Amendment 001 Questions & Answers

The purpose of this amendment is to answer the following questions received in response to

Solicitation # SB1341-15-RQ-0710, Synchrophasor Network Testbed Implementation for Wide

Area Monitoring and Measurement of Power Grid

1. “Does this project require all the personnel must be working at NIST, Maryland? That means any of the tasks cannot be finished outside NIST office in Maryland?”

ANSWER: This is an ongoing NIST project for implementing the ANTD/NIST testbed.

It is essential that the contractor works full-time onsite in order to access the existing

NIST testbed.

2. “Can we invite a university professor to involve as subcontractor? Is an international graduate student of this professor able to work on this project?”

ANSWER: NIST has no privity of contract over the prime contractor’s subcontractors.

However, regardless of any subcontractors used by the prime contractor, all key personnel requirements detailed in the solicitation and subsequent Statement of Work must be met.

3. “Do you have the maximum budget requirement?”

ANSWER: The budget for this procurement is considered procurement sensitive information and will not be shared.