITAL TYPE ACTUATED CONTROLLER (MOD 50)

(CROSSING M-32; FACING EAST)

PUSHBUTTON & R10-3b(L) SIGN

PEDESTAL, FDN

PUSHBUTTON PEDESTAL, ALUM

POCH=28'-6" (SPAN #4)

POCH=23'-11" (SPAN #3)

CASING (13')

STRAIN POLE FDN, 6 BOLT (42"Ø, 16.5')

STRAIN POLE, 30', STEEL, 6 BOLT

(CROSSING M-32; FACING EAST)

PUSHBUTTON & R10-3b(R) SIGN

PEDESTAL, FDN

PEDESTAL, ALUM

= 40 MPH)

(SPEED LIMIT

M-32 (MAIN ST.)

= 55 MPH)

(SPEED LIMIT

M-32 (MAIN ST.)

9'2' 10'

VAR.

VAR.12'VAR.

32'9'

21'

VAR.

VAR.

11' VAR.

9'

9' 2'

20'

14' 10'

29'

9' 12'

49'

34'

12'

11'

65'

25'

11'

10'

43'

40'

12' 9'

17'

SENSOR NODE (TYP.)

WIRELESS VEHICLE

(CROSSING M-32; FACING WEST)

PUSHBUTTON & R10-3b(R) SIGN

POCH=25'-3" (SPAN #2)

POCH=26'-3" (SPAN #1)

CASING (10')

STRAIN POLE FDN, 6 BOLT (42"Ø, 13.5')

STRAIN POLE, 30', STEEL, 6 BOLT

SERIAL PORT PROTOCAL (SPP) RADIO

EX YAGI ANTENNA (FACING EAST)

SERVICE DISCONNECT (NEMA 4X-STAINLESS STEEL)

EX ELECTRIC SERVICE (BY C.E. CO.)

POCH=26'-10" (SPAN #4)

POCH=25'-10" (SPAN #1)

CASING (12')

STRAIN POLE FDN, 6 BOLT (42"Ø, 15')

STRAIN POLE, 30', STEEL, 6 BOLT

NO. ITEM QUANTITIES

LIST OF MATERIAL

Strain Pole Fdn, 6 Bolt 17 Ft

Casing 13 Ft

Conduit, DB, 1, 1 1/2 inch 10 Ft

TS, One Way Span Wire Mtd (LED) 8 Ea

Case Sign (LED), One Way, 24 inch by 30 inch 4 Ea

TS, Pedestrian, Two Way Bracket Arm Mtd, Salv 1 Ea

Strain Pole, Steel, 6 bolt, 30 foot 1 Ea 1

POLE

STEEL

HH

TYPICAL

POCH=26'-3" (SPAN #3)

POCH=25'-6" (SPAN #2)

CS#1

INSTALL

TS#1

INSTALL

TS#2

INSTALL

CS#2

INSTALL

TS#3

INSTALL

TS#4

INSTALL

CS#3

INSTALLTS#5

INSTALL

TS#6

INSTALL

TS#8

INSTALL

TS#7

INSTALL

TS#4

INSTALL

Pushbutton and Sign, Salv 1 Ea

Hh, Round 1 Ea

Span Wire 4 Ea

TS#7, TS#8

TS#5, TS#6,

TS#3, TS#4,

TS#1, TS#2,

BOX SPAN CALCULATIONS

NOT TO SCALE

17' 09' 12' 40'

1W-CS 1W-3C 1W-3C

1W-CS

1W-3C

1W-3C

1W-CS1W-3C1W-3C

1W-CS

1W-3C

1W-3C33"

24"

30"

31"

24" 31"

30"

24"

33"

30"24"32"

25'

11'

10'

43'

29' 09'12'

49'

34'

12'

11'

65'

SPAN #4 POCH: 28'-01"

SPAN #1 POCH: 26'-10"

SPAN #2 POCH: 26'-04"

SPAN #1 POCH: 26'-10"

SPAN #4 POCH: 28'-01"

SPAN #3 POCH: 25'-06"

SPAN #3 POCH:25'-06"

SPAN #2 POCH:26'-04"

SPAN #1

TENSION=1000

SPAN #2

TENSION=1000

SPAN #3

TENSION=1000

FIELD ADJUSTMENTS SHOULD BE MADE TO MAINTAIN MIN 17' BOTTOM HEIGHT.

NOTE: POCH AND STEM LENGTHS ARE SUGGESTIONS ONLY.

Backplate, TS 8 Ea 8

R

Y

G

LED CASE SIGN

24" X 30"

ONE-WAY

INSTALL

ONLY

W/ BACKPLATE

LED TS

1W-3C-SA

INSTALL

Span Wire Tether 4 Ea 9

W/ TOP TETHER

TENSION=1000

SPAN #4

W/ TOP TETHER

W/ TOP TETHER

W/ TOP TETHER

9 & TOP TETHER

INSTALL SPAN#1

& TOP TETHER

INSTALL SPAN#2

& TOP TETHER

INSTALL SPAN#3

(CROSSING M-32; FACING WEST)

SALVAGE PUSHBUTTON & R10-3b(L) SIGN

SALVAGE LED CD PED SIGNAL

INSTALL FDN, 6 BOLT (42"Ø, 16.5'), CASING (13')

INSTALL STRAIN POLE, 30', STEEL, 6 BOLT

& TOP TETHER

INSTALL SPAN#4

1-1•" DB CONDUIT

3-3" DB CONDUITS

Conduit, DB, 3, 3 inch 10 Ft

INSTALL HH & CONDUITS

PhillipsK7 Text Box Schedule A - Attachment 2 Construction Items of Work

NOT TO SCALE

FILE:

Michigan Department of Transportation

MAY 2021

A DOUBLE LANE SHIFT

ON A 7-LANE UNDIVIDED ROADWAY

1 BOUND AND CLTL CLOSURE WITH DATE:

SHEET:

NO:

100-GEN-KEY.dgn 3(1R+2L)LC-2(L)SHIFT

152-CLT(7)-

MAINTAINING TRAFFIC TYPICAL

FILE:

Michigan Department of Transportation

DECEMBER 2021

TYPICAL NUMBERING KEY

DATE:

100-GEN-KEY.dgn

MAINTAINING TRAFFIC TYPICAL

100-GEN-KEY

NO:

TYPICAL NUMBER KEY

CODES

ZIP = ZIPPER MERGE

TS = TEMPORARY SIGNAL

TR = TRAFFIC REGULATOR

STA = STOPPED TRAFFIC ADVISORY

SPEED = SPEED

SP = SPECIAL

SIGN = SIGN

SHL = SHOULDER CLOSURE

SD = SHORT DURATION

RUM = RUMBLE STRIP

ROLL = ROLLING ROADBLOCK

(R) = RIGHT

PCMS = PORTABLE CHANGEABLE MESSAGE SIGN

PARK = PARKING LANE

NFW = NON-FREEWAY

MID = MIDDLE OF INTERSECTION OR ROAD

OUT = OUTSIDE OF SHOULDER

O = OUTSIDE (LANE CLOSURE)

LO = LANE OPEN

LD = LONG DURATION

LC = LANE CLOSURE

(L) = LEFT

L = LANE

INT = INTERSECTION

IN = INSIDE

GORE = FREEWAY GORE AREA

GEN = GENERAL INFORMATION

FW = FREEWAY

ExR = EXIT RAMP

EnR = ENTRANCE RAMP

EM = EARLY MERGE

CruSha = CRUSH AND SHAPE

CROSS = CROSSOVER

CLT = CENTER LEFT TURN LANE

C = CLOSURE

AW = ADVANCE WARNING

AB = ARROW BOARD

2(L)SHIFT = 2 LANES SHIFTED TO THE LEFT.

3(1R+2L)LC = 3 LANES CLOSED, (1 RIGHT LANE AND 2 LEFT LANES).

CTL(7) = CENTER LEFT TURN LANE, 7 LANES TOTAL.

152 - TYPICAL NUMBER

CODE: 152-CTL(7)-3(1R+2L)LC-2(L)SHIFT

EXAMPLE TYPICAL

5000 - SURVEY

4000 - MAINTENANCE

360 - ROLLING ROADBLOCK

350 - GORE LOCATIONS

340 - MERGE SYSTEMS

320 - CRUSH AND SHAPE

310 - CROSSOVER CLOSURE

300 - ADVANCE WARNINGS

230 - FREEWAY EXIT RAMPS

220 - FREEWAY ENTRANCE RAMPS

210 - FREEWAY LANE SHIFTS

200 - FREEWAY CLOSURES

160 - SIGNAL WORK

150 - CLT 7 LANE SECTIONS

140 - PARKING LANES

130 - CENTER LEFT TURN (CLT) LANES

120 - NON-FREEWAY

110 - TRAFFIC REGULATORS

100 - GENERAL NOTES

PhillipsK7 Text Box Schedule A - Attachment 3 Maintaining Traffic Typicals (8 Pages)

Michigan Department of Transportation

MAY 2021

"B", "D" AND "L" TABLES

CHANNELIZING DEVICE SPACING,

SIGN BORDER KEY, AND ROLL-AHEAD SPACING

101-GEN-SPACING-CHARTS.dgn

SPACING-CHARTS

101-GEN-

NO:

DISTANCE BETWEEN TRAFFIC SIGNS, "D"

POSTED SPEED LIMIT, MPH (PRIOR TO WORK AREA)

D (FEET)

DISTANCES

"D"

B (FEET)

GUIDELINES FOR LENGTH OF LONGITUDINAL BUFFER SPACE, "B"

LENGTHS

"B"

30 35 40 45 50 55 60 65 70

25 30 35 40 45 50 55 60 65 70

250 300 350 400 450 500 550 600 650 700

SPEED, MPH (PRIOR TO WORK AREA)

132 181 230 279 329 411 476 542 625

OPERATING SPEED.

* POSTED SPEED, OFF-PEAK 85TH PERCENTILE SPEED PRIOR TO WORK STARTING, OR THE ANTICIPATED

POSTED SPEED LIMIT, MPH (PRIOR TO WORK AREA)

25 30 35 40 45 50 55 60 65 70

1 11

2 100 110 120 130 140

3 135 150 165 180 195 210

4 107 180 200 220 240 260 280

5 103 134 225 250 300 325 350

6 123 160 270 300 330 360 390 420

7 143 187 315 350 385 420 455 490

8 164 214 360 400 440 480 520 560

(FEET)

OFFSET

MINIMUM MERGING TAPER LENGTH, "L" (FEET)

9 184 240 405 450 495 540 585 630

10 205 267 450 500 550 600 650 700

11 225 294 495 550 605 660 715 770

12 180 245 320 540 600 660 720 780 840

13 266 347 585 650 715 780 845 910

14 286 374 630 700 770 840 910 980

15 307 400 675 750 825 900 975 1050

15 21 27 45 50 55 60 65 70 75

90544130

32 45 62 80

42 60 82

53 75 275

63 90

33 83

Michigan Department of Transportation

MAY 2021

"B", "D" AND "L" TABLES

CHANNELIZING DEVICE SPACING

SIGN BORDER KEY AND ROLL-AHEAD SPACING

SPACING-CHARTS

101-GEN-

NO:

SHOWN IN THE ABOVE TABLES ARE AS FOLLOWS:

MERGING TAPER IN DERIVING THE "L" VALUES

THE FORMULAS FOR THE MINIMUM LENGTH OF A

60 THE WORK AREA IS 40 MPH OR LESS

WHERE POSTED SPEED PRIOR TO "L" = W X S

THE WORK AREA IS 45 MPH OR GREATER

WHERE POSTED SPEED PRIOR TO "L" = W X S

W = WIDTH OF OFFSET

S = POSTED SPEED LIMIT IN MPH PRIOR TO WORK AREA

L = MINIMUM LENGTH OF MERGING TAPER

UPSTREAM TAPERS

DOWNSTREAM TAPERS

TAPER LENGTHTYPES OF TAPERS

100' - MAXIMUM2 TO 1 LANE ROAD TAPER

1/3 L - MINIMUMSHOULDER TAPER

1/2 L - MINIMUMSHIFTING TAPER

L - MINIMUMMERGING TAPER

MAXIMUM SPACING FOR CHANNELIZING DEVICES

SPEED LIMIT

WORK ZONE

TAPERTAPER TANGENT TANGENT

< 45 MPH

> 45 MPH 25 FEET100 FEET50 FEET

1 x SPEED LIMIT 2 x SPEED LIMIT

100' (PER LANE)(USE IS RECOMMENDED)

DRUM AND 42" DEVICE SPACING (FT) NIGHTTIME 42" DEVICE SPACING (FT)

25 FEET 50 FEET

50 FEET

EXITEXIT

IS TO BE PLACED ON THE PROJECT

SOLID OUTLINES INDICATE A SIGN THAT

EXISTS ON SITE, AND NEEDS TO BE COVERED.

DASHED OUTLINES INDICATE A SIGN THAT

SIGN OUTLINE KEY

Michigan Department of Transportation

MAY 2021

"B", "D" AND "L" TABLES

CHANNELIZING DEVICE SPACING

SIGN BORDER KEY AND ROLL AHEAD SPACING

SPACING-CHARTS

101-GEN-

NO:

TO WORK ZONE)

(POSTED SPEED PRIOR

PREVAILING SPEED

25 FT

GUIDELINES FOR ROLL-AHEAD DISTANCES FOR TMA VEHICLES - TEST LEVEL 2

VEHICLE

TMA

WEIGHT OF

40 MPH OR LESS

(STATIONARY)

5.5 TONS

TO WORK ZONE)

(POSTED SPEED PRIOR

PREVAILING SPEED

50-55 MPH

100 FT

150 FT

175 FT

VEHICLE

TMA

WEIGHT OF

* ROLL-AHEAD DISTANCES ARE CALCULATED USING A 4,410 POUND IMPACT VEHICLE WEIGHT.

25 FT

25 FT

50 FT

(STATIONARY)

12 TONS

(MOBILE)

5 TONS

45 MPH

60-75 MPH

45 MPH

50-55 MPH

60-75 MPH

TMA VEHICLE TO WORK AREA)

(DISTANCE FROM FRONT OF

ROLL-AHEAD DISTANCE*

TMA VEHICLE TO WORK AREA)

(DISTANCE FROM FRONT OF

ROLL-AHEAD DISTANCE*

* ROLL-AHEAD DISTANCES ARE CALCULATED USING A 10,000 POUND IMPACT VEHICLE WEIGHT.

GUIDELINES FOR ROLL-AHEAD DISTANCES FOR TMA VEHICLES - TEST LEVEL 3

APRIL 2022

TRAFFIC TYPICALS

NOTE SHEET

102-GEN-NOTES.dgn

102-GEN-NOTES

NO:

GENERAL NOTES

BUFFER AREAS.

DO NOT STORE EQUIPMENT, MATERIALS OR PERFORM WORK IN ESTABLISHEDG4:

BY MDOT WILL BE ALLOWED.

APPLICABLE SPECIAL PROVISIONS. ONLY DESIGNS AND MATERIALS APPROVED

STANDARD SPECIFICATIONS FOR CONSTRUCTION, THE STANDARD PLANS AND

MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES, THE CURRENT EDITION OF THE

HARDWARE (MASH) TL-3 AS WELL AS THE CURRENT EDITION OF THE MICHIGAN

REPORT 350 (NCHRP 350) TEST LEVEL 3, OR MANUAL FOR ASSESSING SAFETY

LIGHTING MUST MEET NATIONAL COOPERATIVE HIGHWAY RESEARCH PROGRAM

ALL TEMPORARY SIGNS, TYPE III BARRICADES, THEIR SUPPORT SYSTEMS ANDG3:

ARE ADEQUATELY DELINEATED BY OTHER TRAFFIC CONTROL DEVICES.

WILL BE MADE FOR TRAFFIC PATTERNS FOR WORK LESS THAN THREE DAYS THAT

BE REMOVED BEFORE ANY CHANGE IS MADE IN THE TRAFFIC PATTERN. EXCEPTION

CHANGES IN TRAFFIC PATTERNS OR PROPOSED TEMPORARY TRAFFIC MARKINGS SHALL

ALL EXISTING PAVEMENT MARKINGS WHICH ARE IN CONFLICT WITH EITHER PROPOSED G5:

S9:

OF THE STOP SIGN OR IF SIGNALS ARE BEING USED TO CONTROL TRAFFIC.

STOP AHEAD SIGNS ARE NOT REQUIRED IF THERE IS ADEQUATE VISIBILITY

STOP SIGNS NOT REQUIRED IF SIGNALS ARE ON 4-WAY FLASHING RED.

S8:

PLACE THEM "D" DISTANCE APART.

WHEN SPEED LIMIT SIGNS CANNOT BE PLACED SIDE BY SIDE AS SHOWN,

S7:

THE WORK ZONE.

PLACE ADDITIONAL R8-3 SIGNS AT A MAXIMUM 500' SPACING THROUGHOUT

S6:

STANDARDS.

FABRICATE SPECIAL SIGNS IN ACCORDANCE WITH CURRENT SIGNING DESIGN

S4:

THE W20-5 SIGNS.

WHEN TRAFFIC VOLUMES ARE SIGNIFICANT ENOUGH TO CREATE BACKUPS BEYOND

ADDITIONAL SIGNING AND/OR ELONGATED SIGNING SEQUENCES SHOULD BE USED

S2:

AND CONSOLIDATE THE SEQUENCE AS APPROPRIATE.

OR LONGER. TO APPLY THIS TYPICAL WITHOUT R5-18b SIGNS, REMOVE THE SIGNS

15 DAYS OR LONGER OR NON-FREEWAY PROJECTS WITH A DURATION OF 90 DAYS

R5-18b SIGNS ARE ONLY REQUIRED ON FREEWAY PROJECTS WITH A DURATION OF

S3:

OMIT THIS SIGN IN SUBSEQUENT SEQUENCES IN THE SAME WORK ZONE.

R5-18c IS ONLY REQUIRED IN THE INITIAL SIGNING SEQUENCE IN THE WORK ZONE.

SIGN NOTES

S5:

ACCORDINGLY.

SPEED LIMIT ARE POSTED, OMIT ALL W3-5b AND R2-1 SIGNS AND REDUCE SPACING

OF THE WORK AREA AS INDICATED. IF PERMANENT SIGNS DISPLAYING THE CORRECT

SPEED LIMIT SIGNS RETURNING TRAFFIC TO ITS NORMAL SPEED BEYOND THE LIMITS

WHEN REDUCED SPEED LIMITS ARE UTILIZED IN THE WORK AREA, PLACE ADDITIONAL

ROADWAY SUCH THAT NO SPEED LIMIT SIGNS ARE MORE THAN 2 MILES APART.

IS IN EFFECT. PLACE ADDITIONAL SPEED LIMIT SIGNS AT INTERVALS ALONG THE

ENTRANCE RAMP THAT COMES ONTO THE FREEWAY WHERE THE REDUCED SPEED

EACH MAJOR CROSSROAD THAT INTERSECTS THE WORK ZONE, OR AFTER EACH

PLACE ADDITIONAL SPEED LIMIT SIGNS REFLECTING THE WORK ZONE SPEED AFTER

S1:

SAFETY AND MOBILITY MANUAL, SECTIONS 6.01.09 AND 6.01.10.

CONDITIONS, COVERED, OR REMOVED. FOR GUIDANCE SEE THE WORK ZONE

ALL NON-APPLICABLE SIGNING WITHIN THE CIA MUST BE MODIFIED TO FIT

TCD8:

REVERSE CURVE SIGN, AND THE SECOND REVERSE CURVE SIGN CAN BE OMITTED.

REVERSE CURVE SIGN (W24-1) CAN BE USED INSTEAD OF THE FIRST

WHERE THE SHIFTED SECTION IS SHORTER THAN 600 FEET, A DOUBLE

TYPE III BARRICADES MUST BE LIGHTED FOR OVERNIGHT CLOSURES.TCD3:

"ROAD CLOSED" EXTENDING COMPLETELY ACROSS THE HAUL ROAD.

WHEN THE HAUL ROAD IS NOT IN USE, PLACE LIGHTED TYPE III BARRICADES WITHTCD4:

TEMPORARY TRAFFIC CONTROL DEVICE NOTES

TCD7:

OFF ROAD FROM EDGE OF PAVEMENT TO EDGE OF PAVEMENT.

ADDITIONAL TYPE III BARRICADES MAY BE REQUIRED TO COMPLETELY CLOSE

TCD9:

ARE NOT TO EXCEED 50 FEET AT NIGHT.

45 MPH OR GREATER. THE SPACING FOR 42 INCH CHANNELIZING DEVICE TANGENTS

EXCEED 100 FEET ON ROADWAYS WITH A POSTED WORK ZONE SPEED LIMIT OF

WITH A POSTED WORK ZONE SPEED LIMIT LESS THAN 45 MPH AND SHOULD NOT

SHOULD NOT EXCEED TWICE THE WORK ZONE SPEED LIMIT IN MPH FOR ROADWAYS

THE MAXIMUM DISTANCE IN FEET BETWEEN CHANNELIZING DEVICES IN A TANGENTTCD2:

TAPERS ARE NOT TO EXCEED 25 FEET AT NIGHT.

LIMIT OF 45 MPH OR GREATER. THE SPACING FOR 42 INCH CHANNELIZING DEVICE

SHOULD NOT EXCEED 50 FEET ON ROADWAYS WITH A POSTED WORK ZONE SPEED

ROADWAYS WITH A POSTED WORK ZONE SPEED LIMIT LESS THAN 45 MPH AND

SHOULD NOT EXCEED 1.0 TIMES THE WORK ZONE SPEED LIMIT IN MPH FOR

THE MAXIMUM DISTANCE IN FEET BETWEEN CHANNELIZING DEVICES IN A TAPERTCD1:

AT A CONSISTENT DISTANCE, BETWEEN 10' AND 20' APART.

THREE RUMBLE STRIPS. PLACE THE RUMBLE STRIPS IN THE ARRAY

RECOMMENDATIONS. AN ARRAY OF RUMBLE STRIPS CONTAINS

SHOWN, AND IN ACCORDANCE WITH THE RUMBLE STRIP MANUFACTURER'S

IF NOT SPECIFIED IN THE CONTRACT, PLACE RUMBLE STRIPS AS

RUMBLE STRIPS ARE TO BE PLACED AS SPECIFIED IN THE CONTRACT.

RAMP NOTES

DIVERGE IN A FREE MANNER

CHANELIZING DEVICES MUST BE POSITIONED TO ENABLE RAMP TRAFFIC TO

WHEN CONDITIONS ALLOW, E5-1 SIGNS MUST BE REMOVED OR COVERED ANDRMP1:

WORK SHOULD BE EXPEDITED TO AVOID THE STOP AND/OR YIELD CONDITIONS.

THE RAMP TO COMPLETE WORK TO ALLOW AN ADEQUATE MERGE DISTANCE.

IN PLACE OF W3-2 SIGNS. CONSIDERATION SHOULD BE GIVEN TO CLOSING

R1-2 SIGNS. WHEN R-1 SIGNS ARE USED, W3-1 SIGNS MUST BE USED

WHEN CONDITIONS WARRANT, R1-1 SIGNS MAY BE USED IN PLACE OF

STOP AND YIELD CONDITIONS SHOULD BE AVOIDED WHENEVER PRACTICAL.RMP2:

G2:

THE ENGINEER.

GEN-KEY ARE APPROXIMATE AND MAY NEED ADJUSTING AS DIRECTED BY

DISTANCE BETWEEN SIGNS, "D", THE VALUES FOR WHICH ARE SHOWN IN TYPICAL

BOARD IN THE CLOSED LANE AS CLOSE TO THE BEGINNING OF TAPER AS POSSIBLE.

SECTIONS, IF ARROW BOARD CANNOT BE PLACED BEHIND CURB, PLACE ARROW

MOTORISTS WHEN PHYSICAL LIMITATIONS RESTRICT PLACEMENT. IN CURBED

PRACTICAL, BUT NOT IN A MANNER THAT WILL OBSCURE OR CONFUSE APPROACHING

PLACE LIGHTED ARROW PANELS AS CLOSE TO THE BEGINNING OF TAPERS AS TCD6:

S10:

A SPEED REDUCTION IN THIS DIRECTION.

PLACE REDUCED SPEED ZONE AHEAD SIGN (W3-5b) HERE WHEN USING

TCD10:

SIDES OF THE ROAD 1000 FEET FROM EACH OTHER.

CORRECT PCMS MESSAGING. STAGGER PCMS THAT ARE ON OPPOSING

CHANGEABLE MESSAGE SIGN GUIDELINES FOR RECCOMENDED AND

SEE THE WORK ZONE SAFETY AND MOBILITY MANUAL, PORTABLE

AN ANGLE OF 45 DEGREES IN THE DIRECTION VEHICULAR TRAFFIC IS TO PASS.

HAVE ALTERNATING DIAGONAL ORANGE AND WHITE STRIPES SLOPING DOWNWARD AT

AND WHITE RETROREFLECTIVE SHEETING. THE RETROREFLECTIVE SHEETING MUST

A MINIMUM OF 12 INCHES IN WIDTH AND 36 INCHES IN HEIGHT AND HAVE ORANGE

WHEN USED WITH A TEMPORARY SIGNAL SYSTEM. THE OBJECT MARKERS MUST BE

IN THE STANDARD PLAN FOR TEMPORARY CONCRETE BARRIER (R-53, AND R-126)

USE OBJECT MARKER SIGNS IN LIEU OF THE TYPE B HIGH INTENSITY LIGHT SHOWNTCD5:

ROLL AHEAD DISTANCE

B = LENGTH OF LONGITUDINAL BUFFER

L = MINIMUM LENGTH OF TAPER

D = DISTANCE BETWEEN TRAFFIC CONTROL DEVICES

SEE GEN-SPACING-CHARTS FOR COMMON VALUES INCLUDING:G1:

TRAFFIC REGULATOR NOTES

TR1:

BY THE ROADWAY ADT, GEOMETRICS, AND AS DIRECTED BY THE ENGINEER.

THE MAXIMUM DISTANCE BETWEEN THE TRAFFIC REGULATORS IS DETERMINED

AND THE VIDEO "HOW TO SAFELY REGULATE TRAFFIC IN MICHIGAN".

THE CURRENT VERSIONS OF THE TRAFFIC REGULATOR'S INSTRUCTION MANUAL

SPECIFICATIONS, THE STANDARD PLANS AND APPLICABLE SPECIAL PROVISIONS,

TRAFFIC REGULATORS MUST FOLLOW ALL THE REQUIREMENTS IN THE STANDARD

TR2:

THE HOURS OF DARKNESS.

REGULATOR'S STATIONS WHEN TRAFFIC REGULATING IS ALLOWED DURING

PROVIDE APPROPRIATE BALLOON LIGHTING TO SUFFICIENTLY ILLUMINATE TRAFFIC

S11:

LENGTH OF SHIFT AND AS PER THE ENGINEER.

SHIFTS MORE THAN 12FT, PLACE THREE OR MORE W1-6(R)(L) SIGNS DEPENDING UPON

SHIFTS 5FT TO 12FT, PLACE TWO W1-6(R)(L)

SHIFTS 4FT OR LESS, PLACE ONE W1-6(R)(L)

THE NUMBER OF W1-6 SHIFT SIGNS TO PLACE FOR A SHIFT IS AS FOLLOWS:

S12:

IN THIS DIRECTION

PLACE R2-1 SIGNS AS DETAILED IN NOTE S5 WHEN THERE IS A SPEED REDUCTION

THE FOLLOWING NOTES APPLY IF CALLED FOR ON THE TRAFFIC TYPICAL

APRIL 2022

TRAFFIC TYPICALS

NOTE SHEET

102-GEN-NOTES.dgn

102-GEN-NOTES

NO:

SIGNAL NOTES

TRUCK IS LOCATED OVER ACTIVE TRAVEL LANES.

THE CONTRACTOR MUST HAVE A DESIGNATED SPOTTER IF THE AERIAL BUCKETSIG4:

INTERSECTION WHEN TRAFFIC IS PLACED IN A 4 WAY STOP.

COMPROMIZED. USE TRAFFIC REGULATORS TO CONTROL TRAFFIC THROUGH THE

THE INTERSECTION IN A 4 WAY STOP IF THE 14 FOOT VERTICAL CLEARANCE IS

CLEARANCE. THE CONTRACTOR MUST UTILIZE AN ALTERNATE SET UP, OR PLACE

THE LOWEST POINT OF THE BUCKET MAY NOT TRAVEL BELOW 14 FOOT VERTICALSIG5:

TRUCK MAY BE MOVED TO FACILITATE WORK.

DELINEATE THE TRUCK WITH CHANNELIZING DEVICES. THE POSITION OF THESIG6:

42 INCH CHANNELIZING DEVICES FOR NIGHTTIME WORK.

DELINEATE THE WORK ZONE AREA WITH 28 INCH CONES FOR DAYTIME WORK, ORSIG3:

SIGNAL IS IN OPERATION.SIG2:

EXISTING SIGNAL MUST BE EITHER 4-WAY FLASHING RED, BAGGED, OR TURNED OFF.SIG1:

MAINTENANCE AND SURVEYING NOTES

ACTIVATED AMBER BEACON.

WORK AND SHADOW VEHICLES SHALL BE APPROPRIATELY EQUIPPED WITH AN MS4:

SIGHT DISTANCE IN ADVANCE OF VERTICAL OR HORIZONTAL CURVES.

SLOW DOWN AND TRAVEL AT A FARTHER DISTANCE TO PROVIDE ADEQUATE

AREA AND PROCEEED AT THE SAME SPEED. THE SHADOW VEHICLE SHOULD

VEHICLES SHOULD MAINTAIN THE RECOMENDED DISTANCE FROM THE WORK

WHENEVER STOPPING SIGHT DISTANCE EXISTS TO THE REAR, THE SHADOW MS1:

TABLES.

SHOULD BE PARKED ACCORDING TO THE ROLL AHEAD DISTANCE

SEPARATE THE WORK SPACE FROM TRAFFIC. IF USED, THE VEHICLES

WORK OR SHADOW VEHICLES WITH OR WITHOUT A TMA MAY BE USED TO MS3:

TO) IS THE LAYOUT OF CONCRETE PATCHES.

SPACING MUST BE USED. AN EXAMPLE OF AN OPERATION (BUT NOT LIMITED

CHANNELIZING DEVICES TO DELINEATE OPEN OR CLOSED LANES AT 50 FT

A MOBILE OPERATION IS OCCURRING DURING THE NIGHTTIME HOURS,

WHEN WORKERS ARE OUTSIDE THEIR VEHICLES IN AN EXISTING LANE WHILEMS5:

TYPE OF WORK TAKING PLACE AS PER THE ENGINEER.

W21-6 AND W20-1 SIGNS MAY BE SUBSTITUTED AS DETERMINED BY THE MS6:

"END ROAD WORK" SIGN.

AND THE "END WORK CONVOY" SIGN, OR BETWEEN THE "WORK ZONE BEGINS" AND

WITH AN ACTIVATED BEACON, BETWEEN THE "BEGIN WORK CONVOY" SIGN

WORKERS OUTSIDE OF VEHICLES SHOULD WORK WITHIN 150' OF WORK VEHICLES MS2:

THE FOLLOWING NOTES APPLY IF CALLED FOR ON THE TRAFFIC TYPICAL

MAY 2021

LONGER THAN 1 HOUR

ON A 5-LANE UNDIVIDED ROADWAY

SIGNAL WORK AT INTERSECTION DATE:

160-INT-LD-CLT-MID.dgn

INT-LD-CLT-MID

160-

NO:

SIDE STREET

SIDE STREET

M A I

S

R E

E T

M A

R E

E T

D D

D L

V a r i e s

M A

X

N

L

DDDL

100' MAX.

50' MIN.

Varies

D D

D

X

N

Varies

VariesLDDD

W O

R K

E

V

R

IE

S

WORK AREA

STOP

R1-1

STOP

R1-1

STOP

R1-1

STOP

R1-1

W3-1

W3-1

W3-1

W3-1

CLOSED

AHEAD

LEFT LANE

W20-5L

CLOSED

AHEAD

LEFT LANE

W20-5L

CLOSED

AHEAD

LEFT LANE

W20-5L

CLOSED

AHEAD

LEFT LANE

W20-5L

PROHIBITED.)

ALWAYS BE

TURN MOVEMENT SHALL

WORK AREA. (LEFT

BASED ON POSITION OF

SIGN REQUIREMENT

PROHIBITED.)

SHALL ALWAYS BE

(LEFT TURN MOVEMENT

OF WORK AREA.

BASED ON POSITION

SIGN REQUIREMENT

ALWAYS BE PROHIBITED.)

(LEFT TURN MOVEMENT SHALL

POSITION OF WORK AREA.

SIGN REQUIREMENT BASED ON

ALWAYS BE PROHIBITED.)

(LEFT TURN MOVEMENT SHALL

POSITION OF WORK AREA.

SIGN REQUIREMENT BASED ON

100' MAX.

50' MIN.

G

WORK

AHEAD

W20-1c

SINAL

G

WORK

AHEAD

W20-1c

SINAL

G

WORK

AHEAD

W20-1c

SINAL

G

WORK

AHEAD

W20-1c

SINAL

SEE NOTE S9

TRAFFIC FLOW

NIGHTTIME WORK

WORK. USE LIGHTED ARROW PANEL FOR

USE TARGET ARROW (W1-6) FOR DAYTIME

CHANNELIZING DEVICES

KEY

SIGNAL:

DEVICES:

SIGNING:

GENERAL:

SIG1, SIG3, SIG4, SIG5

TCD1, TCD2, TCD6

S1, S9

G1, G2, G3

STANDARD NOTES

(SEE 102-GEN-NOTES)

R3-5R R3-2

OR

ONLY

R3-5R R3-2

OR

ONLY

R3-5R R3-2

OR

ONLY

R3-5R R3-2

OR

ONLY

MAY 2021

ROADWAY LONGER THAN 1 HOUR

ON A 4-LANE UNDIVIDED ROADWAY

SIGNAL WORK AT INTERSECTION OUTSIDE DATE:

163-INT-LD-OUT.dgn

163-INT-LD-OUT

NO:

M A

R E

E T

SIDE STREET

SIDE STREET

M A

R E

E T

D

D

KEY

WHERE WORK IS TAKING PLACE

WHERE WORK EQUIPMENT IS LOCATED OR

SIGN IS ONLY REQUIRED IN ADVANCE OF

LIGHTS

WORK VEHICLE WITH FLASHING OR ROTATING

TRAFFIC FLOW

G

WORK

AHEAD

W20-1

SINAL

G

WORK

AHEAD

W20-1

SINAL

SIGNAL:

SIGNING:

GENERAL:

SIG4, SIG5

S1

G1, G2, G3

STANDARD NOTES

(SEE 102-GEN-NOTES)

20SP-820A-01

MICHIGAN

DEPARTMENT OF TRANSPORTATION

SPECIAL PROVISION

FOR

STEEL STRAIN POLE

SIG:EMS 1 of 2 APPR:NAP:POJ:04-29-20

FHWA:APPR:05-05-20

a. Description. This work consists of furnishing, fabricating, and erecting a traffic signal steel strain pole as shown on the plans, in accordance with the standard specifications, and as specified herein. This special provision is for an anchor base type (six anchor bolt system) strain pole and includes all other associated hardware required to complete the work.

b. Material. Provide material in accordance with sections 906, 908, and 921 of the Standard Specifications for Construction and this special provision.

Ensure strain pole meets ASTM A572/A572M, Grade 50 or ASTM A595/A595M, Grade A. Ensure base plate meets ASTM A36/A36M. Blast clean fabricated components to remove mill scale and welding slag before galvanizing. Galvanize strain pole and components in accordance with

AASHTO M111M/M111.

Ensure bolts, nuts, and washers meet subsection 906.07 of the Standard Specifications for Construction.

Stainless steel must meet AISI (American Iron and Steel Industry) 300 series.

Acceptance of strain pole is based on general certification in accordance with MDOT’s materials quality assurance procedures manual.

c. Fabrication. Ensure fabrication and welding is in accordance with American Welding Society (AWS) D1.1:2010, Structural Welding Code-Steel (as modified by the current 20SP-707A

- Structural Steel and Aluminum Construction), hereafter called AWS D1.1, except as modified herein.

Fabricator must possess a valid American Institute of Steel Construction (AISC) Bridge Component Quality Management System Certification (CPT).

Submit shop drawings in Portable Document Format (PDF) to the Engineer for approval in accordance with subsection 104.02 of the Standard Specifications for Construction prior to commencing fabrication. Fabricate strain pole as detailed in the contract.

Ensure all welds are 100 percent visual test (VT) inspected by an AWS certified welding inspector (CWI). Ensure all fillet welds are 25 percent magnetic particle test (MT) inspected by a technician qualified in accordance with American Society of Nondestructive Testing (ASNT) Level II, except fillet welds used to secure strain pole cap detail. Perform MT inspection in conformance with ASTM E709 with dry powder using the yoke method. Use half-wave rectified alternating current (direct current) for MT inspection. Ensure all complete joint penetration (CJP) welds are 100 percent ultrasonic test (UT) inspected by a technician qualified in accordance with ASNT Level II.

PhillipsK7 Text Box Schedule A - Attachment 5 Special Provisions (20 Pages)

20SP-820A-01

SIG:EMS 2 of 2 04-29-20

1. Base plate warpage must not exceed 1/16 inches per foot.

2. Tolerance for overall length of strain pole is ±1/8 inch. Tolerance for sweep and camber of strain pole 1/8 inch per 10 foot. Tolerance for twist of strain pole is ±10 degrees.

3. Strain pole wall may be single or multi-ply.

4. Strain pole cannot have more than one longitudinal weld. Transverse welds are prohibited.

d. Erection. Snug tighten anchor bolts in accordance with subsection 810.03.N.2 of the

Standard Specifications for Construction.

Ensure all installation procedures are witnessed by the Engineer.

e. Construction. Ensure all work is in accordance with subsection 810.03 and sections 819 and 820 of the Standard Specifications for Construction and the contract.

For repair coating, apply a coating 1½ times the thickness or thickness equivalent specified for galvanizing on the item, but not less than 5 mils. Use zinc-based solder, zinc-rich primer, or zinc metallizing in accordance with ASTM A780/A780M. Obtain the Engineer’s approval before using zinc metalizing.

f. Measurement and Payment. The completed work, as described, will be measured and paid for at the contract unit price using the following pay item:

Pay Item Pay Unit

Strain Pole, Steel, 6 bolt, __ foot ............................................................................... Each

Strain Pole, Steel, 6 bolt, __ foot includes furnishing all materials, fabrication, shop cleaning, galvanizing, shipping, and erection.

No extension of time or additional compensation will be granted due to obtaining the proper AISC certifications and/or endorsements required for this project.

Construction of the foundation will be included in other items.

20SP-820F-02

PUSHBUTTON AND SIGN, SALVAGE

SIG:EMS 1 of 1 APPR:HLO:NJB:05-26-21

FHWA:APPR:05-27-21

a. Description. This work consists of removing, storing, and reinstalling an existing pushbutton and sign at locations shown on the plans.

This work includes removal, storing and installation of interface equipment, mounting assembly, brackets, hardware, fittings, connectors, wiring, cable to controller, grounding, risers, conduit, and any other material required to ensure a complete removal and installation.

b. Materials. None specified.

c. Construction. Complete this work in accordance with sections 819 and 820 of the Standard Specifications for Construction, as shown on the plans, and as directed by the Engineer.

Remove an existing pushbutton and sign, store salvaged materials in a protected and clean environment, and re-install the materials.

d. Measurement and Payment. The completed work, as described, will be measured and

Pushbutton and Sign, Salv ........................................................................................ Each

Pushbutton and Sign, Salv includes removing a pushbutton, and sign if one is present, storing the removed materials on site and reinstalling materials at a location shown on the plans. This pay item includes removing and re-installing, as applicable, interface equipment, mounting assembly, brackets, hardware, fittings, connectors, wiring, cable to controller, grounding, risers, conduit and any other material required to ensure a complete removal and installation.

20SP-820FF-01

TRAFFIC SIGNAL BACKPLATE

SIG:EMS 1 of 2 APPR:HLO:NJB:05-01-20

FHWA:APPR:05-06-20

a. Description. This work consists of completing one or more of the following work types at location(s) shown on the plans:

1. Furnishing and installing a traffic signal backplate.

2. Removing and disposing of an existing traffic signal backplate.

3. Removing, storing and reinstalling an existing traffic signal backplate.

As applicable, this work includes removal or installation of hardware, connectors, fittings and all material necessary to complete the work.

b. Materials. Material must meet sections 819, 820, and 921 of the Standard Specifications for Construction.

1. Provide a one-piece backplate for three or four section traffic signal heads as indicated on the plans or as directed by the Engineer. Ensure that five section (doghouse) signal head combinations are provided with no more than three vacuum formed pieces.

2. Provide backplates that are designed to precisely fit the manufacturer’s signal heads and supplied with necessary hardware to attach the backplate to the signal.

3. Provide backplates that are vacuum formed from 0.125 inch thick black acrylonitrile butadiene styrene (ABS) plastic with a hair cell finish on the front side (facing approaching traffic) to reduce glare.

4. Provide backplates that are constructed with a minimum 5/8 inch flange on all sides to provide structural rigidity. Ensure the backplates are provided with a three inch corner radius.

5. Ensure that all backplates extend approximately five inches around the perimeter of the traffic signal combinations after installation.

6. Provide backplates with an ASTM Type IV reflective yellow tape border. Ensure that a one inch border is used with yellow signal heads and visors, and a two inch border is used with black signal heads and visors.

7. Warranty. Provide materials with a manufacturer’s warranty/guarantee, transferable to MDOT, that the supplied materials will be free from all defects in materials and workmanship for the stated time period from the date of shipment. Supply the Engineer with any warranty or guarantee documents from the manufacturer and a copy of the invoice showing date of

20SP-820FF-01

SIG:EMS 2 of 2 05-01-20 shipment.

c. Construction. Complete this work in accordance with sections 819 and 820 of the Standard Specification for Construction, as shown on the plans, and as directed by the Engineer.

Remove, store, and dispose of material in accordance with section 204 of the Standard Specification for Construction.

paid for at the contract unit price using the following pay items:

Backplate, TS ............................................................................................................ Each Backplate, TS, Rem ................................................................................................... Each Backplate, TS, Salv ................................................................................................... Each

1. Backplate, TS includes installing the backplate on existing or new signal head(s) at location(s) shown on the plans where installation is specified. Furnish and install a traffic signal backplate, as indicated on the plans or as directed by the Engineer.

2. Backplate, TS, Rem includes removing the existing backplate, hardware, and other appurtenances, required for a complete removal where removal is specified. Dispose of removed materials.

3. Backplate, TS, Salv includes removing the existing backplate, hardware, and other appurtenances required for a complete removal, storing salvaged materials in a clean environment, and reinstalling the materials where salvage is specified. Complete reinstallation in accordance with subsection c. of this special provision.

20SP-820GG-01

SPAN WIRE TETHER

SIG:EMS 1 of 1 APPR:NJB:HLO:05-01-20

a. Description. This work consists of furnishing and installing hardware, connector hangers, fittings, tether plate, span wire clamps, associated stainless steel fasteners and a span wire tether.

Top tether traffic signal heads. Bottom tethering can only be used with approval of the Engineer and the Statewide Signal Shop.

b. Materials. Provide material meeting the requirements of sections 819, 820, and 921 of the Standard Specifications for Construction.

1. Provide tether span wire that is 1/4 inch nominal diameter, 7-strand, galvanized, Class C in accordance with ASTM A475 with common grade breaking strength of 1900 pounds.

Maintain clearance of 17 feet over roadway.

2. Connector hanger, tether plate, span wire clamps and associates stainless steel fasteners, materials and hardware to furnish and install a span wire tether.

3. Warranty. Provide materials with a manufacturer’s warranty/guarantee, transferable to MDOT, that the supplied materials will be free from all defects in materials and workmanship for the stated time period from the date of shipment. Supply the Engineer with any warranty or guarantee documents from the manufacturer and a copy of the invoice showing date of shipment.

c. Construction. Complete this work in accordance with sections 819, 820 and 821 of the

Standard Specification for Construction, as shown on the plans, and as directed by the Engineer.

Where installation is specified, install the span wire tether on existing or new signal head(s) at location(s) shown on the plans. Furnish, install, remove or install on the project, a span wire tether, as indicated on the plans or as directed by the Engineer.

Span Wire Tether ...................................................................................................... Each

20SP-820I-01

TRAFFIC SIGNAL WORK - CONSTRUCTION METHODS

SIG:EMS 1 of 2 APPR:HLO:NJB:04-29-20

a. Description. This special provision is for electrical construction and/or relocation of traffic signal facilities is to be used in addition to the applicable sections of the standard specifications.

In case of conflict use whichever is most restrictive.

b. Materials. Furnish new material and equipment, unless specified otherwise, and comply with sections 918 and 921 of the Standard Specifications for Construction. Materials furnished by the Department to the Contractor will be picked up by the Contractor at such site as designated by either MDOT, or the Local Agency representing MDOT, with any associated costs included in pay items as indicated on the plans and will not be paid for separately.

1. General. Provide manufacturer’s certifications, in accordance with the specifications, for all wire and cable and other items or as directed by the Engineer. Do not install any wire or cable before it has been approved by the Engineer. Include statement “Materials are in accordance with the Specifications” on their material order, especially on wire and cable.

Reuse only the best of the existing material and equipment where the contract calls for reuse of existing material and equipment as directed by the Engineer. The Department will have the right to furnish the Contractor with a new part if any are found defective prior to dismantling.

Any part or parts damaged by the Contractor subsequent to starting the removal are a liability of the Contractor.

Furnish the Engineer an as-built record of all underground or overhead work installed within 5 days after completion of each section of the underground conduit, cable or overhead line work. This record must include the size and length of cable and duct lines, location of the lines, handholes and manholes, and location and size of support poles. Tag and stamp all wires and cables using a brass tag indicating the source and use of the cable.

Connect the ground wire to the ground rod with a UL rated copper or bronze ground clamp.

c. Construction. All work must comply with sections 819 and 820 of the Standard

Specifications for Construction, the applicable “typical” signal construction details, this special provision, and requirements of the NEC, National Electrical Safety Code (NESC), and the Michigan Department of Licensing and Regulatory Affairs (LARA). Contact the LARA for electric service inspection and be responsible for payment of all applicable fees.

1. Maintain all existing street lighting, traffic signal, primary, transmission, communication cables, etc. circuits in an operational condition, unless otherwise noted on the plans or as directed by the Engineer.

2. In addition to subsections 104.07 and 812.03 of the Standard Specifications for

20SP-820I-01

SIG:EMS 2 of 2 04-29-20

Construction, the following applies to Contractor maintenance of permanent or temporary traffic signal installations which are being worked on by the Contractor:

A. The Contractor is responsible for maintaining any portion of a traffic signal which has been worked on by the Contractor until final acceptance of that specific location.

B. If MDOT forces are required to work on an emergency traffic signal malfunction that is determined to have been caused by the work of a Contractor, the cost of the work will be the responsibility of the Contractor.

C. If vandalism occurs to equipment that is not energized, the Contractor is responsible for replacement.

3. Utility Coordination. Notify the System Operating Division of the local utility 72 hours in advance of any work on underground or overhead transmission or distribution circuits. If possible, the System Operating Division will shutdown and red tag the line by 8 a.m. for the day requested. Notify the System Operating Division when the work is complete.

Provide coordination and make arrangements, as described above, to work on traffic signal circuits.

Schedule, coordinate, install, and pay for work provided by the local utility company(s), as indicated on the plans or as directed by the Engineer. The Engineer will not authorize payment for delay caused by the Contractor’s failure to properly schedule and coordinate any utility work.

4. Agency Coordination. Secure all necessary permits covering the operations, including permits from the Public Authorities having jurisdiction over the streets, or other Public Properties in which the work is located, and the improvements therein. Obtain the amount of any charges for payment, including fees or inspection charges required by such authorities, and include the cost of these fees in the bid prices.

The local traffic authority may impose restrictions regarding particular times of certain days of the week wherein the Contractor cannot perform work and may, in fact, be required to clear the area of work obstacles or construction equipment. The Contractor must take note of this and there will be no extra payment to perform the work with possible restrictions imposed.

The Engineer will not authorize extra payment if the Contractor chooses to perform work during overtime status.

5. Ensure construction is performed by persons who are experienced and qualified for the work required. On-site licensed (Journeyman electrician) supervision is required for the electrical system installation (including placement of traffic loops, conduits, and/or cables in dirt, foundations, and handholes) and must be present at all times when electrical construction is in progress. Ensure the ratio of electrical journeymen or master electricians to registered apprentice electricians is on the basis of one electrical journeyman or master electrician to one registered apprentice electrician in accordance with Michigan Law section 338.883e. This ratio is to be enforced on a jobsite basis. For traffic signal work a single jobsite is defined as a single intersection or single electronic traffic control device.

20SP-1003A-01

QUALITY INDEX FOR PORTLAND CEMENT CONCRETE

CFS:CPM 1 of 9 APPR:JFS:TES:04-30-20

FHWA:APPR:05-19-20

a. Description. This special provision establishes pay factor and price adjustments for Portland cement concrete based on Department administered Quality Assurance (QA) testing of 28-day compressive strength and fresh concrete air content of Portland cement concrete (PCC).

Perform all work in accordance with the standard specifications and this special provision.

Percent-within-limits (PWL) analysis for payment adjustments apply for mainline, shoulder, miscellaneous concrete pavement (including ramps), and concrete pavement overlay applications. Non-PWL analysis for payment adjustments apply for all other applications.

b. Materials. Mixture requirements will be in accordance with section 1004 of the Standard Specifications for Construction, unless otherwise specified in the contract.

c. Sampling. Sampling will be in accordance with subsections 1003.03.H and 1003.03.L of the Standard Specifications for Construction, except as modified herein. A sample is defined as a representative quantity of concrete taken during production which is used to measure the quality characteristics for the concrete. Compressive strength specimens for each sample consist of two cylinders, either 4-inch by 8-inch or 6-inch by 12-inch.

1. PWL Applications. Production lots for PWL analysis are made of at least five approximately equal sublots. The Engineer may approve occasional small individual quantities of concrete to be combined with a larger production lot provided they are of the same grade, contain the same Job Mix Formula (JMF), and are used for the same PWL application.

The random number method for PWL sampling will be used to determine the sampling locations. A random number will be generated for each sublot. The sampling frequency for a production lot is one QA sample per sublot.

If a sublot is not completed in sufficient quantity to permit it to be randomly sampled during its production day, as planned, the quantity of concrete for the sublot that was not placed as part of the day’s production will be sampled during the following production day in accordance with the original random number sampling protocol. The random sample will then represent the total quantity of concrete for the sublot placed over the respective multiple days of production.

If the quantity of a grade of concrete to be sampled on the last day of production for the project is not sufficient to make up three or more equivalent sublots, combine the test results for these one or two remaining sublots, or fraction thereof, with the previous day’s production lot for quality index analysis.

The Engineer will mold and cure two additional compressive strength cylinders, in the same

CFS:CPM 2 of 9 04-30-20 manner as the QA specimens, that are to be retained in the event of dispute resolution.

2. Non-PWL Applications. See subsection 1003.03.L of the Standard Specifications for Construction.

3. Small Incidental Quantities. See subsection 1003.03.J in the Standard Specifications for Construction for reduced sampling and testing for small incidental quantities.

d. Quality Index Analysis. The Engineer’s QA test results will be used to determine the pay factor (PF) and price adjustment (ADJ). The Contractor QC test results will not be used for PF and ADJ analysis. The Engineer will complete PF and ADJ analysis within 7 working days after completion of all 28-day compressive strength testing for the represented production lot or quantity of concrete. All values for PWL, overall lot pay factor (OLPF), and PF are in percent.

PWL values are rounded to the nearest whole number. PF and OLPF values are rounded to two decimal places.

1. PWL Applications. The PWL, PF, OLPF, and associated ADJ will be determined using the MDOT Concrete PWL Worksheet. The acceptable quality level (AQL), rejectable quality limit (RQL), lower specification limit (LSL), and upper specification limit (USP) are shown in Table 1. The Engineer will perform the quality index analysis for all concrete represented by lot size and makeup necessary for random sampling.

Table 1: Quality Index Parameter Specification Limits for PWL Applications

Quality Index Parameters Grade of Concrete

3500/3500HP

28-Day Compressive Strength

Specification Limit – Lower (LSL) (psi) 3500

Specification Limit – Upper (USL) N/A

Acceptable Quality Level (AQL) 95 PWL

Rejectable Quality Level (RQL) 50 PWL

Rejection Limit for an Individual Strength Sample Test Result (psi) 2500

Air Content of Fresh Concrete

Specification Limit – Lower (LSL) (percent) 5.5

Specification Limit – Upper (USL) (percent) 8.5

Acceptable Quality Level (AQL) 90 PWL

Rejectable Quality Level (RQL) 50 PWL

Suspension Limits (percent) < 5.0 or > 9.0

A. Pay Factor Determination for PWL Applications. The MDOT Concrete PWL

Worksheet uses the following formulas to calculate the PF and associated ADJ for each production lot. The maximum calculated numerical values for PF and OLPF will not exceed 105.00.

(1) Pay Factor for 28-day Compressive Strength (PFs). If PWL for 28-day compressive strength (PWLs) is 95 to 100 inclusive, use the following formula to determine PFs:

PFs = 5 + PWLs

CFS:CPM 3 of 9 04-30-20

If PWLs is from 50 to less than 95, use the following formula to determine PFs:

PFs = 47.22 + (0.5556 x PWLs)

If PWLs is less than 50, the production lot is rejectable and the Engineer will require additional evaluation to decide what further action may be warranted as described in section e of this special provision.

(2) Pay Factor for Air Content of Fresh Concrete (PFac). If PWL for air content of fresh concrete (PWLac) is 70 to 100 inclusive, use the following formula to determine PFac:

PFac = 55 + (0.5 x PWLac)

If PWLac is from 50 to less than 70, use the following formula to determine PFac:

PFac = 37.5 + (0.75 x PWLac)

If PWLac is less than 50, the Engineer will elect to do one of the following:

(a) Require removal and replacement of the entire production lot with new testing conducted on the replacement concrete and repeat the evaluation procedure.

(b) Provided no individual test results for the production lot are outside the suspension limits for air content, allow the production lot to remain in place and apply an Overall Lot Pay Factor (OLPF) of 50.00.

(c) Allow submittal of a corrective action plan for the Engineer’s approval. If the Engineer does not approve the plan for corrective action, subsections d.1.A.(2).(a) or d.1.A.(2).(b) of this special provision will be applied, as determined by the Engineer. All costs associated with plan submittal and corrective action under this subsection will be borne by the Contractor. Positive ADJ (quality initiative) will not apply for production lots subject to corrective action.

(3) Overall Lot Pay Factor (OLPF). Use the following formula to calculate the

OLPF:

OLPF = (0.60 x PFs) + (0.40 x PFac)

B. Price Adjustment for PWL Applications. Both pay factors (PFs and PFac) must be

100.00 or greater for the production lot to be eligible for positive ADJ (quality initiative) consideration. Use the following formula to determine price adjustment for each production lot, using the established Base Price for the pay item included in the contract:

ADJ = (OLPF-100)(Price)/100

2 Non-PWL Applications. Positive ADJ (quality initiative) does not apply for non-PWL applications. Each individual QA strength sample test result will be used to determine the PF and ADJ for the respective quantity of concrete that it represents, based on the sampling rate.

CFS:CPM 4 of 9 04-30-20

The specification limits for non-PWL applications are defined in Tables 2 and 3. Unless otherwise specified in the contract, concrete not conforming to the requirements specified in Tables 2 and 3 is rejectable and subject to further evaluation.

Table 2: Quality Index Parameter Specification Limits for Non-PWL Applications

Quality Characteristic Specification Limits

Air Content of Fresh Concrete (percent) 5.5 – 8.5

Rejection Limit (percent) <5.0 or >9.0

Conc. Temp. (deg. F) 45 - 90 at time of placement

Slump (max.) (inch) See footnotes a through l in Table 1004-1 of the Standard Specifications for Construction

28-day Compressive Strength (psi) For LSL see Table 3

Rejection Limit - 28-day Compressive Strength See Table 3

Table 3: Quality Index Parameter Specification Limits for 28-Day Compressive Strength (psi) for Non-PWL Applications

A. Pay Factor Determination for…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .