SBU_Document_Notice.pdf

PDF 83 KB Posted

Attached to
Amistad Reservoir Plugging of Penstock #4
Solicitation number
191BWC26B0006
Issued by

About this file

This document is a cover page for RFP 191BWC26B0006 issued by the International Boundary and Water Commission (IBWC) for the Amistad Dam Plugging Penstock #4 project.

Interested contractors must complete and submit an IBWC Form 358 Nondisclosure Agreement to the Contracting Officer (suzette.smith@ibwc.gov) to gain access to the solicitation documents. Access will be limited to no more than two email addresses per contractor. The document lists 25 available Supporting Business Unit (SBU) documents that include technical specifications, drawings, inspection reports, design documents, and operation and maintenance manuals related to Penstock #4 at Amistad Dam. These documents range from historical records dating to 1970 through 2021 and include reference materials for the dam structure. Additionally, all unsuccessful contractors are required to submit IBWC Form 358A-Nondisclosure Agreement Release within seven days of receiving notice of their unsuccessful offer. All required federal forms are available at www.ibwc.gov/resources-info/.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP 191BWC26B0006 - Amistad Dam Plugging Penstock #4

The documents listed below will be made available to interested contractors once a IBWC Form 358

Nondisclosure Agreement has been completed and provided to the CO (suzette.smith@ibwc.gov). Access will be granted for no more than two email addresses per contractor.

All unsuccessful contractors must submit IBWC Form 358A-Nondisclosure Agreement Release within seven days of receiving notice of their unsuccessful offer.

AVAILABLE SBU DOCUMENTS

SBU_00_01_15_Table_1_Plugging_Penstock_4_Drawings_20240628.pdf

SBU_00_01_15_Table_2_1_of_2_Amistad_Dam_Drawings_for_Reference.pdf

SBU_00_01_15_Table_2_2_of_2_Amistad_Dam_Drawings_for_Reference.pdf

SBU_00_31_19-1_4_A_1-Amistad_Penstock_4_Final_DDR_20211203.pdf

SBU_00_31_19-1_4_A_2-Amistad_Penstock_Final_Inspection_Report_20140321_RD.pdf

SBU_00_31_19-1_4_A_2-Amistad_Penstock_Final_Inspection_Report_App_A-20131107.AVI

SBU_00_31_19-1_4_A_2-Amistad_Penstock_Final_Inspection_Report_App_B-20131021.wmv

SBU_00_31_19-1_4_A_3-Report_on_Control_Changes_Penstock_Gates_4_5_19701119.pdf

SBU_00_31_19-1_4_A_4-Amistad_Penstock_4_Inspection_of_Liner_19771027.pdf

SBU_00_31_19-1_4_A_5-Penstock_#4_Leakage_Inspection_19820112.pdf

SBU_00_31_19-1_4_A_6-Amistad_Dam_Irrigation_Penstock_Gate_Study_200610_REDACTED.pdf

SBU_00_31_19-1_4_A_7-Amistad_Dam_Inspection_of_Penstock_4_20110819.pdf

SBU_00_31_19-1_4_A_8-Opening_Gates_in_Penstock_4_19860506.pdf

SBU_00_31_19-1_4_B_1-2012_04_24_Amistad_Penstock_4_Concrete_Damage.wmv

SBU_00_31_19-1_4_B_2-2013_08_23_Amistad_Penstock_4_Concrete_Damage.wmv

SBU_00_31_19-1_4_B_3-2013_12_06_Amistad_Penstock_4_Concrete_Damage.wmv

SBU_00_31_19-1_4_B_4-2013_02_06_Seepage_Amistad_Penstock_4_Gate.wmv

SBU_00_31_19-1_4_C-Amistad_Specifications_Vol_II_UDA_65-3.pdf

SBU_00_31_19-1_4_C-Amistad_Specifications_Vol_I_UDA_65-3.pdf

SBU_00_31_19-1_4_E-Amistad_Dam_1971_O-M_Manual.pdf

SBU_01_55_26-1_6_C-Amistad_Dam_Structural_Analysis_of_Bridge_Deck_200601.pdf

All forms are available at: www.ibwc.gov/resources-info/ mailto:suzette.smith@ibwc.gov https://www.ibwc.gov/resources-info/