SB1341-15-RP-0023_-_Amendment_2_SF_30.pdf

PDF 3 MB Posted

Attached to
NIST Semi-Anechoic Chamber Federal contract opportunity
Solicitation number
SB1341-15-RP-0023
Issued by
Department of Commerce National Institute of Standards and Technology

About this file

SB1341-15-RP-0023 - Amendment 2_SF 30

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NSN 7540-01-152-8070 STANDARD FORM 30. (Rev. 10-83) Previous Edition unusable Prescribed by GSA FAR (48 CFR) 53.243

Page of Pages AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. Contract ID Code

2. AMENDMENT MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (if applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE

(x) 9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

8. NAME AND ADDRESS OF CONTRACTOR (NO., Street, Country, State and ZIP Code)

CODE FACILITY CODE

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning ______ copies of amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OR OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

Check One

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return _______ copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible)

Except as provided herein, all terms and conditions of the document referenced in item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR 16B. UNITED STATES OF AMERICA

(Signature of person authorized to sign)

15C. DATE SIGNED

(Signature of Contracting Officer)

16C. DATE SIGNED

Continuation Page

PAGE 2 OF 21 SB1341-15-RP-0023/002

Continued from Block 14...

2. Revise the Performance Specification as a result of questions received. Attachment 2 to this amendment identifies the performance specification paragraph number, original wording and the changed wording.

3. Incorporate a revised Attachment B - Performance Specification dated 7/16/15. This revised performance specification includes all changed paragraphs. The revised Attachment B - Performance Specification dated 7/16/15 hereby replaces the previous version in its entirety. Changed paragraphs are highlighted.

4. Clarify that offers shall be submitted to:

National Institute of Standards & Technology Acquisition Management Division, Team E ATTN: Matthew Gomer 325 Broadway Building 111 Boulder, CO 80305

5. Extend the offer due date to July 24, 2015 at 4:00pm Mountain Time.

Table of Contents

PAGE 3 OF 21 SB1341-15-RP-0023/002

SECTION

. 1 Attachment 1 of RFP Amendment 2

. 2 Attachment 2 of RFP Amendment 2

. 3 Attachment 3 of RFP Amendment 2

PAGE 4 OF 21 SB1341-15-RP-0023/002

SECTION

. 1 Attachment 1 of RFP Amendment 2

ATTACHMENT 1 of RFP AMENDMENT 2 Site Visit Questions and Government Response

Question No.

Attachment No.

REFERENCE QUESTION GOVERNMENT RESPONSE

Page Section Para.

1 B N/A N/A N/A Will the crane be repositioned prior to installation? The overhead crane in room 1300 will be parked up against the north wall of the room, as far away as possible from the installation area.

2 B 8 III N/A Will NIST provide a forklift for use during installation? No. The contractor is responsible for providing a forklift during installation of the chamber. See Attachment B, page 8, under the "Installation" section.

3 C 1 N/A N/A What is the dimension between the floor and the existing fire stand pipe on the ceiling?

This dimension is 23 feet. Please see specification 2.4 in Attachment B (page 2).

4 B 2 III 2.2 What is the dimension between the east and west wall of the chamber (as shown on the drawing)?

This dimensions is 25 feet, 6 inches.

Note that this dimension revises the original width dimension of 26 feet.

5 B 6 III 10 Can you confirm that this chamber will only require fire detection?

As stated throughout Paragraph 10 of Attachment B (page 6), this chamber requires a VESDA brand air sampling fire detection system. A suppression system is not required.

6 B 7 III 12 Where should the camera be located? Where should the second camera be installed in the future?

Aside from the requirements in specification 12 of Attachment B (page 7), there is no strict requirement on the location of the camera, or the location of the future camera.

7 B 2 III 4 How will the space be ventilated during the attachment of the absorber?

The contractor is responsible for ensuring there is adequate ventilation to conduct their installation activities. If fans are required, it is the contractor's responsibility to provide them.

PAGE 5 OF 21 SB1341-15-RP-0023/002

8 B 8 III N/A Can work that may be disruptive to other building occupants be done at night (e.g., anything generating fumes)?

Work may not be performed at night.

Work may only be performed during the hours shown in Attachment B, page 8, under the "Installation" section.

9 B 5 III 7 How are the clear door dimensions specified? If absorber is fixed to the door, the door may be very large in order to meet the clear dimensional requirement.

We clarify specification 7 of Attachment B (page 5) to say that the absorber on the large door (north side of chamber) may be removed in order to meet the clear dimension requirements. The requirements for the smaller personnel door on the east side of the chamber remain unchanged. The clear dimension requirements for this door must be met without removing the absorber from the door.

10 B 5 III 9 Confirm the rod/hook arrangement in the chamber. NIST will provide the conductive fabric?

Specification 9 of Attachment B outlines the dielectric rods/hooks that the contractor is responsible for installing in the chamber. NIST will provide the conductive fabric that hangs from these hooks.

11 N/A N/A N/A N/A If NIST personnel (and their forklift) will off-load chamber materials that are shipped to NSIT, what is the capacity of the NIST forklift

NIST personnel and their forklift will not be available for use by the vendor. The vendor will be responsible for unloading freight that arrives at the NIST site. If a forklift is required for this, it is the vendor's responsibility to provide it.

12 B 8 III N/A Are we [the vendor] responsible for any disposal costs of de-construction debris?

As stated in the "Installation" section of Attachment B (page 8), the contractor is responsible for removing all trash generated by the installation process.

13 B 8 III N/A Can we [the vendor] have the name of disposal companies for our construction disposal?

Waste Management is the current disposal company at NIST Boulder.

14 B N/A III N/A Can materials be staged in the area outside of the building?

Material may be staged in the area outside of the 1300 room, but may not interfere with traffic on the street or block any entry points of the building.

PAGE 6 OF 21 SB1341-15-RP-0023/002

15 C 1 N/A N/A Are the clear space dimensions for the chamber provided on the drawings?

Some dimensions are provided on the drawing. Additional dimensions are provided in specification 2 of attachment B (page 2).

16 B 11 III N/A Will installers have site access after the badging process? Once installers complete the badging process, they will be able to access the site without first having to go through the visitor's center.

17 B 11 III N/A Will installers be escorted at all times? Installers will be allowed to work in room 1300, unescorted. However, installers will not be allowed to work when there is not a NIST technical representative on-site.

18 B 5 III 8 Is there going to be an HVAC connection to the main building?

There will be no connection between the chamber and the building's HVAC system.

19 B 5 III 8 Is there a CFM requirement for the HVAC system in the chamber?

There is no specific CFM requirement for the chamber's HVAC system.

20 A 5 III 9 Will NIST accept early delivery (ahead of the deliverables scheulde shown in Attachemnt B)?

Yes. The schedule shown in Section VII of Attachment B represents the longest schedule NIST will accept. Offerors are encouraged to submit schedules that are more aggressive (but still reasonable) in their proposals. Note that due to the construction activities required to prepare the space, NIST will not be able to facilitate the chamber being installed before December 1st, 2015.

PAGE 7 OF 21 SB1341-15-RP-0023/002

21 I am a little leery on the spec part about the Notifier responsibility. I have no idea what they currently have. It could be a simple update to the existing system, but if it's a large campus with multi nodes that all require updating with this VESDA system you could be looking at many hours of on-site labor to implement this small VESDA system. To properly quote this part of thr specification we would neeed access to the Notifier facility system design drawings and overall understanding of the system complexity in order to adequately quote updating the facility program and drawings with the added VESDA system. PLEASE ADVISE HOE EXTENSIVE YOU WANT THE

SYSTEM TO BE.

NIST currently has a site-wide Notifier brand fire alarm system. The Contractor is responsible for (through a NESCO/Notifier certified contractor) terminating the fire alarm wires from the semi-anechoic chamber’s detection system into the building’s fire alarm controller, setting the VESDA detector level (i.e., obscuration thresholds), updating the fire alarm system drawings, and updating the NIST site-wide Notifier program to recognize and respond to the chamber’s VESDA detection system.

For security reasons, NIST is unable to disclose the exact specifications of its fire alarm network. However, we feel that this is enough information for a NESCO/Notifier contactor to make an assessment regarding how much labor is required to complete the required tasks.

Specifications 10.6 and 10.7 in Section III of Attachment B have been updated to reflect this clarification.

PAGE 8 OF 21 SB1341-15-RP-0023/002

. 2 Attachment 2 of RFP Amendment 2

ATTACHMENT 2 of RFP AMENDMENT 2 – PWS Changes

1. Paragraph 2.2 (page 2 of 12) of Section III of Attachment B is changed FROM: “The volume shown on Attachment C measures: 43 feet long, 26 feet wide and 22 feet high.

The final size of the chamber (including any structural support) shall be contained within this volume. The door ramp, steps, electrical power filters, and HVAC components and ducting (if required) may exceed this volume.”

TO READ: “The volume shown on Attachment C measures: 43 feet long, 25.5 feet wide and 21.5 feet high. The final size of the chamber (including any structural support) shall be contained within this volume. The door ramp, steps, electrical power filters, and

HVAC components and ducting (if required) may exceed this volume.”

2. The following is added to the end of Paragraph 7.1 (page 4 of 12) of Attachment B:

“Note that to achieve the required clear opening, any absorber attached to the door may be removed when the door is opened.”

3. Paragraph 10.6 (page 6 of 12) of Section III of Attachment B is changed FROM: “The

Contractor is responsible for ensuring that the chamber’s detection system is tied into the site-wide fire alarm system (which is a Notifier brand system). This must be done by an authorized Notifier contractor.”

TO READ: “The Contractor is responsible for terminating the fire alarm wires from the semi-anechoic chamber’s detection system into the building’s fire alarm controller, and setting the VESDA detector level (i.e., obscuration thresholds). Only certified Notifier contractors that are also a Notifier Engineered Systems Company (NESCO) will be permitted to connect to and update the NIST fire alarm system.”

4. Paragraph 10.7 (page 6 of 12) of Section III of Attachment B is changed FROM: “The

Contactor shall also have an authorized Notifier contractor update the NIST system program and applicable drawings to reflect the addition of this new air sampling system.

The Notifier contractor performing these updates must also be a Notifier Engineered

Systems Company (NESCO).”

TO READ: “The Contactor shall also have an authorized Notifier contractor update the

NIST system program to respond to the semi-anechoic chamber’s detection system and applicable drawings to reflect the addition of this new air sampling system. This work must also be done by a Notifier/NESCO certified contractor.”

PAGE 9 OF 21 SB1341-15-RP-0023/002

5. The last sentence of Paragraph 1 of the Installation sub-section of Section III of

Attachment B (page 9 of 12) is changed FROM: “Installation is to begin within 200 days of award.”

TO READ: “Installation may begin as soon as December 1st, 2015, but shall not begin more than 270 days of award.”

6. Section VII Deliverables (page 10 of 12): The due date for the “Start of installation of the Semi-Anechoic Research Chamber” is changed FROM: “270 days after award of this requirement/”

TO READ: “270 days after award of this requirement, but not earlier than December 1st, 2015.”

PAGE 10 OF 21 SB1341-15-RP-0023/002

. 3 Attachment 3 of RFP Amendment 2

PERFORMANCE SPECIFICATION

7/16/2015

TITLE: Semi-Anechoic Research Chamber

I. BACKGROUND INFORMATION

The Communications Technology Laboratory is in the process of expanding its research efforts related to spectrum sharing. This research spans a broad area covering topics associated with distributed spectrum sensing, signal propagation, interference between devices, and evaluating a device’s ability to share spectrum. As we explore each of these topics, a controlled RF environment where signals can be radiated is required. This environment ensures that its interior volume is shielded from signals radiated from outside the chamber. Further, the interior of the chamber is equipped with absorbing material on the walls and ceiling such that signals radiated from within the chamber are absorbed and do not scatter (ideally). This type of environment is commonly referred to as a semi-anechoic chamber. Most semi-anechoic chambers are designed, built, and used for testing pursuant to specific EMC standards (e.g., IEC 61000-4-3). However, the specifications of a semi-anechoic chamber that will have a research focus are slightly different than for a chamber being used for standard EMC tests, as described below. One of the key differences is that we intend to use a majority of the volume of the chamber in our research (rather than a designated “test volume”). As this chamber will be used for wireless communications research, it is neither feasible nor reasonable to specify the exact application and/or measurements that will take place within the chamber.

II. SCOPE OF WORK

Using the common semi-anechoic chamber specifications as a foundation, several changes are being made that result in a chamber that is more suitable for the type of research NIST will be conducting. Like most semi-anechoic chambers, we envision this chamber consisting of the following key components: a shielded enclosure, two doors allowing ingress/egress to the chamber, electromagnetic absorbing material (foam-type absorber and ferrite tiles) lining the walls and ceiling, and a raised floor within the chamber that serves as an electrical ground plane.

Given the specific use of this chamber, a fire suppression system is not required within the chamber. The contractor shall minimize or eliminate the use of exposed combustible materials.

For example, in cases where oriented strand board (OSB) is commonly used, we require less combustible materials instead (e.g., fire-resistant plywood). Additionally, any absorbing materials used in the chamber shall be of limited-combustibility and tested in accordance with the appropriate standards, as detailed below.

III. SPECIFICATIONS

The Contractor shall provide one (1) semi-anechoic research chamber that meets the following minimum technical requirements. The Contractor shall design and install the chamber, and provide training as described below.

PAGE 11 OF 21 SB1341-15-RP-0023/002

1. The chamber shall operate from 100 MHz to 40 GHz.

2. This chamber shall be constructed inside existing Government laboratory spaces. The chamber shall be free-standing within the space. The floor of the space is constructed of reinforced concrete approximately 10-12 inches thick. Any structure supporting the chamber may be anchored to this floor, but attaching to any existing walls or the ceiling is not permitted.

2.1. Given the size of the space available, this chamber will be similar to (or the same as) the dimensions of a typical 5 meter semi-anechoic EMC test chamber. The attached drawing

(Attachment C) shows the existing room, and the volume the new chamber shall not exceed.

2.2. The volume shown on Attachment C measures: 43 feet long, 25.5 feet wide and 21.5 feet high. The final size of the chamber (including any structural support) shall be contained within this volume. The door ramp, steps, electrical power filters, and HVAC components and ducting (if required) may exceed this volume.

2.3. The dashed area shown in the southeast corner of the chamber diagram is currently an access hatch that will be sealed prior to the chamber being installed. The floor in this area may not be the same thickness as the rest of the floor, but will be such that it can support the weight of the chamber.

2.4. The ceiling height of the room in which this chamber will be constructed is 24 feet.

However, there are pipes running along the ceiling. In these areas, there is only 23 feet between the floor and ceiling.

2.5. The chamber designed shall be stamped by a licensed PE prior to submission to NIST.

2.6. The chamber shall be designed pursuant to the appropriate design standards given the chamber’s installation location in Boulder, CO.

2.7. NIST will be responsible for leveling the floor underneath the chamber. This will be done prior to the start of installation.

3. The shielded enclosure shall be capable of providing at least 100 dB of shielding (electric field or plane wave) across the full frequency range of operation. This will be verified during the construction of the chamber at the following frequencies, as described in Section VII.

4. The absorbing material(s) used inside the chamber shall meet, at a minimum, the following reflection characteristics:

Table I. Absorber Requirements

Frequency (MHz) Maximum Typical

Reflectivity (Normal

Incident Angle) (dB)

100 -20

500 -20

1,000 -20

5,000 -24

10,000 -25

20,000 -23

40,000 -24 Note that values shown are exceeded when the reflectivity is less than what is shown. For example, if at 100 MHz, the absorber has a reflectivity of -25 dB, it exceeds the performance requirement of -20 dB.

PAGE 12 OF 21 SB1341-15-RP-0023/002

4.1. All of the absorbing material(s) used on the walls and ceiling of the chamber (not just in specular regions) shall meet the above minimum requirements. In areas where two or more walls join together, there is an air vent, or a door, a different material may be used.

This substitute material should have a maximum typical normal incident reflectivity of -

10 dB at all frequencies above 500 MHz.

4.2. For the frequencies not specified in the table above (but still within the 100 MHz to 40

GHz range), the reflectivity of the absorbing material shall not be greater than -20 dB.

4.3. The total depth of the absorbing material used in the chamber (excluding moveable absorber on the floor) shall not exceed 38 inches. This is measured from the back of the absorbing material to the top. For example, if ferrite tiles and pyramidal foam absorber are used, the distance from the back of the tile to the top of pyramid should not exceed

38 inches.

4.4. If multiple types of absorbing material are used, (e.g., foam absorber on top of ferrite tiles), the combination of the materials used shall meet the above specifications.

4.5. If pyramidal foam absorber is used as the top layer of absorbing material (exposed to the inside of the chamber) it should be protected with a Styrofoam cap (or similar), except in areas where it is not practical to do so (e.g., corners, doors).

4.5.1. The absorbing material used shall be able to safely absorb a radiated signal with a maximum continuous strength of 200 V/m.

4.5.2. Any foam type absorber used within the chamber shall conform to the following standards: NRL 8093 (tests 1, 2, and 3), and either UL 94, ISO 11925-2, or ASTM

E84.

5. The solid floor (also serving as the electrical ground plane) within the shielded enclosure shall be raised such that a cable conduit measuring 4 inches (inner diameter) can be housed underneath the floor. The raised floor should not exceed 12 inches in height, and shall be level to 0.25 inches in any 10 foot span (non-cumulative).

5.1. This floor shall be capable of safely supporting a 1,000 pound load distributed on four points over one square meter.

5.2. In between the bottom shielding panel of the chamber and the raised floor, cable conduits shall be provided. These conduits should have an inner diameter of 4 inches and run from the bulkhead access panels on the exterior of the chamber to the access panels mounted in the raised floor. The access panels are noted on the attached drawing

(Attachment C).

5.2.1. The cable conduits shall extend from the two bulkhead panels intended for access between the exterior and the area underneath the raised floor (as described in 6.3) to panels located in the interior of the chamber. The approximate location of the panels is shown on the attached drawing (Attachment C). In general, there should be one panel in the center of the floor, and one additional panel in each of the four interior quadrants.

5.3. The cable conduit running underneath the floor shall be rated and approved for housing electrical wires (with voltages not exceeding 240 VAC).

5.3.1. The approximate paths of the cable conduits are shown in the attached drawing

(Attachment C).

5.4. The Contractor is not responsible for installing any RF cabling. However, the design should be such that RF cables can be pulled through the conduit at a later date.

5.4.1. The Contractor shall provide fishing/pulling lines that will allow for the

PAGE 13 OF 21 SB1341-15-RP-0023/002

installation of RF cable(s) at a later date. The Contractor is not responsible for providing the RF cable(s).

6. The chamber shall come equipped with four bulkhead panels that facilitate the passing of cables from the interior to the exterior of the chamber. Each panel should be removable from the chamber wall to allow it to be machined. The approximate location of these panels is shown on the attached drawing (Attachment C).

6.1. All four panels shall be blank, in that no RF connectors are installed. RF connectors will be installed by NIST personnel at a later date.

6.2. The panel on the south wall of the chamber shall be placed to allow access between the exterior and underneath the raised floor. This panel should measure approximately 6 inches tall and be approximately 24 inches wide.

6.3. There shall be three panels on the north wall of the chamber, each at a different height.

6.3.1. One panel on the north wall will allow for access between the exterior and underneath the raised floor. This panel should measure approximately 6 inches tall and be approximately 24 inches wide.

6.3.2. The second panel on the north wall will allow for access between the exterior and area above the raised floor of the chamber. This panel will measure approximately

16 inches tall and be approximately 16 inches wide. This panel must be accessible from the interior of the chamber. When not in use, this panel should have a form-fitting piece of absorbing material to cover it. This panel should be placed approximately 12 inches above the height of the raised floor inside the chamber.

6.3.3. The third panel on the north wall will allow for access between the exterior and the working volume of the chamber. This panel will measure approximately 16 inches tall and be approximately 16 inches wide. This panel must be accessible from the interior of the chamber. When not in use, this panel should have a form-fitting piece of absorbing material to cover it. This panel should be placed approximately eight feet above floor of the parent building.

6.3.4. In addition to the aforementioned blank bulkhead panels, one extra panel shall be provided. This panel will be used as a spare panel, installed only when other panels are removed for machining. The Contractor shall provide one extra panel of each type used. That is if there are two different sized panels used, one extra panel of each size shall be provided. These extra panels shall be blank (i.e. no installed RF connectors).

6.3.5. The dimensions given for bulkhead panels are listed as approximate. Deviations from the size given is allowed to enable the Contractor to utilize one of their

“standard” panel sizes; one that is close in size (if not exact) to the dimensions given.

7. The chamber shall include two access doors. Both doors must be operable from either inside or outside the chamber.

7.1. One door shall provide an unobstructed clearance of approximately 70 inches wide and

84 inches tall. The unobstructed clearance of the door may deviate from the approximate dimensions not more than 1” smaller to 6” larger in either dimension. This door may have one or two panels, and may be manually operated. This door should be located along the west portion of the north wall. The door shown on the attached drawing (Attachment C) represents an approximate location. Note that to achieve the

PAGE 14 OF 21 SB1341-15-RP-0023/002

required clear opening, any absorber attached to the door may be removed when the door is opened.

7.2. The second door is intended to be used as a personnel access door, and should provide an unobstructed clearance of approximately 48 inches wide and 84 inches tall. The unobstructed clearance of the door may deviate from the approximate dimensions not more than 1” smaller to 6” larger in either dimension If the door threshold is more than

4” off the ground, , a step external to the chamber shall be included, and capable of supporting a person. This step may exceed the volume specified above. This door should be located in the north portion of the east wall. A sample location is shown on the attached drawing (Attachment C).

7.2.1. The step, if required, shall have a tread depth of at least 11” and a riser height of between 4” and 7”. The stair must be the same width as the door. A handrail is only required if two or more risers are used. The Contractor is responsible for providing a handrail, if needed.

7.3. One door maintenance kit shall be included for each door. This kit shall include any parts necessary to perform one routine maintenance service on each door.

7.4. To allow for rolling equipment into the chamber a ramp shall be provided for use with the 70 inch wide door. This should extend from the building floor up onto the raised floor inside the chamber. This ramp shall not protrude more than 6’ from the exterior wall of the chamber when in use. This ramp may be removable, or fixed (i.e., anchored to the floor of the room housing the chamber).

7.5. Both doors shall be equipped with emergency lighting on the interior of the chamber.

These lights should activate in the event of a power failure and provide enough light for someone inside the chamber to locate the door, operate the door, and safely exit the chamber. These emergency lights maybe powered via battery in the event of a main power failure.

8. The chamber shall include an appropriate number of HVAC vents that allow the air to pass between the inside of the chamber, and the room outside the chamber. External to one of these vents should be a blower (or similar device) that will circulate air through the interior of the chamber.

8.1. Each HVAC vent shall be properly shielded and, if necessary, covered with absorber designed to allow air to pass through it. This absorber is exempt from the requirements listed in Table I.

8.2. The noise generated by the HVAC blower (or similar) shall not exceed 65 dBA (as measured at 1 meter from the blower).

9. The chamber shall be equipped with the ability to have sheets of conductive fabric hung from the ceiling. These sheets will hang from the ceiling, and extend to the raised floor, weighing a maximum of 25 pounds for a sheet measuring 8 feet wide and 20 feet long. To allow for the sheets to hang, the chamber shall be equipped with non-reflective (in the RF sense) rods extending from the ceiling through the absorbing material and into the chamber.

9.1. Each rod shall extend approximately 12 inches below the tip of any absorbing material.

Rods shall be placed at 8 foot intervals around the perimeter of the interior of the chamber.

9.2. Rods shall be placed far enough in from the vertical walls to allow sheets to hang without interfering with the absorbing material on the wall.

PAGE 15 OF 21 SB1341-15-RP-0023/002

9.3. Each rod shall be equipped with a non-reflective hook or eye-let to allow the fabric to hang from it.

9.4. The ceiling of the chamber shall be capable of supporting the weight of the hanging fabric, assuming that all of the walls were covered simultaneously.

10. An air sampling smoke detection system is required. Through the use of limited and/or non-combustible materials and equipment we do not require a wet or dry fire suppression system.

The Contractor is responsible for the design, installation, and verification of this system. To ensure compatibility with the NIST site-wide fire detection system, this system must be a

VESDA brand system.

10.1. The air sampling inlet(s) shall be placed at least 12 inches below the absorber surface/cone tip. For example, if the sensing units are mounted on the ceiling of the chamber and pyramidal absorber is used, the inlet shall be 12 inches lower (closer to the raised floor) than the tip of the absorber.

10.2. The Contractor is responsible for determining the appropriate number of air sampling inlets, and their location within the chamber.

10.3. This system shall include a shunt trip interlock that will automatically disconnect power into the chamber in the event smoke is detected. This shunt trip interlock shall be connected to the air sampling system. The Contractor is responsible for the connection of the shunt-trip interlock to disconnect the chamber power.

10.4. Design and Installation shall be accordance with the latest version of NFPA 72 and manufacturer’s recommendations for this specific installation. Design shall be stamped by an experienced Colorado licensed Professional Engineer in Fire Protection.

10.5. Submission and approval of engineering drawings and calculations will be required prior to the installation of the chamber.

10.6. The Contractor is responsible for terminating the fire alarm wires from the semi-anechoic chamber’s detection system into the building’s fire alarm controller, and setting the VESDA detector level (i.e., obscuration thresholds). Only certified Notifier contractors that are also a Notifier Engineered Systems Company (NESCO) will be permitted to connect to and update the NIST fire alarm system.

10.7. The Contactor shall also have an authorized Notifier contractor update the NIST system program to respond to the semi-anechoic chamber’s detection system and applicable drawings to reflect the addition of this new air sampling system. This work must also be done by a Notifier/NESCO certified contractor.

11. AC Electrical power shall be available inside the chamber. Any electrical power entering the chamber shall be properly filtered. The Contractor is responsible for all electrical wiring inside the chamber, and any electrical wiring that runs along the outside of the chamber.

NIST personnel will make the connection to the building electrical system. The connection point to the building electrical system is indicated on the attached drawing (Attachment C).

11.1. Power line filters used should provide a minimum of 90 dB of insertion loss and function from at least 150 KHz to at least 18 GHz.

11.2. In each of the floor access panels located inside the chamber (as noted on the drawing) there shall be two 120VAC duplex outlets. A total of two 20 amp circuits are available for all of the interior outlets.

11.3. One additional set of two duplex outlets shall be placed on the exterior of the chamber along the north wall. This group of outlets will serve as power for instrumentation located outside the chamber. The power to this outlet need not be

PAGE 16 OF 21 SB1341-15-RP-0023/002

filtered if it does not enter the chamber. There is one 20 amp circuit available for this group of outlets.

11.4. Lights shall be installed on the interior of the chamber. The lights shall be appropriately shielded/filtered to maintain the shielding integrity of the chamber, and to prevent the lights from emitting RF energy into the interior of the chamber.

11.5. The Contactor is responsible for wiring the lights and electrical outlets in the interior of the chamber.

11.6. There shall be a sufficient number of lights placed in appropriate locations to allow equipment to be safely moved into the chamber, and be configured before/after testing. As almost all of the chamber volume will be utilized, equipment may be moved/configured in all areas of the chamber. Thus, lighting shall be sufficient in all areas of the floor.

12. To enable the interior of the chamber to be monitored, a camera shall be installed inside the chamber to allow viewing of any automated test in-progress. This camera shall connect to a screen mounted on the outside of the chamber (this screen shall be provided by the

Contractor). The approximate location of this screen is shown on the attached drawing

(Attachment C).

12.1. Penetrations through the chamber wall shall be properly filtered/shielded to maintain the shielding integrity of the enclosure.

12.2. The camera shall the ability to zoom, pan and tilt inside the chamber via controls placed outside the chamber.

12.3. The camera shall be shielded/EMC hardened and continue to function in radiated fields up to 200 V/m.

12.4. The camera controller (placed outside the chamber) shall be able to control at least two cameras. Though only one camera is required now, an additional camera may be added at a later date.

12.5. The screen used to view the camera’s output will be a multi-purpose screen, also serving as the monitor for a desktop PC. The screen will be connected to the desktop PC via either HDMI, DVI, or VGA cables. NIST personnel will provide the desktop PC and connect it to the screen at a later date.

12.6. The screen shall be capable of being simultaneously connected to the camera and the desktop PC. However, the screen need only be capable of displaying one input at a time.

12.7. The size of this multi-purpose screen shall be at least 50 inches, but not exceed 70 inches (as measured along the diagonal of the screen).

12.8. The screen shall be capable of displaying video with a resolution of 1920x1080 pixels at a minimum refresh rate of 60 Hz.

13. The Contractor shall include enough pyramidal foam type absorber on the floor of the chamber to conduct the testing shown in Section VII. This absorber must conform to the specifications of both the test standard specified in Section VII, and the fire standards specified in 4.5.2. None of this absorber shall be walkway type absorber.

14. The Contractor shall only use new materials in the construction of the chamber. The use of used/refurbished materials is not permissible.

Contract Options

PAGE 17 OF 21 SB1341-15-RP-0023/002

The following items should be included as options in the proposal:

1. Enough RF absorber to cover 100 % of the useable floor space inside the chamber shall be included as an option in the proposal (less the amount provided as part of paragraph 13 above). Approximately 50 % of the absorber shall be “walkway absorber” in that it is designed to support the weight of a person walking on top of it. The remaining floor absorber may be typical pyramidal or wedge type absorber. This absorber shall be moveable, and not mounted to any surface inside the chamber. This absorber will be used between 500 MHz –

40 GHz.

1.1. The maximum normal incident reflection of the non-walkway floor absorber shall not exceed -20 dB at any frequency between 500 MHz and 40 GHz. The maximum normal incident reflectivity of the walkway absorber shall not exceed -15 dB at any frequency between 500 MHz and 40 GHz.

1.2. The absorber intended for the floor shall conform to the following standards: NRL 8093

(tests 1, 2, and 3), and either UL 94, ISO 11925-2, or ASTM E84.

2. A vertical scanning mast to be used to scan or set the height of an antenna (for example) above the raised floor shall be included as an option in the proposal. The mast shall move the antenna along an axis perpendicular to the raised floor. The mast design must be such that its position within the chamber can be changed, and such that it can be removed from the chamber. It is permissible for disassembly of the mast to be required when moving the mast within or into/out of the chamber. Non-boresighting masts are permissible.

2.1. Only vertical motion is required (no angular motion of the antenna is required).

Motorized adjustment of the antenna’s polarization is also required.

2.2. The mast shall be capable of supporting at least 25 pounds, including any required counterweights.

2.3. A controller capable of moving the mast shall be included. This controller shall be operable as a standalone unit (i.e., does not require a connection to a desktop PC for operation). The controller shall have the option of being connected to a desktop PC for automated operations. The controller shall connect to the desktop PC with one (or more) of the following connector types: USB, RS-232 serial, GPIB, and/or Ethernet. A list of commands for automated mast control shall be included with the mast.

2.4. A hand held remote (which may be wired) shall also be included that allows for the mast to be moved while a person is standing inside the chamber. This remote will be used within 6’ of the antenna mast.

2.5. The system shall be set up such that the height of the mast can be changed from outside the chamber, while all of the chamber doors are closed. In this configuration, these changes may be made using buttons on the controller or via a PC.

3. An 11 feet wide and 7 feet tall color image of the United States flag printed on top of the

Styrofoam (or similar) absorber caps centered in the upper half of the interior of the south wall of the chamber shall be included as an option. If this option is selected, the Contractor will be provided with an image of appropriate resolution for printing.

3.1. In the event printing the image directly on top of the absorber caps is not practical, printing the image on another surface and affixing that surface to the top of the absorber is permissible.

Installation:

The Contractor shall install the chamber in Building 24, Room 1300, at NIST Boulder, CO.

PAGE 18 OF 21 SB1341-15-RP-0023/002

Installation shall include, at a minimum, uncrating/unpacking of all materials, construction of the chamber, demonstration of specifications, and removal of all trash. The chamber will operate to manufacturer’s specifications upon installation. Installation will take place between 7:30 am and

5:30 pm mountain time, Monday through Friday (except Federal Holidays) and between 8:00 am and 4:00 pm mountain time on Saturdays. Installation may begin as soon as December 1st, 2015, but shall not begin more than 270 days of award.

All construction materials must be able to pass thorough an opening measuring 120 inches wide by 96 inches tall. The location of this opening is on the north wall of the room.

If the Contractor deems a forklift, and/or scissor lift necessary for the installation of the chamber, they are responsible for providing them. Because the installation area is inside, only electric, propane, or natural gas powered lifts are acceptable. The Contractor is responsible for ensuring their personnel are properly trained/certified to safely operate any equipment used during the installation process.

Warranty:

The Contractor shall provide, at a minimum, a one year warranty on the installation of the chamber, its shielding, and all features installed by the Contractor. Absorber used on the interior of the chamber shall be warrantied for a minimum period of 5 years. The warranty shall cover all parts, labor and travel (if required). The warranty shall commence upon successful completion of delivery, installation, training and demonstration of all required specifications.

Training:

Include at least 4 hours of training at NIST for up to 4 NIST personnel covering normal operation, troubleshooting, safety, and routine maintenance. Training will be provided during normal business hours, between 8:30am and 5:00pm mountain time, Monday through Friday, except Federal Holidays, and will be coordinated with the NIST Technical Point of Contact

(TPOC) to ensure maximum availability of NIST personnel. Training is to occur within 10 days of the end of installation. The training may be completed on-site at NIST immediately after installation and demonstration of specifications.

IV. PERIOD OF PERFORMANCE

The period of performance shall be one (1) year from award of this requirement.

V. PLACE OF PERFORMANCE

The design and manufacturing of the chamber shall be completed at the Contractor’s facility.

Installation of the chamber and training shall be accomplished at NIST, 325 Broadway, Boulder, Colorado. Normal duty hours are Monday through Friday, 8:30 a.m. to 5:00 p.m. with the exception of Federal holidays. With Contracting Officer approval, contractors may be given access to the facility on Saturdays between 8:30 a.m. and 5:00 p.m. Contractors desiring access on Saturdays should indicate so in their proposals.

VI. PROJECT STATUS MEETINGS

PAGE 19 OF 21 SB1341-15-RP-0023/002

The Contractor shall provide project updates at least once every 4 weeks from the time the contract is awarded until installation of the chamber begins. Once installation of the chamber begins, the Contractor shall provide a project update at least once every 2 weeks until the completion of the work. At the project update meetings, Contractors shall convey what work has been completed since the last meeting, potential issues/delays, and what work will be taking place before the next meeting.

These meetings may be held in person, or via a teleconference. The Contractor is responsible for scheduling the meetings, which at a minimum, shall be attended by the Contractor’s appointed project manager, and the COR or TPOC. The COR or TPOC is responsible for documenting that the meeting took place and providing a short description of what was discussed at the meeting.

VII. DELIVERABLES

Description Quantity Due Date

Design drawings (excluding the smoke detection system) for NIST’s review and approval. These drawing shall be delivered electronically to the Technical Point of

Contact (TPOC).

One (1) set

45 days after award of this requirement.

Design drawings and calculations for the smoke detection system shall be delivered electronically to the TPOC.

One (1) set

30 days after approving the chamber design drawings.

Start of installation of the Semi-Anechoic

Research Chamber

Once 270 days after award of this requirement, but not earlier than December 1st, 2015.

One (1) paper copy and (1) electronic copy of the operations and maintenance manual for the chamber shall be delivered to the

TPOC.

One (1) set

270 days after award of this requirement

Completion of the chamber installation Once 90 days after the start of installation

Training of NIST personnel at NIST, Boulder, CO

Once 10 days after the end of chamber installation.

Copies of the training information shall be electronically delivered to all training participants.

One (1) set

10 days after the end of chamber installation

One (1) paper copy and (1) electronic copy of the performance verification measurement report (with data) shall be delivered to the TPOC.

One (1) set

10 days after the end of chamber installation

VIII. PERFORMANCE REQUIREMENT SUMMARY

The Contractor shall demonstrate that all performance standards in this statement of work have been met by use of all four of the methods shown below. In particular, the Contractor shall

PAGE 20 OF 21 SB1341-15-RP-0023/002

provide a measurement report (with data) showing that the installed chamber meets the performance standards. Further, the measurements in the report shall be conducted by an independent third party company. These verification measurements would be done assuming there is only the minimum (or no) absorber on the floor. Minimum absorber is dictated by the measurement standard. The electromagnetic performance specifications shall be verified by use of:

1. IEEE 299: Enclosure shielding shall be verified, prior to any absorber being installed, but after all penetrations (e.g., doors, bulkhead panels, vents, lights, etc.) have been installed in the chamber walls. Shielding shall be verified at the following frequencies: 100 MHz, 1 GHz, 5 GHz, 10 GHz, 18 GHz, and 40 GHz.

2. ANSI C63.4: Normalized site attenuation shall be measured between 100 MHz and 1

GHz, and be within the standard +/- 4 dB variance requirement described in C63.4.

3. CISPR 16-1-4: The site voltage standing wave ratio (SVSWR) shall be measured from 1

GHz to 18 GHz in accordance with CISPR 16-1-4. When measured, the SWSWR of the chamber shall be less than or equal to 2:1 at all measured frequencies. For the purposes of this test, a test volume measuring 3.0 meters in diameter shall be used. This test volume extends from the floor/ground plane to a height of 3.0 meters.

4. IEC 61000-4-3: It shall be shown that a given test plane in the chamber meets the field uniformity requirements specified in IEC 61000-4-3 from 1 GHz – 18 GHz.

IX. GENERAL INFORMATION

Safety: The Contractor and its employees shall be responsible for knowing and complying with

NIST installation safety prevention regulations. Such regulations include, but are not limited to, general safety, fire prevention, and waste disposal and are available upon request.

Patent Rights: The Government retains a Government use license to all inventions arising from this work.

Security: NIST is a restricted campus. An identification badge is required for access for entry into buildings and also is shown to the armed Security Police when entering the campus.

Identification Badges: Contractor employees that come on-site to install the chamber must be

U.S. citizens and comply with NIST identification and access requirements. Contractors shall familiarize themselves with and comply with the Real ID Act of 2005 requirements. The

Contractor employee is responsible for absences due to expired identification and access documents. Each Contractor employee shall wear a visible identification badge provided by the

NIST Security Office. The badge must show the full name, title, and if required by NIST, the words “Contractor” in front. The Contractor employee shall turn in the NIST identification badge and vehicle pass to the TPOC, COR, or Contracting Officer (CO) upon termination of their services under this contract.

To facilitate the badging process all installation team members that will be on-site will be required to complete the badging/security process prior to working on-site. Therefore, the names and required information of the installation team must be sent to the TPOC at least 8 weeks prior to the start of installation.

PAGE 21 OF 21 SB1341-15-RP-0023/002

Vehicle Registration: All Contractor employees must register their vehicles with the NIST

Security Office to gain access to the campus. A valid driver’s license, Government-furnished civilian ID, proof of insurance and current registration must be presented to the NIST Security

Office, at which time a NIST vehicle pass will be issued. The pass shall be displayed on the vehicle’s rear view mirror in accordance with instructions. The Contractor employee shall follow NIST procedures for removal and turn-in of the vehicle pass upon termination of services under this contract.

Media Inquiries: The Contractor employee shall not respond to any media inquiries. Any inquiries from the media shall be immediately relayed to the TPOC, COR, and/or CO. There shall be no interviews, comments, or any other response without the knowledge and approval of the NIST Director.

Descript: The purpose of this amendment is to:

1. Post Contractor questions that were received at the site visit conducted on 7/9/15 and the Government responses to the questions. The questions and responses are included herein as Attachment 1 to this amendment. ...See Continuation Page

Descript1:
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT:
IDCode:
pdfpage1: 1
Pages: 21
DocNo: 002
EffDate: JUL 17, 2015