Federal Aviation Administration

Federal Aviation Administration

Surveillance Broadcast and Information

Services (SBIS)

Industry Event

July 28, 2021

Federal Aviation Administration

Pamela Maxwell Surveillance Broadcast and

Information Services

Project Lead

3July 28, 2021 Surveillance Broadcast and Information

Services Industry Event

SBIS Industry Event

Welcome

Opening Remarks

Ground Rules

SBIS Acquisition Plans

Break

SBIS Systems Engineering

Break

SBIS Cost Estimates

Break

RFI-2 and Open Q&A

Closing

Pamela Maxwell

Dan Hicok

Phil Moyers

Pamela Maxwell

Andy Leone

Shahan Stepanian

Pamela Maxwell

Pamela Maxwell

Federal Aviation Administration

Dan Hicok Surveillance Services

Director

Federal Aviation Administration

Phil Moyers Surveillance Team

Contracting Officer

Contracts Highlights

• Questions during the event

• Posting of materials

• Proprietary information

• No acquisition sensitive information will be discussed today

• Recording of session

6Surveillance Broadcast and Information

Services Industry Event

Federal Aviation Administration

Pamela Maxwell Surveillance Broadcast and

SBIS Acquisition Highlights & Notional Timeline

Unrestricted, competitive procurement for

SBIS beyond 2025!

Targeting 2025 for

Contract Award.

Solution anticipated to remain operational through 2040.

Innovation is the name of the game!

New approaches are welcome.

Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

2020 2021 2022 2023 2024 2025 2026+CY:

RFI #1

Release

P ro je c t

A c ti v it ie s

P ro c u re m e n t

M il e s to n e s

Industry

Day #1

RFI #2 /

Industry

Day #2

Industry

Engmt.

Partial Draft

SIR #1 /

Industry Day #3

Draft

SIR #2

Final

SIR

Contract

Award

J R

C

M il e s to n e s

IARD IID FID

Acquisition Strategy Analysis and Refinement

Transition and

Implementation

SIR Approval

SBIS Requirements and Document Development

Industry

Engmt.

Industry

Engmt.

Surveillance Broadcast and Information

SBIS RFI-2: Key Elements Things to know about RFI-2

There are three categories of RFI attachments: Existing SBS Documentation, Future SBIS Information, and SBIS RFI Response Fil es

The RFI covers: Acquisition Approach, Network/Communications, Transition, Enhancements and Innovation, Security/Resiliency, Cost

Service-Based

Acquisition

Utilizing FAA

Enterprise

Network Services

(FENS)

Other Transaction

Authority (OTA)

Contracts for

Oceanic / Remote

Areas and/or

Surveillance

Processing and

Networking (SPaN)

Transition

Approaches and

Risk Mitigation

Options, Rough

Order of

Magnitude (ROM)

Cost Estimates

Enhancements and Opportunities for Innovation

Responses Due

August 24, 2021

Surveillance Broadcast and Information

SBIS RFI-2: Acquisition Approach

The focus is to explore:

• A service-based acquisition alternative, using FENS, to deliver:

– Existing Services

– Enhancements

– Innovation Opportunities

Service Provider

• Owns & Operates

• Designs & Installs

• Meets Technical Performance Requirements

• Manages SBIS Configuration Management

• Maintains National Operations Center

(NOC)

FAA

• Approves the Design

• Owns the Data

• Controls Performance

Requirements

• Oversees Configuration Management

• Provides 24x7 Navigation and Surveillance Enterprise Control Center (NECC)

SBIS as a Service-Based Acquisition

Surveillance Broadcast and Information

Vendor Engagement

Oceanic and

Remote

Environments

Service Funding

Structures

Transition and

Operational Risk

Implications of

Using FENS

• Opportunities for innovation

• Suggestions for potential OTAs

• Mechanisms to support collaboration and cooperation among vendors

• Recommendations

(strategy / requirements) to provide services in oceanic and/or remote environments

• Recommended pricing construct

• Suggestions for performance incentives and disincentives

• Plans for efficient transition and implementation that minimizes risks and impacts to existing operations

• Plans for allocating performance requirements

(e.g., latency, timing, update interval)

• Plans to measure, monitor, report, and achieve / verify end-to-end performance

SBIS RFI-2: Acquisition Approach Associated RFI-2 Topics:

V.1.a V.1.b

V.1.c V.1.d

Seeking industry feedback on:

• Your recommended SBIS acquisition approach and architecture

• Your ideas for engagement to shape the future for SBIS

Surveillance Broadcast and Information

Any

Questions?

RFI Topics: Acquisition Approach, Network / Communications, Transition, Enhancements and Innovation, Security/Resiliency, Cost

Federal Aviation Administration

Andy Leone Surveillance and Broadcast

Services

Systems Engineering Lead

SBIS RFI-2: Network / Communications

The existing SBS network is a secured private network connecting the Ground Station and Control segments to

Service Delivery Points at FAA facilities.

Associated RFI-2 Topics:

V.2.a

V.2.b V.2.c

V.2.d

Service Delivery

Control Segment

Airspace Segment

Ground Station Segment

1090 ES A/V UAT A/V ATCRBS/Mode S A/V

Radio Station

Radio Station MLAT Radio Station

Control Station Control Station

FAA TIS-B Data SDPFAA ATC Automation S DP FAA Service Monitor S DP

MLAT Radio Station

NOC

Space-Based

ADS-B

Weather Data

S B

S P riv a te N e tw o rk

Existing SBS Network Architecture

S e c u rity G a te w a y

Surveillance Broadcast and Information

S e c u rity G a te w a y

SBIS RFI-2: Network / Communications

FAA Facilities

Control Segment

Airspace Segment

Ground Station Segment

1090 ES A/V UAT A/V ATCRBS/Mode S A/V

Radio Station

Radio Station MLAT Radio Station

Control Station Control Station

FAA Radar DataFAA ATC Automation FAA Service Monitor

MLAT Radio Station

NOC

Space-Based

ADS-B

Weather Data

S B

IS

P riv a te N e tw o rk

FENS

Associated RFI-2 Topics:

V.2.a

V.2.b V.2.c

V.2.d

The FAA is exploring the appropriate use of FENS within the

SBIS architecture and is looking for input on how industry would integrate FENS into their proposed solution.

G o v e rn m e n t V e n d o r

Notional SBIS FENS Network Architecture

Security Gateway SDPs

Surveillance Broadcast and Information

SBIS RFI-2: Transition

An SBIS transition may be complex.

Implementation considerations have been provided in Attachment 10.

Seeking industry feedback on:

• A transition approach and timeline for your implementation strategy

• Major assumptions and constraints

• An approach to de-conflict undue frequency interference (1030, 1090 and 978MHz) and account for coordination of the UAT channel management of the ground segment time slots between the operational SBS system and the new SBIS system

• Transition risks and mitigation opportunities

• Technical suggestions for transition risk mitigation which could be implemented prior to SBIS contract award, should a transition be required

Site Logistics

Uplink Advisory Services

Flight Inspection

Automation Integration

Transition Considerations

Associated RFI-2 Topics:

V.3.a

V.3.b V.3.c

V.3.d

Surveillance Broadcast and Information

SBIS RFI-2: Enhancements

• Minimum Operational Performance Standards (MOPS)

• Updated Interfaces

• Alternate/Backup Timing Source

• ADS-B Surface Expansion

• Surveillance Services for Remote Towers

• WAM Expansion (En Route and Terminal WAM Service Volumes)

• Expansion of 3NM Separation throughout En Route Airspace

• Information Systems Security

• Supply Chain Risk Management

The FAA is considering the list of enhancements below for inclusion in the future SBIS system. RFI-2 requests input specifically for those in black;

however, responses are also welcome for the topics in grey.

Note: See Attachment 7 – SBIS ConOps Supplement

Key:

• Topic included in RFI-2

• Topic not included in RFI-2

Surveillance Broadcast and Information

SBIS RFI-2: Enhancements Minimum Operational Performance Standards (MOPS)

New 1090 ES MOPS

(DO-260C)

• Phase Overlay

• Increased maximum squitter rate

• Additional data fields in ABS-B messages

– Weather messages

– Interrogation and reply monitoring

– UAS contingency

– High altitude, high velocity extended squitter

Associated RFI-2 Topics:

V.4.c

V.4.k

Surveillance Broadcast and Information

SBIS RFI-2: Enhancements Alternate non-GPS Dependent Timing Source

• SBIS will require the use of an alternate timing source

• Global Positioning System (GPS) timing has potential to expose systems to unintended or malicious signal jamming

• System owners must migrate to a

National Institute of Standards and

Technology (NIST) or United States Naval

Observatory (USNO) traceable source provided by resilient FAA enterprise timing systems and/or services

• Department of Transportation (DOT) is in the process of defining the requirements and parameters for Reference Timing

• See Executive Order 13905 and FAA

Order 1770.68

GPS Timing (UTC)

Radio Station

Alternate

Timing Source

Associated RFI-2 Topics:

V.4.d

V.5.b

Surveillance Broadcast and Information

SBIS RFI-2: Enhancements Reduced 3NM Separation throughout En Route Airspace

Efficiency benefits can be obtained by expanding the airspace where ADS-B can be used for 3NM separation to all en route airspace, including that above Flight Level 230.

• Requires changes in performance requirements for en route service volumes to provide ADS-B updates at 3 seconds (95%) or better in all 1090 MHz interference environments.

• Position validation capabilities will be required to utilize thresholds applicable for 3NM airspace.

• Conflict alert and conflict probe thresholds for FAA Automation Systems will need to be adjusted to support reducing separation in the airspace above Flight Level 230.

20Surveillance Broadcast and Information

SBIS RFI-2: Enhancements Information Systems Security

• SBS/SBIS is a FIPS-199 “High” security categorized system

– Subject to all governmental reporting requirements

– Infrastructure migration for predominately Internet Protocol (IP)-based capabilities and transport

(versus legacy Time Division

Multiplexing)

– Resiliency requirements include mitigation of GPS and ADS-B jamming

/ spoofing threats, cyber resiliency / operational redundancy

– Integration with NAS Cyber

Operations

Associated RFI-2 Topics:

V.5.a

V.5.b V.5.c

V.5.d

Surveillance Broadcast and Information

SBIS RFI-2: Opportunities for Innovation

• Oceanic and Remote Service Coverage

• Gulf of Mexico

• Surveillance Processing and Networking (SPaN)

• Surveillance Services for Staffed VFR Towers

• Enhanced Weather/New FIS-B Products

• Incentives to Support Commercial Space Evolution

• Surveillance Architecture

• Future SBIS Enabled Applications

• Contingency / Disaster Recovery Planning

The FAA is looking for feedback on innovative approaches to the list of topics below for inclusion in the future SBIS system. RFI-2 requests input specifically for those in black; however, responses are also welcome for the topics in grey.

Key:

• Topic included in RFI-2

• Topic not included in RFI-2

Surveillance Broadcast and Information

SBIS RFI-2: Innovation Opportunities Oceanic and Remote Service Coverage

• The FAA is looking for solutions to provide services in oceanic and remote airspace

– Airspace where deploying a ground-based infrastructure is challenging, due to terrain, water, lack of infrastructure, etc.

• Draft requirements are included in Attachment 9 -

Oceanic/Remote Service

Specification

Associated RFI-2 Topics:

V.4.h

V.4.j V.6.a.ii

V.6.a.iii V.6.a.iv

ZNY

ZAN

Oceanic

ZOA

ZAN

Arctic

1 Average Daily ATOP Operations from October 2015 to September 2016

Facility Miles of Airspace Flights per Day1

New York (ZNY) 3.3M sq miles 680

Oakland (ZOA) 18.6M sq miles 878

Anchorage (ZAN) 1.2M sq miles 255

1 Average Daily ATOP Operations from March 2019 to February 2020

Surveillance Broadcast and Information

SBIS RFI-2: Innovation Opportunities Gulf of Mexico

Challenges

• Platform availability and longevity

– Affected by oil prices

• Restricted access (helicopters, boats)

– No scheduled transportation methods available to

FAA and FAA contractors

• Environmental impacts on equipment

– Tropical storms, hurricanes, high temperatures, high humidity, and saltwater have a heavy impact on equipment

• Space limitations on platforms

– Unobstructed line of site is challenging and may require costly platform modifications

• Reliance on platform telecom

– Not designed to meet FAA reliability requirements

Associated RFI-2 Topics:

V.1.b

V.4.h V.4.i

V.4.j V.6.a.ii

Source: Helicopter Association International

Surveillance Broadcast and Information

Security Gateway SDPs

SBIS RFI-2: Innovation Opportunities Surveillance Processing and Networking (SPaN)

• Manage and process surveillance information (ADS-B, WAM, and Radar)

• Enhance FAA surveillance processing and networking capabilities and broaden the surveillance infrastructure

• Increase data distribution capabilities allowing new applications

• Additional processing applications and capabilities

FAA Facilities

SBIS Segment

Radio Stations Control Station

External Users (e.g., UAS, Commercial Space)FAA ATC Surveillance Sensors

MLAT Radio Station

SBIS Private Network

FENS

Associated RFI-2 Topics:

V.1.a

V.1.d V.4.g

Surveillance Processing and Network

NOC

Centralized Tracking (CSTS)

Advanced Applications for

TBO

Inter-Sensor Coordination

Sensor Data Integration xTM/UTM/Space Vehicle Data Integration

Service-Level Centralized Monitor ing

Future Application

Surveillance Broadcast and Information

SBIS RFI-2: Innovation Opportunities Surveillance Architecture

• Evolve surveillance architecture to an open, standards-based, modular architecture

• SPaN would be the backbone of this architecture

Benefits include:

• Reducing costs to develop, operate, and sustain NAS surveillance and automation systems (in support of Automation Evolution)

• Reducing time to develop, integrate, and deploy new capabilities

• Leveraging commercial industry best practices

• Establishing a broad industry base to support the FAA across a range of development and deployment capabilities

SPaN

Surveillance Broadcast and Information

SBIS RFI-2: Other Innovation Opportunities

• Improved capabilities to track commercial spacecraft

• Commercial spacecraft equipped with ADS-B would provide real-time surveillance information to both Air Traffic and the operators z y x

RX 1 RX 2

RX 3RX 4

Intersecting

Hyperbolas

Mode A/C/S Replies and ADS-B Squitters

TDOA

Processing

NAV Position Uplink

ADS-B Phase Overlay

• Provide operators real-time

ADS-B data for a more complete picture of the airspace in which they are operating

• Provide Air Traffic improved visibility and allow for better airspace management

Commercial Space Evolution

UAS/UTM Support

APNT Support / Applications

• SBIS provision of APNT through phase overlay broadcast service

• Alternative Navigation Application

Surveillance Broadcast and Information

SBIS RFI-2: Service Volumes for Cost ROM

Southern California TRACON (SCT)

• Terminal (both ADS-B and WAM)

• Three underlying surface ADS-B volumes (LAX, SAN, SNA) were also included

• They fall within SCT, and their infrastructure would likely contribute to the terminal ADS-B and WAM SVs

– ADS-B and associated ADS-B In services are intended to meet the current coverage provided to ATC and aircraft operators

– WAM coverage will be to the published MVAs – 300 feet

– It should be assumed that the overlying en route SV will have a ceiling of 1,051,500 feet (173 NM)

ADS-B Coverage WAM Coverage

Surveillance Broadcast and Information

SBIS RFI-2: Service Volumes for Cost ROM

29Surveillance Broadcast and Information

Services Industry Event

Alaska

Gulf of Mexico

• Looking for innovative approaches for tackling these more challenging environments

• Ceiling for all of the en route SVs will include Upper Class E, up to 1,051,500 feet (173 NM)

New York Oceanic

Any

Questions?

RFI Topics: Acquisition Approach, Network / Communications, Transition, Enhancements and Innovation, Security/Resiliency, Cost

Federal Aviation Administration

Shahan Stepanian Surveillance Broadcast and

Cost Lead

RFI-2 requests the following details pertaining to cost estimates:

• Provide a ROM for development/first article costs

• Provide a ROM for your preferred acquisition approach to include all SBS services and the SBIS enhancements described in Attachment 7, for the following Service Volumes:

– Southern California TRACON (SCT)

• Terminal (both ADS-B and WAM), plus three underlying surface ADS-B volumes (Los Angeles, San

Diego, John Wayne-Orange County)

– Gulf of Mexico

– Alaska

– New York Oceanic

• Please provide the methodology that may be used to extrapolate NAS-wide for all service volumes

• Please discuss your recommended pricing construct and performance incentives/disincentives

• Reminder, mark all confidential and proprietary information accordingly

SBIS RFI-2: Cost Estimates Associated RFI-2 Topics:

V.1.c

V.6.a V.6.b

V.6.c

Surveillance Broadcast and Information

SBIS RFI-2: Cost Estimate

RFI-2 provides cost templates for the following:

Development / First Article

Costs (1) Individual Service Volumes (7) Summary (1)

Includes non-recurring costs and costs to stand up the system

(e.g., software development, Factory

Acceptance Testing)

Terminal Southern California plus three underlying surface ADS-B volumes (Los Angeles, San Diego, John Wayne-Orange County)

Alaska, Gulf of Mexico, and New York

Oceanic

Summary of all the individual cost templates

Surveillance Broadcast and Information

SBIS RFI-2: Cost Estimate Inputs – Labor, Material and Schedule

WBS

• FAA WBS v5.3 (WBS dictionary provided as attachment: FAA WBS

5.3)

Material / ODC

• Build up of Material and ODC

• All additional details to be captured in the cost template backup tabs (e.g., source information, specific information on cost buildup, etc.)

Labor

• High-level labor categories

• Fully loaded labor rates

Schedule

• Provide a high-level production and installation schedule

Surveillance Broadcast and Information

SBIS RFI-2: Cost Estimate WBS Matrix

35Surveillance Broadcast and Information

SBIS RFI-2: Cost Estimate WBS Matrix (Continued)

Review of cost model template

Surveillance Broadcast and Information

Any

Questions?

RFI Topics: Acquisition approach, Network / Communications, Transition, Enhancements and Innovation, Security/Resiliency, Cost

Federal Aviation Administration

Pamela Maxwell Surveillance Broadcast and

RFI-2 and Open Q&A

Submit Your RFI Responses

• Submit RFI-2 Responses by August 24, 2021 to Phil Moyers, Phillip.L.Moyers@faa.gov and

Aleksandra Skoric, Aleksandra.Skoric@faa.gov

• Today's presentation will be posted on SAM.gov

Please provide your solutions for the SBIS missions and/or ideas for engagement to define the acquisition.

Looking ahead:

Partial Draft SIR #1

3rd Quarter 2022

*Note: Any proprietary or confidential information contained in any industry submissions that should not be released to the public should be appropriately marked, and industry should be prepared to provide justification to the FAA of such designations, if requested.

Surveillance Broadcast and Information

Services Industry Event https://sam.gov/opp/df36f5fa43904cb48b02468594eb567c/view

BACKUP

SBIS RFI-2 Attachments

• Attachments reflecting current SBS requirements o Attachment 1 – SBS Services Description Document o Attachment 2 – ConOps for SBS o Attachment 3 – Gulf of Mexico o Attachment 4 – SBS ADS‐B and ADS‐R Critical Services Specification o Attachment 5 – SBS Essential Services System Specification o Attachment 6 – WAM Critical Service Specification

• Attachments describing future SBIS requirements/concepts o Attachment 7 – SBIS ConOps Supplement o Attachment 8 – SBIS Service Volume Description Document o Includes SBIS_SCT_SV-T1_ADS-B_Coverage.kmz o Attachment 9 – Oceanic/Remote Service Specification (DRAFT) o Attachment 10 – SBIS Implementation Considerations

• Attachments for responding to the RFI o Attachment 11 – COST/ROM Template o Attachment 12 – SBIS RFI-2 Comment and Question Matrix

42Surveillance Broadcast and Information